NO SKETSA HITUNGAN
1 Plat T = 15 cm
2 Plat T = 10 cm
1 M3 = 51.28 M'
Beugel
Ø8= 51.28 : 0.15 = 341.88 ¥ 342.00 Bh
= 342.00 x 0.53 x 0.3968 = 71.924 KG
Ø 10 = 51.28 x 4.00 x 0.620 = 127.179 KG
199.103 ¥ 200.00 Kg
Pemakaian Bekisting :
51.28 x 0.30 = 15.3846 ¥ 15.385 M2
NO SKETSA HITUNGAN
1 M3 = 33.33 M'
Beugel
Ø8= 33.33 : 0.15 = 222.22 ¥ 223.00 Bh
= 223.00 x 0.57 x 0.3968 = 50.437 KG
Ø 10 = 33.33 x 4.00 x 0.620 = 82.667 KG
133.104 ¥ 135.00 Kg
Pemakaian Bekisting :
33.33 x 0.40 = 13.3333 ¥ 13.333 M2
1 M3 = 25.00 M'
Beugel
Ø8= 25.00 : 0.15 = 166.667 ¥ 167.00 Bh
= 167.00 x 0.77 x 0.397 = 51.025 KG
Ø 12 = 25.00 x 4.00 x 0.893 = 89.280 KG
140.305 ¥ 145.00 Kg
Pemakaian Bekisting :
25.00 x 0.80 = 20.00 ¥ 20.000 M2
1 M3 = 51.28 M'
Beugel
Ø8= 51.28 : 0.15 = 341.880 ¥ 342.00 Bh
= 342.00 x 0.53 x 0.397 = 71.924 KG
Ø 10 = 51.28 x 4.00 x 0.620 = 127.179 KG
199.103 ¥ 200.00 Kg
Pemakaian Bekisting :
51.28 x 0.30 = 15.38 ¥ 15.385 M2
6 Pas.Reng Balok 15/20
1 M3 = 33.33 M'
Beugel
Ø8= 33.33 : 0.15 = 222.222 ¥ 223.00 Bh
= 223.00 x 0.57 x 0.397 = 50.437 KG
Ø 10 = 33.33 x 4.00 x 0.620 = 82.667 KG
133.104 ¥ 135.00 Kg
Pemakaian Bekisting :
33.33 x 0.70 = 23.33 ¥ 23.333 M2
6 Pas.Kolom Teras
1 M3 = 12.50 M'
Beugel
Ø8= 12.50 : 0.15 = 83.333 ¥ 84.00 Bh
= 84.00 x 2.53 x 0.397 = 84.328 KG
Ø 12 = 12.50 x 8.00 x 0.893 = 89.280 KG
173.608 ¥ 175.00 Kg
Pemakaian Bekisting :
NO SKETSA HITUNGAN
12.50 x 2.00 = 25.00 ¥ 25.000 M2
7 Pas.Kolom 13/13
1 M3 = 59.17 M'
Beugel
Ø8= 59.17 : 0.15 = 394.477 ¥ 395.00 Bh
= 395.00 x 0.49 x 0.397 = 76.801 KG
Ø 10 = 59.17 x 4.00 x 0.620 = 146.746 KG
223.546 ¥ 225.00 Kg
Pemakaian Bekisting :
59.17 x 0.26 = 15.38 ¥ 15.385 M2
1 M3 = 44.44 M'
Beugel
Ø8= 44.44 : 0.15 = 296.296 ¥ 297.00 Bh
= 297.00 x 0.57 x 0.397 = 67.174 KG
Ø 10 = 44.44 x 4.00 x 0.620 = 110.222 KG
177.396 ¥ 180.00 Kg
Pemakaian Bekisting :
44.44 x 0.30 = 13.33 ¥ 13.333 M2
1 M3 = 51.28 M'
Beugel
Ø8= 51.28 : 0.15 = 341.880 ¥ 342.00 Bh
= 342.00 x 0.43 x 0.397 = 58.353 KG
Ø 10 = 51.28 x 4.00 x 0.620 = 127.179 KG
185.533 ¥ 190.00 Kg
Pemakaian Bekisting :
51.28 x 0.30 = 15.38 ¥ 15.385 M2
1 M3 = 27.78 M'
Beugel
Ø8= 27.78 : 0.12 = 231.481 ¥ 232.00 Bh
= 232.00 x 0.57 x 0.397 = 52.473 KG
Ø 10 = 27.78 x 4.00 x 0.620 = 68.889 KG
121.362 ¥ 125.00 Kg
Pemakaian Bekisting :
27.78 x 0.70 = 19.44 ¥ 19.444 M2
YENFRI FITRAHADY, ST
Direktur
REKAPITULASI
Kegiatan : Rehab Rumah Dinas DPRD
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
JUMLAH
NO URAIAN PEKERJAAN HARGA
(Rp)
1 2 3
Jumlah 54,182,118.68
Dibulatkan 54,182,100.00
Terbilang : Lima puluh empat juta se ratus delapan puluh dua ribu se ratus rupiah.
