LANTAI 1
A SLOOF
1 S1 PANJANG AS-AS = 6.00 M
LEBAR = 0.20 M
JUMLAH S1 B. 4 M = 14.00 BH
0.2
VOL. BETON SLOOF S1 = panjang x lebar x tinggi X JUMLAH
5.75 x 0.20 x 0.45 X 14.00
BEKISTING = 72.45 m2
PEMBESIN
BESI ATAS MENERUS = 4.00 BTG
BESI ATAS TEPI = 1.00 BTG
BESI TENGAH MENERUS = 2.00 BTG
BESI BAWAH MENERUS = 3.00 BTG
BESI BAWAH TEPI = 1.00 BTG
JUMLAH BEUGEL = 47.00 BTG 47.00
= 24.00 M = 25.01 KG
= 3.12 M 3.251 KG
= 12 M 7.40 KG
= 18.00 M 18.75 KG
= 3.52 M 3.67 KG
= 27.73 M 86.18 KG
2 S2 PANJANG = 8.45 M
TINGGI = 0.20 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.56 M
0.2 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG
VOL. BESI
V. BEUGEL
BEKISTING
VOL. BESI
V. BEUGEL
BEKISTING
2 rb PANJANG = 38.45 M
TINGGI = 0.20 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.56 M
0.2 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG
VOL. BESI
V. BEUGEL
BEKISTING
B KOLOM
1 K1
JUMLAH KOLOM = 11.00 BH
TINGGI = 3.30 M
LEBAR = 0.63 M
0.63 PANJANG = 0.15 M
BEKISTING = 56.63 M2
PEMBESIAN
VOL. TULANGAN = JUMLAH KOLOM X TINGGI X JUMLAH TULANGAN X BERAT JENIS Ø10
= 11.00 X 3.30 X 10.00 X 0.62
= 223.79 KG
VOL. BEUGEL
1 k2\
JUMLAH KOLOM = 4.00 BH
TINGGI = 3.53 M
LEBAR = 0.30 M
0.3 PANJANG = 0.30 M
BEKISTING = 16.94 M2
PEMBESIAN
VOL. BEUGEL
JUMLAH BEUGEL = TINGGI : JARAK BEUGEL X JUMLAH KOLOM
= 3.53 : 0.15 X 4.00
= 94.13 BH
2 KP
JUMLAH = 19.00 BH
TINGGI = 3.30 M
C BALOK LATEI
2 15/20 PANJANG = 24.00 M 100.5 M
TINGGI = 0.20 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.56 M
0.2 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG
VOL. BESI
V. BEUGEL
BEKISTING
LANTAI 2
A dak atap
1 PLAT LANTAI 2 TEBAL = 0.12 M
LUAS BIDANG = 275.02 M2
PEMBESIAN = 7590.552 KG
B ringbalk
1 rb1 PANJANG AS-AS = 6.00 M
LEBAR = 0.20 M
BEKISTING = 62.79 M2
PEMBESIN
BESI ATAS MENERUS = 3.00 BTG
BESI ATAS TEPI = 1.00 BTG
BESI TENGAH MENERUS = 2.00 BTG
BESI BAWAH MENERUS = 2.00 BTG
BESI BAWAH TEPI = 1.00 BTG
JUMLAH BEUGEL = 45.00 BTG 47.00
= 18.00 M = 18.75 KG
= 3.12 M 3.251 KG
= 12 M 7.40 KG
= 12.00 M 12.50 KG
= 3.52 M 3.67 KG
VOL. BESI
V. BEUGEL
BEKISTING
C KOLOM
1 K1
JUMLAH KOLOM = 9.00 BH
TINGGI = 3.50 M
LEBAR = 0.35 M
0.35 PANJANG = 0.35 M
BEKISTING = 44.10 M2
PEMBESIAN
VOL. BEUGEL
2 KP
JUMLAH = 2.00 BH
TINGGI = 3.50 M
D BALOK LATEI
2 S2 PANJANG = 16.00 M
TINGGI = 0.15 M
LEBAR = 0.15 M
PANJANG BEUGEL = 0.44 M
0.15 JARAK BEUGEL = 0.15 M
TULANGAN = 4 BTG
VOL. BESI
V. BEUGEL
BEKISTING
TOP FLOOR
A PLAT LANTAI
