BETON
V=PxLxT
VOLUME
VOLUME
NO P L T KETERANGAN
(M) (M) (M) M 3
1 2 3 4 5(2x3x4) 6
1 54.5 0.15 0.2 1.635 Beton Sloof
2 0.150 0.150 63.000 1.418 Beton Kolom
3 54.500 0.15 0.200 1.635 Beton Ring Balk
Total 3.053
PEK. BEGISTING
VOLUME
LUAS
NO P L T KETERANGAN
(M) (M) (M) M 2
1 2 3 4 5 6
1 54.50 0.15 0.20 21.80 Begisting Sloof
2 0.15 0.15 63.00 37.80 Begisting Kolom
3 54.50 0.15 0.20 21.80 Begisting Ring Balk
Total 59.600
GALIAN
PANJANG = 27.000
TINGGI = 1.100
LEBAR ATAS = 1.300
LEBAR BAWAH = 1.000
PAS BATU KALI
LEBAR ATAS = 0.300
LEBAR BAWAH = 0.800
TINGGI = 0.800
AANSTAMPING
LEBAR = 1.000
TINGI = 0.200
URUGAN PASIR
LEBAR = 1.000
TINGGI = 0.100
PEK.PONDASI TYPE 1
VOLUME JUMLAH
NO P L T M3 KETERANGAN
(M) (M) (M)
1 2 3 4 5(2X3X4) 6
1 27.00 1.15 1.1 34.155 GALIAN PONDASI MENERUS
2 27.00 0.55 0.80 11.88 PAS BATU KALI
3 27.00 1.00 0.20 5.4 AANSTAMPING
4 27.00 1.00 0.1 2.700 URUGAN PASIR
GALIAN
PANJANG = 27.500
TINGGI = 1.050
LEBAR ATAS = 1.050
LEBAR BAWAH = 0.900
PAS BATU KALI
LEBAR ATAS = 0.300
LEBAR BAWAH = 0.800
TINGGI = 0.800
AANSTAMPING
LEBAR = 0.900
TINGI = 0.200
URUGAN PASIR
LEBAR = 0.900
TINGGI = 0.100
PEK.PONDASI TYPE 2
VOLUME JUMLAH
NO P L T M3 KETERANGAN
(M) (M) (M)
1 2 3 4 5(2X3X4) 6
1 27.5 0.975 1.05 28.15313 GALIAN PONDASI MENERUS
2 27.5 0.55 0.80 12.1 PAS BATU KALI
3 27.5 0.90 0.20 4.950 AANSTAMPING
4 27.5 0.90 0.1 2.475 URUGAN PASIR
PEK. BETON
VOLUME JUMLAH
NO P L T (M3)
(M) (M) (M) KETERANGAN
1 2 3 4 5(2X3X4) 6
1 0.15 0.15 63 1.42 BETON KOLOM
2 54.50 0.15 0.20 1.64 BETON SLOOF
3 54.50 0.15 0.20 1.64 BETON RING BALK
TOTAL 4.69
PEK. BETON
VOLUME JUMLAH
NO P L T (M3)
(M) (M) (M) KETERANGAN
1 2 3 4 5(2X3X4) 6
1 54.50 0.15 0.20 1.64 BETON SLOOF
2 0.15 0.15 63.00 1.42 BETON KOLOM
3 54.50 0.15 0.20 1.64 BETON RING BALK
TOTAL 4.69
KOLOM
LEBAR =
PANJANG =
TINGGI =
JUMLAH =
SLOOF
PANJANG =
LEBAR =
TINGGI =
RING BALK
PANJANG =
LEBAR =
TINGGI =
BEGISTING
NO VOLUME KETERANGAN
JUMLAH
P L T (M3)
(M) (M) (M)
1 2 3 4 5 6
1 0.15 0.15 63 1.35 BEGISTING KOLOM
2 54.50 0.15 0.20 0.70 BEGISTING SLOOF
3 54.50 0.15 0.20 0.700 BEGISTING RING BALK
TOTAL 2.75
0.15
0.15
3.5
18
54.5
0.15
0.20
54.5
0.15
0.2
KOLOM
A. TULANGAN POKOK
∅ TULANGAN = 0.012 m
JUMLAH TULANGAN = 4 buah
TINGGI = 3.5 m
BERAT JENIS = 0.89 kg/m3
JUMLAH KOLOM = 18 buah
B. BEGEL
∅ BESI BEGEL = 0.008 m
PANJANG BEGEL = 0.56 m
JARAK BEGEL = 0.2 m
JUMLAH = 18.5 buah
BERAT JENIS = 0.395 kg/m3
SELIMUT BETON = 0.025 m
B. BEGEL B. BEGEL
∅ BESI BEGEL = 0.008 m ∅ BESI BEGEL = 0.008 m
PANJANG BEGEL = 0.56 m PANJANG BEGEL = 0.56 m
JARAK BEGEL = 0.2 m JARAK BEGEL = 0.2 m
JUMLAH = 273.5 buah JUMLAH = 273.5 buah
BERAT JENIS = 0.395 kg/m3 BERAT JENIS = 0.395 kg/m3
SELIMUT BETON = 0.025 m SELIMUT BETON = 0.025 m
P/ALAS L T
NO URAIAN JUMLAH VOLUME SATUAN
M M M
LUASAN ATAP 54 M3
1 BENTANG 6
BALOK TARIK 3 0.08 0.12 2 0.058 M3
BALOK KUNCI 1 0.08 0.12 1 0.010 M3
BALOK GAPIT 4.55 0.05 0.10 1 0.023 M3
TIANG KUDA-KUDA 2.97 0.08 0.15 1 0.036 M3
BALOK SOKONG 2.17 0.08 0.12 2 0.042 M3
KAKI KUDA-KUDA 4.78 0.08 0.15 2 0.115 M3
GORDING 7.7 0.08 0.12 1 0.074 M3
BALOK NOK 7.7 0.08 0.12 1 0.074 M3
PAPAN REUTER 7.7 0.02 0.2 1 0.031 M3
MURPLAT 7.7 0.8 0.12 1 0.739 M3
VOLUME TOTAL BENTANG 6 1.200 M3
2 USUK 4 0.05 0.07 42 0.594 M2
3 RENG 4 0.02 0.03 315 0.756 M2
4 GENTING 0.3 0.21 0.063 M2
VOLUME TOTAL 1.413 M2
JUMLAH GENTING=LUAS ATAP/LUAS GENTENG = 857 buah
KUSEN PINTU DAN JENDELA
NO URAIAN TINGGI LEBAR TEBAL JUMLAH VOLUME SATUAN
KUSEN J1 1.8 0.8 0.05 0.15 7 10.08 M3
1 KUSEN J2 1.8 1.1 0.05 0.15 2 3.96 M3
KUSEN J3 0.8 0.6 0.05 0.15 2 0.96 M3
KUSEN P1 2.15 0.9 0.05 0.15 1 1.935 M3
2 KUSEN P2 2.15 0.9 0.05 0.15 4 7.74 M3
KUSEN P3 2.15 0.7 0.05 0.15 2 3.01 M3
KACA JENDELA
NO URAIAN TINGGI LEBAR TEBAL JUMLAH LUASAN SATUAN
KACA J1 1.5 0.1 0.003 1 0.1500 M3
1
KACA J2 1.45 0.55 0.003 2 0.7975 M3
Pek. Daun
TINGGI LEBAR TEBAL LUASAN KETERANGAN
NO JUMLAH
(M) (M) (M) (M2)
I II III IV V VI VII
1 2.10 0.80 0.04 5 8.40 Daun Pintu 1
2 2.10 0.70 0.04 1 1.47 Daun Pintu 2
3 1.20 0.60 0.04 7 5.04 Daun Jendela 1
4 0.80 0.60 1.04 2 0.96 Daun Jendela 2
Total 15.87
Pek. Kaca
NO TINGGI LEBAR TEBAL JUMLAH VOLUME KETERANGAN
(M) (M) (M) M 3
I II III IV VI VII IX
1 1.00 0.40 0.005 7 2.8 Kaca Jendela 1
2 0.60 0.40 0.005 2 0.48 Kaca Jendela 2
Total 3.28
PEKERJAAN LANTAI
KERAMIK LUASAN
NO URAIAN PANJANG LEBAR JUMLAH SATUAN
M2 M2
1 KERAMIK 20x20 cm 0.4 0.4 0.16 2.4975 280 buah
2 KERAMIK 40x40 cm 0.2 0.2 0.04 44.8495 62 buah
LUAS LANTAI 47.347 M2
TOTAL 343 buah
REKAPITULASI
PEMBANGUNAN RUMAH TINGGAL
TYPE 36/60
KENDAL
Nama
Jabatan
PEMBANGUNAN RUMAH TINGGAL
KENDAL
1 2 3 4 5 6 7=3x6
A PEKERJAAN PERSIAPAN
1 Rangka kuda-kuda kayu (gording, nok, papan reuter, murplat, 1.20 m3 A.4.6.1.34. Rp 11,785,730.00 Rp 14,140,683.85 5.734
kaki kuda-kuda, balok gapit, balok kunci, balok tarik)
2 Penutup Atap (usuk dan reng) 1.35 m3 A.4.6.1.17.a Rp 219,519.00 Rp 296,350.65 0.120
3 penutup atap Genteng 54.00 M2 A.4.5.2.51. Rp 240,504.00 Rp 12,987,216.00 5.266
4 bubungan 7.70 M1 A.4.5.2.52. Rp 118,661.00 Rp 913,689.70 0.371
5 Rangka Plafond Kayu Klas II 47.35 M2 A.4.5.1.10.2 Rp 85,827.00 Rp 4,063,650.97 1.648
6 plafond gipsum 47.35 M2 A.4.5.1.7. Rp 43,981.00 Rp 2,082,368.41 0.844
7 Kayu List Plafond 65.90 M1 A.4.5.1.9. Rp 16,093.00 Rp 1,060,528.70 0.430
Jumlah Rp 35,544,488.280
I PEKERJAAN PENGECATAN
WAKTU PELAKSANNAN
JUMLAH HRG NILAI
NO. URAIAN PEKERJAAN VOL. SAT. Agustus September Oktober
(RP) BOBOT
Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8 Minggu 9 Minggu 10 Minggu 11 Minggu 12 Minggu 13 Minggu 14
1 2 3 4 5 6 01-07 08-14 15-21 22-28 29-04 05-11 12-18 19-25 26-02 03-09 10-16 17-23 24-30 31
A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 1.00 Ls 1,000,000.00 0.406 0.406
2 Pengukuran / Pemasangan Bouplank 1.00 Ls 3,000,000.00 1.217 1.217
E PEKERJAAN LANTAI
1 Urugan Pasir Bawah Lantai 47.35 m3 11,994,936.33 4.864 4.864
2 Rabat Beton 1:3:5 47.35 m3 48,171,832.09 19.534 9.767 9.767
3 Pas. Keramik Lantai 20/20 2.50 m2 531,455.51 0.216 0.216
4 Pas. Keramik Lantai 40/40 44.85 m2 9,140,193.55 3.706 3.706
4 Jendela J2 60/80
Kusen Jendela 0.05 m3 638,827.20 0.259 0.259
Daun Jendela 2.00 Buah 1,972,276.00 0.800 0.800
- Kaca 5 mm 0.48 m2 72,393.12 0.029 0.029
- Hak Angin / Gagang Jendela 4.00 Buah 158,904.00 0.064 0.064
- Engsel Jendela 4.00 Buah 144,768.00 0.059 0.059
G PEKERJAAN ATAP DAN PLAFOND
1 Rangka kuda-kuda kayu (gording, papan reuter, murplat, 1.20 m3 14,140,683.85 5.734 5.734
nok, kaki kuda-kuda, balok gapit, balok kunci, balok tarik)
2 Penutup Atap (usuk dan reng) 1.35 m3 296,350.65 0.120 0.120
3 penutup atap Genteng 54.00 M2 12,987,216.00 5.266 5.266
4 bubungan 7.70 M1 913,689.70 0.371 0.371
5 Rangka Plafond Kayu Klas II 47.35 M2 4,063,650.97 1.648 1.648
6 plafond gipsum 47.35 M2 2,082,368.41 0.844 0.844
7 Kayu List Plafond 65.90 M1 1,060,528.70 0.430 0.430
I PEKERJAAN PENGECATAN
1 Cat Dinding Luar 93.10 m2 5,497,368.80 2.229 2.229
2 Cat Dinding Dalam 203.35 m2 6,551,733.65 2.657 2.657
4 Cat Kusen, Daun Pintu / Jendela 16.36 m2 1,013,252.21 0.411 0.411
120.000
100.000
80.000
60.000
40.000
20.000
-
1 2 3 4 5 Row 106
6 7 8 9 10 11
LAPORAN MINGGUAN
Minggu ke : Kesatu
Tanggal : 01 s.d. 07 Agustus 2022
HASIL PEKERJAAN %
JUMLAH HRG NILAI
NO. URAIAN PEKERJAAN VOLUME BOBOT JENIS
(RP) BOBOT MINGGU LALU MINGGU INI JUMLAH
% PEKERJAAN
1 2 3 4 5 6 7 8 9 10
A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 1.00 Ls 1,000,000.00 0.406 1.00 Ls 1.00 Ls 0.406 100
2 Pengukuran / Pemasangan Bouplank 1.00 Ls 3,000,000.00 1.217 1.00 Ls 1.00 Ls 1.217 100
E PEKERJAAN LANTAI
1 Urugan Pasir Bawah Lantai 47.35 m3 11,994,936.33 4.864
2 Rabat Beton 1:3:5 47.35 m3 48,171,832.09 19.534
3 Pas. Keramik Lantai 20/20 2.50 m2 531,455.51 0.216
4 Pas. Keramik Lantai 40/40 44.85 m2 9,140,193.55 3.706
4 Jendela J2 60/80
Kusen Jendela 0.05 m3 638,827.20 0.259
Daun Jendela 2.00 Buah 1,972,276.00 0.800
- Kaca 5 mm 0.48 m2 72,393.12 0.029
- Hak Angin / Gagang Jendela 4.00 Buah 158,904.00 0.064
- Engsel Jendela 4.00 Buah 144,768.00 0.059
G PEKERJAAN ATAP DAN PLAFOND
1 Rangka kuda-kuda kayu (gording, papan reuter, murplat, 1.20 m3 14,140,683.85 5.734
nok, kaki kuda-kuda, balok gapit, balok kunci, balok tarik)
2 Penutup Atap (usuk dan reng) 1.35 m3 296,350.65 0.120
3 penutup atap Genteng 54.00 M2 12,987,216.00 5.266
4 bubungan 7.70 M1 913,689.70 0.371
5 Rangka Plafond Kayu Klas II 47.35 M2 4,063,650.97 1.648
6 plafond gipsum 47.35 M2 2,082,368.41 0.844
7 Kayu List Plafond 65.90 M1 1,060,528.70 0.430
I PEKERJAAN PENGECATAN
1 Cat Dinding Luar 93.10 m2 5,497,368.80 2.229
2 Cat Dinding Dalam 203.35 m2 6,551,733.65 2.657
3 Cat Kusen, Daun Pintu / Jendela 16.36 m2 1,013,252.21 0.411
Realisasi 10.741 %
Rencana 10.741 %
Deviasi - %
LAPORAN MINGGUAN
Minggu ke : Kedua
Tanggal : 08 s.d. 14 Agustus 2022
HASIL PEKERJAAN %
JUMLAH HRG NILAI
NO. URAIAN PEKERJAAN VOLUME BOBOT JENIS
(RP) BOBOT MINGGU LALU MINGGU INI JUMLAH
% PEKERJAAN
1 2 3 4 5 6 7 8 9 10
A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 1.00 Ls 1,000,000.00 0.406 1.00 Ls 1.00 Ls 0.406 100.000
2 Pengukuran / Pemasangan Bouplank 1.00 Ls 3,000,000.00 1.217 1.00 Ls 1.00 Ls 1.217 100.000
E PEKERJAAN LANTAI
1 Urugan Pasir Bawah Lantai 47.35 m3 11,994,936.33 4.864
2 Rabat Beton 1:3:5 47.35 m3 48,171,832.09 19.534
3 Pas. Keramik Lantai 20/20 2.50 m2 531,455.51 0.216
4 Pas. Keramik Lantai 40/40 44.85 m2 9,140,193.55 3.706
4 Jendela J2 60/80
Kusen Jendela 0.05 m3 638,827.20 0.259
Daun Jendela 2.00 Buah 1,972,276.00 0.800
- Kaca 5 mm 0.48 m2 72,393.12 0.029
- Hak Angin / Gagang Jendela 4.00 Buah 158,904.00 0.064
- Engsel Jendela 4.00 Buah 144,768.00 0.059
I PEKERJAAN PENGECATAN
1 Cat Dinding Luar 93.10 m2 5,497,368.80 2.229
2 Cat Dinding Dalam 203.35 m2 6,551,733.65 2.657
3 Cat Kusen, Daun Pintu / Jendela 16.36 m2 1,013,252.21 0.411
Realisasi 18.116 %
Rencana 18.116 %
Deviasi - %
BACK UP DATA VOLUME PEKERJAAN
A. PEKERJAAN PERSIAPAN
1. Pembersihan Lapangan
Lebar = 8.00 m
Panjang = 13 m
Luas = (PxL)
= 104.00 M²
2. Pemasangan Bouwplank
Lebar = 10.00 m
Panjang = 15 m
Keliling = 2 (P + L )
= 50.00 M
3 Urugan Pasir
Lebar atas = 0.80 m
Lebar bawah = 0.80 m
Tinggi = 0.10 m
Panjang = 55.00 m
Volume = (PxLxT)
= 1.65 M³
Volume = (2xTxP)
= M2
Volume = ( P x L x T ) x Unit
= M³
Volume = (( 2 x P ) + ( 2 x L) x T) x Jumlah
= M2
Volume = (PxLxT)
= M³
Ø Tul. Begel = mm
H
Jarak Begel = mm
Panjang Begel = mm
= ((B - (2xselimut beton)) + (H - (2xselimut beton)) + (2 x 6d))
=
Jumlah Begel = bh
= ( P Tul.Pokok / Jarak Begel) + 1
=
Volume = ( Jmlh Begel x P x Berat Jenis Tulangan )
= KG
3.d Bekisting Sloof
Tinggi = m
Panjang = m
Volume = (2xTxP)
= M2
Luas = (PxT)
= M²
Selasar
Tinggi = m
Panjang = m
Luas = (PxT)
= M²
Pengurang (Pintu, Jendela, Bouven, dll)
Pintu P1
Tinggi = m
Lebar = m
Jumlah = unit
Luas = ( L x T ) x unit
= M²
Luas = (PxT )
= M²
Luas = ( L x T ) x unit
= M²
Luas = ( P x L x T ) x unit
= 0.00 M³
Luas = ( P x L x T ) x unit
= 0.00 M³
Luas = ( P x L x T ) x unit
= M³
Luas = ( P x L) x unit
= M²
F PEKERJAAN PINTU, JENDELA DAN KUNCI
1 Kusen Pintu P1
Panjang = m
Lebar = m
Tinggi = m
Jumlah = unit
Luas = ( P x L x T ) x unit
= M³
2 Daun Pintu P1
Panjang = m
Lebar = m
Jumlah = unit
Luas = ( P x L ) x unit
= M²
3 Engsel Pintu P1
Buah = Bh
Jumlah = unit
Luas = ( Bh ) x unit
= Bh
4 Kunci Pintu P1
Buah = Bh
Jumlah = unit
Luas = ( Bh ) x unit
= Bh
5 Kusen Ventilasi P1
