Anda di halaman 1dari 25

Daftar Harga Satuan Upah dan Bahan

Tahun 2016

I HARGA SATUAN UPAH

NO URAIAN SATUAN HARGA SATUAN


1 Pekerja / Buruh Tak Terlatih Orang / Hari = Rp. 80,000.00
2 Buruh Terlatih Orang / Hari = Rp. 95,000.00
3 Mandor Orang / Hari = Rp. 0.00
4 Tukang Cat Orang / Hari = Rp. 120,000.00
5 Tukang Kayu Orang / Hari = Rp. 120,000.00
6 Tukang Batu Orang / Hari = Rp. 120,000.00
7 Tukang Besi Orang / Hari = Rp. 120,000.00
7 Kepala Tukang Orang / Hari = Rp. 160,000.00

II HARGA SATUAN BAHAN

NO URAIAN SATUAN HARGA SATUAN


1 Pasir Pasang 1400 kg/m3 M3 = Rp. 80,000.00
2 Pasir Urug M3 = Rp. 50,000.00
3 Tanah Urug M3 = Rp. 45,000.00
4 Kerikil Bersih 1350kg/m3 M3 = Rp. 115,000.00
5 Batu Pecah 15 - 20 M3 = Rp. 150,000.00
6 Batu Pecah 2 - 3 M3 = Rp. 230,000.00
7 Sirtu Darat M3 = Rp. 78,000.00
8 Batu Pecah Tersaring M3 = Rp. 247,500.00
9 Batu Bata BH = Rp. 625.00
10 Batu Rooster uk. 10 x 20 cm BH = Rp. 8,125.00
11 Air Bersih LTR = Rp. 200.00
SEMEN
12 Semen PC @ 40 Kg ZAK = Rp. 50,000.00
13 Semen Putih @ 40 Kg ZAK = Rp. 125,000.00
KERAMIK & BATU ALAM
14 Granite Tile 60 x 60 cm BH = Rp. 60,937.50
15 Keramik 20x20 cm BH = Rp. 2,768.00
16 Keramik Dinding 20x25 cm BH = Rp. 3,375.00
17 Keramik 40x40 cm BH = Rp. 13,216.00
18 Keramik 20x40 cm M2 = Rp. 90,000.00
19 Keramik 30x30 cm M3 = Rp. 6,030.00
20 Batu Candi M2 = Rp. 216,000.00
21 Batu Alam Paras Jogja M2 = Rp. 222,000.00
SANITAIR
21 Kloset Jongkok @ American Standard BH = Rp. 242,000.00
22 Bak Cuci Piring 2 Lubang Stainlessteel SET = Rp. 360,000.00
23 Kran Air 3/4" Stainlesssteel BH = Rp. 25,000.00
24 Bak Mandi PVC BH = Rp. 295,000.00
25 Pipa PVC dia. 3/4" M' = Rp. 9,166.67
26 Pipa PVC dia. 3" M' = Rp. 54,666.67
NO URAIAN SATUAN HARGA SATUAN
27 Pipa PVC dia. 4" M' = Rp. 44,166.67
28 Floor Drain BH = Rp. 25,000.00
29 Sealtape BH = Rp. 3,000.00
ATAP
28 Genteng Metal 0.35 mm Uk. (120 x 80 cm) LBR = Rp. 87,500.00
29 Rabung Genteng Metal 0.35 mm LBR = Rp. 47,200.00
30 Rangka Atap Baja Ringan C.75.75 M2 = Rp. 215,000.00
31 Calsiplank Uk. 3m x 20 cm x 8 mm Bh = Rp. 56,600.00
KAYU
31 Kayu Semi/ Setara Merati M3 = Rp. 13,145,000.00
32 Kayu Sembarang Keras M3 = Rp. 5,600,000.00
33 Kayu Dolken BTG = Rp. 20,000.00
34 Multipleks 3 mm LBR = Rp. 61,950.00
35 Multipleks 4 mm LBR = Rp. 81,000.00
36 Multipleks 6 mm LBR = Rp. 111,000.00
37 Multipleks 9 mm LBR = Rp. 162,500.00
38 Multipleks 12 mm LBR = Rp. 199,500.00
39 Lem Kayu KG = Rp. 25,000.00
PLAFOND
40 Gypsum Board 9 mm LBR = Rp. 86,400.00
41 Profil Gypsum M' = Rp. 15,000.00
42 Rangka Furing Btg = Rp. 24,600.00
CAT TEMBOK
52 Cat Tembok Vinilex KG = Rp. 24,000.00
53 Cat Kilat Kuda Terbang KG = Rp. 65,000.00
54 Cat Dasar KG = Rp. 28,300.00
55 Plamur KG = Rp. 27,000.00
56 Cat Menie KG = Rp. 29,400.00
57 Solar LTR = Rp. 6,900.00
58 Tinner LTR = Rp. 15,000.00
59 Kertas Amplas LBR = Rp. 2,950.00
60 Kuas 4 Inc BH = Rp. 20,000.00
61 Minyak Bekisting LTR = Rp. 7,000.00
BESI
62 Paku Biasa KG = Rp. 15,600.00
63 Paku Gypsum KG = Rp. 25,000.00
64 Paku Atap Genteng KG = Rp. 21,500.00
65 Besi Beton KG = Rp. 9,000.00
66 Kawat Beton KG = Rp. 18,500.00
67 Besi Profil KG = Rp. 39,000.00
ALAT ELEKTRIKAL
74 Kabel NYA 2,5 mm M' = Rp. 3,562.50
75 SL 18 Watt BH = Rp. 49,450.00
76 SL 8 Watt BH = Rp. 27,600.00
77 Armatur Down Light 3 Inc BH = Rp. 56,250.00
78 Saklar Ganda BH = Rp. 25,300.00
79 Saklar Tunggal BH = Rp. 13,800.00
80 Stop Kontak Broco BH = Rp. 19,550.00
PINTU & JENDELA
80 Grendel 4" BH = Rp. 4,700.00
81 Grendel 3" BH = Rp. 4,500.00
82 Engsel 4" BH = Rp. 10,600.00
83 Engsel 3" BH = Rp. 7,650.00
83 Kunci Tanam Besar BH = Rp. 110,000.00
84 Kunci Tanam Kecil BH = Rp. 70,800.00
85 Hak Angin BH = Rp. 18,000.00
86 Kaca 3 MM M2 = Rp. 68,888.89
87 Kaca 5 MM M2 = Rp. 100,000.00
NO URAIAN SATUAN HARGA SATUAN
87 Silikon Kg = Rp. 64,000.00
LANSEKAP
85 Paving Block 22 x 11 x 6 BH = Rp. #REF!