1 PLAT LANTAI 2 TEBAL = 0.12 M
LUAS BIDANG = 52.41 M2
PEMBESIAN = 716.97 KG
B BALOK
1 B1 PANJANG AS-AS = 4.00 M
LEBAR = 0.20 M
JUMLAH B1 B. 4 M = 16.00 BH
0.2
VOL. BETON SLOOF S1 = panjang x lebar x tinggi X JUMLAH
3.65 x 0.20 x 0.29 X 16.00
BEKISTING = 45.55 M2
PEMBESIN
BESI ATAS MENERUS = 2.00 BTG
BESI ATAS TEPI = 3.00 BTG
BESI TENGAH MENERUS = 2.00 BTG
BESI BAWAH MENERUS = 2.00 BTG
BESI BAWAH TEPI = 2.00 BTG
JUMLAH BEUGEL = 30.00 BTG 30.00
= 8.00 M = 12.67 KG
= 6.36 M 10.070 KG
= 8 M 8.33 KG
= 8.00 M 12.67 KG
= 5.04 M 7.98 KG
= 30 M 18.51 KG POLOS
C KOLOM
1 KP
JUMLAH = 8.00 BH
TINGGI = 0.50 M
D RINGBALK
1 RINGBALK
PANJANG = 24.00 M
E TANGGA
JUMLAH ANAK TANGGA = 18.00 BH
LEBAR TANGGA = 1.00 M1
PANJANG PLAT TANGGA = 6.14 M1
LEBAR BORDES = 1.07 M1
PANJANG BORDES = 2.07 M1
TEBAL PLAT = 0.12 M1
TINGGI ANAK TANGGA = 0.20 M1
LEBAR PIJAKAN = 0.30 M1
JUMLAH BORDES = 1.00 M1
JUMLAH TANGGA = 1.00 BH
VOL. BETON PLAT TANGGA = PANJANG PLAT TANGGA X LEBAR TANGGA X TEBAL PLAT
= 0.74 M3
VOL. BETON PLAT BORDES = LEBAR BORDES X PANJANG BORDES X TEBAL PLAT X J. BORDES
= 0.27 M3
BETON ANAK TANGGA =
0.54 M3
BEGISTING = 12.04 M2
I. PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi Ls 1.00 Rp 5,000,000 Rp 5,000,000
2 Pek. Pembongkaran Dindding Ls 1.00 Rp 1,000,000 Rp 1,000,000
3 Pek. Pembongkaran Keramik Lantai dan Dinding Ls 1.00 Rp 10,000,000 Rp 10,000,000
4 Pek. Pembongkaran Atap Ls 1.00 Rp 15,000,000 Rp 15,000,000
5 Pek. Pembongkaran Plafon+rangka Ls 1.00 Rp 7,000,000 Rp 7,000,000
6 Pek. Pembongkaran Kusen Ls 1.00 Rp 500,000 Rp 500,000
7 Adminstrasi & Dokumentasi Ls 1.00 Rp 5,000,000 Rp 5,000,000
8 Papan Nama Proyek Ls 1.00 Rp 250,000 Rp 250,000
9 Penyediaan Air Bersih & Listrik Kerja Ls 1.00 Rp 2,000,000 Rp 2,000,000
10 Kesehatan & Keselamatan Kerja (K3) Ls 1.00 Rp 14,900,000 Rp 14,900,000
JUMLAH I Rp 60,650,000
JUMLAH II Rp 24,796,644
V. PEKERJAAN PENGECATAN
1 Pek. Pengecatan Tembok Baru M² 76.90 Rp 29,635 Rp 2,278,952
2 Pek. Pengecatan Tembok Lama M² 387.00 Rp 23,139 Rp 8,954,655
3 Pek. Pengecatan Plafon M² 2,212.28 Rp 35,759 Rp 79,108,965
4 Pek. Pengecatan Kalsiplank M² 88.49 Rp 69,252 Rp 6,127,979
JUMLAH V Rp 96,470,551
X. PEKERJAAN AKHIR
1 Pembersihan Akhir Ls 1.00 Rp 5,000,000 Rp 5,000,000
JUMLAH X Rp 5,000,000
REKAPITULASI
BILL OF QUANTITY
JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp )
DIREKTUR/DIREKTRIS
NO JENIS PEKERJAAN GAMBAR/SKETS PERHITUNGAN
b POER PLAT P2
1 GALIAN TANAH POER PLAT JUMLAH = 14.00 BH
