Anda di halaman 1dari 68

NO JENIS PEKERJAAN GAMBAR/SKETS PERHITUNGAN

LANTAI 1
A SLOOF
1 S1 PANJANG AS-AS = 6.00 M

PANJANG EFEKTIF = 5.75

0.45 TINGGI = 0.45 M

LEBAR = 0.20 M

JUMLAH S1 B. 4 M = 14.00 BH
0.2
VOL. BETON SLOOF S1 = panjang x lebar x tinggi X JUMLAH
5.75 x 0.20 x 0.45 X 14.00

VOL. BETON = 7.25 M3

BEKISTING = 72.45 m2

PEMBESIN
BESI ATAS MENERUS = 4.00 BTG
BESI ATAS TEPI = 1.00 BTG
BESI TENGAH MENERUS = 2.00 BTG
BESI BAWAH MENERUS = 3.00 BTG
BESI BAWAH TEPI = 1.00 BTG
JUMLAH BEUGEL = 47.00 BTG 47.00

- BESI TEPI ATAS D13 = 4.00 X 6.00

= 24.00 M = 25.01 KG

- BESI TEPI ATAS D13 = 2.00 X 1.56

= 3.12 M 3.251 KG

BESI TENGAH D13 = 2.00 X 6.00

= 12 M 7.40 KG

BESI TEPI BAWAH D 13 = 3.00 X 6.00

= 18.00 M 18.75 KG

BESI BAWAH LAPANGAN D 13 = 1.00 X 3.52

= 3.52 M 3.67 KG

VOLUME PEMBESIAN S1 B. 4 M = 813.05 KG

BEUGEL D8 = 47.00 X 0.59

= 27.73 M 86.18 KG

2 S2 PANJANG = 8.45 M
TINGGI = 0.20 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.56 M
0.2 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG

BEUGEL DIA. 8 = 0.39456 KG/M


TULANGAN DIA. 10 = 0.6165 KG/M

0.15 VOL. BETON = TINGGI X LEBAR X PANJANG


= 0.20 X 0.15 X 8.45
= 0.25 M3

VOL. BESI
V. BEUGEL

JUMLAH BEUGEL = 8.45 : 0.15


= 57.33 = 57.33 BTG

V. BEUGEL = PANJANG BEUGEL X JUMLAH BEUGEL


= 0.56 X 57.3333333333333
= 32.1066666666667 M1
= 12.67 KG

V. TULANGAN = J. TULANGAN X PANJANG


= 4 X 8.45
= 33.8 M1
= 20.84 KG

BEKISTING

V. BEKISTING = TINGGI X 2 X PANJANG


= 0.20 X 2 X 8.45
= 3.38 M2
2 BALOK TALANG PANJANG = 27.00 M
TINGGI = 0.20 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.56 M
0.2 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG

BEUGEL DIA. 6 = 0.39456 KG/M


TULANGAN DIA. 12 = 0.6165 KG/M

0.15 VOL. BETON = TINGGI X LEBAR X PANJANG


= 0.20 X 0.15 X 27
= 0.81 M3

VOL. BESI
V. BEUGEL

JUMLAH BEUGEL = 27 : 0.15


= 181.00 = 181.00 BTG

V. BEUGEL = PANJANG BEUGEL X JUMLAH BEUGEL


= 0.56 X 181
= 101.36 M1
= 39.99 KG
V. TULANGAN = J. TULANGAN X PANJANG
= 4 X 27
= 108 M1
= 66.58 KG

BEKISTING

V. BEKISTING = TINGGI X 2 X PANJANG


= 0.20 X 2 X 27
= 10.8 M2

2 rb PANJANG = 38.45 M
TINGGI = 0.20 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.56 M
0.2 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG

BEUGEL DIA. 6 = 0.39456 KG/M


TULANGAN DIA. 12 = 0.6165 KG/M

0.15 VOL. BETON = TINGGI X LEBAR X PANJANG


= 0.20 X 0.15 X 38.45
= 1.15 M3

VOL. BESI
V. BEUGEL

JUMLAH BEUGEL = 38.45 : 0.15


= 257.33 = 257.33 BTG

V. BEUGEL = PANJANG BEUGEL X JUMLAH BEUGEL


= 0.56 X 257.333333333333
= 144.106666666667 M1
= 56.86 KG

V. TULANGAN = J. TULANGAN X PANJANG


= 4 X 38.45
= 153.8 M1
= 94.82 KG

BEKISTING

V. BEKISTING = TINGGI X 2 X PANJANG


= 0.20 X 2 X 38.45
= 15.38 M2

B KOLOM
1 K1
JUMLAH KOLOM = 11.00 BH
TINGGI = 3.30 M
LEBAR = 0.63 M
0.63 PANJANG = 0.15 M

JUMLAH TULANGAN = 10.00 BH


JARAK BEUGEL = 0.15 M
PANJANG BEUGEL = 1.42 M
0.15
BERAT JENIS Ø10 = 0.62 KG/M
BERAT JENIS Ø8 = 0.395 KG/M

VOL. BETON = TINGGI X LEBAR X PANJANG X JUMLAH KOLOM


= 3.30 X 0.63 X 0.15 X 11.00
= 3.43 M3

BEKISTING = 56.63 M2

PEMBESIAN

VOL. TULANGAN = JUMLAH KOLOM X TINGGI X JUMLAH TULANGAN X BERAT JENIS Ø10
= 11.00 X 3.30 X 10.00 X 0.62
= 223.79 KG

VOL. BEUGEL

JUMLAH BEUGEL = TINGGI : JARAK BEUGEL X JUMLAH KOLOM


= 3.30 : 0.15 X 11.00
= 242.00 BH

VOL. BEUGEL = JUMLAH BEUGEL X PANJANG BEUGEL X BERAT JENIS Ø8


= 242.00 X 1.42 X 0.395
= 135.59 KG

1 k2\
JUMLAH KOLOM = 4.00 BH
TINGGI = 3.53 M
LEBAR = 0.30 M
0.3 PANJANG = 0.30 M

JUMLAH TULANGAN = 8.00 BH


JARAK BEUGEL = 0.15 M
PANJANG BEUGEL = 0.98 M
0.3
BERAT JENIS D 13 = 1.04 KG/M
BERAT JENIS Ø6 = 0.222 KG/M

VOL. BETON = TINGGI X LEBAR X PANJANG X JUMLAH KOLOM


= 3.53 X 0.30 X 0.30 X 4.00
= 1.27 M3

BEKISTING = 16.94 M2

PEMBESIAN

VOL. TULANGAN = JUMLAH KOLOM X TINGGI X JUMLAH TULANGAN X BERAT JENIS D 13


= 4.00 X 3.53 X 8.00 X 1.04
= 117.69 KG

VOL. BEUGEL
JUMLAH BEUGEL = TINGGI : JARAK BEUGEL X JUMLAH KOLOM
= 3.53 : 0.15 X 4.00
= 94.13 BH

VOL. BEUGEL = JUMLAH BEUGEL X PANJANG BEUGEL X BERAT JENIS Ø6


= 94.13 X 0.98 X 0.222
= 20.47 KG

2 KP
JUMLAH = 19.00 BH
TINGGI = 3.30 M

VOL. KOLOM = JUMLAH X TINGGI


= 34.00 X 3.10 + 3.8 x 39.00
= 253.60 M

C BALOK LATEI
2 15/20 PANJANG = 24.00 M 100.5 M
TINGGI = 0.20 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.56 M
0.2 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG

BEUGEL DIA. 6 = 0.222 KG/M


0.15 TULANGAN DIA. 10 = 0.617 KG/M

VOL. BETON = TINGGI X LEBAR X PANJANG


= 0.20 X 0.15 X 24
= 0.72 M3

VOL. BESI
V. BEUGEL

JUMLAH BEUGEL = 24 : 0.15


= 161.00 = 161 BTG

V. BEUGEL = PANJANG BEUGEL X JUMLAH BEUGEL


= 0.56 X 161
= 90.16 M1
= 20.02 KG

V. TULANGAN = J. TULANGAN X PANJANG


= 4 X 24
= 96 M1
= 59.23 KG

BEKISTING

V. BEKISTING = TINGGI X 2 X PANJANG


= 0.20 X 2 X 24
= 9.6 M2

LANTAI 2
A dak atap
1 PLAT LANTAI 2 TEBAL = 0.12 M
LUAS BIDANG = 275.02 M2

VOL BETON = TEBAL X LUAS BIDANG


= 0.12 X 275.02
= 33.0024 M3

VOL. BEKISTING = 275.02 M2

PEMBESIAN = 7590.552 KG

B ringbalk
1 rb1 PANJANG AS-AS = 6.00 M

PANJANG EFEKTIF = 5.75

0.4 TINGGI = 0.40 M

LEBAR = 0.20 M

JUMLAH rB1 B. 6 M = 14.00 BH


0.2
VOL. BETON SLOOF S1 = panjang x lebar x tinggi X JUMLAH
5.75 x 0.20 x 0.40 X 14.00

VOL. BETON = 6.44 M3

BEKISTING = 62.79 M2

PEMBESIN
BESI ATAS MENERUS = 3.00 BTG
BESI ATAS TEPI = 1.00 BTG
BESI TENGAH MENERUS = 2.00 BTG
BESI BAWAH MENERUS = 2.00 BTG
BESI BAWAH TEPI = 1.00 BTG
JUMLAH BEUGEL = 45.00 BTG 47.00

- BESI TEPI ATAS D13 = 3.00 X 6.00

= 18.00 M = 18.75 KG

- BESI TEPI ATAS D13 = 2.00 X 1.56

= 3.12 M 3.251 KG

BESI TENGAH D10 = 2.00 X 6.00

= 12 M 7.40 KG

BESI TEPI BAWAH D 13 = 2.00 X 6.00

= 12.00 M 12.50 KG

BESI BAWAH LAPANGAN D 13 = 1.00 X 3.52

= 3.52 M 3.67 KG

VOLUME PEMBESIAN BL1 B. 6 M = 638.02 KG ULIR


BEUGEL 10 = 47.00 X 0.98

= 46.06 M 143.15 KG POLOS

2 15/20 PANJANG = 35.85 M 100.5 M


TINGGI = 0.20 M
LEBAR = 0.15 M
PANJANG BEUGEL = TINGGI M
0.2 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG

BEUGEL DIA. 6 = 0.222 KG/M


0.15 TULANGAN DIA. 10 = 0.617 KG/M

VOL. BETON = TINGGI X LEBAR X PANJANG


= 0.20 X 0.15 X 35.85
= 1.08 M3

VOL. BESI
V. BEUGEL

JUMLAH BEUGEL = 35.85 : 0.15


= 240.00 = 161 BTG

V. BEUGEL = PANJANG BEUGEL X JUMLAH BEUGEL


= 0.56 X 161
= 90.16 M1
= 20.02 KG

V. TULANGAN = J. TULANGAN X PANJANG


= 4 X 35.85
= 143.4 M1
= 88.48 KG

BEKISTING

V. BEKISTING = TINGGI X 2 X PANJANG


= 0.20 X 2 X 35.85
= 14.34 M2

C KOLOM
1 K1
JUMLAH KOLOM = 9.00 BH
TINGGI = 3.50 M
LEBAR = 0.35 M
0.35 PANJANG = 0.35 M

JUMLAH TULANGAN = 8.00 BH


JARAK BEUGEL = 0.15 M
PANJANG BEUGEL = 1.20 M
0.35
BERAT JENIS D 16 = 1.58 KG/M
BERAT JENIS Ø8 = 0.395 KG/M

VOL. BETON = TINGGI X LEBAR X PANJANG X JUMLAH KOLOM


= 3.50 X 0.35 X 0.35 X 9.00
= 3.86 M3

BEKISTING = 44.10 M2

PEMBESIAN

VOL. TULANGAN = JUMLAH KOLOM X TINGGI X JUMLAH TULANGAN X BERAT JENIS D 16


= 9.00 X 3.50 X 8.00 X 1.58
= 398.16 KG

VOL. BEUGEL

JUMLAH BEUGEL = TINGGI : JARAK BEUGEL X JUMLAH KOLOM


= 3.50 : 0.15 X 9.00
= 210.00 BH

VOL. BEUGEL = JUMLAH BEUGEL X PANJANG BEUGEL X BERAT JENIS Ø8


= 210.00 X 1.20 X 0.395
= 99.54 KG

2 KP
JUMLAH = 2.00 BH
TINGGI = 3.50 M

VOL. KOLOM = JUMLAH X TINGGI


= 2.00 X 3.50
= 7.00 M

D BALOK LATEI
2 S2 PANJANG = 16.00 M
TINGGI = 0.15 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.44 M
0.15 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG

BEUGEL DIA. 6 = 0.222 KG/M


0.15 TULANGAN DIA. 10 = 0.617 KG/M

VOL. BETON = TINGGI X LEBAR X PANJANG


= 0.15 X 0.15 X 16
= 0.36 M3

VOL. BESI
V. BEUGEL

JUMLAH BEUGEL = 16 : 0.15


= 106.67 = 107 BTG

V. BEUGEL = PANJANG BEUGEL X JUMLAH BEUGEL


= 0.44 X 107
= 47.08 M1
= 10.45 KG

V. TULANGAN = J. TULANGAN X PANJANG


= 4 X 16
= 64 M1
= 39.49 KG

BEKISTING

V. BEKISTING = TINGGI X 2 X PANJANG


= 0.15 X 2 X 16
= 4.8 M2

TOP FLOOR
A PLAT LANTAI
1 PLAT LANTAI 2 TEBAL = 0.12 M
LUAS BIDANG = 52.41 M2

VOL BETON = TEBAL X LUAS BIDANG


= 0.12 X 52.41
= 6.2892 M3

VOL. BEKISTING = 40.73 M2

PEMBESIAN = 716.97 KG

B BALOK
1 B1 PANJANG AS-AS = 4.00 M

PANJANG EFEKTIF = 3.65

0.4 TINGGI = 0.40 M

LEBAR = 0.20 M

JUMLAH B1 B. 4 M = 16.00 BH
0.2
VOL. BETON SLOOF S1 = panjang x lebar x tinggi X JUMLAH
3.65 x 0.20 x 0.29 X 16.00