Medan, Desember 2017

Disetujui oleh : Diperiksa oleh : Dibuat oleh :


Kepala Bidang Cipta Karya Kasi Perencanaan Konsultan Perencana
Dinas PUPR Kabupaten Langkat Dinas PUPR Kabupaten Langkat PT. DWI PUTERA ADIYASA

KHAIRUL AZMI, S.STP SADINO, ST, MT. Ir. HERRI SURYADI SAMOSIR
NIP. 19850216 200312 1 001 Nip. 19790912 200604 1 004 Direktur
Analisa Harga Satuan Pekerjaan
Berdasarkan Permen PUPR 28-2016
PEDOMAN ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUM

PEKERJAAN TANAH
A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 meter
Tenaga Kerja
Pekerja 0.750 Oh x Rp. 80,000.00 = Rp. 60,000.00
Mandor 0.025 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 60,000.00

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah


Tenaga Kerja
Pekerja 0.500 Oh x Rp. 80,000.00 = Rp. 40,000.00
Mandor 0.050 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 40,000.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


Bahan
Pasir Urug 1.200 m3 x Rp. 50,000.00 = Rp. 60,000.00
Jumlah = Rp. 60,000.00
Tenaga Kerja
Pekerja 0.300 Oh x Rp. 80,000.00 = Rp. 24,000.00
Mandor 0.010 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 24,000.00
Total = Rp. 84,000.00

PEKERJAAN DIDNDING

A.4.4.1.7. Pemasangan 1 m2 dinding bata merah tebal 1/2 bata, campuran 1 SP : 2 PP


