IV Biaya Pemadatan
1 Solar wales ( 1 bln) @200 ltr/hari 6,000 liter 11,000 66,000,000
2 Solar Armada (1 bln) @ 60 ltr/hari 3 MOBIL 1,800 liter 11,000 19,800,000
3 intensip operator 30 hari 300,000 9,000,000
Rp 94,800,000
V Biaya Lain-lain
1 Biaya pembuatan jembatan 1 bh 200,000,000.00 200,000,000.00
2 Biaya koordinasi 1 ls 100,000,000.00 100,000,000.00
3 Biaya lain-lain 1 ls 100,000,000.00 100,000,000.00
Rp 400,000,000.00
TOTAL Rp 4,616,810,500.00
Rp 4,616,810,500.00
RAB PEMBUATAN SALURAN PERUMAHAN PESONA KAHURIPAN 2
LUAS LAHAN : 105,489 M2 ( 10 HA)
VOLUME : 29.584 M2
TOTAL
NO URAIAN PEKERJAAN VOLUME SAT HRG. SAT
JUMLAH
I Biaya Pembuatan Saluran
1 Cor beton U-DITH 30 cm ( 6,200 bh ) 89 mobil 4,818,000 428,802,000
2 Upah pengecoran & Pemasangan 89 mobil 3,550,000 315,950,000
3 Cor beton U-DITH 40 cm ( 956 bh ) 18 mobil 4,818,000 86,724,000
4 Upah pengecoran & Pemasangan 18 mobil 3,550,000 63,900,000
5 Besi 10 9,800 btg 65,000 637,000,000
6 Triplek 5 mm 350 lbr 85,000 29,750,000
7 Terpal 100 m2 9,000 900,000
8 pipa 1 1/4 400 btg 40,000 16,000,000
9 Upah pembesian U-Dith 7,156 BH 10,000 71,560,000
10 Biaya oprasional 1 ls 30,000,000 30,000,000
Rp 1,680,586,000
II Biaya Pembuatan Deker
1 Pembelian Box deker 170 bh 2,300,000 391,000,000
2 Upah Pemasangan 170 bh 125,000 21,250,000
Rp 412,250,000
TOTAL Rp 2,092,836,000
DIBULATKAN
RENCANA ANGGARAN BIAYA TANAH
PESONA KAHURIPAN 2
Luasan Tanah : 105,489 m2