VOL. BETON = 3.39 M3

BEKISTING = 45.55 M2

PEMBESIN
BESI ATAS MENERUS = 2.00 BTG
BESI ATAS TEPI = 3.00 BTG
BESI TENGAH MENERUS = 2.00 BTG
BESI BAWAH MENERUS = 2.00 BTG
BESI BAWAH TEPI = 2.00 BTG
JUMLAH BEUGEL = 30.00 BTG 30.00

- BESI TEPI ATAS D16 = 2.00 X 4.00

= 8.00 M = 12.67 KG

- BESI TEPI ATAS D16 = 6.00 X 1.06

= 6.36 M 10.070 KG

BESI TENGAH D13 = 2.00 X 4.00

= 8 M 8.33 KG

BESI TEPI BAWAH D 16 = 2.00 X 4.00

= 8.00 M 12.67 KG

BESI BAWAH LAPANGAN D 16 = 2.00 X 2.52

= 5.04 M 7.98 KG

VOLUME PEMBESIAN BL1 B. 6 M = 827.47 KG ULIR

BEUGEL 10 = 30.00 X 1.00

= 30 M 18.51 KG POLOS

C KOLOM
1 KP
JUMLAH = 8.00 BH
TINGGI = 0.50 M

VOL. KOLOM = JUMLAH X TINGGI


= 8.00 X 0.50
= 4.00 M

D RINGBALK
1 RINGBALK
PANJANG = 24.00 M

E TANGGA
JUMLAH ANAK TANGGA = 18.00 BH
LEBAR TANGGA = 1.00 M1
PANJANG PLAT TANGGA = 6.14 M1
LEBAR BORDES = 1.07 M1
PANJANG BORDES = 2.07 M1
TEBAL PLAT = 0.12 M1
TINGGI ANAK TANGGA = 0.20 M1
LEBAR PIJAKAN = 0.30 M1
JUMLAH BORDES = 1.00 M1
JUMLAH TANGGA = 1.00 BH

VOL. BETON PLAT TANGGA = PANJANG PLAT TANGGA X LEBAR TANGGA X TEBAL PLAT

= 6.14 X 1.00 X 0.12

= 0.74 M3

VOL. BETON PLAT BORDES = LEBAR BORDES X PANJANG BORDES X TEBAL PLAT X J. BORDES

= 1.07 X 2.07 X 0.12 X 1.00

= 0.27 M3
BETON ANAK TANGGA =

0.50 X T. ANAK TANGGA X L. PIJAKAN X J. A. TANGGA X L. TANGGA

0.50 X 0.20 X 0.30 X 18.00 X 1.00

0.54 M3

BEGISTING = 12.04 M2

KERAMIK TANGGA 30/60 = 11.18 M2

PEMBESIAN PLAT DAN BORDES = 218.63 KG

PEMBESIAN ANAK TANGGA = 51.09 KG

RAILING TANGGA = 15.15 M2

RAILING BALKON = 4.00 M2


BILL OF QUANTITY
( BOQ )

PEKERJAAN : PERENCANAAN REHABILITASI KANTOR DPRD DI KABUPATEN KOLAKA TIMUR


LOKASI : KOLAKA TIMUR
TAHUN ANGGARAN : 2022

HARGA SATUAN TOTAL HARGA


NO URAIAN PEKERJAAN SATUAN VOLUME
(Rp) (Rp)

I. PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi Ls 1.00 Rp 5,000,000 Rp 5,000,000
2 Pek. Pembongkaran Dindding Ls 1.00 Rp 1,000,000 Rp 1,000,000
3 Pek. Pembongkaran Keramik Lantai dan Dinding Ls 1.00 Rp 10,000,000 Rp 10,000,000
4 Pek. Pembongkaran Atap Ls 1.00 Rp 15,000,000 Rp 15,000,000
5 Pek. Pembongkaran Plafon+rangka Ls 1.00 Rp 7,000,000 Rp 7,000,000
6 Pek. Pembongkaran Kusen Ls 1.00 Rp 500,000 Rp 500,000
7 Adminstrasi & Dokumentasi Ls 1.00 Rp 5,000,000 Rp 5,000,000
8 Papan Nama Proyek Ls 1.00 Rp 250,000 Rp 250,000
9 Penyediaan Air Bersih & Listrik Kerja Ls 1.00 Rp 2,000,000 Rp 2,000,000
10 Kesehatan & Keselamatan Kerja (K3) Ls 1.00 Rp 14,900,000 Rp 14,900,000
JUMLAH I Rp 60,650,000

II. PEKERJAAN PENAMBAHAN RUANG PANEL & KAMAR MANDI


1 Pek. Pondasi
-Pek. Galian M3 2.535 Rp 89,844 Rp 227,754
-Pek. Urugan Pasir M3 0.21125 Rp 270,538 Rp 57,151
-Pek. Batu Kosong M3 0.4225 Rp 530,194 Rp 224,007
-Pek. Pas. Batu Gunung M3 0.7605 Rp 1,021,194 Rp 776,618
2 Pek. Sloof 15/20
-Beton M3 0.25 Rp 1,290,508 Rp 327,144
-Pembesian dengan Besi Polos Kg 33.51 Rp 19,698 Rp 660,007
-Begisting M2 3.38 Rp 212,437 Rp 718,036
3 Pek. Kolom Praktis 11/11 M1 27 Rp 108,019 Rp 2,916,508
4 Pek. Ringbalk 10/15 M1 8.45 Rp 137,080 Rp 1,158,324
5 Pek. Pas. Dinding Batu Bata M2 34.625 Rp 135,656 Rp 4,697,075
6 Pek. Plasteran M2 69.25 Rp 75,606 Rp 5,235,741
7 Pek. Pemasangan Pintu
-P1 Bh 1.00 Rp 4,615,041 Rp 4,615,041
-P2 Bh 1.00 Rp 2,365,950 Rp 2,365,950
8 Pek. Lantai
-Pek. Penimbunan Tanah Didatangkan M3 2.40 Rp 101,344 Rp 243,225
-Pek.urugan Pasir M3 0.40 Rp 270,538 Rp 108,215
-Pek. Rabat Beton M3 0.40 Rp 1,164,620 Rp 465,848

JUMLAH II Rp 24,796,644

III. PEKERJAAN LANTAI DAN DINDING GRANIT


1 Pemasangan Keramik 60x60 Interior M² 113.42 Rp 311,794 Rp 35,363,655
2 Pemasangan Keramik KM 60x60 (Unpolished) M² 11.00 Rp 380,064 Rp 4,180,699
3 Pemasangan Dinding Keramik KM 60x60 KM M² 50.40 Rp 443,917 Rp 22,373,428
JUMLAH III Rp 61,917,782
IV. PEKERJAAN KUSEN
1 Kusen P1 Bh 2.00 Rp 4,615,041 Rp 9,230,082
JUMLAH IV Rp 9,230,082

V. PEKERJAAN PENGECATAN
1 Pek. Pengecatan Tembok Baru M² 76.90 Rp 29,635 Rp 2,278,952
2 Pek. Pengecatan Tembok Lama M² 387.00 Rp 23,139 Rp 8,954,655
3 Pek. Pengecatan Plafon M² 2,212.28 Rp 35,759 Rp 79,108,965
4 Pek. Pengecatan Kalsiplank M² 88.49 Rp 69,252 Rp 6,127,979
JUMLAH V Rp 96,470,551

VI. PEKERJAAN PLAFON


1 Pek. Rangka Hollow Plafon M² 2,212.28 Rp 121,963 Rp 269,816,859
2 Pek. Plafon Gypsun M² 1,591.00 Rp 65,761 Rp 104,625,608
3 Pek. Plafon Kalsiboard M² 621.28 Rp 60,657 Rp 37,684,897
4 Pek. List Plafon M' 1,436.71 Rp 37,667 Rp 54,116,531
JUMLAH VI Rp 466,243,895

VII. PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP


1 Pek. Atap Spandeks Hitam Kasar T. 0,35 mm M² 2,180.60 Rp 205,241 Rp 447,547,434
2 Pek. Nok atap Spandeks M' 250.00 Rp 85,434 Rp 21,358,375
3 Pek. Pemasangan Lapisan Membran Bakar Ls/m 308.97 Rp 205,000 Rp 63,338,850
4 Pek. Pemasangan Kalsiplank 2 Lapis M' 589.92 Rp 74,361 Rp 43,867,133
JUMLAH VII Rp 576,111,793

VIII. PEKERJAAN INSTALASI LISTRIK


1 pemasangan 1 Buah Titik Lapmu Bh 47.00 Rp 231,903 Rp 10,899,453
2 Kap Lampu Downlight Bh 47.00 Rp 95,850 Rp 4,504,950
3 Pemasangan Lampu LED 20 Watt Bh 47.00 Rp 102,350 Rp 4,810,450
4 Pemasangan Saklar Ganda Bh 7.00 Rp 63,900 Rp 447,300
5 Pemasangan Saklar Tunggal Bh 2.00 Rp 31,950 Rp 63,900
JUMLAH VIII Rp 20,726,053

IX. PEKERJAAN SANITASI


1 Pemasangan Kloset Duduk ex TOTO Bh 3.00 Rp 4,697,382 Rp 14,092,146
2 pemasangan Pipa PVC 3/4 Inchi M' 16.00 Rp 29,457 Rp 471,306
3 pemasangan Pipa PVC 1 Inchi M' 12.00 Rp 50,813 Rp 609,753
4 pemasangan Pipa PVC 3 Inchi M' 8.00 Rp 66,798 Rp 534,382
5 pemasangan Pipa PVC 4 Inchi M' 12.00 Rp 152,224 Rp 1,826,689
6 Pemasangan Jet Washer Bh 3.00 Rp 460,661 Rp 1,381,984
7 Pemasangan Keran Air 3/4 Inchi Bh 3.00 Rp 81,161 Rp 243,484
8 Pemasangan Floor Drain Bh 3.00 Rp 113,879 Rp 341,636
9 Pemasangan Washtafle Bh 3.00 Rp 2,024,696 Rp 6,074,089
10 Pek. Septictank Ls 1.00 Rp 15,000,000 Rp 15,000,000
JUMLAH IX Rp 40,575,469

X. PEKERJAAN AKHIR
1 Pembersihan Akhir Ls 1.00 Rp 5,000,000 Rp 5,000,000
JUMLAH X Rp 5,000,000
REKAPITULASI
BILL OF QUANTITY

PEKERJAAN : PERENCANAAN REHABILITASI KANTOR DPRD DI KABUPATEN KOLAKA TIMUR


LOKASI : KOLAKA TIMUR
TAHUN ANGGARAN : 2022

JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp )

I. PEKERJAAN PENDAHULUAN Rp 34,750,000.00


III. PEKERJAAN PENAMBAHAN RUANG PANEL & KAMAR MANDI Rp 29,183,227.30
IV. PEKERJAAN LANTAI DAN DINDING GRANIT Rp 61,917,782.45
V. PEKERJAAN KUSEN Rp 9,230,081.59
VI. PEKERJAAN PENGECATAN Rp 96,470,551.33
VII. PEKERJAAN PLAFON Rp 466,243,894.53
VIII. PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP Rp 576,111,792.60
IX. PEKERJAAN INSTALASI LISTRIK Rp 20,726,052.75
X. PEKERJAAN SANITASI Rp 33,575,468.81
XI. PEKERJAAN AKHIR Rp 5,000,000.00

A REAL COST = Rp Rp 1,333,208,851.35


B PPN 11 % = Rp Rp 146,652,973.65
C TOTAL(A+B) = Rp.
TERBILANG :

KOLAKA TIMUR, …………………. 2022


DIBUAT OLEH:
PT/CV. ....................................