Panjang = m
Lebar = m
Tinggi = m
Jumlah = unit
Luas = ( P x L x T ) x unit
= M³
6 Papan Ventilasi P1
Panjang = m
Lebar = m
Tinggi = m
Jumlah = unit
Luas = ( P x L x T ) x unit
= M³
7 Kusen Jendela J1
Panjang = m
Lebar = m
Tinggi =
Jumlah = unit
Luas = ( P x L x T ) x unit
= M²
8 Daun Jendela J1
Panjang = m
Lebar = m
Jumlah = unit
Luas = ( P x L ) x unit
= M²
9 Kaca Jendela J1
Panjang = m
Lebar = m
Jumlah = unit
Luas = ( P x L ) x unit
= M²
10 Engsel Jendela J1
Buah = Bh
Jumlah = unit
Luas = ( Bh ) x unit
= Bh
11 Kunci Jendela J1
Buah = Bh
Jumlah = unit
Luas = ( Bh ) x unit
= Bh
Luas = ( Bh ) x unit
= Bh
13 Kusen Ventilasi J1
Panjang = m
Lebar = m
Tinggi =
Jumlah = unit
Luas = ( P x L x T ) x unit
= M³
14 Papan Ventilasi J1
Panjang = m
Lebar = m
Tinggi = m
Jumlah = unit
Luas = ( P x L x T ) x unit
= M³
15 Kusen Jendela J2
Panjang = m
Lebar = m
Tinggi = m
Jumlah = unit
Luas = ( P x L x T ) x unit
= M²
16 Daun Jendela J2
Panjang = m
Lebar = m
Jumlah = unit
Luas = ( P x L ) x unit
= M²
17 Kaca Jendela J2
Panjang = m
Lebar = m
Jumlah = unit
Luas = ( P x L ) x unit
= M²
18 Engsel Jendela J2
Buah = Bh
Jumlah = unit
Luas = ( Bh ) x unit
= Bh
19 Kunci Jendela J2
Buah = Bh
Jumlah = unit
Luas = ( Bh ) x unit
= Bh
Luas = ( Bh ) x unit
= Bh
21 Kusen Ventilasi J2
Panjang = m
Lebar = m
Tinggi = m
Jumlah = unit
Luas = ( P x L x T ) x unit
= M²
22 Papan Ventilasi J2
Panjang = m
Lebar = m
Tinggi = m
Jumlah = unit
Luas = ( P x L x T ) x unit
= M³
Volume = ( P x L x T ) x Jumlah
= M3
Volume = (PxL)
= M2
Volume = (PxU)
= M¹
Volume = (PxU)
= M¹
Rangka Plafond
Panjang = m
Lebar = m
Jumlah = Unit
Volume = ( P x L ) x unit
= M²
Plafon Triplek 6 mm M²
Saklar Tunggal Bh
Saklar dauble Bh
Stop Kontak Bh
I PEKERJAAN PENGECATAN
Cat Dinding Bata Luar Dan Dalam M²
Cat Plafond
Panjang = m
Lebar = m
Jumlah = Unit
Volume = (PxL)
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L ) x unit
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L) x unit
= M²
Luas = ( P x L) x unit
= M²
J PEKERJAAN PLUMBING
Pipa 3' Bh
Pipa 1/2' Bh
Closet Jongkok Bh
Wastafel Bh
BACK UP DATA VOLUME PEKERJAAN
GAMBAR
DAFTAR HARGA SATUAN PEKERJAAN BIDANG CIPTA KARYA K
(Sudah termasuk overhead dan profit, belum termasuk PPN) E
(Tahun 2019, Semester 2) T
E
HARGA SATUAN R
No KODE ANALISA URAIAN PEKERJAAN SATUAN
(Rp) A
N
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN Pebruari 2020 G
1 A.2.2.1.1. (K3) Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter m2 328,471.00 A
N
2 dihit A.2.2.1.2.1 Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter m2 216,014.00 revisi semua
3 dihit A.2.2.1.2.2 Pembuatan 1 m2 pagar sementara dari sasak bambu, tinggi 2,00 meter m2 91,102.00 revisi semua
4 dihit A.2.2.1.2.3 Pembuatan 1 m2 pagar sementara dari MMT, tinggi 2,00 meter m2 68,871.00
5 A.2.2.1.3. Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter m2 248,322.00 Revisi harga
6 A.2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank m' 113,723.00
7 A.2.2.1.5. (K3) Pembuatan 1 m2 kantor sementara lantai plesteran m2 2,454,424.00
8 A.2.2.1.6. (K3) Pembuatan 1 m2 rumah jaga (konstruksi kayu ) m2 2,826,065.00
9 A.2.2.1.7. (K3) Pembuatan 1 m2 gudang semen dan peralatan m2 2,355,688.00
10 A.2.2.1.8. (K3) Pembuatan 1 m2 bedeng pekerja m2 2,299,093.00
11 A.2.2.1.9. (K3) Pembersihan 1 m2 lapangan dan perataan m2 15,125.00
12 A.2.2.1.10. (K3) Pembuatan 1 m2 steger/perancah dari bambu m2 382,025.00
13 A.2.2.1.11. Pembuatan 1 buah kotak adukan ukuran 40cm x 50cm x 25cm buah 207,504.00 Harga papan
14 A.2.2.1.12. Pembuatan 1 m2 jalan sementara m2 183,383.00
15 A.2.2.1.13. Pembongkaran 1 m3 beton bertulang m3 255,027.00
16 dihit A.2.2.1.13.a Pembongkaran 1 m3 pasangan batu m3 219,726.00 analisa baru
17 dihit A.2.2.1.14. Pembongkaran 1 m3 dinding tembok bata m3 100,826.00 REVISI menj
18 A.2.2.1.15. Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm m2 104,914.00 revisi harga p
14 dihit A.3.3.1.12.2 Pengadaan & Pemancangan Cerucuk bambu petung Ø 10 cm, sedalam 2 meter titik 37,790.00
K
E
T
E
HARGA SATUAN R
No KODE ANALISA URAIAN PEKERJAAN SATUAN
(Rp) A
N
Pengadaan & Pemancangan Minipile / Triangle Pile 200x200x200 mm (drop
15 dihit A.3.3.1.13.1 m' 295,343.00 GHarga lama i
hammer) A
N
16 dihit A.3.3.1.13.2 Pengadaan & Pemancangan Minipile / Triangle Pile 200x200x200 mm (mekanis) m' 211,918.00
Harga lama in
Pengadaan & Pemancangan Minipile / Triangle Pile 250x250x250 mm (drop
17 dihit A.3.3.1.13.3 m' 339,770.00 Harga lama i
hammer)
18 dihit A.3.3.1.13.4 Pengadaan & Pemancangan Minipile / Triangle Pile 250x250x250 mm (mekanis) m' 284,745.00 Harga lama i
20 dihit A.3.3.1.13.6 Pengadaan & Pemancangan Minipile / Triangle Pile 280x280x280 mm (mekanis) m' 330,998.00 Harga lama i
22 dihit A.3.3.1.13.8 Pengadaan & Pemancangan Minipile / Triangle Pile 300x300x300 mm (mekanis) m' 365,486.00 Harga lama i
24 dihit A.3.3.1.13.10 Pengadaan & Pemancangan Minipile / Triangle Pile 320x320x320 mm (mekanis) m' 381,556.00 Harga lama i
25 dihit A.3.3.1.13.11 Pengadaan & Pemancangan Minipile / kotak 300x300 mm K.500 (drop hammer) m' 576,575.00
26 dihit A.3.3.1.13.12 Pengadaan & Pemancangan Minipile / kotak 300x300 mm K.500 (mekanis) m' 503,567.00
27 dihit A.3.3.1.13.13 Pengadaan & Pemancangan Minipile / kotak 400x400 mm K.500 (drop hammer) m' 617,840.00
28 dihit A.3.3.1.13.14 Pengadaan & Pemancangan Minipile / kotak 400x400 mm K.500 (mekanis) m' 538,777.00
45 dihit A.4.2.1.24.a Pemasangan 1 M2 pasang kuda-kuda baja ringan + reng untuk atap asbes / spandek m2 254,700.00
Pemasangan Daun Pintu Rangka Alumunium warna natural / silver, Panil Kaca
45 dihit A.4.2.1.25 buah 1,092,500.00 kenaikan har
Rayban 5 mm Ukuran 70/210 cm
Pemasangan Daun Pintu Rangka Alumunium warna Powder Coating, Panil Kaca
46 dihit A.4.2.1.26 buah 1,169,747.00
Rayban 5 mm Uk.70/210 cm
Pemasangan Daun Pintu Rangka Alumunium warna natural / silver, Panil Kaca
46 dihit A.4.2.1.27 buah 1,148,850.00 kenaikan har
Rayban 5 mm Ukuran 80/210 cm
Pemasangan Daun Pintu Rangka Alumunium warna Powder Coating, Panil Kaca
47 dihit A.4.2.1.28 buah 1,229,000.00
Rayban 5 mm Ukuran 80/210 cm
Pemasangan Daun Pintu Rangka Alumunium warna natural / silver, Panil Kaca
47 dihit A.4.2.1.29 buah 1,205,199.00 kenaikan har
Rayban 5 mm Ukuran 90/210 cm
Pemasangan Daun Pintu Rangka Alumunium warna Powder Coating, Panil Kaca
48 dihit A.4.2.1.30 buah 1,288,254.00
Rayban 5 mm Ukuran 90/210 cm
Pemasangan Daun Jendela Rangka Alumunium warna natural / silver, Panil Kaca
48 dihit A.4.2.1.31 buah 661,572.00 kenaikan har
Rayban 5 mm Ukuran 50/100 cm
Pemasangan Daun Jendela Rangka Alumunium warna Powder Coating, Panil Kaca
49 dihit A.4.2.1.32 buah 696,178.00
Rayban 5 mm Ukuran 50/100 cm
Pemasangan Daun Jendela Rangka Alumunium warna natural / silver, Panil Kaca
49 dihit A.4.2.1.33 buah 758,073.00 kenaikan har
Rayban 5 mm Ukuran 60/120 cm
Pemasangan Daun Jendela Rangka Alumunium warna Powder Coating, Panil Kaca
50 dihit A.4.2.1.34 buah 799,939.00
Rayban 5 mm Ukuran 60/120 cm
Pemasangan Daun Jendela Rangka Alumunium warna natural / silver, Panil Kaca
50 dihit A.4.2.1.35 buah 884,410.00 kenaikan har
Rayban 5 mm Ukuran 70/140 cm
Pemasangan Daun Jendela Rangka Alumunium warna Powder Coating, Panil Kaca
51 dihit A.4.2.1.36 buah 933,536.00
Rayban 5 mm Ukuran 70/140 cm
Pemasangan Daun Jendela Rangka Alumunium warna natural / silver, Panil Kaca
51 dihit A.4.2.1.37 buah 638,094.00 kenaikan har
Rayban 5 mm Ukuran 60/80 cm
Pemasangan Daun Jendela Rangka Alumunium warna Powder Coating, Panil Kaca
52 dihit A.4.2.1.38 buah 670,280.00
Rayban 5 mm Ukuran 60/80 cm
Pemasangan Jendela Boven Rangka Alumunium Panil Kaca Rayban 5 mm Ukuran
52 dihit A.4.2.1.39 buah 491,379.00 kenaikan har
50/40 cm
K
E
T
E
HARGA SATUAN R
No KODE ANALISA URAIAN PEKERJAAN SATUAN
(Rp) A
N
Pemasangan Jendela Boven Rangka Alumunium Panil Kaca Rayban 5 mm Ukuran
53 dihit A.4.2.1.40 buah 518,116.00 Gkenaikan har
60/40 cm A
Pemasangan Jendela Boven Rangka Alumunium Panil Kaca Rayban 5 mm Ukuran N
54 dihit A.4.2.1.41 buah 544,852.00 kenaikan har
70/40 cm
Pemasangan Jendela Boven Rangka Alumunium Panil Kaca Rayban 5 mm Ukuran
55 dihit A.4.2.1.42 buah 571,588.00 kenaikan har
80/40 cm
Pemasangan Jendela Boven Rangka Alumunium Panil Kaca Rayban 5 mm Ukuran
56 dihit A.4.2.1.43 buah 598,324.00 kenaikan har
90/40 cm
Pemasangan Daun Pintu Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran 70/210
57 dihit A.4.2.1.44 buah 2,257,728.00
cm
Pemasangan Daun Pintu Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran 80/210
58 dihit A.4.2.1.45 buah 2,549,001.00
cm
Pemasangan Daun Pintu Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran 90/210
59 dihit A.4.2.1.46 buah 2,840,275.00
cm
Pemasangan Daun Jendela Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
60 dihit A.4.2.1.47 buah 991,401.00
50/100 cm
Pemasangan Daun Jendela Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
61 dihit A.4.2.1.48 buah 1,299,301.00
60/120 cm
Pemasangan Daun Jendela Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
62 dihit A.4.2.1.49 buah 1,658,806.00
70/140 cm
Pemasangan Daun Jendela Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
63 dihit A.4.2.1.50 buah 986,138.00
60/80 cm
Pemasangan Jendela Boven Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
64 dihit A.4.2.1.51 buah 577,636.00
50/40 cm
Pemasangan Jendela Boven Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
65 dihit A.4.2.1.52 buah 630,126.00
60/40 cm
Pemasangan Jendela Boven Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
66 dihit A.4.2.1.53 buah 682,615.00
70/40 cm
Pemasangan Jendela Boven Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
67 dihit A.4.2.1.54 buah 735,104.00
80/40 cm
Pemasangan Jendela Boven Rangka Kayu Jati Panil Kaca Rayban 5 mm Ukuran
68 dihit A.4.2.1.55 buah 787,593.00
90/40 cm
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP :
1 A.4.4.1.1. m2 284,746.00 Revisi harga
2 PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP :
2 A.4.4.1.2. m2 273,918.00 Revisi harga
3 PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 4
3 A.4.4.1.3. m2 265,541.00 Revisi harga
PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 5
4 A.4.4.1.4. m2 262,805.00 Revisi harga
PP
Pemasangan 1 m2 dinding Bata Merah (5x11x22) cm tebal 1 batu campuran 1 SP : 6
5 A.4.4.1.5. m2 265,258.00 Revisi harga
PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP :
6 A.4.4.1.6 m2 249,751.00 Revisi harga
3KP : 10PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :
7 A.4.4.1.7 m2 137,594.00 Revisi harga
2PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :
8 A.4.4.1.8 m2 131,819.00 Revisi harga
3PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran
9 A.4.4.1.9 m2 128,877.00 Revisi harga
1SP :4PP
Pemasangan 1 m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1 SP :
10 A.4.4.1.10 m2 127,048.00 Revisi harga
5 PP
Pemasangan 1 m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1 SP :
11 A.4.4.1.11 m2 126,652.00 Revisi harga
6 PP
Pemasangan 1 m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :
12 A.4.4.1.12 m2 124,437.00 Revisi harga
8 PP
Pemasangan 1 m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :
13 A.4.4.1.13 m2 125,917.00 Revisi harga
3KP :10PP
Pemasangan 1 m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SM :
14 A.4.4.1.14 m2 107,985.00 Revisi harga