…………………………………..
NIP. …………………………………..
HARGA PERKIRAAN SENDIRI
HARGA
NO URAIAN PEKERJAAN SAT VOL SATUAN JUMLAH PPh 10% Total
(Rp)
1 2 3 4 5 6
I KAMAR MANDI UTAMA 18,527,048.49
a Membongkar Lantai dan Dinding Keramik Lama M2 11.52 31,762.50 365,904.00 36,590.40 402,494.40
b Pas. Pipa Air Bersih PVC dia. 1/2" Wavin AW M1 4.00 27,214.00 108,856.00 10,885.60 119,741.60
c Pas. Keramik Lantai Toilet 25 x 25 cm (Merk IKAD) M2 2.08 215,470.00 448,177.60 44,817.76 492,995.36
d Pas. Granit Dinding Toilet 15 x 60 cm (Merk IKAD) M3 2.08 225,170.00 468,353.60 46,835.36 515,188.96
e Pas. Klosed Duduk Merk American Standard + Asessoris Unit 1.00 4,740,835.00 4,740,835.00 474,083.50 5,214,918.50
f Pas. Bathtub + Asessoris Unit 1.00 8,704,674.00 8,704,674.00 870,467.40 9,575,141.40
g Pas. Wastafel Unit 1.00 1,552,995.40 1,552,995.40 155,299.54 1,708,294.94
h Pas. Shower Unit 1.00 65,568.25 65,568.25 6,556.83 72,125.08
i Pas. Kaca Bh 1.00 150,000.00 150,000.00 15,000.00 165,000.00
j Pas. Floor Drain Bh 1.00 237,407.50 237,407.50 23,740.75 261,148.25
k Pas. Kran Air 1/2' Tembok Bh 64,158.88 - - -
l Pas. Kran shower Bawah (toto) Bh 64,158.88 - - -
m Pas. Tempat Sabun Bh 175,000.00 - - -
II KAMAR MANDI TAMU 8,934,526.35
a Membongkar Lantai dan Dinding Keramik Lama M2 11.52 31,762.50 365,904.00 36,590.40 402,494.40
b Pas. Pipa Air Bersih PVC dia. 1/2" Wavin AW M1 4.50 27,214.00 122,463.00 12,246.30 134,709.30
c Pas. Keramik Lantai Toilet 25 x 25 cm (Merk IKAD) M2 2.08 215,470.00 448,177.60 44,817.76 492,995.36
d Pas. Keramik Dinding Toilet 25 x 50 cm (Merk IKAD) M3 2.08 211,031.70 438,945.94 43,894.59 482,840.53
e Pas. Klosed Duduk Merk American Standard + Asessoris Unit 1.00 4,740,835.00 4,740,835.00 474,083.50 5,214,918.50
f Pas. Wastafel merk Toto Unit 1.00 1,552,995.40 1,552,995.40 155,299.54 1,708,294.94
g Pas. Shower Unit 1.00 65,568.25 65,568.25 6,556.83 72,125.08
h Pas. Cermin Grafir Pada Wastafel uk. 40 x 60 cm Bh 1.00 150,000.00 150,000.00 15,000.00 165,000.00