DIREKTUR/DIREKTRIS
NO JENIS PEKERJAAN GAMBAR/SKETS PERHITUNGAN
b POER PLAT P2
1 GALIAN TANAH POER PLAT JUMLAH = 14.00 BH

TINGGI = 0.60 M

LEBAR = 1.30 M

0.60 PANJANG = 1.30 M

VOL. GALIAN = panjang x lebar x tinggi x jumlah


1.30 = 1.30 x 1.30 x 0.6 x 14.00
= 14.20 M3

2 LANTAI KERJA JUMLAH = 14.00 BH

TINGGI = 0.05 M

0.05 LEBAR = 1.30 M

PANJANG = 1.30 M
1.30
VOL. LANTAI KERJA = panjang x lebar x tinggi x jumlah
1.30 x 1.30 x 0.05 x 14.00
= 1.18 M3

3 PASIR URUG JUMLAH = 14.00 BH

TINGGI = 0.05 M

0.05 LEBAR = 1.30 M

PANJANG = 1.30 M
1.30
VOL. PASIR URUG P1 = panjang x lebar x tinggi x jumlah
1.30 x 1.30 x 0.05 x 14.00
= 1.18 M3

4 VOL. POER PLAT JUMLAH = 14.00 BH

TINGGI = 0.30 M
0.3
PANJANG 1.20 M

LEBAR = 1.20 M
1.20
VOL. POER PLAT TINGGI X PANJANG X LEBAR X JUMLAH
=

= 0.30 X 1.20 X 1.20 X 14.00

= 6.05 M3

BEKISTING = ((PANJANG X 2) + (LEBAR X 2)) X TINGGI X JUMLAH

= ((1,2 X 2) + (1,2 X 2)) X 0.30 X 14.00

= 20.16 M2

PEMBESIAN = 418.08 KG polos

4 VOL. urugan tanah kembali = volume galian - 8.41


URUGAN TANAH KEMBALI
PONDASI POER PLAT
= 14.20 - 8.414

= 5.78 M3

e KOLOM PEDESTAL
PANJANG = 0.41 M

TINGGI = 3.45 M

0.41 LEBAR = 0.31 M

JUMLAH KOLOM = 14.00 BH

VOL. KOLOM PEDESTAL = PANJANG x LEBAR x TINGGI x J. KOLOM


0.31 0.41 x 0.31 x 3.45 x 14.00
= 6.14 M3

BEGISTING = TINGGI X ((PANJANG X 2) X (LEBAR X 2)) X J. KOLOM

= 3.45 X ((0,41 X 2) X (0,31X 2)) X 14.00

= 69.55 M2

JUMLAH BESI = 8.00 BH 10.00

PANJANG BEUGEL = 0.98 M

PANJANG TULANGAN = 3.45 M

JARAK BEUGEL = 0.15 M

PANJANG BESI = JUMLAH BESI X PANJANG TULANGAN X JUMLAH KOLOM

= 8.00 X 3.45 X 14.00

= 386.40 M = 401.856 KG ULIR

JUMLAH BEUGEL = TINGGI KOLOM : JARAK BEUGEL X JUMLAH KOLOM

= 3.45 : 0.15 X 14.00

= 336.00 BH
PANJANG BEUGEL = JUMLAH BEUGEL X PANJANG BEUGEL

= 336.00 X 0.98

= 329.28 M = 73.08 KG POLOS


REKAPITULASI
ENGINEERING ESTIMATE

PEKERJAAN : PERENCANAAN REHABILITASI KANTOR DPRD DI KABUPATEN KOLAKA TIMUR


LOKASI : KOLAKA TIMUR
TAHUN ANGGARAN : 2022

JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp )

I. PEKERJAAN PENDAHULUAN Rp 34,750,000.00


II. SMK3 Rp 18,142,500.00
III. PEKERJAAN PENAMBAHAN RUANG PANEL & KAMAR MANDI Rp 29,183,227.30
IV. PEKERJAAN LANTAI DAN DINDING GRANIT Rp 61,917,782.45
V. PEKERJAAN KUSEN Rp 9,230,081.59
VI. PEKERJAAN PENGECATAN Rp 96,470,551.33
VII. PEKERJAAN PLAFON Rp 466,243,894.53
VIII. PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP Rp 576,111,792.60
IX. PEKERJAAN INSTALASI LISTRIK Rp 20,726,052.75
X. PEKERJAAN SANITASI Rp 33,575,468.81
XI. PEKERJAAN AKHIR Rp 5,000,000.00

A REAL COST = Rp Rp 1,351,351,351.35


B PPN 11 % = Rp Rp 148,648,648.65
C TOTAL(A+B) = Rp. Rp 1,500,000,000.00
TERBILANG :

SATU MILYAR LIMA RATUS JUTA RUPIAH

KOLAKA TIMUR, …………………. 2022


DIBUAT OLEH:
CV. ALL DESIGN CONSULTANT

SUARDIN, ST.
DIREKTUR
ENGINEERING ESTIMATE
( EE )
PEKERJAAN : PERENCANAAN REHABILITASI KANTOR DPRD DI KABUPATEN KOLAKA TIMUR
LOKASI : KOLAKA TIMUR
TAHUN ANGGARAN : 2022

HARGA SATUAN TOTAL HARGA


NO URAIAN PEKERJAAN SATUAN VOLUME
(Rp) (Rp)

I. PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi Ls 1.00 Rp 3,500,000 Rp 3,500,000
2 Pek. Pembongkaran Dindding Ls 1.00 Rp 1,000,000 Rp 1,000,000
3 Pek. Pembongkaran Keramik Lantai dan Dinding Ls 1.00 Rp 9,000,000 Rp 9,000,000
4 Pek. Pembongkaran Atap Ls 1.00 Rp 10,000,000 Rp 10,000,000
5 Pek. Pembongkaran Plafon+rangka Ls 1.00 Rp 6,000,000 Rp 6,000,000
6 Pek. Pembongkaran Kusen Ls 1.00 Rp 500,000 Rp 500,000
7 Adminstrasi & Dokumentasi Ls 1.00 Rp 3,500,000 Rp 3,500,000
8 Papan Nama Proyek Ls 1.00 Rp 250,000 Rp 250,000
9 Penyediaan Air Bersih & Listrik Kerja Ls 1.00 Rp 1,000,000 Rp 1,000,000
JUMLAH I Rp 34,750,000

II. SMK3
A Penyiapan RKK
-Pembuatan Dokumen Set
set 1.00 Rp 1,000,000 Rp 1,000,000
-Pembuatan Prosedur & Instruksi Kerja
-Penyiapan Formulir
B Sosialisasi, Promosi dan Pelatihan
1 Induksi K3 (Safety Induction) Org 15.00 Rp 7,500 Rp 112,500
2 Pengarahan K3 (Safety Briefing) Org 12.00 Rp 15,000 Rp 180,000
3 Pelatihan K3 Rp -
a. Bekerja diketinggian Org 12.00 Rp 7,500 Rp 90,000
4 Simulasi K3 Org 12.00 Rp 7,500 Rp 90,000
5 Spanduk (Banner) Lbr 1.00 Rp 150,000 Rp 150,000
6 Poster Lbr 1.00 Rp 50,000 Rp 50,000
7 Papan Informasi K3 Bh 1.00 Rp 500,000 Rp 500,000
C Alat Pelindung Kerja & Alat Pelindung Diri
1 Alat Pelindung Diri :
a. Topi Pelindung (Safety Helmet) Bh 23.00 Rp 60,000 Rp 1,380,000
b. Pelindung Mata (Goggles Spectacles) Bh 15.00 Rp 30,000 Rp 450,000
d. Pelindung Pernafasan & Mulut (Masker) Bh 80.00 Rp 1,500 Rp 120,000
e. Sarung Tangan (Safety Gloves) Psg 60.00 Rp 20,000 Rp 1,200,000
f. Sepatu Keselamatan (Safety Shoes) Psg 15.00 Rp 150,000 Rp 2,250,000
g. Penunjang Seluruh Tubuh (Full Body Harness) Bh 4.00 Rp 750,000 Rp 3,000,000
h. Rompi Keselamatan (Safety Vest) Bh 23.00 Rp 25,000 Rp 575,000
j. Pelindung Jatuh (Fall Arrester) Bh 5.00 Rp 100,000 Rp 500,000
D Asuransi
1 Asuransi Ls 1.00 Rp 1,500,000 Rp 1,500,000
E Fasilitas Sarana & Prasarana Kesehatan
1 Peralatan P3K (Kotak P3K, Obat Luka, dll) Ls 1.00 Rp 300,000 Rp 300,000
2 Peralatan Pengasapan (Fogging) Ls 1.00 Rp 500,000 Rp 500,000
F Rambu-Rambu
1 Rambu Petunjuk Bh 1.00 Rp 75,000 Rp 75,000
2 Rambu Larangan Bh 1.00 Rp 75,000 Rp 75,000
3 Rambu Peringatan Bh 1.00 Rp 75,000 Rp 75,000
4 Rambu Kewajiban Bh 1.00 Rp 75,000 Rp 75,000
5 Rambu Informasi Bh 1.00 Rp 75,000 Rp 75,000
6 Jalur Evakuasi (Escape Route) Ls 1.00 Rp 300,000 Rp 300,000
G Lain-Lain
1 Alat Pemedam Api Ringan (APAR) Bh 1.00 Rp 750,000 Rp 750,000
2 Bendera K3 Bh 1.00 Rp 150,000 Rp 150,000
3 Program Inspeksi Ls 1.00 Rp 2,000,000 Rp 2,000,000
4 Pelaporan & Penyelidikan Insiden Ls 1.00 Rp 500,000 Rp 500,000
5 Pembuatan Kartu Identitas Pekerja (KIP) Lbr 12.00 Rp 10,000 Rp 120,000
JUMLAH II Rp 18,142,500

III. PEKERJAAN PENAMBAHAN RUANG PANEL & KAMAR MANDI


1 Pek. Pondasi
-Pek. Galian M3 2.535 Rp 89,844 Rp 227,754
-Pek. Urugan Pasir M3 0.21125 Rp 270,538 Rp 57,151
-Pek. Batu Kosong M3 0.4225 Rp 530,194 Rp 224,007
-Pek. Pas. Batu Gunung M3 0.7605 Rp 1,021,194 Rp 776,618
2 Pek. Sloof 15/20
-Beton M3 0.25 Rp 1,290,508 Rp 327,144
-Pembesian dengan Besi Polos Kg 33.51 Rp 19,698 Rp 660,007
-Begisting M2 3.38 Rp 212,437 Rp 718,036
3 Pek. Kolom Praktis 11/11 M1 27 Rp 108,019 Rp 2,916,508
4 Pek. Ringbalk 10/15 M1 8.45 Rp 137,080 Rp 1,158,324
5 Pek. Pas. Dinding Batu Bata M2 34.625 Rp 135,656 Rp 4,697,075
6 Pek. Plasteran M2 69.25 Rp 75,606 Rp 5,235,741
7 Pek. Acian M3 69.25 Rp 44,199 Rp 3,060,804
8 Pek. Pemasangan Pintu
-P1 Bh 1.00 Rp 5,307,297 Rp 5,307,297
-P2 Bh 1.00 Rp 2,720,843 Rp 2,720,843
9 Pek. Lantai
-Pek. Penimbunan Tanah Didatangkan M3 5.15 Rp 101,344 Rp 521,856
-Pek.urugan Pasir M3 0.40 Rp 270,538 Rp 108,215
-Pek. Rabat Beton M3 0.40 Rp 1,164,620 Rp 465,848

JUMLAH III Rp 29,183,227

IV. PEKERJAAN LANTAI DAN DINDING GRANIT


1 Pemasangan Granit 60x60 Interior M² 113.42 Rp 311,794 Rp 35,363,655
2 Pemasangan Granit KM 60x60 (Unpolished) M² 11.00 Rp 380,064 Rp 4,180,699
3 Pemasangan Dinding Granit KM 60x60 KM M² 50.40 Rp 443,917 Rp 22,373,428
JUMLAH IV Rp 61,917,782
V. PEKERJAAN KUSEN
1 Kusen P1 Bh 2.00 Rp 4,615,041 Rp 9,230,082
JUMLAH V Rp 9,230,082

VI. PEKERJAAN PENGECATAN


1 Pek. Pengecatan Tembok Baru M² 76.90 Rp 29,635 Rp 2,278,952
2 Pek. Pengecatan Tembok Lama M² 387.00 Rp 23,139 Rp 8,954,655
3 Pek. Pengecatan Plafon M² 2,212.28 Rp 35,759 Rp 79,108,965
4 Pek. Pengecatan Kalsiplank M² 88.49 Rp 69,252 Rp 6,127,979
JUMLAH VI Rp 96,470,551

VII. PEKERJAAN PLAFON


1 Pek. Rangka Hollow Plafon M² 2,212.28 Rp 121,963 Rp 269,816,859
2 Pek. Plafon Gypsun M² 1,591.00 Rp 65,761 Rp 104,625,608
3 Pek. Plafon Kalsiboard M² 621.28 Rp 60,657 Rp 37,684,897
4 Pek. List Plafon M' 1,436.71 Rp 37,667 Rp 54,116,531
JUMLAH VII Rp 466,243,895

VIII. PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP


1 Pek. Atap Spandeks Hitam Kasar T. 0,35 mm M² 2,180.60 Rp 205,241 Rp 447,547,434
2 Pek. Nok atap Spandeks M' 250.00 Rp 85,434 Rp 21,358,375
3 Pek. Pemasangan Lapisan Membran Bakar M² 308.97 Rp 205,000 Rp 63,338,850
4 Pek. Pemasangan Kalsiplank 2 Lapis M' 589.92 Rp 74,361 Rp 43,867,133
JUMLAH VIII Rp 576,111,793

IX. PEKERJAAN INSTALASI LISTRIK


1 pemasangan 1 Buah Titik Lapmu Bh 47.00 Rp 231,903 Rp 10,899,453
2 Kap Lampu Downlight Bh 47.00 Rp 95,850 Rp 4,504,950
3 Pemasangan Lampu LED 20 Watt Bh 47.00 Rp 102,350 Rp 4,810,450
4 Pemasangan Saklar Ganda Bh 7.00 Rp 63,900 Rp 447,300
5 Pemasangan Saklar Tunggal Bh 2.00 Rp 31,950 Rp 63,900
JUMLAH IX Rp 20,726,053

X. PEKERJAAN SANITASI
1 Pemasangan Kloset Duduk ex TOTO Bh 3.00 Rp 4,697,382 Rp 14,092,146
2 pemasangan Pipa PVC 3/4 Inchi M' 16.00 Rp 29,457 Rp 471,306
3 pemasangan Pipa PVC 1 Inchi M' 12.00 Rp 50,813 Rp 609,753
4 pemasangan Pipa PVC 3 Inchi M' 8.00 Rp 66,798 Rp 534,382
5 pemasangan Pipa PVC 4 Inchi M' 12.00 Rp 152,224 Rp 1,826,689
6 Pemasangan Jet Washer Bh 3.00 Rp 460,661 Rp 1,381,984
7 Pemasangan Keran Air 3/4 Inchi Bh 3.00 Rp 81,161 Rp 243,484
8 Pemasangan Floor Drain Bh 3.00 Rp 113,879 Rp 341,636
9 Pemasangan Washtafle Bh 3.00 Rp 2,024,696 Rp 6,074,089
10 Pek. Septictank Ls 1.00 Rp 8,000,000 Rp 8,000,000
JUMLAH X Rp 33,575,469
XI. PEKERJAAN AKHIR
1 Pembersihan Akhir Ls 1.00 Rp 5,000,000 Rp 5,000,000
JUMLAH XI Rp 5,000,000
DAFTAR UPAH DAN HARGA BAHAN