1KP :1PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM :
15 A.4.4.1.15 m2 110,694.00 Revisi harga
1KP :2PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal ½ batu dengan semen
16 dihit A.4.4.1.15.1 m2 209,302.00 Revisi harga
instan
17 A.4.4.1.16 Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 3PP m2 619,025.00 Revisi harga
18 A.4.4.1.17 Pemasangan 1 m2 dinding conblock HB20 campuran 1SP:4PP m2 627,396.00 Revisi harga
K
E
T
E
HARGA SATUAN R
No KODE ANALISA URAIAN PEKERJAAN SATUAN
(Rp) A
N
19 A.4.4.1.18 Pemasangan 1 m2 dinding conblock HB15 campuran 1SP :3PP m2 430,848.00 GRevisi harga
20 A.4.4.1.19 Pemasangan 1 m2 dinding conblock HB15 campuran 1SP :4PP m2 436,746.00 ARevisi harga
21 A.4.4.1.20 Pemasangan 1 m2 dinding conblock HB10 campuran 1SP :3PP m2 267,958.00 NRevisi harga
22 A.4.4.1.21 Pemasangan 1 m2 dinding conblock HB10 campuran 1SP :4PP m2 272,918.00 Revisi harga
23 A.4.4.1.22 Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1SP : 3PP m2 351,664.00 Revisi harga
24 A.4.4.1.23 Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1SP : 4PP m2 351,189.00 Revisi harga
25 dihit A.4.4.1.23.1 Pemasangan 1 m2 dinding terawang (rooster) 20 x 20 cm campuran 1SP : 4PP m2 215,820.00 revisi koef PC
26 dihit A.4.4.1.23.2 Pemasangan 1 m2 dinding terawang (rooster) 40 x 20 cm campuran 1SP : 4PP m2 182,380.00 revisi koef PC
27 dihit A.4.4.1.23.3 Pemasangan 1 m2 dinding terawang (rooster) genteng kecil m2 243,567.00 revisi koef PC
28 dihit A.4.4.1.23.4 Pemasangan 1 m2 dinding terawang (rooster) genteng sedang m2 342,815.00 revisi koef PC
29 dihit A.4.4.1.23.5 Pemasangan 1 m2 dinding terawang (rooster) genteng besar m2 362,175.00 revisi koef PC
30 dihit A.4.4.1.23.6 Pemasangan 1 m2 dinding terawang (rooster) keramik 20 x 20 cm m2 1,241,570.00 revisi koef PC
31 dihit A.4.4.1.23.7 Pemasangan 1 m2 dinding terawang (rooster) keramik 30 x 30 cm m2 887,012.00 revisi koef PC
32 dihit A.4.4.1.23.8 Pemasangan 1 m2 dinding terawang (rooster) GRC m2 980,815.00 Revisi harga s
33 A.4.4.1.24 Pemasangan 1 m2 dinding bata berongga ekspose 12x11x24 campuran 1SP:3PP m2 212,342.00 harga bata b
34 A.4.4.1.25 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai. m2 321,744.00
35 A.4.4.1.26 Pemasangan 1 m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai m2 324,303.00
36 dihit A.4.4.1.27 Pemasangan 1m2 Glass Block 20x20 cm m2 648,862.00 Revisi harga
37 dihit A.4.4.1.28 Pasang Partisi Dobel Gipsum Board 9 mm Rangka Hollow Meni 4 x 4 cm m2 286,073.00
38 dihit A.4.4.1.29 Pasang Partisi Dobel Plywood 6 mm Rangka Hollow Meni 4 x 4 cm m2 312,961.00
39 dihit A.4.4.1.30 Pemasangan 1 m2 Penutup Dinding / Pintu dg HPL Lapis Plywood 9 mm warna polos m2 455,240.00 Harga plywo
40 dihit A.4.4.1.31 Pemasangan 1 m2 Penutup Dinding / Pintu dg HPL Lapis Plywood 9 mm warna kayu m2 466,324.00
Harga plywoo
41 dihit A.4.4.1.32 Pasang Partisi Dobel GRC Board 6 mm Rangka Hollow Meni 4 x 4 cm m2 315,902.00
42 dihit A.4.4.1.33 Pasang Partisi Dobel Gipsum Board 9 mm Rangka Metal Stud / Alumunium m2 208,303.00
43 dihit A.4.4.1.34 Pasang Partisi Dobel Plywood 6 mm Rangka Metal Stud / Alumunium m2 235,191.00
44 dihit A.4.4.1.35 Pasang Partisi Dobel GRC Board 6 mm Rangka Metal Stud / Alumunium m2 238,132.00
37 A.4.4.3.37. Pemasangan 1 m2 Lantai keramik ukuran 10cm x 40 cm untuk variasi/border m2 906,669.00 harga lama t
38 A.4.4.3.38. Pemasangan 1 m2 lantai keramik mozaik ukuran 30cm x 30cm m2 313,359.00 Revisi harga
39 A.4.4.3.39. Pemasangan 1 m’ plint keramik ukuran 10cm x 20cm m' 78,416.00 Revisi harga
40 A.4.4.3.40. Pemasangan 1 m’ plint keramik ukuran 10cm x 10cm m' 107,979.00 Revisi harga
41 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m' 43,008.00 harga kerami
42 A.4.4.3.42. Pemasangan 1 m’ plint internal cove artistik 5cm x 5cm x 20cm m' 397,075.00 Revisi harga
43 A.4.4.3.43. Pemasangan 1 m2 lantai marmer ukuran 100cm x 100cm m2 1,309,189.00 Revisi harga
44 A.4.4.3.44. Pemasangan 1 m2 lantai karpet m2 68,711.00 Harga lem ai
45 A.4.4.3.45. Pemasangan 1 m2 underlayer (pelapis bawah karpet) m2 100,518.00 Harga lem ai
46 A.4.4.3.46. Pemasangan 1 m2 lantai parquet kayu m2 368,142.00
47 A.4.4.3.47. Pemasangan 1 m2 lantai kayu gymfloor m2 495,192.00
48 A.4.4.3.48. Pemasangan 1 m2 dinding porslen 11cm x 11cm m2 240,268.00 Revisi harga
49 A.4.4.3.49. Pemasangan 1 m2 dinding porslen 10cm x 20cm m2 355,191.00 harga keram
50 A.4.4.3.50. Pemasangan 1 m2 dinding porslen 20cm x 20cm (putih) m2 256,136.00 Revisi harga
51 A.4.4.3.51. Pemasangan 1 m2 dinding keramik artistik 10cm x 20cm (Setara Roman) m2 296,891.00 harga lama t
52 A.4.4.3.52. Pemasangan 1 m2 dinding keramik artistik 5cm x 20cm (Setara Roman) m2 736,616.00 harga lama t
53 A.4.4.3.53. Pemasangan 1 m2 dinding keramik 10cm x 20cm (Setara Milan, Roman, KIA) m2 355,191.00 harga keram
54 A.4.4.3.54. Pemasangan 1 m2 dinding keramik artistik 20cm x 20cm (Setara Roman) m2 295,186.00 revisi jenis ke
55 dihit A.4.4.3.54.1a Pemasangan 1 m2 dinding keramik 20cm x 25cm (putih) (Setara Milan, Roman, KIA) m2 261,911.00 Revisi harga
56 dihit A.4.4.3.54.1b Pemasangan 1 m2 dinding keramik 20cm x 25cm (motif) (Setara Milan, Roman, KIA) m2 258,446.00 Revisi harga
57 dihit A.4.4.3.54.2.a Pemasangan 1 m2 Dinding Keramik 20 x 40 cm (Setara Milan, Roman, KIA) m2 292,601.00 Revisi harga
58 dihit A.4.4.3.54.2.b Pemasangan 1 m2 Dinding Keramik 25 x 40 cm (putih) (Setara Milan, Roman, KIA) m2 257,126.00
59 dihit A.4.4.3.54.2.c Pemasangan 1 m2 Dinding Keramik 25 x 40 cm (motif) (Setara Milan, Roman, KIA) m2 284,076.00
60 dihit A.4.4.3.54.3 Pemasangan 1 m2 Dinding Keramik 25 x 50 cm (Setara Milan, Roman, KIA) m2 323,786.00 Revisi harga
61 dihit A.4.4.3.54.4 Pemasangan 1 m2 Dinding Keramik 20 x 60 cm (Setara Milan, Roman, KIA) m2 424,931.00 Revisi harga
62 dihit A.4.4.3.54.5 Pemasangan 1 m2 Dinding Keramik 30 x 60 cm (Setara Milan, Roman, KIA) m2 345,511.00 Revisi harga
63 dihit A.4.4.3.54.6 Pemasangan 1 m2 Dinding Keramik 25 x 33 cm (Setara Milan, Roman, KIA) m2 319,331.00 Revisi harga
64 dihit A.4.4.3.54.7 Pemasangan 1 m2 Dinding Keramik 32,5 x 65,5 cm (Setara Milan, Roman, KIA) m2 339,076.00 Revisi harga
65 dihit A.4.4.3.54.8 Pemasangan 1 m Step Tile 30x30 cm m¹ 99,047.00 Revisi harga
66 dihit A.4.4.3.54.9 Pemasangan 1 m Step Tile 30x60 cm m¹ 86,534.00 Revisi harga
67 dihit A.4.4.3.54.10 Pemasangan 1 m Step Tile 30x120 cm m¹ 151,599.00 Revisi harga
K
E
T
E
HARGA SATUAN R
No KODE ANALISA URAIAN PEKERJAAN SATUAN
(Rp) A
N
68 dihit A.4.4.3.54.11 Pemasangan 1 m Step Nosing Keramik 10x40 cm m' 119,974.00 GRevisi harga
69 dihit A.4.4.3.54.12 Pemasangan 1 m Step Nosing Granit 10x60 cm m' 96,599.00 ARevisi harga
70 dihit A.4.4.3.54.13 Pemasangan 1 m Step Nosing Allumunium m' 331,724.00 NRevisi harga
71 dihit A.4.4.3.54.14 Pemasangan 1 m Step Nosing Karet m' 121,635.00 Revisi harga
72 dihit A.4.4.3.54.15 Pemasangan 1 m Step Nosing Allumunium Karet m' 345,485.00 Revisi harga
73 dihit A.4.4.3.54.16 Pemasangan 1 m2 Kuku Macan 10 cm m2 55,799.00 Revisi harga
74 dihit A.4.4.3.54.17.a Pemasangan 1 m Keramik Border Dinding 5/25 cm m2 98,299.00 Revisi harga
75 dihit A.4.4.3.54.17.b Pemasangan 1 m Keramik Border Dinding 5-8/20 cm m2 75,474.00 Revisi harga
76 dihit A.4.4.3.54.18 Pemasangan 1 m Keramik Border Dinding 10/40 cm m2 75,474.00
77 dihit A.4.4.3.54.19 Pemasangan 1 m Keramik Border Dinding 10/50 cm m2 60,459.00 Revisi harga
78 dihit A.4.4.3.54.20 Pemasangan 1 m Keramik Border Dinding 10/60 cm m¹ 58,149.00 Revisi harga
79 dihit A.4.4.3.54.21 Pemasangan 1 m Keramik Homogenous 40 x 40 cm (setara Granito) m¹ 414,880.00 Revisi harga
80 dihit A.4.4.3.54.22 Pemasangan 1 m2 Keramik Homogenous 60 x 30 cm (setara Granito) m2 327,897.00 Revisi harga s
81 dihit A.4.4.3.54.23 Pemasangan 1 m2 Keramik Homogenous 60 x 60 cm (setara Granito) m2 642,416.00 Revisi harga
82 dihit A.4.4.3.54.24 Pemasangan 1 m2 Keramik Homogenous 80 x 80 cm (setara Granito) m2 813,014.00 Revisi harga
83 A.4.4.3.55. Pemasangan 1 m2 dinding marmer 100cm x 100cm m2 1,412,901.00 Revisi harga
84 A.4.4.3.56. Pemasangan 1 m2 dinding bata pelapis 3cm x 7cm x 24cm m2 392,009.00 harga batu te
85 A.4.4.3.57. Pemasangan 1 m2 dinding batu paras m2 245,047.00 Revisi harga
86 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel hitam m2 293,447.00 Revisi harga
87 dihit A.4.4.3.58.1 Pemasangan 1 m2 Batu Alam Andesit Polos Bakar m2 284,372.00 Revisi harga
88 dihit A.4.4.3.58.2 Pemasangan 1 m2 Batu Alam Andesit Bintik Bakar m2 287,397.00 Revisi harga
89 dihit A.4.4.3.58.3 Pemasangan 1 m2 Batu Alam Andesit Alur Bakar m2 296,472.00 Revisi harga
90 dihit A.4.4.3.58.4 Pemasangan 1 m2 Batu Alam Andesit Motif m2 287,397.00 Revisi harga
91 dihit A.4.4.3.58.5 Pemasangan 1 m2 Batu Candi Hitam m2 293,447.00 Revisi harga
92 dihit A.4.4.3.58.6 Pemasangan 1 m2 Batu Candi Warna m2 260,777.00 Revisi harga
93 dihit A.4.4.3.58.7 Pemasangan 1 m2 Batu Wall Clading m2 334,224.00 harga batu w
94 dihit A.4.4.3.58.8 Pemasangan 1 m2 Batu Sikat (batu mozaik) m2 285,301.00 Revisi harga
95 A.4.4.3.59. Pemasangan 1 m2 lantai vynil ukuran 30cm x 30cm m2 221,019.00
96 A.4.4.3.60. Pemasangan 1 m2 wallpaper lebar 50 cm m2 90,926.00 Harga lama b
97 A.4.4.3.61. Pemasangan 1 m2 floor harderner m2 45,683.00
98 A.4.4.3.62. Pemasangan 1 m’ plint vynil 15cm x 30cm m' 41,941.00
99 A.4.4.3.63. Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm m' 69,993.00
Pemasangan 1 m2 paving block natural tebal 6 cm (K.250)(alas dengan pasir
100 A.4.4.3.64. m2 201,256.00
muntilan)
101 dihit A.4.4.3.64.a Pemasangan 1 m2 paving block natural tebal 6 cm (K.250)(alas dengan pasir urug) m2 191,335.00
Revisi harga p
Pemasangan 1 m2 paving block natural tebal 8 cm (K.300)(alas dengan pasir
102 dihit A.4.4.3.65.a m2 237,307.00
muntilan)
103 dihit A.4.4.3.65.b Pemasangan 1 m2 paving block natural tebal 8 cm (K.300)(alas dengan pasir urug) m2 227,387.00 Revisi harga
1 A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I (jati) m3 32,548,175.00
Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II
2 A.4.6.1.2. m3 17,532,900.00 Harga kayu b
(Bengkirai)
3 A.4.6.1.3. Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II (Bengkirai) m2 733,194.00
4 A.4.6.1.4. Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III (kruing) m2 524,194.00 Harga kayu k
5 A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II (Bengkirai) m2 1,062,325.00
6 dihit A.4.6.1.5.a Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I (Jati) m2 1,713,525.00 analisa baru
7 A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas II (Bengkirai) m2 736,450.00
8 A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas II (Bengkirai) m2 1,397,605.00
Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (Lebar
9 A.4.6.1.8. m2 768,603.00
s/d 90 cm)
10 A.4.6.1.9. Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas II (Bengkirai) m2 826,512.00
32 A.4.6.1.25. Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas III (kruing) m2 406,373.00
K
E
T
E
HARGA SATUAN R
No KODE ANALISA URAIAN PEKERJAAN SATUAN
(Rp) A
N
33 A.4.6.1.26. Pemasangan 1 m2 dinding lambrisering dari Kayu Papan kayu kelas II (Bengkirai) m2 401,885.00 G
34 A.4.6.1.27. Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120 x 240) cm m2 38,945.00 AHarga plywo
35 A.4.6.1.28. Pemasangan 1 m2 dinding bilik bambu, rangka kayu kelas III (kruing) m2 150,103.00 N