TINGGI = 0.60 M
LEBAR = 1.30 M
TINGGI = 0.05 M
PANJANG = 1.30 M
1.30
VOL. LANTAI KERJA = panjang x lebar x tinggi x jumlah
1.30 x 1.30 x 0.05 x 14.00
= 1.18 M3
TINGGI = 0.05 M
PANJANG = 1.30 M
1.30
VOL. PASIR URUG P1 = panjang x lebar x tinggi x jumlah
1.30 x 1.30 x 0.05 x 14.00
= 1.18 M3
TINGGI = 0.30 M
0.3
PANJANG 1.20 M
LEBAR = 1.20 M
1.20
VOL. POER PLAT TINGGI X PANJANG X LEBAR X JUMLAH
=
= 6.05 M3
= 20.16 M2
= 5.78 M3
e KOLOM PEDESTAL
PANJANG = 0.41 M
TINGGI = 3.45 M
= 69.55 M2
= 336.00 BH
PANJANG BEUGEL = JUMLAH BEUGEL X PANJANG BEUGEL
= 336.00 X 0.98
JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp )
SUARDIN, ST.
DIREKTUR
ENGINEERING ESTIMATE
( EE )
PEKERJAAN : PERENCANAAN REHABILITASI KANTOR DPRD DI KABUPATEN KOLAKA TIMUR
LOKASI : KOLAKA TIMUR
TAHUN ANGGARAN : 2022
I. PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi Ls 1.00 Rp 3,500,000 Rp 3,500,000
2 Pek. Pembongkaran Dindding Ls 1.00 Rp 1,000,000 Rp 1,000,000
3 Pek. Pembongkaran Keramik Lantai dan Dinding Ls 1.00 Rp 9,000,000 Rp 9,000,000
4 Pek. Pembongkaran Atap Ls 1.00 Rp 10,000,000 Rp 10,000,000
5 Pek. Pembongkaran Plafon+rangka Ls 1.00 Rp 6,000,000 Rp 6,000,000
6 Pek. Pembongkaran Kusen Ls 1.00 Rp 500,000 Rp 500,000
7 Adminstrasi & Dokumentasi Ls 1.00 Rp 3,500,000 Rp 3,500,000
8 Papan Nama Proyek Ls 1.00 Rp 250,000 Rp 250,000
9 Penyediaan Air Bersih & Listrik Kerja Ls 1.00 Rp 1,000,000 Rp 1,000,000
JUMLAH I Rp 34,750,000
II. SMK3
A Penyiapan RKK
-Pembuatan Dokumen Set
set 1.00 Rp 1,000,000 Rp 1,000,000
-Pembuatan Prosedur & Instruksi Kerja
-Penyiapan Formulir
B Sosialisasi, Promosi dan Pelatihan
1 Induksi K3 (Safety Induction) Org 15.00 Rp 7,500 Rp 112,500
2 Pengarahan K3 (Safety Briefing) Org 12.00 Rp 15,000 Rp 180,000
3 Pelatihan K3 Rp -
a. Bekerja diketinggian Org 12.00 Rp 7,500 Rp 90,000
4 Simulasi K3 Org 12.00 Rp 7,500 Rp 90,000
5 Spanduk (Banner) Lbr 1.00 Rp 150,000 Rp 150,000
6 Poster Lbr 1.00 Rp 50,000 Rp 50,000
7 Papan Informasi K3 Bh 1.00 Rp 500,000 Rp 500,000
C Alat Pelindung Kerja & Alat Pelindung Diri
1 Alat Pelindung Diri :
a. Topi Pelindung (Safety Helmet) Bh 23.00 Rp 60,000 Rp 1,380,000
b. Pelindung Mata (Goggles Spectacles) Bh 15.00 Rp 30,000 Rp 450,000
d. Pelindung Pernafasan & Mulut (Masker) Bh 80.00 Rp 1,500 Rp 120,000
e. Sarung Tangan (Safety Gloves) Psg 60.00 Rp 20,000 Rp 1,200,000
f. Sepatu Keselamatan (Safety Shoes) Psg 15.00 Rp 150,000 Rp 2,250,000