NO URAIAN JENIS TENAGA/BAHAN SATUAN HARGA SATUAN

1 2 3 4
I UPAH TENAGA KERJA
1 Pekerja Hari 100,000.00
2 Tukang Batu Hari 110,000.00
3 Tukang Kayu Hari 110,000.00
4 Tukang Besi Hari 110,000.00
5 Tukang Cat Hari 110,000.00
6 Kepala Tukang Hari 120,000.00
7 Mandor Hari 125,000.00

II HARGA BAHAN
A. Bahan Dasar
1 Tanah Urug Didatangkan M3 50,000.00
2 Pasir Urug M3 170,000.00
3 Pasir Pasang M3 250,000.00
4 Pasir Beton M3 250,000.00
Kg 178.57
5 Air Kerja Ltr 50.00
6 Kerikil M3 350,000.00
Kg 259.26
7 Semen Portland @ 50 Kg Zak 76,680.00
8 Semen Portland Kg 1,533.60
9 Semen Warna Kg 26,625.00
10 Batu Belah M3 214,286.00
11 Batu Bata Merah Bh 650.00
12 Minyak Pelumas Ltr 17,573.00
13 Koral Hambur M2 75,000.00
B. Bahan Lantai
1 Granit 60 x 60 Cm (Exterior) Bh 72,400.00
2 Granit 60 x 60 Cm (Interior) Bh 53,250.00
3 Granit 10 x 60 Bh 45,900.00
Keramik 20x20 cm Bh 2,769.00
Keramik 50x20 cm Bh 4,326.56
C. Bahan Besi dan Paku
1 Besi Polos Kg 14,500.00
2 Paku Campur (5, 7, 10 Cm) Kg 20,000.00
3 Baut Railing Bh 1,500.00
4 Paku Sekrup Kg 27,900.00
5 Skrup Fixer Bh 1,500.00
6 Kawat Beton Kg 20,000.00
7 Baut Mur Bh 10,000.00
8 Hollow 20.40 mm (Baja Ringan) M1 3,700.00
9 Hollow 40.40 mm (Baja Ringan) M1 5,000.00
D. Bahan Alumunium, Kaca & Kunci
1 Kusen Alumunium 4" M1 134,000.00
2 Sealant Tube 7,455.00
3 Daun Pintu Swing Standard Unit 2,500,000.00
4 Daun Pintu Double Teakwood Unit 3,500,000.00
5 Daun Pintu Alumunium (+Aksesoris) Unit 1,500,000.00
6 Kaca Polos 5 mm M2 170,400.00
7 Handel Pintu Stainless Bh 170,400.00
8 Penggantung Kesmen Bh 65,000.00
9 Esel Pintu Alumunium Psg 26,625.00
Bh 13,312.50
10 Frame Alumunium M1 76,500.00
11 Baja ringan canai dingin C75 Btg 95,850.00
12 Reng M1 7,988.00
13 skrub Bh 250.00

E. Bahan Cat dan Minyak


1 Cat Dasar Kg 18,638.00
2 Cat Penutup Kg 53,250.00
3 Minyak Bekisting Ltr 17,575.00
4 Plamur Tembok Kg 53,250.00
5 Plamir Kayu Kg 48,990.00
6 Cat menie Kg 26,625.00
7 Cat Kilap Kayu (sejenis Avian) Kg 63,900.00
8 Kuas Bh 31,950.00
9 Thener Ltr 26,625.00
10 Ampelas Lembar 7,445.00

F. Bahan Kayu dan Atap


1 Balok Kayu Kls II M3 3,200,000.00
2 Papan Kayu Kls III M3 2,000,000.00
3 Balok Kayu Kls III M3 2,000,000.00
4 Atap Spandeck T.0,3 M 127,000.00
5 Plywood T=9 mm Lbr 213,000.00
6 Dolken Btg 10,000.00
7 Gibsum Board (240x120Cm) Lbr 95,850.00
8 Fiber Tape Gypsun Roll 25,000.00
9 Kalsi Board Lbr 90,525.00
10 List Gypsum M1 12,500.00
11 Kalsiplank M 24,406.25
12 Nok Atap M 40,000.00
13 Roof Light Fiberglass 90x180 M 204,000.00
14 List Kayu Profil M 20,000.00
G. Bahan Elektrikal
1 Saklar Ganda Ex. Panasonic/Setara, SNI Bh 63,900.00
2 Saklar Tunggal Ex. Panasonic/Setara, SNI Bh 31,950.00
3 T. Dus Bh 10,650.00
4 Las Dop Bh 3,195.00
5 Pipa Listrik 5/8 Btg 8,395.00
6 Lampu LED 9 watt Bh 35,000.00
7 Lampu LED 20 watt Bh 102,350.00
8 Kotak Kontak Biasa Bh 31,950.00
9 Lampu RM 2X 36 Watt Bh 380,000.00
10 Kabel NYM M1 13,312.50
11 Pemasangan Lampu LED Strip M1 20,000.00
12 Kap Lampu Downlight BH 95,850.00
13 MCB 10A BH 106,500.00

H. Bahan Sanitasi
1 Kloset Duduk Bh 3,408,000.00
2 Wastafel Dinding ex. Toto Bh 1,071,000.00
3 Floor Drain Bh 85,200.00
4 Kran Air 1/2 '' Bh 20,000.00
5 Sealtape Bh 6,000.00
6 Pipa PVC 3/4 '' M 9,319.00
7 Pipa PVC 2 '' M 21,300.00
8 Pipa PVC 4" M 69,225.00
9 Jetwasher Bh 350,000.00
10 Tandon Air 1200 Liter Bh 2,300,000.00
RINCIAN DAFTAR KUANTITAS DAN HARGA
BIAYA PENYELENGGARAAN SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)

Satuan Harga Satuan Total Harga


No. Uraian Pekerjaan Kuantitas
Ukuran (Rp) (Rp)
A Penyiapan RKK

1 Pembuatan Dokumen Rencana Keselamatan Konstruksi


Set 1.00 1,000,000.00 1,000,000.00
2 Pembuatan Prosedur & Instruksi Kerja
3 Penyiapan Formulir
Sub Total Penyiapan RKK 1,000,000.00
B Sosialisasi, Promosi dan Pelatihan
1 Induksi K3 (Safety Induction) Org 15.00 7,500.00 112,500.00
2 Pengarahan K3 (Safety Briefing) Org 12.00 15,000.00 180,000.00
3 Pelatihan K3
a. Bekerja diketinggian Org 12.00 7,500.00 90,000.00
b. Penggunaan Bahan Kimia (MSDS) Org - 1,500.00 -
4 Simulasi K3 Org 12.00 7,500.00 90,000.00
5 Spanduk (Banner) Lbr 1.00 150,000.00 150,000.00
6 Poster Lbr 1.00 50,000.00 50,000.00
7 Papan Informasi K3 Bh 1.00 500,000.00 500,000.00
Sub Total Sosialisasi, Promosi dan Pelatihan 1,172,500.00
C Alat Pelindung Kerja & Alat Pelindung Diri
1 Alat Pelindung Kerja :
a. Jaring Pengaman (Safety Net) Ls - 540,000.00 -
b. Tali Keselamatan ( Life Line) Ls - 3,600,000.00 -
c. Pagar Pengaman (Guard Railling) Ls - 3,600,000.00 -
d. Pembatas Area (Restricted Area) Ls - 70,000.00 -
2 Alat Pelindung Diri :
a. Topi Pelindung (Safety Helmet) Bh 25.00 60,000.00 1,500,000.00
b. Pelindung Mata (Goggles Spectacles) Bh - 30,000.00 -
c. Tameng Muka (Face Shield) Bh - 300,000.00 -
d. Pelindung Pernafasan & Mulut (Masker) Bh 120.00 1,500.00 180,000.00
e. Sarung Tangan (Safety Gloves) Psg 60.00 20,000.00 1,200,000.00
f. Sepatu Keselamatan (Safety Shoes) Psg 15.00 150,000.00 2,250,000.00
g. Penunjang Seluruh Tubuh (Full Body Harness) Bh - 750,000.00 -
h. Rompi Keselamatan (Safety Vest) Bh 25.00 25,000.00 625,000.00
i. Celemek (Apron/Coveralls) Bh - 150,000.00 -
j. Pelindung Jatuh (Fall Arrester) Bh 5.00 100,000.00 500,000.00
Sub Total Sosialisasi, Promosi dan Pelatihan 6,255,000.00
D Asuransi
1 Asuransi Ls 1.00 1,500,000.0 1,500,000.00
Sub Total Asuransi 1,500,000.00
E Personil K3 Konstruksi
1 Ahli K3 Konstruksi OB - 10,000,000.00 -
2 Petugas K3 Konstruksi OB - 2,500,000.00 -
Sub Total Personil K3 Konstruksi -
F Fasilitas Sarana & Prasarana Kesehatan
1 Peralatan P3K (Kotak P3K, Obat Luka, dll) Ls 1.00 300,000.00 300,000.00
2 Peralatan Pengasapan (Fogging) Ls 1.00 500,000.00 500,000.00
Sub Total Fasilitas Sarana & Prasarana Kesehatan 800,000.00
G Rambu-Rambu
1 Rambu Petunjuk Bh 1.00 75,000.00 75,000.00
2 Rambu Larangan Bh 1.00 75,000.00 75,000.00
3 Rambu Peringatan Bh 1.00 75,000.00 75,000.00
4 Rambu Kewajiban Bh 1.00 75,000.00 75,000.00
5 Rambu Informasi Bh 1.00 75,000.00 75,000.00
6 Jalur Evakuasi (Escape Route) Ls 1.00 300,000.00 300,000.00
Sub Total Rambu-Rambu 675,000.00
H Konsultasi Ahli
1 Konsultasi Ahli K3 Konstruksi OJ - - -
Sub Total Konsultasi Ahli -
I Lain-Lain
Alat Pemedam Api Ringan (APAR) Bh 1.00 750,000.00 750,000.00
Bendera K3 Bh 1.00 150,000.00 150,000.00
Program Inspeksi Ls - 2,000,000.00 -
Pelaporan & Penyelidikan Insiden Ls 1.00 500,000.00 500,000.00
Pembuatan Kartu Identitas Pekerja (KIP) Lbr 12.00 10,000.00 120,000.00
Sub Total Lain-Lain 1,520,000.00
J J u m l a h (A+B+C+D+E+F+G+H+I) 12,922,500.00
K Overhead & Profit 15.0% X D 1,938,375.00
L Harga Satuan Pekerjaan (J+K) 14,900,000.00
A.1.1.1 HARGA SATUAN PEKERJAAN PERSIAPAN
A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.10 100,000.00 10,000.00
Tukang Kayu OH 0.10 110,000.00 11,000.00
Kepala Tukang OH 0.01 120,000.00 1,200.00
Mandor OH 0.005 125,000.00 625.00
JUMLAH TENAGA KERJA 22,825.00
B BAHAN
Kayu balok 5/7 m³ 0.01 3,200,000.00 38,400.00
Paku 2”-3” Kg 0.02 20,000.00 400.00
Kayu papan 3/20 m³ 0.01 2,000,000.00 14,000.00
JUMLAH HARGA BAHAN 52,800.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 75,625.00
E Overhead & Profit 15% xD 11,343.75
F Harga Satuan Pekerjaan (D+E) 86,968.75
Analisis Harga Satuan Pekerjaan (AHSP)
A.2.3.1. HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1. Menggali 1 m³ tanah biasa sedalam 1 m'
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.750 100,000.00 Rp 75,000.00
Mandor L.04 OH 0.025 125,000.00 Rp 3,125.00
Jumlah Tenaga Kerja Rp 78,125.00
B BAHAN

Jumlah Harga Bahan Rp -


C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 78,125.00
E Overhead & Profit 15% X D Rp 11,718.75
F Harga Suatu Pekerjaan (D+E) Rp 89,843.75

A.2.3.1.9. Pengurugan kembali 1 m³ galian tanah


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.5000 100,000.00 Rp 50,000.00
Mandor L.04 OH 0.0500 125,000.00 Rp 6,250.00
Jumlah Tenaga Kerja Rp 56,250.00
B BAHAN

Jumlah Harga Bahan Rp -


C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 56,250.00
E Overhead & Profit 15% X D Rp 8,437.50
F Harga Suatu Pekerjaan (D+E) Rp 64,687.50

Anl. Tanah Page 27


A.2.3.1.11. Pengurungan 1 m³ dengan pasir urug
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 100,000.00 Rp 30,000.00
Mandor L.04 OH 0.010 125,000.00 Rp 1,250.00
Jumlah Tenaga Kerja Rp 31,250.00
B BAHAN
Pasir Urug m³ 1.200 170,000.00 Rp 204,000.00
Jumlah Harga Bahan Rp 204,000.00
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 235,250.00
E Overhead & Profit 15% X D Rp 35,287.50
F Harga Suatu Pekerjaan (D+E) Rp 270,537.50

A.2.3.1.14. Pengurugan 1 m³ tanah urug didatangkan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 100,000.00 Rp 25,000.00
Mandor L.04 OH 0.025 125,000.00 Rp 3,125.00
Jumlah Tenaga Kerja Rp 28,125.00
B BAHAN
Tanah Urug m³ 1.200 50,000.00 Rp 60,000.00
Jumlah Harga Bahan Rp 60,000.00
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 88,125.00
E Overhead & Profit 15% X D Rp 13,218.75
F Harga Suatu Pekerjaan (D+E) Rp 101,343.75