i Pas. Floor Drain Bh 1.00 237,407.50 237,407.50 23,740.75 261,148.25
j Pas. Kran Air 1/2' Tembok Bh 64,158.88 - - -
k Pas. Kran shower Bawah (toto) Bh 64,158.88 - - -
l Pas. Tempat Sabun Bh 175,000.00 - - -
III KAMAR MANDI ANAK 1 7,116,838.48
a Membongkar Lantai dan Dinding Keramik Lama M2 11.52 31,762.50 365,904.00 36,590.40 402,494.40
b Pas. Pipa Air Bersih PVC dia. 1/2" Wavin AW M1 4.00 27,214.00 108,856.00 10,885.60 119,741.60
c Pas. Keramik Lantai Toilet 25 x 25 cm (Merk IKAD) M2 2.08 215,470.00 448,177.60 44,817.76 492,995.36
d Pas. Keramik Dinding Toilet 25 x 25 cm (Merk IKAD) M3 2.08 211,031.70 438,945.94 43,894.59 482,840.53
e Pas. Klosed Duduk Merk American Standard + Asessoris Unit 1.00 4,740,835.00 4,740,835.00 474,083.50 5,214,918.50
f Pas. Shower Unit 1.00 65,568.25 65,568.25 6,556.83 72,125.08
g Pas. Kran Air 1/2" Tembok Bh 1.00 64,158.88 64,158.88 6,415.89 70,574.76
h Pas. Floor Drain Bh 1.00 237,407.50 237,407.50 23,740.75 261,148.25
j Pas. Kaca Bh 150,000.00 - - -
k Pas. Kran shower Bawah (toto) Bh 64,158.88 - - -
l Pas. Tempat Sabun Bh 175,000.00 - - -
VI KAMAR MANDI ANAK 2 7,116,838.48
a Membongkar Lantai dan Dinding Keramik Lama M2 11.52 31,762.50 365,904.00 36,590.40 402,494.40
b Pas. Pipa Air Bersih PVC dia. 1/2" Wavin AW M1 4.00 27,214.00 108,856.00 10,885.60 119,741.60
c Pas. Keramik Lantai Toilet 25 x 25 cm (Merk IKAD) M2 2.08 215,470.00 448,177.60 44,817.76 492,995.36
d Pas. Keramik Dinding Toilet 25 x 25 cm (Merk IKAD) M3 2.08 211,031.70 438,945.94 43,894.59 482,840.53
e Pas. Klosed Duduk Merk American Standard + Asessoris Unit 1.00 4,740,835.00 4,740,835.00 474,083.50 5,214,918.50
f Pas. Shower Unit 1.00 65,568.25 65,568.25 6,556.83 72,125.08
g Pas. Kran Air 1/2" Tembok Bh 1.00 64,158.88 64,158.88 6,415.89 70,574.76
h Pas. Floor Drain Bh 1.00 237,407.50 237,407.50 23,740.75 261,148.25
j Pas. Kaca Bh 150,000.00 - - -
k Pas. Kran shower Bawah (toto) Bh 64,158.88 - - -