g. Penunjang Seluruh Tubuh (Full Body Harness) Bh 4.00 Rp 750,000 Rp 3,000,000
h. Rompi Keselamatan (Safety Vest) Bh 23.00 Rp 25,000 Rp 575,000
j. Pelindung Jatuh (Fall Arrester) Bh 5.00 Rp 100,000 Rp 500,000
D Asuransi
1 Asuransi Ls 1.00 Rp 1,500,000 Rp 1,500,000
E Fasilitas Sarana & Prasarana Kesehatan
1 Peralatan P3K (Kotak P3K, Obat Luka, dll) Ls 1.00 Rp 300,000 Rp 300,000
2 Peralatan Pengasapan (Fogging) Ls 1.00 Rp 500,000 Rp 500,000
F Rambu-Rambu
1 Rambu Petunjuk Bh 1.00 Rp 75,000 Rp 75,000
2 Rambu Larangan Bh 1.00 Rp 75,000 Rp 75,000
3 Rambu Peringatan Bh 1.00 Rp 75,000 Rp 75,000
4 Rambu Kewajiban Bh 1.00 Rp 75,000 Rp 75,000
5 Rambu Informasi Bh 1.00 Rp 75,000 Rp 75,000
6 Jalur Evakuasi (Escape Route) Ls 1.00 Rp 300,000 Rp 300,000
G Lain-Lain
1 Alat Pemedam Api Ringan (APAR) Bh 1.00 Rp 750,000 Rp 750,000
2 Bendera K3 Bh 1.00 Rp 150,000 Rp 150,000
3 Program Inspeksi Ls 1.00 Rp 2,000,000 Rp 2,000,000
4 Pelaporan & Penyelidikan Insiden Ls 1.00 Rp 500,000 Rp 500,000
5 Pembuatan Kartu Identitas Pekerja (KIP) Lbr 12.00 Rp 10,000 Rp 120,000
JUMLAH II Rp 18,142,500
X. PEKERJAAN SANITASI
1 Pemasangan Kloset Duduk ex TOTO Bh 3.00 Rp 4,697,382 Rp 14,092,146
2 pemasangan Pipa PVC 3/4 Inchi M' 16.00 Rp 29,457 Rp 471,306
3 pemasangan Pipa PVC 1 Inchi M' 12.00 Rp 50,813 Rp 609,753
4 pemasangan Pipa PVC 3 Inchi M' 8.00 Rp 66,798 Rp 534,382
5 pemasangan Pipa PVC 4 Inchi M' 12.00 Rp 152,224 Rp 1,826,689
6 Pemasangan Jet Washer Bh 3.00 Rp 460,661 Rp 1,381,984
7 Pemasangan Keran Air 3/4 Inchi Bh 3.00 Rp 81,161 Rp 243,484
8 Pemasangan Floor Drain Bh 3.00 Rp 113,879 Rp 341,636
9 Pemasangan Washtafle Bh 3.00 Rp 2,024,696 Rp 6,074,089
10 Pek. Septictank Ls 1.00 Rp 8,000,000 Rp 8,000,000
JUMLAH X Rp 33,575,469
XI. PEKERJAAN AKHIR
1 Pembersihan Akhir Ls 1.00 Rp 5,000,000 Rp 5,000,000
JUMLAH XI Rp 5,000,000
DAFTAR UPAH DAN HARGA BAHAN
1 2 3 4
I UPAH TENAGA KERJA
1 Pekerja Hari 100,000.00
2 Tukang Batu Hari 110,000.00
3 Tukang Kayu Hari 110,000.00
4 Tukang Besi Hari 110,000.00
5 Tukang Cat Hari 110,000.00
6 Kepala Tukang Hari 120,000.00
7 Mandor Hari 125,000.00
II HARGA BAHAN
A. Bahan Dasar
1 Tanah Urug Didatangkan M3 50,000.00
2 Pasir Urug M3 170,000.00
3 Pasir Pasang M3 250,000.00
4 Pasir Beton M3 250,000.00
Kg 178.57
5 Air Kerja Ltr 50.00
6 Kerikil M3 350,000.00
Kg 259.26
7 Semen Portland @ 50 Kg Zak 76,680.00
8 Semen Portland Kg 1,533.60
9 Semen Warna Kg 26,625.00
10 Batu Belah M3 214,286.00
11 Batu Bata Merah Bh 650.00
12 Minyak Pelumas Ltr 17,573.00