Anl. Tanah Page 28


Analisis Harga Satuan Pekerjaan (AHSP)
A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.1 Pemasangan 1 m³ pondasi batu belah campuran 1SP : 3PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 100,000.00 Rp 150,000.00
Tukang Batu L.02 OH 0.750 110,000.00 Rp 82,500.00
Kepala Tukang L.03 OH 0.075 120,000.00 Rp 9,000.00
Mandor L.04 OH 0.075 125,000.00 Rp 9,375.00
Jumlah Tenaga Kerja Rp 250,875.00
B BAHAN
Batu Belah m³ 1.200 214,286.00 Rp 257,143.20
Semen Portland Kg 202.000 1,533.60 Rp 309,787.20
Pasir Pasang m³ 0.485 250,000.00 Rp 121,250.00
Jumlah Harga Bahan Rp 688,180.40
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 939,055.40
E Overhead & Profit 15% X D Rp 140,858.31
F Harga Suatu Pekerjaan (D+E) Rp 1,079,913.71

A.3.2.1.2 Pemasangan 1 m³ pondasi batu belah campuran 1SP : 4PP


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 100,000.00 Rp 150,000.00
Tukang Batu L.02 OH 0.750 110,000.00 Rp 82,500.00
Kepala Tukang L.03 OH 0.075 120,000.00 Rp 9,000.00
Mandor L.04 OH 0.075 125,000.00 Rp 9,375.00
Jumlah Tenaga Kerja Rp 250,875.00
B BAHAN
Batu Belah m³ 1.200 214,286.00 Rp 257,143.20
Semen Portland Kg 163.000 1,533.60 Rp 249,976.80
Pasir Pasang m³ 0.520 250,000.00 Rp 130,000.00
Jumlah Harga Bahan Rp 637,120.00
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 887,995.00
E Overhead & Profit 15% X D Rp 133,199.25
F Harga Suatu Pekerjaan (D+E) Rp 1,021,194.25

Anl. Pondasi Page 29


A.3.2.1.9. (K3) Pemasangan 1 m³ batu kosong (anstamping)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.780 100,000.00 Rp 78,000.00
Tukang Batu L.02 OH 0.390 110,000.00 Rp 42,900.00
Kepala Tukang L.03 OH 0.039 120,000.00 Rp 4,680.00
Mandor L.04 OH 0.039 125,000.00 Rp 4,875.00
Jumlah Tenaga Kerja Rp 130,455.00
B BAHAN
Batu Belah m³ 1.200 214,286.00 Rp 257,143.20
Pasir Urug m³ 0.432 170,000.00 Rp 73,440.00
Jumlah Harga Bahan Rp 330,583.20
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 461,038.20
E Overhead & Profit 15% X D Rp 69,155.73
F Harga Suatu Pekerjaan (D+E) Rp 530,193.93

Anl. Pondasi Page 30


A.4.1.1 HARGA
A.4.1.1.1. SATUAN
Pembuatan 1 mPEKERJAAN BETON
3
Beton Mutu f’c = 7,4 Mpa (K100) Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 100,000.00 165,000.00
Tukang batu L.02 OH 0.275 110,000.00 30,250.00
Kepala tukang L.03 OH 0.028 120,000.00 3,360.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
JUMLAH TENAGA KERJA 208,985.00
B BAHAN
Semen Portland Kg 247.00 1,533.60 378,799.20
Pasir Beton Kg 869.00 178.57 155,178.57
Kerikil Kg 999.00 259.26 259,000.00
Air Kg 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 803,727.77
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,012,712.77
E Overhead & Profit 0.150 xD 151,906.92
F Harga Satuan Pekerjaan (D+E) 1,164,619.69

A.4.1.1.5. Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 100,000.00 165,000.00
Tukang batu L.02 OH 0.275 110,000.00 30,250.00
Kepala tukang L.03 OH 0.028 120,000.00 3,360.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
JUMLAH TENAGA KERJA 208,985.00
B BAHAN
Semen Portland Kg 326.00 1,533.60 499,953.60
Pasir Beton Kg 760.00 178.57 135,714.29
Kerikil Kg 1,029.00 259.26 266,777.78
Air Ltr 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 913,195.66
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,122,180.66
E Overhead & Profit 0.150 xD 168,327.10
F Harga Satuan Pekerjaan (D+E) 1,290,507.76
A.4.1.1.8. Pembuatan 1 m3 Beton Mutu f’c = 21,7 Mpa (K250)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 100,000.00 165,000.00
Tukang batu L.02 OH 0.275 110,000.00 30,250.00
Kepala tukang L.03 OH 0.028 120,000.00 3,360.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
JUMLAH TENAGA KERJA 208,985.00
B BAHAN
Semen Portland Kg 384.00 1,533.60 588,902.40
Pasir Beton Kg 760.00 178.57 135,714.29
Kerikil Kg 1,029.00 259.26 266,777.78
Air Ltr 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 1,002,144.46
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,211,129.46
E Overhead & Profit 0.150 xD 181,669.42
F Harga Satuan Pekerjaan (D+E) 1,392,798.88

A.4.1.1.17 Pembesian 10 kg dengan besi polos


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 100,000.00 7,000.00
Tukang besi L.02 OH 0.070 110,000.00 7,700.00
Kepala tukang L.03 OH 0.007 120,000.00 840.00
Mandor L.04 OH 0.004 125,000.00 500.00
JUMLAH TENAGA KERJA 16,040.00
B BAHAN
Besi polos Kg 10.500 14,500.00 152,250.00
Kawat beton Kg 0.150 20,000.00 3,000.00
JUMLAH HARGA BAHAN 155,250.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 171,290.00
E Overhead & Profit 0.150 xD 25,693.50
F Harga Satuan Pekerjaan (D+E) 196,983.50
G Harga Satuan Pekerjaan 1 Kg Besi 19,698.35
A.4.1.1.19. Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 100,000.00 52,000.00
Tukang kayu L.02 OH 0.260 110,000.00 28,600.00
Kepala tukang L.03 OH 0.026 120,000.00 3,120.00
Mandor L.04 OH 0.026 125,000.00 3,250.00
JUMLAH TENAGA KERJA 86,970.00
B BAHAN
Kayu kelas III m³ 0.045 2,000,000.00 90,000.00
Paku 5 cm – 10 cm Kg 0.300 20,000.00 6,000.00
Minyak bekisting Ltr 0.100 17,575.00 1,757.50
JUMLAH HARGA BAHAN 97,757.50
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 184,727.50
E Overhead & Profit 0.150 xD 27,709.13
F Harga Satuan Pekerjaan (D+E) 212,436.63

A.4.1.1.20. Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 100,000.00 66,000.00
Tukang kayu L.02 OH 0.330 110,000.00 36,300.00
Kepala tukang L.03 OH 0.033 120,000.00 3,960.00
Mandor L.04 OH 0.033 125,000.00 4,125.00
JUMLAH TENAGA KERJA 110,385.00
B BAHAN
Kayu kelas III m³ 0.040 2,000,000.00 80,000.00
Paku 5 cm – 12 cm Kg 0.400 20,000.00 8,000.00
Minyak bekisting Ltr 0.200 17,575.00 3,515.00
Balok kayu kelas II m³ 0.015 3,200,000.00 48,000.00
Plywood tebal 9 mm Lbr 0.350 213,000.00 74,550.00
Dolken kayu Ø 8-10cm –panj 4 m Btg 2.000 10,000.00 20,000.00
JUMLAH HARGA BAHAN 234,065.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 344,450.00
E Overhead & Profit 0.150 xD 51,667.50
F Harga Satuan Pekerjaan (D+E) 396,117.50
A.4.1.1.21. Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 100,000.00 66,000.00
Tukang kayu L.02 OH 0.330 110,000.00 36,300.00
Kepala tukang L.03 OH 0.033 120,000.00 3,960.00
Mandor L.04 OH 0.033 125,000.00 4,125.00
JUMLAH TENAGA KERJA 110,385.00
B BAHAN
Kayu kelas III m³ 0.040 2,000,000.00 80,000.00
Paku 5 cm – 12 cm Kg 0.400 20,000.00 8,000.00
Minyak bekisting Ltr 0.200 17,575.00 3,515.00
Balok kayu kelas II m³ 0.018 3,200,000.00 57,600.00
Plywood tebal 9 mm Lbr 0.350 213,000.00 74,550.00
Dolken kayu (8–10) cm 4 m Btg 2.000 10,000.00 20,000.00
JUMLAH HARGA BAHAN 243,665.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 354,050.00
E Overhead & Profit 0.150 xD 53,107.50
F Harga Satuan Pekerjaan (D+E) 407,157.50

A.4.1.1.22. Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 100,000.00 66,000.00
Tukang kayu L.02 OH 0.330 110,000.00 36,300.00
Kepala tukang L.03 OH 0.033 120,000.00 3,960.00
Mandor L.04 OH 0.033 125,000.00 4,125.00
JUMLAH TENAGA KERJA 110,385.00
B BAHAN
Kayu kelas III m3 0.040 2,000,000.00 80,000.00
Paku 5 cm – 12 cm kg 0.400 20,000.00 8,000.00
Minyak bekisting Liter 0.200 17,575.00 3,515.00
Balok kayu kelas II m3 0.015 3,200,000.00 48,000.00
Plywood tebal 9 mm Lbr 0.350 213,000.00 74,550.00
Dolken Btg 6.000 10,000.00 60,000.00
JUMLAH HARGA BAHAN 274,065.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 384,450.00
E Overhead & Profit 0.150 xD 57,667.50
F Harga Satuan Pekerjaan (D+E) 442,117.50
A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.180 100,000.00 18,000.00
Tukang batu L.02 OH 0.020 110,000.00 2,200.00
Tukang kayu L.02 OH 0.020 110,000.00 2,200.00
Tukang besi L.02 OH 0.020 110,000.00 2,200.00
Kepala tukang L.03 OH 0.006 120,000.00 720.00
Mandor L.04 OH 0.009 125,000.00 1,125.00
JUMLAH TENAGA KERJA 26,445.00
B BAHAN
Kayu kelas III m3 0.002 2,000,000.00 4,000.00
Paku 5 cm – 12 cm kg 0.010 20,000.00 200.00
Minyak bekisting Liter -
Besi beton polos kg 3.000 14,500.00 43,500.00
Kawat beton kg 0.450 20,000.00 9,000.00
Semen Portland kg 4.000 1,533.60 6,134.40
Pasir Beton m3 0.006 250,000.00 1,500.00
Kerikil m3 0.009 350,000.00 3,150.00
JUMLAH HARGA BAHAN 67,484.40
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 93,929.40
E Overhead & Profit 0.150 xD 14,089.41
F Harga Satuan Pekerjaan (D+E) 108,018.81

A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.297 100,000.00 29,700.00
Tukang batu L.02 OH 0.033 110,000.00 3,630.00
Tukang kayu L.02 OH 0.033 110,000.00 3,630.00
Tukang besi L.02 OH 0.033 110,000.00 3,630.00
Kepala tukang L.03 OH 0.010 120,000.00 1,200.00
Mandor L.04 OH 0.015 125,000.00 1,875.00
JUMLAH TENAGA KERJA 43,665.00
B BAHAN
Kayu kelas III m3 0.003 2,000,000.00 6,000.00
Paku 5 cm – 12 cm kg 0.020 20,000.00 400.00
Minyak bekisting Liter -
Besi beton polos kg 3.600 14,500.00 52,200.00
Kawat beton kg 0.050 20,000.00 1,000.00
Semen Portland kg 5.500 1,533.60 8,434.80
Pasir beton m3 0.009 250,000.00 2,250.00
Kerikil m3 0.015 350,000.00 5,250.00
JUMLAH HARGA BAHAN 75,534.80
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 119,199.80
E Overhead & Profit 0.150 xD 17,879.97
F Harga Satuan Pekerjaan (D+E) 137,079.77
A.4.1.1.36 (SPL) Membuat 1 m’ balok latei beton bertulang (10 x 15) cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.297 100,000.00 29,700.00
Tukang batu L.02 OH 0.033 110,000.00 3,630.00
Tukang kayu L.02 OH 0.033 110,000.00 3,630.00
Tukang besi L.02 OH 0.033 110,000.00 3,630.00
Kepala tukang L.03 OH 0.010 120,000.00 1,200.00
Mandor L.04 OH 0.015 125,000.00 1,875.00
JUMLAH TENAGA KERJA 43,665.00
B BAHAN
Kayu kelas III m3 0.003 2,000,000.00 6,000.00
Paku 5 cm – 12 cm kg 0.020 20,000.00 400.00
Minyak bekisting Liter -
Besi beton polos kg 3.600 14,500.00 52,200.00
Kawat beton kg 0.050 20,000.00 1,000.00
Semen Portland kg 5.500 1,533.60 8,434.80
Pasir beton m3 0.009 250,000.00 2,250.00
Kerikil m3 0.015 350,000.00 5,250.00
JUMLAH HARGA BAHAN 75,534.80
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 119,199.80
E Overhead & Profit 0.150 xD 17,879.97
F Harga Satuan Pekerjaan (D+E) 137,079.77
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.043 100,000.00 4,300.00
Tukang khusus Alumunium L.03 OH 0.043 Err:509 Err:509
Kepala tukang L.03 OH 0.004 120,000.00 516.00
Mandor L.04 OH 0.002 125,000.00 262.50
JUMLAH TENAGA KERJA Err:509
B BAHAN
Profil alluminium m 1.10
Skrup fixer buah 2.00
Sealant Tube 0.06
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.12. Pemasangan 1 m2 pintu alluminium strip lebar 8 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.09
Tukang khusus 0.09
allumunium L.03 OH
Kepala tukang L.03 OH 0.01
Mandor L.04 OH 0.00
JUMLAH TENAGA KERJA
B BAHAN
Profil alluminium m 4.40
Alluminium strip m 14.60
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.09
Tukang 0.09
allumunium/kaca L.03 OH
Kepala tukang L.03 OH 0.01
Mandor L.04 OH 0.01
JUMLAH TENAGA KERJA
B BAHAN
Pintu alluminium m 4.40
Profil kaca m 4.50
Sealant Tube 0.27
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.17. Pemasangan 1 m2 jendela nako & tralis