l Pas. Tempat Sabun Bh 175,000.00 - - -
V KAMAR MANDI ANAK 3 7,116,838.48
a Membongkar Lantai dan Dinding Keramik Lama M2 11.52 31,762.50 365,904.00 36,590.40 402,494.40
b Pas. Pipa Air Bersih PVC dia. 1/2" Wavin AW M1 4.00 27,214.00 108,856.00 10,885.60 119,741.60
c Pas. Keramik Lantai Toilet 25 x 25 cm (Merk IKAD) M2 2.08 215,470.00 448,177.60 44,817.76 492,995.36
d Pas. Keramik Dinding Toilet 25 x 25 cm (Merk IKAD) M3 2.08 211,031.70 438,945.94 43,894.59 482,840.53
e Pas. Klosed Duduk Merk American Standard + Asessoris Unit 1.00 4,740,835.00 4,740,835.00 474,083.50 5,214,918.50
f Pas. Shower Unit 1.00 65,568.25 65,568.25 6,556.83 72,125.08
g Pas. Kran Air 1/2" Tembok Bh 1.00 64,158.88 64,158.88 6,415.89 70,574.76
h Pas. Floor Drain Bh 1.00 237,407.50 237,407.50 23,740.75 261,148.25
i Pas. Kaca Bh 150,000.00 - - -
j Pas. Kran shower Bawah (toto) Bh 64,158.88 - - -
k Pas. Tempat Sabun Bh 175,000.00 - - -
VI KAMAR MANDI ANAK 4 2,912,023.74
a Membongkar Lantai dan Dinding Keramik Lama M2 11.52 31,762.50 365,904.00 36,590.40 402,494.40
b Pas. Pipa Air Bersih PVC dia. 1/2" Wavin AW M1 27,214.00 - - -
c Pas. Keramik Lantai Toilet 25 x 25 cm (Merk IKAD) M2 2.08 215,470.00 448,177.60 44,817.76 492,995.36
d Pas. Keramik Dinding Toilet 25 x 25 cm (Merk IKAD) M3 2.08 211,031.70 438,945.94 43,894.59 482,840.53
e Pas. Klosed Jongkok Unit 1.00 1,092,700.40 1,092,700.40 109,270.04 1,201,970.44
f Pas. Kran Air 1/2" Tembok Bh 1.00 64,158.88 64,158.88 6,415.89 70,574.76
g Pas. Floor Drain Bh 1.00 237,407.50 237,407.50 23,740.75 261,148.25
h Pas. Kaca Bh 150,000.00 - - -
i Pas. Tempat Sabun Bh 175,000.00 - - -
VII PENGECTAN KAMAR UTAMA 2,458,004.67
a Pek. Cat Dinding Ulang dengan Cat Air Dullux Interior ( Bagian Ruang Dalam ) M2 90.78 24,615.00 2,234,549.70 223,454.97 2,458,004.67
JUMLAH 54,182,118.68
DIBULATKAN 54,182,100.00
HARGA
NO URAIAN PEKERJAAN SAT VOL SATUAN JUMLAH PPh 10% Total
(Rp)
1 2 3 4 5 6
…………………………………..
NIP. …………………………………..