36 dihit A.4.6.1.29. Pembuatan dan pemasangan 1 m3 Kusen pintu dan jendela kayu Kruing m3 13,308,900.00
37 dihit A.4.6.1.30. Pembuatan dan Pemasangan 1 m2 Daun Pintu Panel, Kayu Kruing m2 845,900.00
38 dihit A.4.6.1.31. Pembuatan dan Pemasangan 1 m2 Pintu dan Jendela Kaca Kayu Kruing m2 611,050.00
Pembuatan dan Pemasangan 1 m2 Pintu Plywood Rangkap Rangka Kayu Kruing (L
39 dihit A.4.6.1.32. m2 686,378.00 Harga plywo
s/d 90 cm)
Pembuatan dan Pemasangan 1 m2 Pintu Plywood Rangkap Rangka Expose Kayu
40 dihit A.4.6.1.33. m2 741,152.00 Harga plywo
Kruing
Pembuatan dan Pemasangan 1 m3 Konstruksi Kuda-Kuda Konvensional Kayu Kruing
41 dihit A.4.6.1.34. m3 11,785,730.00
Bentang 6 m
42 dihit A.4.6.1.35. Pemasangan 1 m3 Konstruksi Gording, Kayu Kruing m3 10,941,810.00
43 dihit A.4.6.1.36. Pemasangan 1 m2 Rangka Atap Genteng Keramik, Kayu Kruing m2 155,589.00 Harga kruing
44 dihit A.4.6.1.37. Pemasangan 1 m2 Rangka Atap Genteng Beton, Kayu Kruing m2 145,986.00 Harga kruing
Pembuatan dan Pemasangan 1 m3 Konstruksi Kuda - Kuda Konfensional Kayu Lokal
45 dihit A.4.6.1.38. m3 5,675,230.00
6m
46 dihit A.4.6.1.39. Pemasangan 1 m2 Rangka Atap Genteng Kecil, Kayu Lokal m2 67,100.00 Link lama pa
47 dihit A.4.6.1.40. Pemasangan 1 m3 Rangka Dinding Pemisah (60x120) cm Kayu Lokal m3 162,019.00 Link lama pa
48 dihit A.4.6.1.41.a Pembuatan dan Pemasangan 1 m2 Pintu dan Jendela Kaca Kayu Lokal m2 432,850.00 Harga papan
49 dihit A.4.6.1.41.b Pembuatan dan Pemasangan 1 m2 Pintu dan Jendela Kayu jati panel Kaca m2 1,127,170.00
50 dihit A.4.6.1.42. Pembuatan dan Pemasangan 1 m2 Kusen Pintu dan Jendela Kayu Lokal m2 6,642,900.00 Link lama pa
Pengecatan 1 m2 tembok baru ( 1 lapis cat dasar, 2 lapis cat penutup) Interior
11 dihit A.4.7.1.10.a setara Mowilex (Decorcryl, Dulux Pentalite, Nippon) m2 25,696.00
Pengecatan 1 m2 tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat
12 dihit A.4.7.1.10.b penutup) Exterior setara Mowilex (Decorcryl, Dulux Pentalite, Nippon) m2 59,048.00
Pengecatan 1 m2 tembok baru ( 1 lapis cat dasar, 2 lapis cat penutup) Exterior
13 dihit A.4.7.1.10.c setara Mowilex (Decorcryl, Dulux Pentalite, Nippon) m2 52,448.00
Pengecatan 1 m2 tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat
14 dihit A.4.7.1.10.d penutup) Interior setara Catylac (Vinilex, Property, Danacryl, Avitex) m2 26,488.00
Pengecatan 1 m2 tembok baru ( 1 lapis cat dasar, 2 lapis cat penutup) Interior
15 dihit A.4.7.1.10.e setara Catylac (Vinilex, Property, Danacryl, Avitex) m2 19,888.00
Pengecatan 1 m2 tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat
16 dihit A.4.7.1.10.f penutup) Exterior setara Catylac (Vinilex, Property, Danacryl, Avitex) m2 33,748.00
Pengecatan 1 m2 tembok baru ( 1 lapis cat dasar, 2 lapis cat penutup) Exterior
17 dihit A.4.7.1.10.g setara Catylac (Vinilex, Property, Danacryl, Avitex) m2 27,148.00
Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup) Interior
18 A.4.7.1.11. m2 21,213.00
setara Mowilex (Decorcryl, Dulux Pentalite, Nippon)
Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup) Exterior
19 dihit A.4.7.1.11.a m2 40,470.00
setara Mowilex (Decorcryl, Dulux Pentalite, Nippon)
Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup) Interior
20 dihit A.4.7.1.11.b m2 16,644.00
setara Catylac (Vinilex, Property, Danacryl, Avitex)
Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup) Exterior
21 dihit A.4.7.1.11.c m2 22,089.00
setara Catylac (Vinilex, Property, Danacryl, Avitex)
22 A.4.7.1.12. Pelaburan 1 m2 tembok dengan kalkarium m2 8,695.00
23 A.4.7.1.13. Pelaburan 1 m2 tembok dengan kapur sirih m2 19,104.00
24 A.4.7.1.14. Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan) m2 11,206.00
25 A.4.7.1.15. Pemasangan 1 m2 wallpaper minimalis (motif sederhana) m2 92,358.00
26 dihit A.4.7.1.15.a Pemasangan 1 m2 wallpaper Artistik ( motif warna warni ) m2 92,358.00
27 A.4.7.1.16. Pengecatan 1 m2 permukaan besi / baja dengan menie besi m2 29,700.00
28 A.4.7.1.17. Pengecatan 1 m2 permukaan besi / baja dengan menie besi dengan perancah m2 55,632.00
29 A.4.7.1.18. Pengecatan 1 m2 permukaan besi / baja galvanis secara manual 4 lapis m2 73,869.00
Pengecatan 1 m2 permukaan besi / baja galvanis secara manual sistem 1 lapis cat
30 A.4.7.1.19. m2 36,886.00
mutakhir
31 A.4.7.1.20. Pengecatan 1 m2 permukaan besi / baja galvanis secara manual sistem 3 lapis m2 160,366.00
Pengecatan 1 m2 permukaan besi / baja galvanis secara semprot sistem 3 lapis cat
32 A.4.7.1.21. m2 143,858.00
mutakhir
33 A.4.7.1.22. Plituran 10 m2 dengan plitur melamic 10 m2 2,139,115.00
34 dihit A.4.7.1.23. Pengecatan 1 m2 kerb dengan cat genteng m2 41,309.00
35 dihit A.4.7.1.24. Pengecatan 1 m2 Kerb dengan cat besi m2 41,749.00
36 dihit A.4.7.1.25. Pelapisan 1 m2 batu alam dengan cat coating (Natural / Hitam / Gloss) m2 41,115.00
37 dihit A.4.7.1.26. Pengecatan 1 m2 Tembok Dengan Cat Waterproofing ( 3 Lapis ) m2 34,870.00
38 dihit A.4.7.1.27.a Pengecatan 1 m2 Plat Atap/Talang Dengan Lapisan Membran Waterproofing m2 81,136.00
39 dihit A.4.7.1.27.b Pengecatan 1 m2 Plat Atap/Talang Dengan Cat Waterproofing ( 3 lapis ) m2 34,793.00
40 dihit A.4.7.1.28. 1 m2 pengecatan tembok dengan cat mengkilap m2 34,870.00 harga cat da
41 dihit A.4.7.1.29. 1 m2 pengecatan permukaan besi dan baja dengan cat besi 3 lapis cat penutup m2 53,663.00
K
E
T
E
HARGA SATUAN R
No KODE ANALISA URAIAN PEKERJAAN SATUAN
(Rp) A
N
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG G
1 A.5.1.1.1. (K3) Pemasangan 1 buah closet duduk/monoblock (biasa) buah 1,556,830.00 A
2 dihit A.5.1.1 1.a Pemasangan 1 buah closet duduk/monoblock (setara INA) dengan jet washer buah 3,480,730.00 N
3 dihit A.5.1.1 1.b Pemasangan 1 buah closet duduk/monoblock (setara TOTO) dengan jet washer buah 3,364,130.00
4 A.5.1.1 2. Pemasangan 1 buah closet jongkok porselen (biasa) buah 429,682.00 Revisi harga
5 dihit A.5.1.1 2.a Pemasangan 1 buah closet jongkok porselen (Setara INA) buah 459,932.00 Revisi harga
6 A.5.1.1 3. Pemasangan 1 buah closet jongkok teraso buah 463,617.00 Revisi harga
7 A.5.1.1 4. (K3) Pemasangan 1 buah urinoir buah 2,091,727.00 Revisi harga
8 A.5.1.1 5. (K3) Pemasangan 1 buah wastafel buah 1,083,742.00
9 A.5.1.1 6. (K3) Pemasangan 1 buah bathcuip porselen buah 3,926,109.00
10 dihit A.5.1.1 7.a Pemasangan 1 buah Reservoir fibreglass vol 1 m3 (Roof tank) buah 3,096,390.00
11 A.5.1.1 9. Pemasangan 1 buah bak mandi teraso vol 0,30 m3 buah 1,519,430.00
12 dihit A.5.1.1 10.a Pemasangan 1 buah bak mandi fibreglass vol 120 liter (oval) buah 548,326.00
13 dihit A.5.1.1 10.b Pemasangan 1 buah bak mandi fibreglass vol 120 liter (kotak) buah 398,392.00
14 A.5.1.1 11. Pemasangan 1 buah bak beton volume 1 m3 buah 5,638,842.00
15 A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel buah 560,587.00
16 A.5.1.1 13. Pemasangan 1 buah bak cuci piring teraso buah 1,040,022.00 Revisi harga
17 A.5.1.1 14. Pemasangan 1 buah floor drain buah 114,262.00
18 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm buah 478,252.00 Revisi harga
19 A.5.1.1 16. Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm tinggi 50 cm buah 713,108.00 Revisi harga
20 A.5.1.1 17. Pemasangan 1 buah bak kontrol pasangan bata 60cm x60cm tinggi 65 cm buah 868,117.00 Revisi harga
21 A.5.1.1 18. Pemasangan 1 m’ pipa galvanis medium A diameter ½” buah 64,587.00
22 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” (Stainles steel) buah 121,522.00
23 dihit A.5.1.1 19.a Pemasangan 1 buah kran diameter ½” atau 3/4” (Plastik) buah 61,022.00
24 dihit A.5.1.1 19.b Pemasangan 1 buah shower setara ONDA buah 226,022.00
24 A.5.1.1 20. Pemasangan 1 m’ pipa galvanis medium B diameter 3/4” m' 67,171.00 Revisi harga
25 A.5.1.1 21. Pemasangan 1 m’ pipa galvanis medium B diameter 1” m' 77,863.00 Revisi harga
26 A.5.1.1 22. Pemasangan 1 m’ pipa galvanis medium B diameter 1 ½” m' 117,991.00 Revisi harga
27 dihit A.5.1.1 22.a Pemasangan 1 m’ pipa galvanis medium A diameter 1 ½” m' 166,610.00
28 A.5.1.1 23. Pemasangan 1 m’ pipa galvanis medium B diameter 3” m' 233,167.00 Revisi harga
29 A.5.1.1 24. Pemasangan 1 m’ pipa galvanis medium B diameter 4” m' 288,409.00 Revisi harga
30 dihit A.5.1.1 24.a Pemasangan 1 m’ pipa galvanis medium A diameter 4” m' 493,636.00
31 A.5.1.1 25. Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2” m' 23,331.00 Revisi harga
32 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m' 25,113.00 Revisi harga
33 A.5.1.1 27. Pemasangan 1 m’ pipa PVC tipe AW diameter 1” m' 28,677.00 Revisi harga p
34 A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe AW diameter 11/2” m' 50,143.00 Revisi harga
35 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m' 64,399.00 Revisi harga
36 A.5.1.1 30. Pemasangan 1 m’ pipa PVC tipe AW diameter 21/2” m' 86,740.00 Revisi harga
37 A.5.1.1 31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3” m' 113,470.00 Revisi harga
38 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m' 152,674.00 Revisi harga
39 A.5.1.1 33. Pemasangan 1 m’ pipa air limbah jenis pipa tanah diameter 20 cm m' 429,907.00 Revisi harga
40 A.5.1.1 34. Pemasangan 1 m’ pipa air limbah jenis pipa tanah diameter 16 cm m' 252,079.00 Revisi harga
41 A.5.1.1 35. Pemasangan 1 m’ pipa beton diameter 15 - 20 cm m' 125,465.00 Revisi harga
42 A.5.1.1.36. Pemasangan 1 m’ pipa beton diameter 30 - 100 cm m' 528,311.00 Revisi harga
43 dihit A.5.1.1.37. Pemasangan 1 m Talang Air Hujan PVC Persegi m' 50,952.00
44 dihit A.5.1.1.38. Pemasangan 1 m Talang Air Hujan PVC 1/2 Lingkaran 6" m¹ 50,952.00 Barang dipas
45 dihit A.5.1.1.39. Pemasangan 1 m Talang Air Hujan Galvanis 1/2 Lingkaran 6" m¹ 171,237.00 analisa lama
46 dihit A.5.1.1.40. Pemasangan 1 Unit Septictank Dinding Bata Trassram 2x1,5x1,5 m unit 13,274,195.00 Revisi harga
47 dihit A.5.1.1.41. Pemasangan 1 Unit Septictank Dinding Bata Trassram 1,5x1,2x1,7 m unit 9,090,284.00 Revisi harga
48 dihit A.5.1.1.42. Pembuatan 1 Unit Septictank Bio Filter Kapasitas 6 orang unit 5,950,009.00 revisi harga b
49 dihit A.5.1.1.43. Pembuatan 1 Unit Septictank Bio Filter Kapasitas 8 orang unit 6,816,505.00 revisi harga b
50 dihit A.5.1.1.44. Pembuatan 1 Unit Septictank Bio Filter Kapasitas 12 orang unit 9,588,046.00 revisi harga b
28 Ls Penangkal Petir Elektrostatis Kurn R 35 M - BC 50 mm (termasuk biaya pemasangan) unit 7,350,000.00 dihilangkan k
29 Ls Penangkal Petir Elektrostatis Kurn R 85 M - BC 50 mm (termasuk biaya pemasangan) unit 8,925,000.00 dihilangkan k
4 dihit AD.2.4 Mengangkut 1 m3 material / hasil galian / Beton Segar dengan jarak angkut 100 m m¹ 59,565.00
5 dihit AD.2.5 Mengangkut 1 m3 material / hasil galian / Beton Segar dengan jarak angkut 200 m m¹ 94,311.00
6 dihit AD.2.6 Mengangkut 1 m3 material / hasil galian / Beton Segar dengan jarak angkut 300 m m¹ 129,057.00
A.2.2.1.3. Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang Kayu L.02 OH 0.300 110,000.00 33,000.00
Kepala Tukang L.03 OH 0.020 100,000.00 2,000.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
JUMLAH TENAGA KERJA 54,100.00
B BAHAN
Bambu Ø 10 cm panjang 400 cm M.23.b Batang 1.000 14,000.00 14,000.00
Portland cement M.245.a Kg 2.000 1,300.00 2,600.00
Kawat duri M.55.b M’ 25.000 6,000.00 150,000.00
Pasir Beton (muntilan) M.9.a m3 0.005 352,000.00 1,760.00
Koral bulat M.11.a m3 0.009 245,300.00 2,207.70