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.20
Tukang L.03 OH 0.20
Kepala tukang L.03 OH 0.02
Mandor L.04 OH 0.00
JUMLAH TENAGA KERJA
B BAHAN
Jendela nako m2 1.10
(rangka + kaca 5 mm)
Paku skrup buah 10.00
1 cm – 2,5 cm
Besi strip m 7.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.20
Tukang L.03 OH 0.20
Kepala tukang L.03 OH 0.02
Mandor L.04 OH 0.00
JUMLAH TENAGA KERJA
B BAHAN
Seng pelat m 1.05
Paku 1 cm - 2,5 cm kg 0.02
Papan kayu kelas II m3 0.02
atau III
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.19 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.15
Tukang L.03 OH 0.30
Kepala tukang L.03 OH 0.03
Mandor L.04 OH 0.01
JUMLAH TENAGA KERJA
B BAHAN
Seng pelat m 1.05
Paku 1 cm – 2,5 cm kg 0.01
Besi strip kg 0.50
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.20.Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, untuk partisi
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.25
Tukang besi L.02 OH 0.25
Kepala tukang L.03 OH 0.03
Mandor L.04 OH 0.01
JUMLAH TENAGA KERJA
B BAHAN
Rangka metal M1 3.50
hollow 40.40.2 mm
Assesoris Ls 100% x
(perkuatan, las dll) rangka
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, untuk plafon
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.35
Tukang besi L.02 OH 0.35
Kepala tukang L.03 OH 0.04
Mandor L.04 OH 0.02
JUMLAH TENAGA KERJA
B BAHAN
Rangka metal M1 4.00
hollow 40.40.2 mm
Assesoris Ls 100%xrangka
(perkuatan, las
dll)

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.22. (K3) Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.73
Tukang besi L.02 OH 0.73
Kepala tukang L.03 OH 0.07
Mandor L.04 OH 0.04
JUMLAH TENAGA KERJA
B BAHAN
Baja ringan canai dingin C75 kg 3.07
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan % 10.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.22. (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.76
Tukang besi L.02 OH 7,604.00
Kepala tukang L.03 OH 0.08
Mandor L.04 OH 0.04
JUMLAH TENAGA KERJA
B BAHAN
Baja ringan canai kg 4.05
dingin C75
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan % 10.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
Analisis Harga Satuan Pekerjaan (AHSP)
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.3 Pemasangan 1 m² plesteran 1SP : 3PP tebal 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 100,000.00 Rp 30,000.00
Tukang Batu L.03 OH 0.1500 110,000.00 Rp 16,500.00
Kepala Tukang L.03 OH 0.0150 120,000.00 Rp 1,800.00
Mandor L.04 OH 0.0150 125,000.00 Rp 1,875.00
Jumlah Tenaga Kerja Rp 50,175.00
B BAHAN
Semen Portland Kg 7.7760 1,533.60 Rp 11,925.27
Pasir Pasang m³ 0.0230 250,000.00 Rp 5,750.00
Jumlah Harga Bahan Rp 17,675.27
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 67,850.27
E Overhead & Profit 15% X D Rp 10,177.54
F Harga Suatu Pekerjaan (D+E) Rp 78,027.81

A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 100,000.00 Rp 30,000.00
Tukang Batu L.03 OH 0.1500 110,000.00 Rp 16,500.00
Kepala Tukang L.03 OH 0.0150 120,000.00 Rp 1,800.00
Mandor L.04 OH 0.0150 125,000.00 Rp 1,875.00
Jumlah Tenaga Kerja Rp 50,175.00
B BAHAN
Semen Portland Kg 6.2400 1,533.60 Rp 9,569.66
Pasir Pasang m³ 0.0240 250,000.00 Rp 6,000.00
Jumlah Harga Bahan Rp 15,569.66
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 65,744.66
E Overhead & Profit 15% X D Rp 9,861.70
F Harga Suatu Pekerjaan (D+E) Rp 75,606.36

Anl. Plesteran Page 42


Analisis Harga Satuan Pekerjaan (AHSP)
A.4.4.3 HARGA SATUAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.13 (Anl.Spl) Pemasangan 1 m² lantai granit eksterior ukuran 60 cm x 60 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 0.2400 100,000.00 Rp 24,000.00
2 Tukang Batu L.03 OH 0.1200 110,000.00 Rp 13,200.00
3 Kepala Tukang L.03 OH 0.0120 120,000.00 Rp 1,440.00
4 Mandor L.04 OH 0.0120 125,000.00 Rp 1,500.00
Jumlah Tenaga Kerja Rp 40,140.00
B BAHAN
1 Granit 60 x 60 cm Bh 3.1000 72,400.00 Rp 224,440.00
2 Semen Portland Kg 9.6000 1,533.60 Rp 14,722.56
3 Semen Warna Kg 1.5000 26,625.00 Rp 39,937.50
4 Pasir Pasang M3 0.0450 250,000.00 Rp 11,250.00
Jumlah Harga Bahan Rp 290,350.06
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 330,490.06
E Overhead & Profit 15% X D Rp 49,573.51
F Harga Suatu Pekerjaan (D+E) Rp 380,063.57

A.4.4.3.13 (Anl.Spl) Pemasangan 1 m² lantai granit interior ukuran 60 cm x 60 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 0.2400 100,000.00 Rp 24,000.00
2 Tukang Batu L.03 OH 0.1200 110,000.00 Rp 13,200.00
3 Kepala Tukang L.03 OH 0.0120 120,000.00 Rp 1,440.00
4 Mandor L.04 OH 0.0120 125,000.00 Rp 1,500.00
Jumlah Tenaga Kerja Rp 40,140.00
B BAHAN
1 Granit 60 x 60 cm Bh 3.1000 53,250.00 Rp 165,075.00
2 Semen Portland Kg 9.6000 1,533.60 Rp 14,722.56
3 Semen Warna Kg 1.5000 26,625.00 Rp 39,937.50
4 Pasir Pasang M3 0.0450 250,000.00 Rp 11,250.00
Jumlah Harga Bahan Rp 230,985.06
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 271,125.06
E Overhead & Profit 15% X D Rp 40,668.76

Anl. Lantai dan Dinding Page 43


F Harga Suatu Pekerjaan (D+E) Rp 311,793.82

Anl. Lantai dan Dinding Page 44


A.4.4.3.54 (Anl. Spl) Pemasangan 1 m² dinding granit ukuran 60 cm x 60 cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 0.9000 100,000.00 Rp 90,000.00
2 Tukang Batu L.03 OH 0.4500 110,000.00 Rp 49,500.00
3 Kepala Tukang L.03 OH 0.0450 120,000.00 Rp 5,400.00
4 Mandor L.04 OH 0.0450 125,000.00 Rp 5,625.00
Jumlah Tenaga Kerja Rp 150,525.00
B BAHAN
1 Granit 60 x 60 cm Bh 3.1000 53,250.00 Rp 165,075.00
2 Semen Portland Kg 9.3000 1,533.60 Rp 14,262.48
3 Semen Warna Kg 1.9400 26,625.00 Rp 51,652.50
4 Pasir Pasang M3 0.0180 250,000.00 Rp 4,500.00
Jumlah Harga Bahan Rp 235,489.98
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 386,014.98
E Overhead & Profit 15% X D Rp 57,902.25
F Harga Suatu Pekerjaan (D+E) Rp 443,917.23

Anl. Lantai dan Dinding Page 45


Analisis Harga Satuan Pekerjaan (AHSP)
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.8 Pemasangan 1 m² dinding bata merah ( 5x11x22 ) cm tebal 1/2 batu campuran 1SP : 3PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
TENAGA
Pekerja L.01 OH 0.3000 100,000.00 Rp 30,000.00
Tukang Batu L.03 OH 0.1000 110,000.00 Rp 11,000.00
Kepala Tukang L.03 OH 0.0100 120,000.00 Rp 1,200.00
Mandor L.04 OH 0.0150 125,000.00 Rp 1,875.00
Jumlah Tenaga Kerja Rp 44,075.00
B BAHAN
Bata Merah Bh 70.0000 650.00 Rp 45,500.00
Semen Portland Kg 14.3700 1,533.60 Rp 22,037.83
Pasir Pasang m³ 0.0400 250,000.00 Rp 10,000.00
Jumlah Harga Bahan Rp 77,537.83
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 121,612.83
E Overhead & Profit 15% X D Rp 18,241.92
F Harga Suatu Pekerjaan (D+E) Rp 139,854.76

A.4.4.1.9 Pemasangan 1 m² dinding bata merah ( 5x11x22 ) cm tebal 1/2 batu campuran 1SP : 4PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 100,000.00 Rp 30,000.00
Tukang Batu L.03 OH 0.1000 110,000.00 Rp 11,000.00
Kepala Tukang L.03 OH 0.0100 120,000.00 Rp 1,200.00
Mandor L.04 OH 0.0150 125,000.00 Rp 1,875.00
Jumlah Tenaga Kerja Rp 44,075.00
B BAHAN
Bata Merah Bh 70.0000 650.00 Rp 45,500.00
Semen Portland Kg 11.5000 1,533.60 Rp 17,636.40
Pasir Pasang m³ 0,043 250,000.00 Rp 10,750.00
Jumlah Harga Bahan Rp 73,886.40
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 117,961.40
E Overhead & Profit 15% X D Rp 17,694.21
F Harga Suatu Pekerjaan (D+E) Rp 135,655.61

Anl. Pas. Dinding Page 46


Analisa Pekerjaan Kusen, Pintu & Partisi
Analisa Pintu + Jendela
Type PJ1
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
1 Kusen Alumunium 4 " 19.66 m' Rp 134,000.00 Rp 2,634,440
2 Daun Pintu Swing Standard 2.00 Unit Rp 2,500,000.00 Rp 5,000,000
3 * Spare Part & Instalation 2.00 Unit Err:509 Err:509
4 Kaca Polos 8 mm 8.88 m² Err:509 Err:509
5 Silikon/Sealant 29.70 m' Err:509 Err:509
6 Pemasangan & Perakitan 9.45 m² Err:509 Err:509
* engsel 4in, lockset lidah & Hendle Lever
** frictian stay tipe HD & rambuncis
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Type PJ2

No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 33.67 m' Rp 134,000.00 Rp 4,511,780


2 Daun Pintu Swing Standard 1.00 Unit Rp 2,500,000.00 Rp 2,500,000
3 * Spare Part & Instalation 1.00 Unit Err:509 Err:509
4 Kaca Polos 8 mm 12.15 m² Err:509 Err:509
5 Sandblash Full Block 6.57 m² Err:509 Err:509
6 Silikon/Sealant 52.00 m' Err:509 Err:509
7 Pemasangan & Perakitan 13.55 m² Err:509 Err:509
* engsel 4in, lockset lidah & Hendle Lever
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Analisa Pintu
Type P1
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 5.18 m' Rp 134,000.00 694,120.00


2 Daun Pintu Swing Standard 1.00 Unit Rp 2,500,000.00 2,500,000.00
3 * Spare Part & Instalation 1.00 Unit Err:509 Err:509
4 Kaca Polos 8 mm 1.45 m² Err:509 Err:509
5 Silikon/Sealant 5.00 m' Err:509 Err:509
6 Pemasangan & Perakitan 1.89 m² Err:509 Err:509
* engsel 4in, lockset lidah & Hendle Lever
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Type P2

No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 5.20 m' Rp 134,000.00 696,800.00


2 Daun Pintu Teakwood 1.77 Unit Rp 2,500,000.00 4,428,000.00
3 * Spare Part & Instalation 1.00 Unit Err:509 Err:509
4 Pemasangan & Perakitan 1.94 m² Err:509 Err:509
* engsel 4in, lockset lidah & Hendle Lever
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Type P3

No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 5.10 m' Rp 134,000.00 683,400.00


2 Daun Pintu Alumunium + ACC (engsel 3 bh, 1.00 Unit Rp 2,500,000.00 2,500,000.00
handle + lockcase)
3 Pemasangan & Perakitan 1.72 m² Err:509 Err:509
* engsel 4in, lockset lidah & Hendle Lever
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Analisa Jendela
Type J1

No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 60.40 m' Rp 134,000.00 8,093,600.00


2 Kaca Polos 8 mm 22.95 m² Err:509 Err:509
3 Silikon/Sealant 79.96 m' Err:509 Err:509
4 Pemasangan & Perakitan 26.55 m² Err:509 Err:509
** frictian stay tipe HD & rambuncis
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Type J2
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 14.20 m' Rp 134,000.00 1,902,800.00


2 Daun Jendela Casement Jungkit (100x100 cm) 17.08 m' Err:509 Err:509
3 ** Spare Part & Instalation 5.00 Unit Err:509 Err:509
4 Kaca Polos 5 mm 2.39 m² Rp 170,400.00 407,153.76
5 Silikon/Sealant 14.18 m' Err:509 Err:509
6 Pemasangan & Perakitan 4.16 m² Err:509 Err:509
** frictian stay tipe HD & rambuncis
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Type J3

No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 10.35 m' Rp 134,000.00 1,386,900.00