13 Koral Hambur M2 75,000.00
B. Bahan Lantai
1 Granit 60 x 60 Cm (Exterior) Bh 72,400.00
2 Granit 60 x 60 Cm (Interior) Bh 53,250.00
3 Granit 10 x 60 Bh 45,900.00
Keramik 20x20 cm Bh 2,769.00
Keramik 50x20 cm Bh 4,326.56
C. Bahan Besi dan Paku
1 Besi Polos Kg 14,500.00
2 Paku Campur (5, 7, 10 Cm) Kg 20,000.00
3 Baut Railing Bh 1,500.00
4 Paku Sekrup Kg 27,900.00
5 Skrup Fixer Bh 1,500.00
6 Kawat Beton Kg 20,000.00
7 Baut Mur Bh 10,000.00
8 Hollow 20.40 mm (Baja Ringan) M1 3,700.00
9 Hollow 40.40 mm (Baja Ringan) M1 5,000.00
D. Bahan Alumunium, Kaca & Kunci
1 Kusen Alumunium 4" M1 134,000.00
2 Sealant Tube 7,455.00
3 Daun Pintu Swing Standard Unit 2,500,000.00
4 Daun Pintu Double Teakwood Unit 3,500,000.00
5 Daun Pintu Alumunium (+Aksesoris) Unit 1,500,000.00
6 Kaca Polos 5 mm M2 170,400.00
7 Handel Pintu Stainless Bh 170,400.00
8 Penggantung Kesmen Bh 65,000.00
9 Esel Pintu Alumunium Psg 26,625.00
Bh 13,312.50
10 Frame Alumunium M1 76,500.00
11 Baja ringan canai dingin C75 Btg 95,850.00
12 Reng M1 7,988.00
13 skrub Bh 250.00
H. Bahan Sanitasi
1 Kloset Duduk Bh 3,408,000.00
2 Wastafel Dinding ex. Toto Bh 1,071,000.00
3 Floor Drain Bh 85,200.00
4 Kran Air 1/2 '' Bh 20,000.00
5 Sealtape Bh 6,000.00
6 Pipa PVC 3/4 '' M 9,319.00
7 Pipa PVC 2 '' M 21,300.00
8 Pipa PVC 4" M 69,225.00
9 Jetwasher Bh 350,000.00
10 Tandon Air 1200 Liter Bh 2,300,000.00
RINCIAN DAFTAR KUANTITAS DAN HARGA
BIAYA PENYELENGGARAAN SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
A.4.2.1.19 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.15
Tukang L.03 OH 0.30
Kepala tukang L.03 OH 0.03
Mandor L.04 OH 0.01
JUMLAH TENAGA KERJA
B BAHAN
Seng pelat m 1.05
Paku 1 cm – 2,5 cm kg 0.01
Besi strip kg 0.50
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
A.4.2.1.20.Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, untuk partisi
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.25
Tukang besi L.02 OH 0.25
Kepala tukang L.03 OH 0.03
Mandor L.04 OH 0.01
JUMLAH TENAGA KERJA
B BAHAN
Rangka metal M1 3.50
hollow 40.40.2 mm
Assesoris Ls 100% x
(perkuatan, las dll) rangka
JUMLAH HARGA BAHAN
C PERALATAN
A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, untuk plafon
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.35
Tukang besi L.02 OH 0.35
Kepala tukang L.03 OH 0.04
Mandor L.04 OH 0.02
JUMLAH TENAGA KERJA
B BAHAN
Rangka metal M1 4.00
hollow 40.40.2 mm
Assesoris Ls 100%xrangka
(perkuatan, las
dll)