RENCANA ANGGARAN BIAYA
HARGA
NO URAIAN PEKERJAAN SAT VOL SATUAN JUMLAH Total
(Rp)
2 3 4 5 6
JUMLAH 34,922,523.71
DIBULATKAN 34,922,500.00
JUNAIDI
Ketua Mesjid
PERHITUNGAN VOLUME
Pekerjaan :
Lokasi :
Lebar = 2.15 m
Volume = Panjang x Lebar = 4.56 m2
Luas II
5
1
Panjang = 2.12 m
Lebar = 2.15 m
Volume = Panjang x Lebar = 4.56 m2
Luas Tempat Wudu' Wanita = 9.12 m2
5
30
3
1
6
9
3
6
Wanita Pria
Luas Tempat Wudu' Pria = 9.12 m2
TOTAL = 19.55 m2
2
400
- Untuk dinding Kamar Garim
430
Panjang = 4.00 m
3.70 m
2.65 m
= 10.35 m
Luas Pas Batu
= 0.27 m2
Volume = Panjang x Luas = 2.79 m3
0
6
5
1
60
40
20
PERHITUNGAN VOLUME
Pekerjaan :
Lokasi :
132
130 130 SKETSA GAMBAR URAIAN PERHITUNGAN VOLUME
Lebar = 0.50 m
Luas = Panjang x Lebar = 1.75 m2
Luas II
Panjang = 0.90 m
5
1
Lebar = 1.32 m
Luas = Panjang x Lebar = 1.19 m2
Luas Cort Wudu' Wanita = 2.94 m2
5
30
3
1
6
9
3
6
Tinggi = 3.70
3
Wanita Pria
Luas = Jumlah Sisi Sejajar x Tingg = 24.61 = 12.30 m2
2 2.00
Luas Total = 15.24 m2
Volume Cor Lantai Tebal 12 cm
2
1
- Kamar Garim
Panjang = 14.15 m
Tinggi = 3.00 m
Volume = Panjang x Tinggi = 42.45 m2 x 2 sisi = 84.90 m2
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
JUNAIDI
Ketua Mesjid
HARGA SATUAN BAHAN DAN UPAH
HARGA
NO URAIAN BAHAN DAN UPAH SATUAN KETERANGAN
SATUAN
BAHAN
1 Pasir Pasang M3 Rp. 140,000.00 ###
Kg Rp. 116.67
2 Semen Portland (Semen Padang) 50 Kg zak Rp. 66,000.00 ###
Kg Rp. 1,300.00
3 Granit 60 x 60 cm Kotak Rp. 175,000.00
4 Keramik 40 x 40 cm Merk Ikad Kotak Rp. 75,000.00
5 Keramik 25 x 40 cm Merk Ikad Kotak Rp. 90,000.00
6 Keramik 25 x 25 cm Merk Ikad Kotak Rp. 70,000.00
7 Semen warna Kg Rp. 10,500.00
8 Klosed Duduk Komplit setara American Standard Bh Rp. 3,600,000.00 Terpasang
9 Klosed Jongkok setara KIA Bh Rp. 650,000.00 Terpasang
10 Watafel Keramik & Asesoris setara American Standard Bh Rp. 950,000.00 Terpasang
11 Cermin Grafir Bh Rp. 150,000.00 Terpasang
12 Floor Drain Bh Rp. 200,000.00 Terpasang
13 Kran Air Stainless Steel Bh Rp. 42,500.00 Terpasang
14 Pipa PVC diameter 1/2" AW M1 Rp. 8,000.00
15 Cat dasar Kg Rp. 21,000.00
16 Alkali Kg Rp. 60,000.00
17 Cat Tembok Interior Dullux Kg Rp. 72,000.00
18 Plamur wall putty Kg Rp. 18,000.00
19 Minyak Bekisting Ltr Rp. 10,000.00
20 Minyak Solar Ltr Rp. 5,500.00
21 Minyak Pelumas Ltr Rp. 35,000.00
22 Seal Tape Bh Rp. 5,000.00
23 Bath Tub Bh Rp. 6,500,000.00
24 Tempat Sabun Bh Rp. 175,000.00
HARGA
NO URAIAN BAHAN DAN UPAH SATUAN KETERANGAN
SATUAN
UPAH
1 Mandor Hari Rp. 155,000.00
2 Tukang Kayu Hari Rp. 125,000.00
3 Tukang Batu Hari Rp. 125,000.00
4 Tukang Besi/Las Hari Rp. 125,000.00
5 Tukang Kuda-kuda Hari Rp. 125,000.00
6 Tukang Cat Hari Rp. 125,000.00
7 Tukang Besi/Las Hari Rp. 125,000.00
8 Kepala Tukang Hari Rp. 155,000.00
9 Operator Mesin Hari Rp. 155,000.00
10 Pekerja Hari Rp. 100,000.00
…………………………………..
NIP. …………………………………..