2 Daun Jendela Casement Jungkit (100x100 cm) 12.92 m' Err:509 Err:509
3 ** Spare Part & Instalation 4.00 Unit Err:509 Err:509
4 Kaca Polos 5 mm 1.46 m² Rp 170,400.00 248,886.24
5 Silikon/Sealant 9.72 m' Err:509 Err:509
6 Pemasangan & Perakitan 2.96 m² Err:509 Err:509
** frictian stay tipe HD & rambuncis
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Type J4

No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 20.95 m' Rp 134,000.00 2,807,300.00


2 Daun Jendela Casement Jungkit (100x100 cm) 19.32 m' Err:509 Err:509
3 ** Spare Part & Instalation 4.00 Unit Err:509 Err:509
4 Kaca Polos 5 mm 5.52 m² Rp 170,400.00 941,425.92
5 Silikon/Sealant 26.32 m' Err:509 Err:509
6 Pemasangan & Perakitan 3.65 m² Err:509 Err:509
** frictian stay tipe HD & rambuncis
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Type J5
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 45.63 m' Rp 134,000.00 6,114,420.00


2 Daun Jendela Casement Jungkit (100x100 cm) 33.04 m' Err:509 Err:509
3 ** Spare Part & Instalation 4.00 Unit Err:509 Err:509
4 Kaca Polos 5 mm 24.76 m² Rp 170,400.00 4,219,768.56
5 Silikon/Sealant 109.48 m' Err:509 Err:509
6 Pemasangan & Perakitan 33.28 m² Err:509 Err:509
** frictian stay tipe HD & rambuncis
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509
Analisa Ventilasi
Type V1

No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 16.22 m' Rp 134,000.00 2,173,480.00


2 Jalusi Alumunium 3.00 Unit Err:509 Err:509
3 Kaca Polos 5 mm 1.78 m² Rp 170,400.00 303,312.00
4 Silikon/Sealant 7.56 m' Err:509 Err:509
5 Pemasangan & Perakitan 4.63 m² Err:509 Err:509
** frictian stay tipe HD & rambuncis
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509

Type V2

No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)

1 Kusen Alumunium 4 " 1.60 m' Rp 134,000.00 214,400.00


2 Kaca Polos 5 mm 0.13 m² Rp 170,400.00 22,833.60
3 Silikon/Sealant 1.36 m' Err:509 Err:509
4 Pemasangan & Perakitan 0.15 m² Err:509 Err:509
A Jumlah Err:509
B Overhead & Profit 15% x A Err:509
C Harga Satuan Pekerjaan (A+B) Err:509
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

A.4.2.1.22. Pemasangan 1 m2 Atap Pelana Rangka Atap Baja Ringan (Canai Dingin) profil C75 rangka atap baja canai dingin profil
C75
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.734 100,000.00 73,400.00
Tukang besi L.02 OH 0.734 110,000.00 80,740.00
Kepala tukang L.03 OH 0.073 120,000.00 8,760.00
Mandor L.04 OH 0.037 125,000.00 4,625.00
JUMLAH TENAGA KERJA 167,525.00
B BAHAN
Baja ringan canai dingin C75 Btg 0.873 95,850.00 83,677.05
83,677.05
C PERALATAN
Peralatan % 10% 95,850.00 9,585.00
JUMLAH HARGA ALAT 9,585.00
D Jumlah (A+B+C) 260,787.05
E Overhead & Profit 15% xD 39,118.06
F Harga Satuan Pekerjaan (D+E) 299,905.11
A.4.2.1.24. Pemasangan 1 m Kusen Aluminium
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0430 100,000.00 Rp 4,300.00
Tukang Besi Konstruksi L.03 OH 0.0430 110,000.00 Rp 4,730.00
Kepala Tukang L.03 OH 0.0043 120,000.00 Rp 516.00
Mandor L.04 OH 0.0021 125,000.00 Rp 262.50
Jumlah Tenaga Kerja Rp 9,808.50
B BAHAN
Kusen Alumunium 4" M' 1.1000 134,000.00 Rp 147,400.00
Skrup Fixer Bh 2.0000 1,500.00 Rp 3,000.00
Sealant Tube 0.0600 7,455.00 Rp 447.30
Jumlah Harga Bahan Rp 150,847.30
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 160,655.80
E Overhead & Profit 0% X D Rp -
F Harga Suatu Pekerjaan (D+E) Rp 160,655.80
SPL Pemasangan 1 m Bingkai Daun Jendele alluminium
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0430 100,000.00 Rp 4,300.00
Tukang Besi Konstruksi L.03 OH 0.0430 110,000.00 Rp 4,730.00
Kepala Tukang L.03 OH 0.0043 120,000.00 Rp 516.00
Mandor L.04 OH 0.0021 125,000.00 Rp 262.50
Jumlah Tenaga Kerja Rp 9,808.50
B BAHAN
frame Alumunium M' 1.1000 76,500.00 Rp 84,150.00
Sealant Tube 0.0600 7,455.00 Rp 447.30
Alat Bantu + Accessoris dll Ls 1.0000 8,415.00 Rp 8,415.00
Jumlah Harga Bahan Rp 93,012.30
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 102,820.80
E Overhead & Profit 0% X D Rp -
F Harga Suatu Pekerjaan (D+E) Rp 102,820.80

A.4.2.1.21 Spl. Pemasangan 1 m2 Rangka hollow Galvalume 40.40. dan 20.40 mm, untuk plafon
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 100,000.00 35,000.00
Tukang besi L.02 OH 0.350 110,000.00 38,500.00
Kepala tukang L.03 OH 0.035 120,000.00 4,200.00
Mandor L.04 OH 0.018 125,000.00 2,250.00
JUMLAH TENAGA KERJA 79,950.00
B BAHAN
Hollow 20.40 mm (baja Ringan) m' 3.800 3,700.00 14,060.00
Hollow 40.40 mm (baja Ringan) m' 1.800 5,000.00 9,000.00
Aksesoris % 35.000 8,700.00 3,045.00
JUMLAH HARGA BAHAN 26,105.00
C PERALATAN
Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 106,055.00
E Overhead & Profit 15% xD 15,908.25
F Harga Satuan Pekerjaan (D+E) 121,963.25
Analisis Harga Satuan Pekerjaan (AHSP)

1 (Anl. Spl) Pek. Pintu P1


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan (Rp) Harga (Rp)
A TENAGA KERJA

Jumlah Tenaga Kerja -


B BAHAN
1 Pas. Kusen Alluminium M' 5.180 160,655.80 832,197.04
2 Pas. Daun Pintu Double Teakwood Lapis HPL Unit 1.000 3,500,000.00 3,500,000.00
3 Pas. Handel Pintu Stainless Bh 1.000 233,025.00 233,025.00
4 Pas. Engsel Pintu Stainless Psg 1.500 33,212.50 49,818.75
Jumlah Bahan 4,615,040.79
C PERALATAN
1 Alat Bantu % - - -
Jumlah Peralatan -
D Jumlah A + B + C 4,615,040.79
E Overhead & Profit 15% XD 692,256.12
F Harga Suatu Pekerjaan (D+E) 5,307,296.91

4 (Anl. Spl) Pek. Pintu P2


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan (Rp) Harga (Rp)
A TENAGA KERJA

Jumlah Tenaga Kerja -


B BAHAN
1 Pas. Kusen Alluminium M' 5.080 160,655.80 816,131.46
2 Pas. Daun Pintu Aluminium Unit 1.000 1,500,000.00 1,500,000.00
3 Pas. Engsel Pintu Kesmen Psg 1.500 33,212.50 49,818.75
Jumlah Bahan 2,365,950.21
C PERALATAN
1 Alat Bantu % - - -
Jumlah Peralatan -
D Harga Satuan A + B + C 2,365,950.21
E Overhead & Profit 15% XD 354,892.53
F Harga Suatu Pekerjaan (D+E) 2,720,842.75
Analisis Harga Satuan Pekerjaan (AHSP)
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
A.4.6.2.2(Anl. Spl) Pemasangan 1 buah hendel pintu stenlis
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0100 100,000.00 Rp 1,000.00
Tukang Kayu L.02 OH 0.5000 110,000.00 Rp 55,000.00
Kepala Tukang L.03 OH 0.0500 120,000.00 Rp 6,000.00
Mandor L.04 OH 0.0050 125,000.00 Rp 625.00
Jumlah Tenaga Kerja Rp 62,625.00
B BAHAN
Hendel Pintu Stenlis Bh 1.0000 170,400.00 Rp 170,400.00
Jumlah Harga Bahan Rp 170,400.00
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 233,025.00
E Overhead & Profit 0% X D Rp -
F Harga Suatu Pekerjaan (D+E) Rp 233,025.00

A.4.6.2.5 Pemasangan 1 buah engsel pintu Alumunium


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0150 100,000.00 Rp 1,500.00
Tukang Kayu L.02 OH 0.1500 110,000.00 Rp 16,500.00
Kepala Tukang L.03 OH 0.0150 120,000.00 Rp 1,800.00
Mandor L.04 OH 0.0008 125,000.00 Rp 100.00
Jumlah Tenaga Kerja Rp 19,900.00
B BAHAN
Engsel Pintu Alumunium Bh 1.0000 Rp 13,312.50 Rp 13,312.50
Jumlah Harga Bahan Rp 13,312.50
C PERALATAN

Jumlah Harga Alat Rp -


D J u m l a h (A+B+C) Rp 33,212.50
E Overhead & Profit 0% X D Rp -
F Harga Suatu Pekerjaan (D+E) Rp 33,212.50

Anl. Kunci dan Kaca Page 54


A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
A.4.7.1.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,07 100,000.00 7,000.00
Tukang cat L.02 OH 0,105 110,000.00 11,550,000.00
Kepala tukang L.03 OH 0,004 120,000.00 480,000.00
Mandor L.04 OH 0,003 125,000.00 375,000.00
JUMLAH TENAGA KERJA 19,405.00
B BAHAN
Cat menie Kg 0,20 26,625.00 5,325.00
Plamuur Kg 0,15 48,990.00 #VALUE!
Cat dasar Kg 0,17 18,638.00 #VALUE!
Cat penutup Kg 0,35 63,900.00 #VALUE!
Kuas Bh 0,01 31,950.00 #VALUE!
Pengencer Kg 0,03 26,625.00 #VALUE!
Ampelas Kg 0,2 7,445.00 #VALUE!
JUMLAH HARGA BAHAN 40,814.21
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 60,219.21
E Overhead & Profit 15% xD 9,032.88
F Harga Satuan Pekerjaan (D+E) 69,252.09

A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.02 100,000.00 2,000.00
Tukang cat L.02 OH 0.06 110,000.00 6,930.00
Kepala tukang L.03 OH 0.01 120,000.00 756.00
Mandor L.04 OH 0.00 125,000.00 375.00
JUMLAH TENAGA KERJA 10,061.00
B BAHAN
Cat dasar Kg 0.10 18,638.00 1,863.80
Cat penutup Kg 0.26 53,250.00 13,845.00
JUMLAH HARGA BAHAN 15,708.80
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 25,769.80
E Overhead & Profit 15% xD 3,865.47
F Harga Satuan Pekerjaan (D+E) 29,635.27
A.4.7.1.11. Pengecatan 1 m2 tembok Lama ( 1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,028 100,000.00 2,800.00
Tukang cat L.02 OH 0,042 110,000.00 4,620,000.00
Kepala tukang L.03 OH 0,0042 120,000.00 #VALUE!
Mandor L.04 OH 0,003 125,000.00 375,000.00
JUMLAH TENAGA KERJA 8,299.00
B BAHAN
Cat dasar Kg 0,12 18,638.00 #VALUE!
Cat penutup Kg 0,18 53,250.00 #VALUE!
JUMLAH HARGA BAHAN 11,821.56
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 20,120.56
E Overhead & Profit 15% xD 3,018.08
F Harga Satuan Pekerjaan (D+E) 23,138.64

A.4.7.1.10 Spl. Pengecatan 1 m2 Plafond (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.02 100,000.00 2,000.00
Tukang cat L.02 OH 0.06 110,000.00 6,930.00
Kepala tukang L.03 OH 0.01 120,000.00 756.00
Mandor L.04 OH 0.00 125,000.00 375.00
JUMLAH TENAGA KERJA 10,061.00
B BAHAN
Plamuur Kg 0.10 53,250.00 5,325.00
Cat dasar Kg 0.10 18,638.00 1,863.80
Cat penutup Kg 0.26 53,250.00 13,845.00
JUMLAH HARGA BAHAN 21,033.80
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 31,094.80
E Overhead & Profit 15% xD 4,664.22
F Harga Satuan Pekerjaan (D+E) 35,759.02
A.4.4.2 HARGA SATUAN PEKERJAAN PLAFON
A. 4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) cm, tebal 9 mm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.10 100,000.00 10,000.00
Tukang Alumunium L.03 OH 0.05 110,000.00 5,500.00
Kepala tukang L.03 OH 0.005 120,000.00 600.00
Mandor L.04 OH 0.005 125,000.00 625.00
JUMLAH TENAGA KERJA 16,725.00
B BAHAN
gybsun Board Lbr 0.36 95,850.00 34,889.40
Fiber Tape Gypsun Roll 0.10 25,000.00 2,500.00
Paku Sekrub Kg 0.11 27,900.00 3,069.00
JUMLAH HARGA BAHAN 40,458.40
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 57,183.40
E Overhead & Profit 15% xD 8,577.51
F Harga Satuan Pekerjaan (D+E) 65,760.91