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
A.4.2.1.22. (K3) Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.73
Tukang besi L.02 OH 0.73
Kepala tukang L.03 OH 0.07
Mandor L.04 OH 0.04
JUMLAH TENAGA KERJA
B BAHAN
Baja ringan canai dingin C75 kg 3.07
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan % 10.00
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
A.4.2.1.22. (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.76
Tukang besi L.02 OH 7,604.00
Kepala tukang L.03 OH 0.08
Mandor L.04 OH 0.04
JUMLAH TENAGA KERJA
B BAHAN
Baja ringan canai kg 4.05
dingin C75
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan % 10.00
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
Analisis Harga Satuan Pekerjaan (AHSP)
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.3 Pemasangan 1 m² plesteran 1SP : 3PP tebal 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 100,000.00 Rp 30,000.00
Tukang Batu L.03 OH 0.1500 110,000.00 Rp 16,500.00
Kepala Tukang L.03 OH 0.0150 120,000.00 Rp 1,800.00
Mandor L.04 OH 0.0150 125,000.00 Rp 1,875.00
Jumlah Tenaga Kerja Rp 50,175.00
B BAHAN
Semen Portland Kg 7.7760 1,533.60 Rp 11,925.27
Pasir Pasang m³ 0.0230 250,000.00 Rp 5,750.00
Jumlah Harga Bahan Rp 17,675.27
C PERALATAN
A.4.4.1.9 Pemasangan 1 m² dinding bata merah ( 5x11x22 ) cm tebal 1/2 batu campuran 1SP : 4PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 100,000.00 Rp 30,000.00
Tukang Batu L.03 OH 0.1000 110,000.00 Rp 11,000.00
Kepala Tukang L.03 OH 0.0100 120,000.00 Rp 1,200.00
Mandor L.04 OH 0.0150 125,000.00 Rp 1,875.00
Jumlah Tenaga Kerja Rp 44,075.00
B BAHAN
Bata Merah Bh 70.0000 650.00 Rp 45,500.00
Semen Portland Kg 11.5000 1,533.60 Rp 17,636.40
Pasir Pasang m³ 0,043 250,000.00 Rp 10,750.00
Jumlah Harga Bahan Rp 73,886.40
C PERALATAN
Type PJ2
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Analisa Pintu
Type P1
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Type P2
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Type P3
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Analisa Jendela
Type J1
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Type J2
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Type J3
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Type J4
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Type J5
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
Type V2
No. Uraian Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp.)