TIME SCHEDULE
Kegiatan : Pembangunan Gedung Kantor
Pekerjaan : Pembangunan Gedung Kantor Kejaksaan
Lokasi : Kota Payakumbuh
JUMLAH #NAME? ### ### ### ### ### ### ### ### ### ### ### ### ### ### 4.86 ### ######
KOMULATIF 0.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
KET :
Jangka Waktu Pelaksanaan 120 ( seratus dua puluh ) Hari Kalender
…………………………………..
NIP. …………………………………..
PERHITUNGAN VOLUME
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
lebar = 0.36 M
tinggi = 0.43 M
Volume = 18.31 x 0.36 x 0.43 = 2.83 M3 2.83 M3
- Pasir Urug
panjang = 18.31 M
lebar = 0.36 M
tinggi = 0.05 M
Volume = 18.31 x 0.36 x 0.05 = 0.33 M3 0.33 M3
- Lantai Kerja Beton Cor K-100
panjang = 18.31 M
lebar = 0.36 M
tinggi = 0.08 M
Volume = 18.31 x 0.36 x 0.08 = 0.53 M3 0.53 M3
- Bekisting
panjang = 18.31 M
lebar = 0.30 M
jumlah = 2.00 Bdg
Volume = 18.31 x 0.30 x 2.00 = 10.99 M2 10.99 M2
- Pembesian Ø 16 mm
panjang = 27.45 M
jumlah = 4.00 Btg
indek = 1.5872
Volume = 27.45 x 4.00 x 1.5872 = 174.27 Kg 174.27 Kg
- Pembesian Ø 12 mm
panjang = 27.45 M
jumlah = 2.00 Btg
indek = 0.8928
Volume = 27.45 x 2.00 x 0.8928 = 49.01 Kg 49.01 Kg
PERHITUNGAN VOLUME
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
- Pembesian Ø 12 mm
panjang = 6.10 M
jumlah = 4.00 Btg
indek = 0.8928
Volume = 6.10 x 4.00 x 0.8928 = 21.78 Kg 21.78 Kg
- Pembesian Ø 8 mm
panjang = 0.60 M
jumlah = 49.80 M
indek = 0.3968
Volume = 0.60 x 49.80 x 0.3968 = 11.86 Kg 11.86 Kg
- Stamp Beton K-175
panjang = 6.10 M
lebar = 0.15 M
tinggi = 0.20 M
Volume = 6.10 x 0.15 x 0.20 = 0.18 M3 0.18 M3
- Pembesian Ø 16 mm
panjang = 5.60 M
jumlah = 4.00 x 2.00 = 8.00 Btg
indek = 1.5872
Volume = 5.60 x 8.00 x 1.5872 = 71.11 Kg 71.11 Kg
- Pembesian Ø 8 mm
panjang = 0.70 M
jumlah = 91.60 Bh
indek = 0.3968
Volume = 0.70 x 91.60 x 0.40 = 25.44 Kg 25.44 Kg
Stamp Beton K-250
panjang = 5.60 M
lebar = 0.25 M
tinggi = 0.25 M
jumlah = 2.00 Bh
Volume = 5.60 x 0.25 x 0.25 x 2.00 = 0.70 M3 0.70 M3
- Pembesian Ø 16 mm
panjang = 29.28 M
jumlah = 8.00 Btg
indek = 1.5872
Volume = 29.28 x 8.00 x 1.5872 = 371.79 Kg 371.79 Kg
- Pembesian Ø 8 mm
panjang = 1.10 M
jumlah = 204.20 Bh
indek = 0.3968
Volume = 1.10 x 204.20 x 0.3968 = 89.13 Kg 89.13 Kg
- Stamp Beton K-250
panjang = 26.40 M
lebar = 0.25 M
tinggi = 0.33 M
Volume = 26.40 x 0.25 x 0.33 = 2.18 M3 2.18 M3
- Pembesian Ø 8 mm