Paku 5 cm M.56.d Kg 0.060 18,000.00 1,080.00
JUMLAH HARGA BAHAN 171,647.70
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 225,747.70
E Overhead & Profit 10% 0.100 22,574.77
F Harga Satuan Pekerjaan (D+E) 248,322.00
A TENAGA
Pekerja L.01 OH 0.250 85,000.00 21,250.00
Mandor L.04 OH 0.008 105,000.00 875.00
JUMLAH TENAGA KERJA 22,125.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 22,125.00
E Overhead & Profit 10% 0.100 2,212.50
F Harga Satuan Pekerjaan (D+E) 24,337.00
A.3.2.1.10. (K3) Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.400 85,000.00 289,000.00
Tukang Batu L.02 OH 0.850 100,000.00 85,000.00
Kepala Tukang L.03 OH 0.085 100,000.00 8,500.00
Mandor L.04 OH 0.170 105,000.00 17,850.00
JUMLAH TENAGA KERJA 400,350.00
B BAHAN
Batu belah (quarry - lokasi pekerjaan) M.2.b m3 0.480 317,500.00 152,400.00
Portland cement M.245.a Kg 194.000 1,300.00 252,200.00
Pasir Beton (muntilan) M.9.a m3 0.312 352,000.00 109,824.00
Koral beton M.11.b m3 0.468 350,000.00 163,800.00
Besi beton (ulir) M.46.b Kg 126.000 11,800.00 1,486,800.00
Kawat beton M.54 Kg 1.800 15,000.00 27,000.00
JUMLAH HARGA BAHAN 2,192,024.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 2,592,374.00
E Overhead & Profit 10% 0.100 259,237.40
F Harga Satuan Pekerjaan (D+E) 2,851,611.00
A.4.1.1.5. Membuat 1 m3 beton mutu f’ = 14,5 MPa (K 175), slump (12 ±2) cm, w/c = 0,66 (manual)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 85,000.00 140,250.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 100,000.00 2,800.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
JUMLAH TENAGA KERJA 179,265.00
B BAHAN
Portland cement M.245.a kg 326.000 1,300.00 423,800.00
Pasir Beton M.9.b kg 760.000 300.00 228,000.00
Koral beton (kg) M.12 kg 1,029.00 300.00 308,700.00
Air, M.550.b Liter 215.000 15.00 3,225.00
JUMLAH HARGA BAHAN 963,725.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,142,990.00
E Overhead & Profit 10% 0.100 114,299.00
F Harga Satuan Pekerjaan (D+E) 1,257,289.00
A.4.1.1.6 Membuat 1 m3 beton mutu f’= 16,9 MPa (K 200), slump (120 ± 20) mm, w/c = 0,61 (manual)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 85,000.00 140,250.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 100,000.00 2,800.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
JUMLAH TENAGA KERJA 179,265.00
B BAHAN
Portland cement M.245.a kg 352.000 1,300.00 457,600.00
Pasir Beton M.9.b kg 731.000 300.00 219,300.00
Koral beton (kg) M.12 kg 1,031.00 300.00 309,300.00
Air, M.550.b Liter 215.000 15.00 3,225.00
JUMLAH HARGA BAHAN 989,425.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,168,690.00
E Overhead & Profit 10% 0.100 116,869.00
F Harga Satuan Pekerjaan (D+E) 1,285,559.00
A.4.1.1.7. Membuat 1 m3 beton mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58 (manual)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 85,000.00 140,250.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 100,000.00 2,800.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
JUMLAH TENAGA KERJA 179,265.00
B BAHAN
Portland cement M.245.a kg 371.000 1,300.00 482,300.00
Pasir Beton M.9.b kg 698.000 300.00 209,400.00
Koral beton (kg) M.12 kg 1,047.00 300.00 314,100.00
Air, M.550.b Liter 215.000 15.00 3,225.00
JUMLAH HARGA BAHAN 1,009,025.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,188,290.00
E Overhead & Profit 10% 0.100 118,829.00
F Harga Satuan Pekerjaan (D+E) 1,307,119.00
A.4.1.1.8. Membuat 1 m3 beton mutu f’= 21,7 MPa (K 250), slump (120 ± 20) mm, w/c = 0,56 (manual)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 85,000.00 140,250.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 100,000.00 2,800.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
JUMLAH TENAGA KERJA 179,265.00
B BAHAN
Portland cement M.245.a kg 384.000 1,300.00 499,200.00
Pasir Beton M.9.b kg 692.000 300.00 207,600.00
Koral beton (kg) M.12 kg 1,039.00 300.00 311,700.00
Air, M.550.b Liter 215.000 15.00 3,225.00
JUMLAH HARGA BAHAN 1,021,725.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,200,990.00
E Overhead & Profit 10% 0.100 120,099.00
F Harga Satuan Pekerjaan (D+E) 1,321,089.00
A.4.1.1.13 Membuat 1 m3 beton kedap air dengan strorox - 100
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.100 85,000.00 178,500.00
Tukang Batu L.02 OH 0.350 100,000.00 35,000.00
Kepala Tukang L.03 OH 0.035 100,000.00 3,500.00
Mandor L.04 OH 0.105 105,000.00 11,025.00
JUMLAH TENAGA KERJA 228,025.00
B BAHAN
Portland cement M.245.a kg 400.000 1,300.00 520,000.00
Pasir Beton (muntilan) M.9.a m3 0.480 352,000.00 168,960.00
Koral beton M.11.b m3 0.800 350,000.00 280,000.00
Strorox - 100 M.401 kg 1.200 183,000.00 219,600.00
JUMLAH HARGA BAHAN 1,188,560.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,416,585.00
E Overhead & Profit 10% 0.100 141,658.50
F Harga Satuan Pekerjaan (D+E) 1,558,243.00
A.4.1.2.2. (K3) Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.165 85,000.00 14,025.00
Tukang batu L.02 OH 0.028 100,000.00 2,800.00
Kepala Tukang L.03 OH 0.003 100,000.00 300.00
Mandor L.04 OH 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 17,965.00
B BAHAN
Portland cement M.245.a Kg 32.600 1,300.00 42,380.00
Pasir beton M.9.b Kg 76.000 300.00 22,800.00
Koral beton (kg) M.12 Kg 102.900 300.00 30,870.00
Air, M.550.b Liter 21.500 15.00 322.50
JUMLAH HARGA BAHAN 96,372.50
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 114,337.50
E Overhead & Profit 10% 0.100 11,433.75
F Harga Satuan Pekerjaan (D+E) 125,771.00
A.4.1.2.3. (K3) Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.198 85,000.00 16,830.00
Tukang batu L.02 OH 0.033 100,000.00 3,300.00
Kepala Tukang L.03 OH 0.003 100,000.00 300.00
Mandor L.04 OH 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 21,480.00
B BAHAN
Portland cement M.245.a Kg 39.120 1,300.00 50,856.00
Pasir beton M.9.b Kg 91.200 300.00 27,360.00
Koral beton (kg) M.12 Kg 123.480 300.00 37,044.00
Air, M.550.b Liter 25.800 15.00 387.00
JUMLAH HARGA BAHAN 115,647.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 137,127.00
E Overhead & Profit 10% 0.100 13,712.70
F Harga Satuan Pekerjaan (D+E) 150,839.00
A.4.1.2.4. (K3) Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.248 85,000.00 21,080.00
Tukang batu L.02 OH 0.041 100,000.00 4,100.00
Kepala Tukang L.03 OH 0.004 100,000.00 400.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
JUMLAH TENAGA KERJA 26,945.00
B BAHAN
Portland cement M.245.a Kg 48.900 1,300.00 63,570.00
Pasir beton M.9.b Kg 114.000 300.00 34,200.00
Koral beton (kg) M.12 Kg 154.350 300.00 46,305.00
Air, M.550.b Liter 32.250 15.00 483.75
JUMLAH HARGA BAHAN 144,558.75
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 171,503.75
E Overhead & Profit 10% 0.100 17,150.38
F Harga Satuan Pekerjaan (D+E) 188,654.00
A.4.1.2.5. Pembuatan 1 m2 bekisting untuk plat beton pracetak ( 5 kali pakai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.007 85,000.00 595.00
Tukang batu L.02 OH 0.076 100,000.00 7,600.00
Kepala Tukang L.03 OH 0.008 100,000.00 800.00
Mandor L.04 OH 0.001 105,000.00 105.00
JUMLAH TENAGA KERJA 9,100.00
B BAHAN
Lantai kerja tebal 10cm m3 0.008 1,008,300.00 8,066.40
Besi hollow 50.50.3 (Kg) M.47.b Kg 9.394 5,900.00 55,424.60
Kayu kruing (kaso 5x7) M.27.a m3 0.005 7,714,300.00 38,571.50
Phenol film 12mm (1 muka) M.33.a Lembar 0.080 146,000.00 11,680.00
Minyak bekisting M.397 Liter 0.200 17,000.00 3,400.00
Dynabolt dia 12mm (10-15cm) M.75.f buah 3.882 4,900.00 19,021.80
JUMLAH HARGA BAHAN 136,164.30
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 145,264.30
E Overhead & Profit 10% 0.100 14,526.43
F Harga Satuan Pekerjaan (D+E) 159,790.00
A.4.1.2.6. Pembuatan 1 m2 bekisting untuk balok beton pracetak ( 10-12 kali pakai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.004 85,000.00 340.00
Tukang batu L.02 OH 0.038 100,000.00 3,800.00
Kepala Tukang L.03 OH 0.004 100,000.00 400.00
Mandor L.04 OH 0.001 105,000.00 105.00
JUMLAH TENAGA KERJA 4,645.00
B BAHAN
Kayu kruing (kaso 5x7) M.27.a m3 0.005 7,714,300.00 38,571.50
Phenol film 12mm (1 muka) M.33.a Lembar 0.043 146,000.00 6,278.00
Minyak bekisting M.397 Liter 0.200 17,000.00 3,400.00
Paku 7 cm M.56.e Kg 0.046 18,000.00 828.00
Dynabolt dia 12mm (10-15cm) M.75.f buah 0.693 4,900.00 3,395.70
JUMLAH HARGA BAHAN 52,473.20
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 57,118.20
E Overhead & Profit 10% 0.100 5,711.82
F Harga Satuan Pekerjaan (D+E) 62,830.00
A.4.1.2.7. Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10-12 kali pakai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.004 85,000.00 340.00
Tukang batu L.02 OH 0.038 100,000.00 3,800.00
Kepala Tukang L.03 OH 0.004 100,000.00 400.00
Mandor L.04 OH 0.001 105,000.00 105.00
JUMLAH TENAGA KERJA 4,645.00
B BAHAN
Kayu kruing (balok) 5/7 M.27.a m3 0.004 7,714,300.00 30,857.20
Phenol film 12mm (1 muka) M.33.a Lembar 0.048 146,000.00 7,008.00
Minyak bekisting M.397 Liter 0.200 17,000.00 3,400.00
Paku 7 cm M.56.e Kg 0.046 18,000.00 828.00
Dynabolt dia 12mm (10-15cm) M.75.f buah 0.693 4,900.00 3,395.70
JUMLAH HARGA BAHAN 45,488.90
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 50,133.90
E Overhead & Profit 10% 0.100 5,013.39
F Harga Satuan Pekerjaan (D+E) 55,147.00
A.4.1.2.8. Pemasangan dan membuka bekisting 1 buah komponen plat beton pracetak
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.053 85,000.00 4,505.00
Tukang kayu L.02 OH 0.018 110,000.00 1,980.00
Mandor L.04 OH 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 7,010.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 7,010.00
E Overhead & Profit 10% 0.100 701.00
F Harga Satuan Pekerjaan (D+E) 7,711.00
A.4.1.2.9. Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.089 85,000.00 7,565.00
Tukang kayu L.02 OH 0.030 110,000.00 3,300.00
Mandor L.04 OH 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 11,390.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 11,390.00
E Overhead & Profit 10% 0.100 1,139.00
F Harga Satuan Pekerjaan (D+E) 12,529.00
A.4.1.2.10. Pemasangan dan membuka bekisting 1 buah komponen Kolom beton pracetak
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,035.00
Tukang kayu L.02 OH 0.024 110,000.00 2,640.00
Mandor L.04 OH 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 9,200.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 9,200.00
E Overhead & Profit 10% 0.100 920.00
F Harga Satuan Pekerjaan (D+E) 10,120.00
A.4.2.1.4. Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.050 85,000.00 89,250.00
Tukang Las Konstruksi L.02 OH 1.050 110,000.00 115,500.00
Kepala Tukang L.03 OH 0.105 100,000.00 10,500.00
Mandor L.04 OH 0.052 105,000.00 5,460.00
JUMLAH TENAGA KERJA 220,710.00
B BAHAN
Besi siku L 30.30.3 M.46.f Kg 15.000 12,300.00 184,500.00
Besi plat baja M.46.h Kg 32.800 15,000.00 492,000.00
Kawat las listrik M.57 Kg 0.050 25,000.00 1,250.00
Pengerjaan 1 cm pengelasan dengan las listrik L.04 cm 20.000 1,958.30 39,166.00
JUMLAH HARGA BAHAN 716,916.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 937,626.00
E Overhead & Profit 10% 0.100 93,762.60
F Harga Satuan Pekerjaan (D+E) 1,031,388.00
A.4.2.1.5. Pengerjaan 1 cm pengelasan dengan las listrik
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.040 85,000.00 3,400.00
Tukang Las Konstruksi L.02 OH 0.020 110,000.00 2,200.00
Kepala Tukang L.03 OH 0.002 100,000.00 200.00