A.4.2.1.22. Pemasangan 1 m2 Atap Pelana Rangka Atap Baja Ringan (Canai Dingin) profil C75 rangka atap baja canai dingin profil
C75
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.734 100,000.00 73,400.00
Tukang besi L.02 OH 0.734 110,000.00 80,740.00
Kepala tukang L.03 OH 0.073 120,000.00 8,760.00
Mandor L.04 OH 0.037 125,000.00 4,625.00
JUMLAH TENAGA KERJA 167,525.00
B BAHAN
Baja ringan canai dingin C75 Btg 0.873 95,850.00 83,677.05
83,677.05
C PERALATAN
Peralatan % 10% 95,850.00 9,585.00
JUMLAH HARGA ALAT 9,585.00
D Jumlah (A+B+C) 260,787.05
E Overhead & Profit 15% xD 39,118.06
F Harga Satuan Pekerjaan (D+E) 299,905.11
A.4.2.1.24. Pemasangan 1 m Kusen Aluminium
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0430 100,000.00 Rp 4,300.00
Tukang Besi Konstruksi L.03 OH 0.0430 110,000.00 Rp 4,730.00
Kepala Tukang L.03 OH 0.0043 120,000.00 Rp 516.00
Mandor L.04 OH 0.0021 125,000.00 Rp 262.50
Jumlah Tenaga Kerja Rp 9,808.50
B BAHAN
Kusen Alumunium 4" M' 1.1000 134,000.00 Rp 147,400.00
Skrup Fixer Bh 2.0000 1,500.00 Rp 3,000.00
Sealant Tube 0.0600 7,455.00 Rp 447.30
Jumlah Harga Bahan Rp 150,847.30
C PERALATAN
A.4.2.1.21 Spl. Pemasangan 1 m2 Rangka hollow Galvalume 40.40. dan 20.40 mm, untuk plafon
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 100,000.00 35,000.00
Tukang besi L.02 OH 0.350 110,000.00 38,500.00
Kepala tukang L.03 OH 0.035 120,000.00 4,200.00
Mandor L.04 OH 0.018 125,000.00 2,250.00
JUMLAH TENAGA KERJA 79,950.00
B BAHAN
Hollow 20.40 mm (baja Ringan) m' 3.800 3,700.00 14,060.00
Hollow 40.40 mm (baja Ringan) m' 1.800 5,000.00 9,000.00
Aksesoris % 35.000 8,700.00 3,045.00
JUMLAH HARGA BAHAN 26,105.00
C PERALATAN
Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 106,055.00
E Overhead & Profit 15% xD 15,908.25
F Harga Satuan Pekerjaan (D+E) 121,963.25
Analisis Harga Satuan Pekerjaan (AHSP)
A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.02 100,000.00 2,000.00
Tukang cat L.02 OH 0.06 110,000.00 6,930.00
Kepala tukang L.03 OH 0.01 120,000.00 756.00
Mandor L.04 OH 0.00 125,000.00 375.00
JUMLAH TENAGA KERJA 10,061.00
B BAHAN
Cat dasar Kg 0.10 18,638.00 1,863.80
Cat penutup Kg 0.26 53,250.00 13,845.00
JUMLAH HARGA BAHAN 15,708.80
C PERALATAN
A.4.7.1.10 Spl. Pengecatan 1 m2 Plafond (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.02 100,000.00 2,000.00
Tukang cat L.02 OH 0.06 110,000.00 6,930.00
Kepala tukang L.03 OH 0.01 120,000.00 756.00
Mandor L.04 OH 0.00 125,000.00 375.00
JUMLAH TENAGA KERJA 10,061.00
B BAHAN
Plamuur Kg 0.10 53,250.00 5,325.00
Cat dasar Kg 0.10 18,638.00 1,863.80
Cat penutup Kg 0.26 53,250.00 13,845.00
JUMLAH HARGA BAHAN 21,033.80
C PERALATAN
A. 4.5.1.7 SPL Pemasangan 1 m2 langit-langit Kalsiboard board ukuran (120 x 240 x 9) cm, tebal 9 mm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.10 100,000.00 10,000.00
Tukang Alumunium L.03 OH 0.05 110,000.00 5,500.00
Kepala tukang L.03 OH 0.005 120,000.00 600.00
Mandor L.04 OH 0.005 125,000.00 625.00
JUMLAH TENAGA KERJA 16,725.00
B BAHAN
Kalsiboard Lbr 0.36 90,525.00 32,951.10
Paku Sekrub Kg 0.11 27,900.00 3,069.00
JUMLAH HARGA BAHAN 36,020.10
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.15 100,000.00 15,000.00
Tukang Listrik L.02 OH 0.15 110,000.00 16,500.00
Kepala tukang L.03 OH 0.180 120,000.00 21,600.00
Mandor L.04 OH 0.150 125,000.00 18,750.00
JUMLAH TENAGA KERJA 71,850.00
B BAHAN
Pipa Listrik 5/8" btg 1.00 8,395.00 8,395.00
Kabel NYC M 6.00 13,312.50 79,875.00
T Dus Buah 3.00 10,650.00 31,950.00
Las Dop Buah 3.00 3,195.00 9,585.00
JUMLAH HARGA BAHAN 129,805.00
C PERALATAN