panjang = 0.85 M
jumlah = 151.04 Bh
indek = 0.3968
Volume = 0.85 x 151.04 x 0.3968 = 50.94 Kg 50.94 Kg
- Stamp Beton K-250
panjang = 18.76 M
lebar = 0.15 M
tinggi = 0.08 M
Volume = 18.76 x 0.15 x 0.08 = 0.23 M3 0.23 M3
g Pek. Acian
Volume = Volume plesteran - Volume Dinding Keramik
= 75.4210 - 8.45 = 66.97 M2 66.97 M2
h Afwerking Beton kolom, Tangga & Balok B.4 & B.4'
Kolom
panjang = 3.67 M
lebar = 1.70 M
jumlah = 8.00 Bh
luas = 3.67 x 1.70 x 8.00 = 49.91 M2
Tangga
panjang = 10.50 M
lebar = 1.75 M
luas = 10.50 x 1.75 = 18.375 M2
PERHITUNGAN VOLUME
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
b Urugan Pasir
panjang = 1.50 M
lebar = 1.20 M
tinggi = 0.05 M
Volume = 1.50 x 1.20 x 0.05 = 0.09 M3 0.09 M3
IX PEKERJAAN PLAFOND
a Pas. Plafond PVC
- Elev.+4,25 = 1.23 x 34.13 = 41.98 M2
- Elev.+4,61 = 7.60 x 9.50 = 72.20 M2
- Samping = 0.36 x 30.42 = 10.95 M2
Volume = 41.98 + 72.20 + 10.95 = 125.13 M2 125.13 M2
X PEKERJAAN LANTAI
a Cor Beton K-100
panjang = 10.71 M
lebar = 9.06 M
tinggi = 0.08 M
Volume = 10.71 x 9.06 x 0.08 = 7.76 M3
panjang = 5.81 M
lebar = 2.75 M
tinggi = 0.08 M
Volume = 5.81 x 2.75 x 0.08 = 1.28 M3
Total = 7.76 + 1.28 = 9.04 M3 7.76 M3
b Pas. Keramik Lantai 40 x 40 cm (Merk IKAD)
panjang = 10.71 M
lebar = 9.06 M
Volume = 10.71 x 9.06 = 97.03 M2 97.03 M2
PERHITUNGAN VOLUME
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
X PEKERJAAN CAT
a Pek. Cat Dinding & Kolom
Volume = Volume Acian Dinding + Afwerking Beton
= 66.97 + 98.71 = 165.69 M2 165.69 M2
LANTAI. 2
I PEKERJAAN BETON
a Pek. Kolom Beton Bertulang K-225, Uk. 25 x 25 cm (K.3)
- Bekisting
panjang = 3.65 M
lebar = 1.00 M
jumlah = 2.00 Bh
Volume = 3.65 x 1.00 x 2.00 = 7.30 M2 7.30 M2
- Pembesian Ø 16 mm
panjang = 3.65 M
jumlah = 4.00 x 2.00 = 8.00 Btg
indek = 1.5872
Volume = 3.65 x 8.00 x 1.59 = 46.35 Kg 46.35 Kg
- Pembesian Ø 8 mm
panjang = 0.70 M
jumlah = 59.40 Bh
indek = 0.3968
Volume = 0.70 x 59.40 x 0.3968 = 16.50 Kg 16.50 Kg
e Pek. Acian
Volume = Luas Plesteran - Luas Keramik Dinding 25 x 40 cm
= 163.35 - -18.21 = 181.56 M2 181.56 M2
PT.2
panjang = 7.36 M
tinggi = 3.20 M
luas = 7.36 x 3.20 = 23.55 M2
PERHITUNGAN VOLUME
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
PT.4
panjang = 2.88 M
tinggi = 3.20 M
luas = 2.88 x 3.20 = 9.22 M2
PT.5
panjang = 2.90 M
tinggi = 3.20 M
