RAB PEMBUATAN JALAN PERUMAHAN PESONA KAHURIPAN 2

Luas Lahan : 103.403M2


VOLUME : 29.584 M2
TOTAL
NO URAIAN PEKERJAAN VOLUME SAT HRG. SAT
JUMLAH
I Biaya Pembuatan Jalan
1 Kebutuhan coran Redymix ( T. 0.12 CM) 2,400 m3 803,000 1,927,200,000
2 Upah pengecoran 19,163 m2 13,000 249,119,000
3 Biaya oprasional 15 hari 9,000,000 135,000,000
Rp 2,311,319,000
II Biaya Pembuatan gedek
1 Bambu 16,200 batang 13,000 210,600,000
2 Upah Perakitan 19,163 m2 7,500 143,722,500
3 Upah Gelar @ 14.44 M2 (3.8X3.8) 19,163 m 2
6,500 124,559,500
Rp 478,882,000
III Biaya Batu Karang dan Limestones
1 Batu karang (T.45) 8,623 m3 115,000 991,645,000
2 Upah 19,163 m2 6,500 124,559,500
3 Limestones 2,015 m 3
107,000 215,605,000
Rp 1,331,809,500

IV Biaya Pemadatan
1 Solar wales ( 1 bln) @200 ltr/hari 6,000 liter 11,000 66,000,000
2 Solar Armada (1 bln) @ 60 ltr/hari 3 MOBIL 1,800 liter 11,000 19,800,000
3 intensip operator 30 hari 300,000 9,000,000
Rp 94,800,000
V Biaya Lain-lain
1 Biaya pembuatan jembatan 1 bh 200,000,000.00 200,000,000.00
2 Biaya koordinasi 1 ls 100,000,000.00 100,000,000.00
3 Biaya lain-lain 1 ls 100,000,000.00 100,000,000.00
Rp 400,000,000.00
TOTAL Rp 4,616,810,500.00

Rp 4,616,810,500.00
RAB PEMBUATAN SALURAN PERUMAHAN PESONA KAHURIPAN 2
LUAS LAHAN : 105,489 M2 ( 10 HA)
VOLUME : 29.584 M2
TOTAL
NO URAIAN PEKERJAAN VOLUME SAT HRG. SAT
JUMLAH
I Biaya Pembuatan Saluran
1 Cor beton U-DITH 30 cm ( 6,200 bh ) 89 mobil 4,818,000 428,802,000
2 Upah pengecoran & Pemasangan 89 mobil 3,550,000 315,950,000
3 Cor beton U-DITH 40 cm ( 956 bh ) 18 mobil 4,818,000 86,724,000
4 Upah pengecoran & Pemasangan 18 mobil 3,550,000 63,900,000
5 Besi 10 9,800 btg 65,000 637,000,000
6 Triplek 5 mm 350 lbr 85,000 29,750,000
7 Terpal 100 m2 9,000 900,000
8 pipa 1 1/4 400 btg 40,000 16,000,000
9 Upah pembesian U-Dith 7,156 BH 10,000 71,560,000
10 Biaya oprasional 1 ls 30,000,000 30,000,000
Rp 1,680,586,000
II Biaya Pembuatan Deker
1 Pembelian Box deker 170 bh 2,300,000 391,000,000
2 Upah Pemasangan 170 bh 125,000 21,250,000
Rp 412,250,000

TOTAL Rp 2,092,836,000
DIBULATKAN
RENCANA ANGGARAN BIAYA TANAH
PESONA KAHURIPAN 2
Luasan Tanah : 105,489 m2

No Jenis Pekerjaan Sat Volume Harga Sat Jml Harga Rp


I Pembebasan tanah
1 Pembelian Tanah m2 105,489 300,000 31,646,700,000
2 Upah Pembelian ( Biong ) <250.000 m2 47,000 15,000 705,000,000
3 Pelepasan hak (SPH) m 2
105,489 6,000 632,934,000
32,984,634,000
II Pekerjaan Izin
1 Ijin Lokasi m2 105,489 2,000 210,978,000
2 Aspek TGT m2 105,489 1,000 105,489,000
3 Tanah Makam m2 2,110 200,000 421,956,000
4 UKL/UPL ls 1 30,000,000 30,000,000
5 Amdal Lalin ls 1 35,000,000 35,000,000
6 Pengesahan Site Plan ls 1 50,000,000 50,000,000
853,423,000
III Pekerjaan Dokumen Sertifikat
1 Sertipikat Induk m2 105,489 7,000 738,423,000
2 PPH m 2
105,489 7,125 751,609,125
3 BPHTB/SSB m2 105,489 15,000 1,582,335,000
4 Oprasional Ukur BPN m2 105,489 200 21,097,800
3,093,464,925
IV Pekerjaan Dokumen SPPT INDUK
1 Denda Pajak m2 -
2 Pajak tahun berjalan m 2
-

V Pekerjaan dokumen imb induk


1 Survey Lokasi ls 1 5,000,000 5,000,000
2 Biaya PDRT Unit 890 100,000 89,000,000
3 IMB induk Unit 890 50,000 44,500,000
4 Oprasional Imb induk ls 1 5,000,000 5,000,000
5 BPJS ketenagakerjaan Unit 890 50,000 44,500,000
188,000,000
VI Pematangan Lahan
2 Pengukuran dan Pengaplingan m2 105,489 500 52,744,500
3 Pematangan Lahan m 2
105,489 3,500 369,211,500
3 Sarana dan Prasarana ls 1 6,709,646,500
7,131,602,500
VII JUMLAH
Total Biaya Untuk 105.489 m2 44,251,124,425
Harga Satuan Kavling Efektif 60% 44,251,124,425 63,293 699,143
Dibulatkan 700,000