Mandor L.04 OH 0.002 105,000.00 210.00
JUMLAH TENAGA KERJA 6,010.00
B BAHAN
Kawat las listrik M.57 Kg 0.040 25,000.00 1,000.00
Solar (industri) M.393.a Liter 0.030 14,500.00 435.00
Minyak pelumas M.398 Liter - 25,000.00 -
JUMLAH HARGA BAHAN 1,435.00
C PERALATAN
Sewa alat las alat 62 Jam 0.170 71,400.00 12,138.00
JUMLAH HARGA ALAT 12,138.00
D Jumlah (A+B+C) 19,583.00
E Overhead & Profit 10% 0.100 1,958.30
F Harga Satuan Pekerjaan untuk 10 cm 38,831.00
G Harga Satuan Pekerjaan (F/10) 2,154.10
A.4.2.1.19 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang batu L.02 OH 0.300 100,000.00 30,000.00
Kepala Tukang L.03 OH 0.030 100,000.00 3,000.00
Mandor L.04 OH 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 46,590.00
B BAHAN
Seng plat, Lebar 45 cm M.137.f m 1.050 14,062.50 14,765.63
Paku 2,5 cm M.56.b kg 0.010 18,500.00 185.00
Besi strip M.46.g kg 0.500 15,500.00 7,750.00
JUMLAH HARGA BAHAN 22,700.63
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 69,290.63
E Overhead & Profit 10% 0.100 6,929.06
F Harga Satuan Pekerjaan (D+E) 76,219.00
A.4.2.1.20. Pemasangan 1 m2 rangka besi hollow 1 x 40 x 40 x 0.4 mm, modul 60 x 120 cm, dinding partisi
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 85,000.00 21,250.00
Tukang Besi L.02 OH 0.250 110,000.00 27,500.00
Kepala Tukang L.03 OH 0.025 100,000.00 2,500.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
JUMLAH TENAGA KERJA 52,615.00
B BAHAN
Rangka metal hollow 40.40.0,4 mm M.47.c m' 5.000 25,900.00 129,500.00
Assesoris (perkuatan, las dll) 100% rangka 25,900.00 25,900.00
JUMLAH HARGA BAHAN 155,400.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 208,015.00
E Overhead & Profit 10% 0.100 20,801.50
F Harga Satuan Pekerjaan (D+E) 228,816.00
A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1 x 40 x 40 x 0,4 mm, modul 60 x 60 cm, plafon
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 85,000.00 29,750.00
Tukang Besi L.02 OH 0.350 110,000.00 38,500.00
Kepala Tukang L.03 OH 0.035 100,000.00 3,500.00
Mandor L.04 OH 0.018 105,000.00 1,890.00
JUMLAH TENAGA KERJA 73,640.00
B BAHAN
Rangka metal hollow 40.40.0,4 mm M.47.c m' 4.000 25,900.00 103,600.00
Assesoris (perkuatan, las dll) 100% rangka 25,900.00 25,900.00
JUMLAH HARGA BAHAN 129,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 203,140.00
E Overhead & Profit 10% 0.100 20,314.00
F Harga Satuan Pekerjaan (D+E) 223,454.00
A.4.2.1.22. (K3) Pemasangan 1 m2 atap pelana rangka atap baja canal dingin profil C75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.734 85,000.00 62,390.00
Tukang Besi L.02 OH 0.734 110,000.00 80,740.00
Kepala Tukang L.03 OH 0.073 100,000.00 7,300.00
Mandor L.04 OH 0.037 105,000.00 3,885.00
JUMLAH TENAGA KERJA 154,315.00
B BAHAN
C channel galvanis lebar 75 mm, t= 1,0 mm (kg) M.436.e kg 3.065 18,600.00 57,009.00
JUMLAH HARGA BAHAN 57,009.00
C PERALATAN
Alat Rangka Atap Baja Canal Dingin % 10.000 57,009.00 5,700.90
JUMLAH HARGA ALAT 5,700.90
D Jumlah (A+B+C) 217,024.90
E Overhead & Profit 10% 0.100 21,702.49
F Harga Satuan Pekerjaan (D+E) 238,727.00
A.4.2.1.23. (K3) Pemasangan 1 m2 atap jurai rangka atap baja canal dingin profil C75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.760 85,000.00 64,634.00
Tukang Besi L.02 OH 0.760 110,000.00 83,644.00
Kepala Tukang L.03 OH 0.076 100,000.00 7,600.00
Mandor L.04 OH 0.038 105,000.00 3,990.00
JUMLAH TENAGA KERJA 159,868.00
B BAHAN
C channel galvanis lebar 75 mm, t= 1,0 mm (kg) M.436.e kg 4.050 18,600.00 75,330.00
JUMLAH HARGA BAHAN 75,330.00
C PERALATAN
Alat Rangka Atap Baja Canal Dingin % 10.000 75,330.00 7,533.00
JUMLAH HARGA ALAT 7,533.00
D Jumlah (A+B+C) 242,731.00
E Overhead & Profit 10% 0.100 24,273.10
F Harga Satuan Pekerjaan (D+E) 267,004.00
A.4.2.1.24. Pemasangan 1m2 pasang kuda-kuda baja ringan + reng untuk atap genteng biasa/metal
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang Besi L.02 OH 0.450 110,000.00 49,500.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 72,750.00
B BAHAN
C channel galvanis lebar 75 mm, t= 1,0 mm M.436.d m' 3.720 21,000.00 78,120.00
Sekrup kait / roofing M.56.p buah 28.000 800.00 22,400.00
Dynabolt dia 12mm (10-15cm) M.75.f buah 2.000 4,900.00 9,800.00
Reng Canal Dingin M.436.a m' 5.400 10,000.00 54,000.00
JUMLAH HARGA BAHAN 164,320.00
C PERALATAN
Alat Rangka Atap Baja Canal Dingin % 10.000 164,320.00 16,432.00
JUMLAH HARGA ALAT 16,432.00
D Jumlah (A+B+C) 253,502.00
E Overhead & Profit 10% 0.100 25,350.20
F Harga Satuan Pekerjaan (D+E) 278,852.00
A.4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 3 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 85,000.00 51,000.00
Tukang Batu L.02 OH 0.200 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.020 100,000.00 2,000.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 76,150.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 140.000 700.00 98,000.00
Portland cement M.245.a Kg 32.950 1,300.00 42,835.00
Pasir Beton (muntilan) M.9.a m3 0.091 352,000.00 32,032.00
JUMLAH HARGA BAHAN 172,867.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 249,017.00
E Overhead & Profit 10% 0.100 24,901.70
F Harga Satuan Pekerjaan (D+E) 273,918.00
A.4.4.1.3. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 85,000.00 51,000.00
Tukang Batu L.02 OH 0.200 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.020 100,000.00 2,000.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 76,150.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 140.000 700.00 98,000.00
Portland cement M.245.a Kg 26.550 1,300.00 34,515.00
Pasir Beton (muntilan) M.9.a m3 0.093 352,000.00 32,736.00
JUMLAH HARGA BAHAN 165,251.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 241,401.00
E Overhead & Profit 10% 0.100 24,140.10
F Harga Satuan Pekerjaan (D+E) 265,541.00
A.4.4.1.4. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 5 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 85,000.00 51,000.00
Tukang Batu L.02 OH 0.200 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.020 100,000.00 2,000.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 76,150.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 140.000 700.00 98,000.00
Portland cement M.245.a Kg 22.200 1,300.00 28,860.00
Pasir Beton (muntilan) M.9.a m3 0.102 352,000.00 35,904.00
JUMLAH HARGA BAHAN 162,764.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 238,914.00
E Overhead & Profit 10% 0.100 23,891.40
F Harga Satuan Pekerjaan (D+E) 262,805.00
A.4.4.1.5. Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 batu campuran 1 SP : 6 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 85,000.00 51,000.00
Tukang Batu L.02 OH 0.200 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.020 100,000.00 2,000.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 76,150.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 140.000 700.00 98,000.00
Portland cement M.245.a Kg 18.500 1,300.00 24,050.00
Pasir Beton (muntilan) M.9.a m3 0.122 352,000.00 42,944.00
JUMLAH HARGA BAHAN 164,994.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 241,144.00
E Overhead & Profit 10% 0.100 24,114.40
F Harga Satuan Pekerjaan (D+E) 265,258.00
A.4.4.1.6 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 85,000.00 51,000.00
Tukang Batu L.02 OH 0.200 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.020 100,000.00 2,000.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 76,150.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 140.000 700.00 98,000.00
Portland cement M.245.a Kg 10.080 1,300.00 13,104.00
Kapur M.563 m3 0.028 263,000.00 7,232.50
Pasir Beton (muntilan) M.9.a m3 0.093 352,000.00 32,560.00
JUMLAH HARGA BAHAN 150,896.50
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 227,046.50
E Overhead & Profit 10% 0.100 22,704.65
F Harga Satuan Pekerjaan (D+E) 249,751.00
A.4.4.1.7 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 18.950 1,300.00 24,635.00
Pasir Beton (muntilan) M.9.a m3 0.038 352,000.00 13,376.00
JUMLAH HARGA BAHAN 87,011.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 125,086.00
E Overhead & Profit 10% 0.100 12,508.60
F Harga Satuan Pekerjaan (D+E) 137,594.00
A.4.4.1.8 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 14.370 1,300.00 18,681.00
Pasir Beton (muntilan) M.9.a m3 0.040 352,000.00 14,080.00
JUMLAH HARGA BAHAN 81,761.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 119,836.00
E Overhead & Profit 10% 0.100 11,983.60
F Harga Satuan Pekerjaan (D+E) 131,819.00
A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 11.500 1,300.00 14,950.00
Pasir Beton (muntilan) M.9.a m3 0.043 352,000.00 15,136.00
JUMLAH HARGA BAHAN 79,086.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 117,161.00
E Overhead & Profit 10% 0.100 11,716.10
F Harga Satuan Pekerjaan (D+E) 128,877.00
A.4.4.1.10 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1 SP : 5 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 9.680 1,300.00 12,584.00
Pasir Beton (muntilan) M.9.a m3 0.045 352,000.00 15,840.00
JUMLAH HARGA BAHAN 77,424.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 115,499.00
E Overhead & Profit 10% 0.100 11,549.90
F Harga Satuan Pekerjaan (D+E) 127,048.00
A.4.4.1.11 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1 SP : 6 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 8.320 1,300.00 10,816.00
Pasir Beton (muntilan) M.9.a m3 0.049 352,000.00 17,248.00
JUMLAH HARGA BAHAN 77,064.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 115,139.00
E Overhead & Profit 10% 0.100 11,513.90
F Harga Satuan Pekerjaan (D+E) 126,652.00
A.4.4.1.12 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 8 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 6.500 1,300.00 8,450.00
Pasir Beton (muntilan) M.9.a m3 0.050 352,000.00 17,600.00
JUMLAH HARGA BAHAN 75,050.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 113,125.00
E Overhead & Profit 10% 0.100 11,312.50
F Harga Satuan Pekerjaan (D+E) 124,437.00
A.4.4.1.13 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 3KP :10PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 4.500 1,300.00 5,850.00
Kapur M.563 m3 0.015 263,000.00 3,945.00
Pasir Beton (muntilan) M.9.a m3 0.050 352,000.00 17,600.00
JUMLAH HARGA BAHAN 76,395.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 114,470.00
E Overhead & Profit 10% 0.100 11,447.00
F Harga Satuan Pekerjaan (D+E) 125,917.00
A.4.4.1.14 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SM : 1KP :1PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 0.018 1,300.00 23.40
Kapur M.563 m3 0.018 263,000.00 4,734.00
Pasir Beton (muntilan) M.9.a m3 0.018 352,000.00 6,336.00
JUMLAH HARGA BAHAN 60,093.40
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 98,168.40
E Overhead & Profit 10% 0.100 9,816.84
F Harga Satuan Pekerjaan (D+E) 107,985.00
A.4.4.1.15 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :2PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 38,075.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 0.014 1,300.00 18.20
Kapur M.563 m3 0.014 263,000.00 3,682.00
Pasir Beton (muntilan) M.9.a m3 0.028 352,000.00 9,856.00
JUMLAH HARGA BAHAN 62,556.20
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 100,631.20
E Overhead & Profit 10% 0.100 10,063.12
F Harga Satuan Pekerjaan (D+E) 110,694.00
A.4.4.1.25 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai.