luas = 2.90 x 3.20 = 9.28 M2
PT.6
panjang = 6.00 M
tinggi = 3.20 M
luas = 6.00 x 3.20 = 19.20 M2
Pengurangan Kusen PJ.2
panjang = 2.58 M
lebar = 0.88 M
jumlah = 1.00 Unit
luas = 2.58 x 0.88 x 1.00 = 2.27 M2
panjang = 1.58 M
lebar = 0.64 M
jumlah = 1.00 Unit
luas = 1.58 x 0.64 x 1.00 = 1.01 M2
Volume = 19.20 - 2.27 - 1.01 = 15.92 M2
PERHITUNGAN VOLUME
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
P.2
panjang = 2.58 + 2.58 + 0.80 + 0.80 =
= 6.76 M
jumlah = 4.00 unit
Volume = 6.76 x 4.00 = 27.04 M1
PERHITUNGAN VOLUME
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
PJ.2
panjang = 2.58 + 2.58 + 1.58 + 1.52 +
1.52 + 0.64 = 10.42
jumlah = 1.00 unit
Volume = 10.42 x 1.00 = 10.42 M1
J.1
panjang = 1.68 + 1.68 + 0.60 + 0.60 +
0.60 = 5.16 M1
jumlah = 7.00 unit
Volume = 5.16 x 7.00 = 36.12 M1
J.2
panjang = 1.68 + 1.68 + 1.68 + 0.60 +
0.60 + 0.60 = 6.84 M1
jumlah = 6.00 unit
Volume = 6.84 x 6.00 = 41.04 M1
J.3
panjang = 1.68 + 1.68 + 1.68 + 1.68 +
0.60 + 0.60 + 0.60 = 8.52 M1
jumlah = 1.00 unit
Volume = 8.52 x 1.00 = 8.52 M1
V.1
panjang = 0.48 + 0.48 + 0.60 + 0.60
= 2.16 M1
jumlah = 2.00 unit
Volume = 2.16 x 2.00 = 4.32 M1
V.2
panjang = 0.48 + 0.48 + 0.48 + 1.24 +
1.24 = 3.92 M1
jumlah = 1.00 unit
Volume = 1.24 x 1.00 = 1.24 M1
Total Volume Kusen
= 13.12 + 27.04 + 31.26 + 10.42 +
36.12 + 41.04 + 8.52 + 4.32 +
1.24 = 173.08 M1 173.08 M1
PERHITUNGAN VOLUME
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
P.2
panjang = 2.10 M
lebar = 0.80 M
jumlah = 4.00 unit
Volume = 2.10 x 0.80 x 4.00 = 6.72 M2
PJ.1
panjang = 2.10 M
lebar = 0.80 M
jumlah = 3.00 unit
Volume = 2.10 x 0.80 x 3.00 = 5.04 M2
PJ.2
panjang = 2.10 M
lebar = 0.80 M
jumlah = 1.00 unit
Volume = 2.10 x 0.80 x 1.00 = 1.68 M2
Total Volume
= 2.94 6.72 5.04 1.68 = 16.38 M2 16.38 M2
b Pas. Pipa Air Bersih PVC dia. 1" setara Wavin AW = 12.50 M2 12.50 M2
c Pas. Pipa Air Kotor Kamar Mandi & Wastafel PVC dia. 2" setara Wavin AW = 12.50 M2 12.50 M2
d Pas. Pipa Air Tinja PVC dia. 4" setara Wavin AW = 10.50 M2 10.50 M2
IX PEKERJAAN CAT
a Pek. Cat Dinding Baru dengan Cat Air Interior ( Bagian Ruang Dalam )
Volume = Volume Acian Dinding
= 181.56 : 2.00 = 90.78 M2 90.78 M2
…………………………………..
NIP. …………………………………..
BERITA ACARA ASISTENSI
Kegiatan #NAME?
Pekerjaan : Rehabilitasi Kamar Mandi Rumah Dinas DPRD
Lokasi : Kota Payakumbuh
T. Anggaran #NAME?