A. 4.5.1.7 SPL Pemasangan 1 m2 langit-langit Kalsiboard board ukuran (120 x 240 x 9) cm, tebal 9 mm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.10 100,000.00 10,000.00
Tukang Alumunium L.03 OH 0.05 110,000.00 5,500.00
Kepala tukang L.03 OH 0.005 120,000.00 600.00
Mandor L.04 OH 0.005 125,000.00 625.00
JUMLAH TENAGA KERJA 16,725.00
B BAHAN
Kalsiboard Lbr 0.36 90,525.00 32,951.10
Paku Sekrub Kg 0.11 27,900.00 3,069.00
JUMLAH HARGA BAHAN 36,020.10
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 52,745.10
E Overhead & Profit 15% xD 7,911.77
F Harga Satuan Pekerjaan (D+E) 60,656.87
A.4.5.1.10. Pemasangan 1 m’ List Langit-Langit
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.05 100,000.00 5,000.00
Tukang Alumunium L.03 OH 0.05 110,000.00 5,500.00
Kepala tukang L.03 OH 0.005 120,000.00 600.00
Mandor L.04 OH 0.003 125,000.00 375.00
JUMLAH TENAGA KERJA 11,475.00
B BAHAN
List Plafon M 1.05 20,000.00 21,000.00
Paku Sekrub Kg 0.01 27,900.00 279.00
JUMLAH HARGA BAHAN 21,279.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 32,754.00
E Overhead & Profit 15% xD 4,913.10
F Harga Satuan Pekerjaan (D+E) 37,667.10
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A.5.1.1.1. (K3) Pemasangan 1 buah closet duduk/monoblock
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.30 100,000.00 330,000.00
Tukang batu L.02 OH 1.10 110,000.00 121,000.00
Kepala tukang L.03 OH 0.01 120,000.00 1,200.00
Mandor L.04 OH 0.16 125,000.00 20,000.00
JUMLAH TENAGA KERJA 472,200.00
B BAHAN
Closet duduk Bh 1.00 3,408,000.00 3,408,000.00
Perlengkapan % 6.00 3,408,000.00 204,480.00
JUMLAH HARGA BAHAN 3,612,480.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 4,084,680.00
E Overhead & Profit 15% xD 612,702.00
F Harga Satuan Pekerjaan (D+E) 4,697,382.00

A.5.1.1 5. (K3) Pemasangan 1 buah wastafel


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.20 100,000.00 120,000.00
Tukang batu L.02 OH 1.45 110,000.00 159,500.00
Kepala tukang L.03 OH 0.15 120,000.00 18,000.00
Mandor L.04 OH 0.06 125,000.00 7,500.00
JUMLAH TENAGA KERJA 305,000.00
B BAHAN
Wastafel unit 1,20 1,071,000.00 1,285,200.00
Semen Portland Kg 6,00 1,533.60 #VALUE!
Pasir pasang M3 0,01 250,000.00 #VALUE!
Perlengkapan % 12,00 1,322,533.60 158,704.03
JUMLAH HARGA BAHAN 1,455,605.63
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,760,605.63
E Overhead & Profit 15% xD 264,090.84
F Harga Satuan Pekerjaan (D+E) 2,024,696.48
A.5.1.1.14 Pemasangan 1 buah floor drain
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.01 100,000.00 1,000.00
Tukang batu L.02 OH 0.10 110,000.00 11,000.00
Kepala tukang L.03 OH 0.01 120,000.00 1,200.00
Mandor L.04 OH 0.01 125,000.00 625.00
JUMLAH TENAGA KERJA 13,825.00
B BAHAN
Floor Drain Bh 1.00 85,200.00 85,200.00
JUMLAH HARGA BAHAN 85,200.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 99,025.00
E Overhead & Profit 15% xD 14,853.75
F Harga Satuan Pekerjaan (D+E) 113,878.75

A.5.1.1.19 Pemasangan 1 buah kran diameter 1/2" atau 3/4"


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.01 100,000.00 1,000.00
Tukang batu L.02 OH 0.40 110,000.00 44,000.00
Kepala tukang L.03 OH 0.04 120,000.00 4,800.00
Mandor L.04 OH 0.01 125,000.00 625.00
JUMLAH TENAGA KERJA 50,425.00
B BAHAN
Kran air Bh 1.00 20,000.00 20,000.00
Sealtape Bh 0.03 6,000.00 150.00
JUMLAH HARGA BAHAN 20,150.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 70,575.00
E Overhead & Profit 15% xD 10,586.25
F Harga Satuan Pekerjaan (D+E) 81,161.25
A.5.1.1 23. Spl Pemasangan 1 m’ pipa PVC diameter 2”
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.14 100,000.00 13,500.00
Tukang Pipa L.02 OH 0.23 110,000.00 24,750.00
Kepala tukang L.03 OH 0.02 120,000.00 2,760.00
Mandor L.04 OH 0.01 125,000.00 875.00
JUMLAH TENAGA KERJA 41,885.00
B BAHAN
Pipa Galvanis 2'' Bh 1.20 69,225.00 83,070.00
Perlengkapan % 35.00 69,225.00 24,228.75
JUMLAH HARGA BAHAN 107,298.75
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 149,183.75
E Overhead & Profit 15% xD 22,377.56
F Harga Satuan Pekerjaan (D+E) 171,561.31

A.5.1.1.19 SPL Pemasangan 1 buah Jetwahser


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.01 100,000.00 1,000.00
Tukang batu L.02 OH 0.40 110,000.00 44,000.00
Kepala tukang L.03 OH 0.04 120,000.00 4,800.00
Mandor L.04 OH 0.01 125,000.00 625.00
JUMLAH TENAGA KERJA 50,425.00
B BAHAN
Jetwasher Bh 1.00 350,000.00 350,000.00
Sealtape Bh 0.03 6,000.00 150.00
JUMLAH HARGA BAHAN 350,150.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 400,575.00
E Overhead & Profit 15% xD 60,086.25
F Harga Satuan Pekerjaan (D+E) 460,661.25
A.5.1.1.25 Pemasangan 1 m pipa pvc tipe AW diameter 3/4"
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100,000.00 3,600.00
Tukang batu L.02 OH 0,06 110,000.00 #VALUE!
Kepala tukang L.03 OH 0,006 120,000.00 720,000.00
Mandor L.04 OH 0,002 125,000.00 250,000.00
JUMLAH TENAGA KERJA 11,170.00
B BAHAN
Pipa PVC 3/4'' Bh 1.20 9,319.00 11,182.80
Perlengkapan % 35.00 9,319.00 3,261.65
JUMLAH HARGA BAHAN 14,444.45
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 25,614.45
E Overhead & Profit 15% xD 3,842.17
F Harga Satuan Pekerjaan (D+E) 29,456.62

A.5.1.1 27. Pemasangan 1 m’ pipa PVC tipe AW diameter 1”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100,000.00 3,600.00
Tukang batu L.02 OH 0,06 110,000.00 #VALUE!
Kepala tukang L.03 OH 0,006 120,000.00 720,000.00
Mandor L.04 OH 0,002 125,000.00 250,000.00
JUMLAH TENAGA KERJA 11,170.00
B BAHAN
Pipa PVC 1'' Bh 1.20 21,300.00 25,560.00
Perlengkapan % 35.00 21,300.00 7,455.00
JUMLAH HARGA BAHAN 33,015.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 44,185.00
E Overhead & Profit 15% xD 6,627.75
F Harga Satuan Pekerjaan (D+E) 50,812.75
A.5.1.1 31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3”
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,081 100,000.00 8,100.00
Tukang batu L.02 OH 0,135 110,000.00 14,850,000.00
Kepala tukang L.03 OH 0,0135 120,000.00 #VALUE!
Mandor L.04 OH 0,004 125,000.00 500,000.00
JUMLAH TENAGA KERJA 25,070.00
B BAHAN
Pipa PVC 2'' Bh 1.20 21,300.00 25,560.00
Perlengkapan % 35.00 21,300.00 7,455.00
JUMLAH HARGA BAHAN 33,015.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 58,085.00
E Overhead & Profit 15% xD 8,712.75
F Harga Satuan Pekerjaan (D+E) 66,797.75

A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,081 100,000.00 8,100.00
Tukang batu L.02 OH 0,135 110,000.00 14,850,000.00
Kepala tukang L.03 OH 0,0135 120,000.00 #VALUE!
Mandor L.04 OH 0,004 125,000.00 500,000.00
JUMLAH TENAGA KERJA 25,070.00
B BAHAN
Pipa PVC 4'' Bh 1.20 69,225.00 83,070.00
Perlengkapan % 35.00 69,225.00 24,228.75
JUMLAH HARGA BAHAN 107,298.75
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 132,368.75
E Overhead & Profit 15% xD 19,855.31
F Harga Satuan Pekerjaan (D+E) 152,224.06
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.39.(SPL) Pemasangan 1 m2 atap spandek
Jumlah Harga
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.12 100,000.00 12,000.00
Tukang kayu L.02 OH 0.06 110,000.00 6,600.00
Kepala tukang L.03 OH 0.006 120,000.00 720.00
Mandor L.04 OH 0.006 125,000.00 750.00
JUMLAH TENAGA KERJA 20,070.00
B BAHAN
Atap Spandek Hitam Kasar T.0,35 m' 1.20 127,000.00 152,400.00
Baut Railing Bh 4.00 1,500.00 6,000.00
JUMLAH HARGA BAHAN 158,400.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 178,470.00
E Overhead & Profit 15% xD 26,770.50
F Harga Satuan Pekerjaan (D+E) 205,240.50

A.4.5.2.42 Pemasangan 1 m' Nok Atap Spandek


Jumlah Harga
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.15 100,000.00 15,000.00
Tukang kayu L.02 OH 0.07 110,000.00 7,700.00
Kepala tukang L.03 OH 0.007 120,000.00 840.00
Mandor L.04 OH 0.006 125,000.00 750.00
JUMLAH TENAGA KERJA 24,290.00
B BAHAN
Nok Atap m' 1.10 40,000.00 44,000.00
Baut Railing Bh 4.00 1,500.00 6,000.00
JUMLAH HARGA BAHAN 50,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 74,290.00
E Overhead & Profit 15% xD 11,143.50
F Harga Satuan Pekerjaan (D+E) 85,433.50
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.21. (SPL) Pemasangan 1 m’ Kalsiplank
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.10 100,000.00 10,000.00
Tukang kayu L.03 OH 0.20 110,000.00 22,000.00
Kepala tukang L.03 OH 0.02 120,000.00 2,400.00
Mandor L.04 OH 0.005 125,000.00 625.00
JUMLAH TENAGA KERJA 35,025.00
B BAHAN
Kalsiplank m 1.10 24,406.25 26,846.88
Sekrup kg 0.10 27,900.00 2,790.00
JUMLAH HARGA BAHAN 29,636.88
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 64,661.88
E Overhead & Profit 15% xD 9,699.28
F Harga Satuan Pekerjaan (D+E) 74,361.16
A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

SPL Pemasangan 1 buah titik lampu

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.15 100,000.00 15,000.00
Tukang Listrik L.02 OH 0.15 110,000.00 16,500.00
Kepala tukang L.03 OH 0.180 120,000.00 21,600.00
Mandor L.04 OH 0.150 125,000.00 18,750.00
JUMLAH TENAGA KERJA 71,850.00
B BAHAN
Pipa Listrik 5/8" btg 1.00 8,395.00 8,395.00
Kabel NYC M 6.00 13,312.50 79,875.00
T Dus Buah 3.00 10,650.00 31,950.00
Las Dop Buah 3.00 3,195.00 9,585.00
JUMLAH HARGA BAHAN 129,805.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 201,655.00
E Overhead & Profit 15% 30,248.25
F Harga Satuan Pekerjaan (D+E) 231,903.25
A.4.4.3.65. (SPL) Pemasangan 1m² Paving Block Natural Tebal 8 cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 0.5000 100,000.00 50,000.00
3 Tukang batu L.03 OH 0.5000 110,000.00 55,000.00
5 Kepala Tukang L.03 OH 0.0500 120,000.00 6,000.00
6 Mandor L.04 OH 0.0013 125,000.00 162.50
Jumlah Tenaga Kerja 111,162.50
B BAHAN
23 Paving Block Segi 4 (Empat) Tbl 8 cm M2 1.0100 Err:509 Err:509
4 Pasir Urug M3 0.0500 170,000.00 8,500.00
Jumlah Harga Bahan Err:509
C PERALATAN
Peralatan 10% Err:509 Err:509

Jumlah Harga Alat Err:509


D J u m l a h (A+B+C) Err:509
E Overhead & Profit 15.0% X D Err:509
F Harga Suatu Pekerjaan (D+E) Err:509
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

(ANL.SPL) Pemasangan 1m² Alumunium Composite Panel


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.0000 Rp 100,000.00 Rp 100,000.00
Tukang Batu L.03 OH 0.5000 Rp 120,000.00 Rp 60,000.00
Kepala Tukang L.03 OH 0.1000 Rp 140,000.00 Rp 14,000.00
Mandor L.04 OH 0.0200 Rp 120,000.00 Rp 2,400.00
Jumlah Tenaga Kerja Rp 176,400.00
B BAHAN
Besi Hollow 40x40x2 mm M1 4.1000 Rp 29,750.00 Rp 121,975.00
Braket siku 4 x 4 cm M1 1.0000 Rp 34,600.00 Rp 34,600.00
ACP Cutting M2 1.1000 Rp 1,100,000.00 Rp 1,210,000.00
Sealant Tube 0.2700 Rp 38,200.00 Rp 10,314.00
Sekrup Bh 8.0000 Rp 200.00 Rp 1,600.00
Jumlah Harga Bahan Rp 1,378,489.00
C PERALATAN
Perlengkapan % 35.00 Rp 1,378,489.00 Rp 482,471.15

Jumlah Harga Alat Rp 482,471.15


D J u m l a h (A+B+C) Rp 2,037,360.15
E Overhead & Profit 15.0% X D Rp 305,604.02
F Harga Suatu Pekerjaan (D+E) Rp 2,342,964.17

Anda mungkin juga menyukai