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.670 85,000.00 56,950.00
Tukang Batu L.02 OH 1.300 100,000.00 130,000.00
Kepala Tukang L.03 OH 0.130 100,000.00 13,000.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 200,265.00
B BAHAN
Hebel Block (ukuran 60x20x7,5 cm) M.235.a buah 8.400 9,800.00 82,320.00
Pengisi bata ringan (Semen MU 380) M.240.c Kg 0.473 3,225.00 1,525.43
JUMLAH HARGA BAHAN 83,845.43
C PERALATAN
Peralatan Pasang Dinding Bata Ringan % 10.000 83,845.43 8,384.54
JUMLAH HARGA ALAT 8,384.54
D Jumlah (A+B+C) 292,494.97
E Overhead & Profit 10% 0.100 29,249.50
F Harga Satuan Pekerjaan (D+E) 321,744.00
A.4.4.1.26 Pemasangan 1 m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.671 85,000.00 57,035.00
Tukang Batu L.02 OH 1.300 100,000.00 130,000.00
Kepala Tukang L.03 OH 0.130 100,000.00 13,000.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 200,350.00
B BAHAN
Hebel Block (ukuran 60x20x10 cm) M.235.b buah 8.400 10,200.00 85,680.00
Pengisi bata ringan (Semen MU 380) M.240.c Kg 0.063 3,225.00 203.18
JUMLAH HARGA BAHAN 85,883.18
C PERALATAN
Peralatan Pasang Dinding Bata Ringan Ls 0.100 85,883.18 8,588.32
JUMLAH HARGA ALAT 8,588.32
D Jumlah (A+B+C) 294,821.49
E Overhead & Profit 10% 0.100 29,482.15
F Harga Satuan Pekerjaan (D+E) 324,303.00
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.1. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm.
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.150 100,000.00 15,000.00
Kepala Tukang L.03 OH 0.015 100,000.00 1,500.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 43,575.00
B BAHAN
Portland cement M.245.a Kg 15.504 1,300.00 20,155.20
Pasir Beton (muntilan) M.9.a m3 0.016 352,000.00 5,632.00
JUMLAH HARGA BAHAN 25,787.20
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 69,362.20
E Overhead & Profit 10% 0.100 6,936.22
F Harga Satuan Pekerjaan (D+E) 76,298.00
A.4.4.2.26. Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2PP.
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.02 OH 0.150 100,000.00 15,000.00
Kepala Tukang L.03 OH 0.015 100,000.00 1,500.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 43,575.00
B BAHAN
Portland cement M.245.a Kg 6.340 1,300.00 8,242.00
Pasir Beton (muntilan) M.9.a m3 0.012 352,000.00 4,224.00
JUMLAH HARGA BAHAN 12,466.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 56,041.00
E Overhead & Profit 10% 0.100 5,604.10
F Harga Satuan Pekerjaan (D+E) 61,645.00
A.4.4.3.13. Pemasangan 1m2 lantai ubin teralux marmer ukuran 60cm x60cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.240 85,000.00 20,400.00
Tukang Batu L.02 OH 0.120 100,000.00 12,000.00
Kepala Tukang L.03 OH 0.012 100,000.00 1,200.00
Mandor L.04 OH 0.012 105,000.00 1,260.00
JUMLAH TENAGA KERJA 34,860.00
B BAHAN
Ubin Teralux Marmer 60 cm x 60 cm M.196.c buah 3.100 250,000.00 775,000.00
Portland cement M.245.a kg 9.600 1,300.00 12,480.00
Semen Warna M.244 Kg 1.500 15,000.00 22,500.00
Pasir Beton (muntilan) M.9.a m3 0.045 352,000.00 15,840.00
JUMLAH HARGA BAHAN 825,820.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 860,680.00
E Overhead & Profit 10% 0.100 86,068.00
F Harga Satuan Pekerjaan (D+E) 946,748.00
A.4.4.3.14. Pemasangan 1m2 lantai ubin teralux marmer ukuran 40cm x40cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 85,000.00 21,250.00
Tukang Batu L.02 OH 0.125 100,000.00 12,500.00
Kepala Tukang L.03 OH 0.013 100,000.00 1,300.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
JUMLAH TENAGA KERJA 36,415.00
B BAHAN
Ubin Teralux Marmer 40 cm x 40 cm M.196.b buah 6.630 90,500.00 600,015.00
Portland cement M.245.a kg 9.800 1,300.00 12,740.00
Semen Warna M.244 Kg 1.300 15,000.00 19,500.00
Pasir Beton (muntilan) M.9.a m3 0.045 352,000.00 15,840.00
JUMLAH HARGA BAHAN 648,095.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 684,510.00
E Overhead & Profit 10% 0.100 68,451.00
F Harga Satuan Pekerjaan (D+E) 752,961.00
A.4.4.3.15. Pemasangan 1m2 lantai ubin teralux marmer ukuran 30cm x30cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.260 85,000.00 22,100.00
Tukang Batu L.02 OH 0.130 100,000.00 13,000.00
Kepala Tukang L.03 OH 0.013 100,000.00 1,300.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
JUMLAH TENAGA KERJA 37,765.00
B BAHAN
Ubin Teralux Marmer 30 cm x 30 cm M.196.a buah 11.870 52,000.00 617,240.00
Portland cement M.245.a kg 10.000 1,300.00 13,000.00
Semen Warna M.244 Kg 1.500 15,000.00 22,500.00
Pasir Beton (muntilan) M.9.a m3 0.045 352,000.00 15,840.00
JUMLAH HARGA BAHAN 668,580.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 706,345.00
E Overhead & Profit 10% 0.100 70,634.50
F Harga Satuan Pekerjaan (D+E) 776,979.00
A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II (Bengkirai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 6.000 85,000.00 510,000.00
Tukang kayu L.02 OH 18.000 110,000.00 1,980,000.00
Kepala Tukang L.03 OH 1.800 100,000.00 180,000.00
Mandor L.04 OH 0.300 105,000.00 31,500.00
JUMLAH TENAGA KERJA 2,701,500.00
B BAHAN
Kayu bengkirai (balok) M.17.a m3 1.200 11,000,000.00 13,200,000.00
Paku 10 cm M.56.f Kg 1.250 18,000.00 22,500.00
Lem Kayu M.572 Kg 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 13,237,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 15,939,000.00
E Overhead & Profit 10% 0.100 1,593,900.00
F Harga Satuan Pekerjaan (D+E) 17,532,900.00
A.4.6.1.3. Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II (Bengkirai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 85,000.00 29,750.00
Tukang kayu L.02 OH 1.050 110,000.00 115,500.00
Kepala Tukang L.03 OH 0.105 100,000.00 10,500.00
Mandor L.04 OH 0.018 105,000.00 1,890.00
JUMLAH TENAGA KERJA 157,640.00
B BAHAN
Kayu bengkirai (papan) M.17.b m3 0.040 12,700,000.00 508,000.00
Paku 7 cm M.56.e Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 508,900.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 666,540.00
E Overhead & Profit 10% 0.100 66,654.00
F Harga Satuan Pekerjaan (D+E) 733,194.00
A.4.6.1.4. Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III (Kruing)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 85,000.00 29,750.00
Tukang kayu L.02 OH 1.050 110,000.00 115,500.00
Kepala Tukang L.03 OH 0.105 100,000.00 10,500.00
Mandor L.04 OH 0.018 105,000.00 1,890.00
JUMLAH TENAGA KERJA 157,640.00
B BAHAN
Kayu kruing (papan) M.18.b m3 0.040 7,950,000.00 318,000.00
Paku 7 cm M.56.e Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 318,900.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 476,540.00
E Overhead & Profit 10% 0.100 47,654.00
F Harga Satuan Pekerjaan (D+E) 524,194.00
A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II (Bengkirai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang kayu L.02 OH 3.000 110,000.00 330,000.00
Kepala Tukang L.03 OH 0.300 100,000.00 30,000.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 450,250.00
B BAHAN
Kayu bengkirai (papan) M.17.b m3 0.040 12,700,000.00 508,000.00
Lem Kayu M.572 Kg 0.500 15,000.00 7,500.00
JUMLAH HARGA BAHAN 515,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 965,750.00
E Overhead & Profit 10% 0.100 96,575.00
F Harga Satuan Pekerjaan (D+E) 1,062,325.00
A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas II (Bengkirai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.800 85,000.00 68,000.00
Tukang kayu L.02 OH 2.400 110,000.00 264,000.00
Kepala Tukang L.03 OH 0.240 100,000.00 24,000.00
Mandor L.04 OH 0.040 105,000.00 4,200.00
JUMLAH TENAGA KERJA 360,200.00
B BAHAN
Kayu bengkirai (papan) M.17.b m3 0.024 12,700,000.00 304,800.00
Lem Kayu M.572 Kg 0.300 15,000.00 4,500.00
JUMLAH HARGA BAHAN 309,300.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 669,500.00
E Overhead & Profit 10% 0.100 66,950.00
F Harga Satuan Pekerjaan (D+E) 736,450.00
A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas II (Bengkirai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang kayu L.02 OH 3.000 110,000.00 330,000.00
Kepala Tukang L.03 OH 0.300 100,000.00 30,000.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 450,250.00
B BAHAN
Kayu bengkirai (papan) M.17.b m3 0.064 12,700,000.00 812,800.00
Lem Kayu M.572 Kg 0.500 15,000.00 7,500.00
JUMLAH HARGA BAHAN 820,300.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,270,550.00
E Overhead & Profit 10% 0.100 127,055.00
F Harga Satuan Pekerjaan (D+E) 1,397,605.00
A.4.6.1.8. Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (Bengkirai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 85,000.00 59,500.00
Tukang kayu L.02 OH 2.100 110,000.00 231,000.00
Kepala Tukang L.03 OH 0.210 100,000.00 21,000.00
Mandor L.04 OH 0.035 105,000.00 3,675.00
JUMLAH TENAGA KERJA 315,175.00
B BAHAN
Kayu bengkirai (papan) M.17.b m3 0.025 12,700,000.00 317,500.00
Paku 2,5 cm M.56.b kg 0.030 18,500.00 555.00
Lem Kayu M.572 kg 0.500 15,000.00 7,500.00
Plywood 4 mm (120x240) M.32.a Lembar 1.000 58,000.00 58,000.00
JUMLAH HARGA BAHAN 383,555.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 698,730.00
E Overhead & Profit 10% 0.100 69,873.00
F Harga Satuan Pekerjaan (D+E) 768,603.00
A.4.6.1.9. Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas II (Bengkirai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.800 85,000.00 68,000.00
Tukang kayu L.02 OH 2.400 110,000.00 264,000.00
Kepala Tukang L.03 OH 0.240 100,000.00 24,000.00
Mandor L.04 OH 0.040 105,000.00 4,200.00
JUMLAH TENAGA KERJA 360,200.00
B BAHAN
Kayu bengkirai (papan) M.17.b m3 0.026 12,700,000.00 325,120.00
Paku 2,5 cm M.56.b kg 0.030 18,500.00 555.00
Lem Kayu M.572 kg 0.500 15,000.00 7,500.00
Plywood 4 mm (120x240) M.32.a Lembar 1.000 58,000.00 58,000.00
JUMLAH HARGA BAHAN 391,175.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 751,375.00
E Overhead & Profit 10% 0.100 75,137.50
F Harga Satuan Pekerjaan (D+E) 826,512.00
A.4.6.1.19. Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas III (Kruing)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang kayu L.02 OH 0.300 110,000.00 33,000.00
Kepala Tukang L.03 OH 0.030 100,000.00 3,000.00
Mandor L.04 OH 0.075 105,000.00 7,875.00
JUMLAH TENAGA KERJA 56,625.00
B BAHAN
Kayu kruing (balok) M.18.a m3 0.015 7,800,000.00 120,120.00
Paku 7 cm M.56.e kg 0.200 18,000.00 3,600.00
JUMLAH HARGA BAHAN 123,720.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 180,345.00
E Overhead & Profit 10% 0.100 18,034.50
F Harga Satuan Pekerjaan (D+E) 198,379.00
A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas III (Kruing)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang kayu L.02 OH 0.300 110,000.00 33,000.00
Kepala Tukang L.03 OH 0.030 100,000.00 3,000.00
Mandor L.04 OH 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 54,050.00
B BAHAN
Kayu kruing (balok) M.18.a m3 0.016 7,800,000.00 127,140.00
Paku 7 cm M.56.e kg 0.250 18,000.00 4,500.00
JUMLAH HARGA BAHAN 131,640.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 185,690.00
E Overhead & Profit 10% 0.100 18,569.00
F Harga Satuan Pekerjaan (D+E) 204,259.00
A.4.6.1.24. Pemasangan 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas III (Kruing)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang kayu L.02 OH 0.450 110,000.00 49,500.00
Kepala Tukang L.03 OH 0.045 100,000.00 4,500.00
Mandor L.04 OH 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 67,590.00
B BAHAN
Kayu kruing (balok) M.18.a m3 0.028 7,800,000.00 218,400.00
Paku 7 cm M.56.e kg 0.150 18,000.00 2,700.00
Teakwood 4 mm (120x240) M.31.b Lembar 0.860 113,500.00 97,610.00
Lem Kayu M.572 kg 0.560 15,000.00 8,400.00
JUMLAH HARGA BAHAN 327,110.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 394,700.00
E Overhead & Profit 10% 0.100 39,470.00
F Harga Satuan Pekerjaan (D+E) 434,170.00
A.4.6.1.25. Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas III (kruing)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang kayu L.02 OH 0.600 110,000.00 66,000.00
Kepala Tukang L.03 OH 0.060 100,000.00 6,000.00
Mandor L.04 OH 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 90,050.00
B BAHAN
Kayu kruing (balok) M.18.a m3 0.028 7,800,000.00 218,400.00
Paku 7 cm M.56.e kg 0.150 18,000.00 2,700.00
Plywood 4 mm (120x240) M.32.a Lembar 0.860 58,000.00 49,880.00
Lem Kayu M.572 kg 0.560 15,000.00 8,400.00
JUMLAH HARGA BAHAN 279,380.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 369,430.00
E Overhead & Profit 10% 0.100 36,943.00
F Harga Satuan Pekerjaan (D+E) 406,373.00
A.4.6.1.26. Pemasangan 1 m2 dinding lambrisering dari Kayu Papan kayu kelas II (Bengkirai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 85,000.00 51,000.00
Tukang kayu L.02 OH 1.800 110,000.00 198,000.00
Kepala Tukang L.03 OH 0.180 100,000.00 18,000.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 270,150.00
B BAHAN
Kayu bengkirai (papan) M.17.b m3 0.007 12,700,000.00 88,900.00
Paku 7 cm M.56.e kg 0.100 18,000.00 1,800.00
Paku sekrup M.56.j kg 0.150 30,000.00 4,500.00
JUMLAH HARGA BAHAN 95,200.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 365,350.00
E Overhead & Profit 10% 0.100 36,535.00
F Harga Satuan Pekerjaan (D+E) 401,885.00
A.4.6.1.28. Pemasangan 1 m2 dinding bilik bambu, rangka kayu kelas III (Kruing)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Tukang kayu L.02 OH 0.050 110,000.00 5,500.00
Kepala Tukang L.03 OH 0.005 100,000.00 500.00
Mandor L.04 OH 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 15,025.00
B BAHAN
Sesek bambu (2x1,5m) M.555.a m2 1.500 8,000.00 12,000.00
Kayu kruing (balok) M.18.a m3 0.014 7,800,000.00 109,200.00
Paku 2,5 cm M.56.b kg 0.012 18,500.00 222.00
List kayu 2/4 M.30.a m' 0.003 3,700.00 11.10
JUMLAH HARGA BAHAN 121,433.10
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 136,458.10
E Overhead & Profit 10% 0.100 13,645.81
F Harga Satuan Pekerjaan (D+E) 150,103.00
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
A.4.6.2.1. Pemasangan 1 buah kunci tanam antik
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.060 85,000.00 5,100.00
Tukang kayu L.02 OH 0.600 110,000.00 66,000.00
Kepala Tukang L.03 OH 0.060 100,000.00 6,000.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 77,415.00
B BAHAN
Kunci tanam antik M.312.a buah 1.000 150,000.00 150,000.00
JUMLAH HARGA BAHAN 150,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 227,415.00
E Overhead & Profit 10% 0.100 22,741.50
F Harga Satuan Pekerjaan (D+E) 250,156.00
A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 85,000.00 5,950.00
Tukang cat L.02 OH 0.009 95,000.00 855.00
Kepala Tukang L.03 OH 0.006 100,000.00 600.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 7,720.00
B BAHAN
Meni kayu M.268.a Kg 0.200 40,000.00 8,000.00
Plamir kayu M.273.a Kg 0.150 41,800.00 6,270.00
Cat dasar (cat kayu) M.260.a Kg 0.170 31,000.00 5,270.00
Cat penutup (cat kayu) M.260.b Kg 0.260 55,000.00 14,300.00
Kuas 1" M.272.d buah 0.010 3,800.00 38.00
Pengencer cat kayu/besi M.276.a Kg 0.030 10,000.00 300.00
Ampelas M.271 Lembar 0.200 2,500.00 500.00
JUMLAH HARGA BAHAN 34,678.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 42,398.00
E Overhead & Profit 10% 0.100 4,239.80
F Harga Satuan Pekerjaan (D+E) 46,637.00
A.4.7.1.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat Penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 85,000.00 5,950.00
Tukang cat L.02 OH 0.105 95,000.00 9,975.00
Kepala Tukang L.03 OH 0.004 100,000.00 400.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 16,640.00
B BAHAN
Meni kayu M.268.a Kg 0.200 40,000.00 8,000.00
Plamir kayu M.273.a Kg 0.150 41,800.00 6,270.00
Cat dasar (cat kayu) M.260.a Kg 0.170 31,000.00 5,270.00
Cat penutup (cat kayu) M.260.b Kg 0.350 55,000.00 19,250.00
Kuas 2" M.272.c buah 0.010 7,000.00 70.00
Pengencer cat kayu/besi M.276.a Kg 0.030 10,000.00 300.00
Ampelas M.271 Lembar 0.200 2,500.00 500.00
JUMLAH HARGA BAHAN 39,660.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 56,300.00
E Overhead & Profit 10% 0.100 5,630.00
F Harga Satuan Pekerjaan (D+E) 61,930.00
A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) Interior setara mowilex
(Decorcryl, Dulux Pentalite, Nippon)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 85,000.00 1,700.00
Tukang cat L.02 OH 0.063 95,000.00 5,985.00
Kepala Tukang L.03 OH 0.006 100,000.00 630.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 8,630.00
B BAHAN
Plamir tembok M.273.b Kg 0.100 60,000.00 6,000.00
Cat dasar (cat tembok interior) setara mowilex M.263.a Kg 0.100 40,000.00 4,000.00
Cat penutup (cat tembok interior) setara mowilex M.263.b Kg 0.260 41,000.00 10,660.00
JUMLAH HARGA BAHAN 20,660.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 29,290.00
E Overhead & Profit 10% 0.100 2,929.00
F Harga Satuan Pekerjaan (D+E) 32,219.00
A.4.7.1.11. Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup) Interior setara mowilex
(Decorcryl, Dulux Pentalite, Nippon)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.028 85,000.00 2,380.00
Tukang cat L.02 OH 0.042 95,000.00 3,990.00
Kepala Tukang L.03 OH 0.004 100,000.00 420.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 7,105.00
B BAHAN
Cat dasar (cat tembok interior) setara mowilex M.263.a Kg 0.120 40,000.00 4,800.00
Cat penutup (cat tembok interior) setara mowilex M.263.b Kg 0.180 41,000.00 7,380.00
JUMLAH HARGA BAHAN 12,180.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 19,285.00
E Overhead & Profit 10% 0.100 1,928.50
F Harga Satuan Pekerjaan (D+E) 21,213.00
A.4.7.1.19. Pengecatan 1 m2 permukaan besi / baja galvanis secara manual sistem 1 lapis cat mutakhir
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.060 85,000.00 5,100.00
Tukang cat L.02 OH 0.060 95,000.00 5,700.00
Kepala Tukang L.03 OH 0.012 100,000.00 1,200.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 12,315.00
B BAHAN
Cat penutup (Cat besi) M.261.c Kg 0.300 70,000.00 21,000.00
Kuas 1" M.272.d buah 0.010 3,800.00 38.00
Thinner M.276.c Liter 0.010 18,000.00 180.00
JUMLAH HARGA BAHAN 21,218.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 33,533.00
E Overhead & Profit 10% 0.100 3,353.30
F Harga Satuan Pekerjaan (D+E) 36,886.00
A.4.7.1.20. Pengecatan 1 m2 permukaan besi / baja galvanis secara manual sistem 3 lapis
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 85,000.00 34,000.00
Tukang cat L.02 OH 0.800 95,000.00 76,000.00
Kepala Tukang L.03 OH 0.080 100,000.00 8,000.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
JUMLAH TENAGA KERJA 120,100.00
B BAHAN
Cat dasar (cat besi) M.261.a Kg 0.110 57,000.00 6,270.00
Cat antara (cat besi) M.261.b Kg 0.170 80,000.00 13,600.00
Cat penutup (Cat besi) M.261.c Kg 0.080 70,000.00 5,600.00
Kuas 1" M.272.d buah 0.010 3,800.00 38.00
Thinner M.276.c Liter 0.010 18,000.00 180.00
JUMLAH HARGA BAHAN 25,688.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 145,788.00
E Overhead & Profit 10% 0.100 14,578.80
F Harga Satuan Pekerjaan (D+E) 160,366.00
A.4.7.1.21. Pengecatan 1 m2 permukaan besi / baja galvanis secara semprot sistem 3 lapis cat mutakhir
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 85,000.00 34,000.00
Tukang cat L.02 OH 0.700 95,000.00 66,500.00
Kepala Tukang L.03 OH 0.070 100,000.00 7,000.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
JUMLAH TENAGA KERJA 109,600.00
B BAHAN
Cat penutup (Cat besi) M.261.c Kg 0.300 70,000.00 21,000.00
Thinner M.276.c Liter 0.010 18,000.00 180.00
JUMLAH HARGA BAHAN 21,180.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 130,780.00
E Overhead & Profit 10% 0.100 13,078.00
F Harga Satuan Pekerjaan (D+E) 143,858.00
A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.160 85,000.00 183,600.00
Tukang batu L.02 OH 0.720 100,000.00 72,000.00
Kepala Tukang L.03 OH 0.072 100,000.00 7,200.00
Mandor L.04 OH 0.011 105,000.00 1,155.00
JUMLAH TENAGA KERJA 263,955.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 40.000 700.00 28,000.00
Portland cement M.245.a Kg 44.000 1,300.00 57,200.00
Pasir Beton (muntilan) M.9.a m3 0.070 352,000.00 24,640.00
Pasir Beton (muntilan) M.9.a m3 0.060 352,000.00 21,120.00
Koral beton M.11.b m3 0.070 350,000.00 24,500.00
Baja tulangan polos U-24 M.46.a Kg 1.600 9,600.00 15,360.00
JUMLAH HARGA BAHAN 170,820.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 434,775.00
E Overhead & Profit 10% 0.100 43,477.50
F Harga Satuan Pekerjaan (D+E) 478,252.00
A.5.1.1 16. Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm tinggi 50 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.200 85,000.00 272,000.00
Tukang batu L.02 OH 1.150 100,000.00 115,000.00
Kepala Tukang L.03 OH 0.011 100,000.00 1,100.00
Mandor L.04 OH 0.016 105,000.00 1,680.00
JUMLAH TENAGA KERJA 389,780.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 70.000 700.00 49,000.00
Portland cement M.245.a Kg 77.000 1,300.00 100,100.00
Pasir Beton (muntilan) M.9.a m3 0.130 352,000.00 45,760.00
Pasir Beton (muntilan) M.9.a m3 0.090 352,000.00 31,680.00
Koral beton M.11.b m3 0.020 350,000.00 7,000.00
Baja tulangan polos U-24 M.46.a Kg 2.600 9,600.00 24,960.00
JUMLAH HARGA BAHAN 258,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 648,280.00
E Overhead & Profit 10% 0.100 64,828.00
F Harga Satuan Pekerjaan (D+E) 713,108.00
A.5.1.1 17. Pemasangan 1 buah bak kontrol pasangan bata 60cm x60cm tinggi 65 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.200 85,000.00 272,000.00
Tukang batu L.02 OH 1.150 100,000.00 115,000.00
Kepala Tukang L.03 OH 0.011 100,000.00 1,100.00
Mandor L.04 OH 0.016 105,000.00 1,680.00
JUMLAH TENAGA KERJA 389,780.00
B BAHAN
Bata merah 5 x 11 x 22 cm M.218.a buah 123.000 700.00 86,100.00
Portland cement M.245.a Kg 114.000 1,300.00 148,200.00
Pasir Beton (muntilan) M.9.a m3 0.184 352,000.00 64,768.00
Pasir Beton (muntilan) M.9.a m3 0.120 352,000.00 42,240.00
Koral beton M.11.b m3 0.033 350,000.00 11,550.00
Baja tulangan polos U-24 M.46.a Kg 4.850 9,600.00 46,560.00
JUMLAH HARGA BAHAN 399,418.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 789,198.00
E Overhead & Profit 10% 0.100 78,919.80
F Harga Satuan Pekerjaan (D+E) 868,117.00
A.5.1.1 33. Pemasangan 1 m’ pipa air limbah jenis pipa tanah diameter 20 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang batu L.02 OH 0.040 100,000.00 4,000.00
Kepala Tukang L.03 OH 0.004 100,000.00 400.00
Mandor L.04 OH 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 11,620.00
B BAHAN
Pipa tanah Ø 200 mm SDR-41 (air limbah) M.608.b buah 1.600 204,000.00 326,400.00
Portland cement M.245.a Kg 35.000 1,300.00 45,500.00
Pasir Beton (muntilan) M.9.a m3 0.014 352,000.00 4,928.00
Pasir urug (quarry - lokasi pekerjaan) M.4.b m3 0.014 169,800.00 2,377.20
JUMLAH HARGA BAHAN 379,205.20
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 390,825.20
E Overhead & Profit 10% 0.100 39,082.52
F Harga Satuan Pekerjaan (D+E) 429,907.00
A.5.1.1 34. Pemasangan 1 m’ pipa air limbah jenis pipa tanah diameter 16 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.060 85,000.00 5,100.00
Tukang batu L.02 OH 0.030 100,000.00 3,000.00
Kepala Tukang L.03 OH 0.003 100,000.00 300.00
Mandor L.04 OH 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 8,715.00
B BAHAN
Pipa tanah Ø 160 mm SDR-41 (air limbah) M.608.a m' 1.600 133,200.00 213,120.00
Portland cement M.245.a Kg 0.680 1,300.00 884.00
Pasir Beton (muntilan) M.9.a m3 0.013 352,000.00 4,576.00
Pasir urug (quarry - lokasi pekerjaan) M.4.b m3 0.011 169,800.00 1,867.80
JUMLAH HARGA BAHAN 220,447.80
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 229,162.80
E Overhead & Profit 10% 0.100 22,916.28
F Harga Satuan Pekerjaan (D+E) 252,079.00
A.8.4.4.2 (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 100 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.646 85,000.00 139,910.00
Tukang pipa L.02 OH 0.823 95,000.00 78,185.00
Mandor L.04 OH 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 235,420.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Pipe Cutter alat 102 hari 0.650 372,302.00 241,996.30
Generator set 135 KVA alat 29 hari 0.159 3,301,127.51 524,879.27
Pompa submersible alat 89 hari 1.078 400,000.00 431,200.00
Sewa Tripot/Tackel & handle crane 2 T alat 100 hari 0.911 300,000.00 273,300.00
JUMLAH HARGA ALAT 1,471,375.57
D Jumlah (A+B+C) 1,706,795.57
E Overhead & Profit 10% 0.100 170,679.56
F Harga Satuan Pekerjaan (D+E) 1,877,475.00
A.8.4.4.3 (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 150 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.096 85,000.00 178,160.00
Tukang pipa L.02 OH 1.048 95,000.00 99,560.00
Mandor L.04 OH 0.210 105,000.00 22,050.00
JUMLAH TENAGA KERJA 299,770.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Pipe Cutter alat 102 hari 0.760 372,302.00 282,949.52
Generator set 135 KVA alat 29 hari 0.369 3,301,127.51 1,218,116.05
Pompa submersible alat 89 hari 1.353 400,000.00 541,200.00
Sewa Tripot/Tackel & handle crane 2 T alat 100 hari 1.026 300,000.00 307,800.00
JUMLAH HARGA ALAT 2,350,065.57
D Jumlah (A+B+C) 2,649,835.57
E Overhead & Profit 10% 0.100 264,983.56
F Harga Satuan Pekerjaan (D+E) 2,914,819.00
A.8.4.4.4 (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 200 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.546 85,000.00 216,410.00
Tukang pipa L.02 OH 1.273 95,000.00 120,935.00
Mandor L.04 OH 0.255 105,000.00 26,775.00
JUMLAH TENAGA KERJA 364,120.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Pipe Cutter alat 102 hari 0.870 372,302.00 323,902.74
Generator set 135 KVA alat 29 hari 0.579 3,301,127.51 1,911,352.83
Pompa submersible alat 89 hari 1.628 400,000.00 651,200.00
Sewa Tripot/Tackel & handle crane 2 T alat 100 hari 1.141 300,000.00 342,300.00
JUMLAH HARGA ALAT 3,228,755.57
D Jumlah (A+B+C) 3,592,875.57
E Overhead & Profit 10% 0.100 359,287.56
F Harga Satuan Pekerjaan (D+E) 3,952,163.00