Bahan
Bata merah 70.000 bh x Rp. 625.00 = Rp. 43,750.00
Porland cement 18.950 kg x Rp. 1,250.00 = Rp. 23,687.50
Pasir pasang 0.0380 m3 x Rp. 80,000.00 = Rp. 3,040.00
Jumlah = Rp. 70,477.50
Tenaga
Pekerja 0.300 Oh x Rp. 80,000.00 = Rp. 24,000.00
Tukang batu 0.100 Oh x Rp. 120,000.00 = Rp. 12,000.00
Kepala Tukang 0.010 Oh x Rp. 160,000.00 = Rp. 1,600.00
Mandor 0.000 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 37,600.00
Total = Rp. 108,077.50

A.4.4.1.9. Pemasangan 1 m2 dinding bata merah tebal 1/2 bata, campuran 1 SP : 4 PP


Bahan
Bata merah 70.000 bh x Rp. 625.00 = Rp. 43,750.00
Porland cement 11.500 kg x Rp. 1,250.00 = Rp. 14,375.00
Pasir pasang 0.043 m3 x Rp. 80,000.00 = Rp. 3,440.00
Jumlah = Rp. 61,565.00
Tenaga
Pekerja 0.300 Oh x Rp. 80,000.00 = Rp. 24,000.00
Tukang batu 0.100 Oh x Rp. 120,000.00 = Rp. 12,000.00
Kepala Tukang 0.010 Oh x Rp. 160,000.00 = Rp. 1,600.00
Mandor 0.015 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 37,600.00
Total = Rp. 99,165.00

A.4.4.2.2. Membuat 1 m2 Plesteran 1 SP : 2 PP, tebal 15 mm


Bahan
Porland cement 10.224 kg x Rp. 1,250.00 = Rp. 12,780.00
Pasir Pasang 0.020 m3 x Rp. 80,000.00 = Rp. 1,600.00
Jumlah = Rp. 14,380.00
Tenaga
Pekerja 0.300 Oh x Rp. 80,000.00 = Rp. 24,000.00
Tukang batu 0.150 Oh x Rp. 120,000.00 = Rp. 18,000.00
Kepala Tukang 0.015 Oh x Rp. 160,000.00 = Rp. 2,400.00
Mandor 0.015 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 44,400.00
Total = Rp. 58,780.00

A.4.4.2.4. Pemasangan 1 m2 Plesteran 1 SP : 4 PP, tebal 15 mm


Bahan
Porland cement 6.240 kg x Rp. 1,250.00 = Rp. 7,800.00
Pasir Pasang 0.024 m3 x Rp. 80,000.00 = Rp. 1,920.00
Jumlah = Rp. 9,720.00
Tenaga
Pekerja 0.300 Oh x Rp. 80,000.00 = Rp. 24,000.00
Tukang batu 0.150 Oh x Rp. 120,000.00 = Rp. 18,000.00
Kepala Tukang 0.015 Oh x Rp. 160,000.00 = Rp. 2,400.00
Mandor 0.015 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 44,400.00
Total = Rp. 54,120.00

PEKERJAAN BETON
A.4.1.1.2. Membuat 1 m3 beton mutu f'=9,8 Mpa (K-125)
Bahan
Porland cement 276.00 kg x Rp. 1,250.00 = Rp. 345,000.00
Pasir beton 828 kg x Rp. 57.14 = Rp. 47,314.29
Kerikil (maksimum 30mm ) 1,012 kg x Rp. 85.19 = Rp. 86,207.41
Air 215 Ltr x Rp. 200.00 = Rp. 43,000.00
Jumlah = Rp. 521,521.69
Tenaga
Pekerja 1.650 Oh x Rp. 80,000.00 = Rp. 132,000.00
Tukang batu 0.275 Oh x Rp. 120,000.00 = Rp. 33,000.00
Kepala Tukang 0.028 Oh x Rp. 160,000.00 = Rp. 4,480.00
Mandor 0.083 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 169,480.00
Total = Rp. 691,001.69

A.4.1.1.5. Membuat 1 m3 beton mutu f'=14,5 Mpa (K-175)


Bahan
Porland cement 326.000 kg x Rp. 1,250.00 = Rp. 407,500.00
Pasir beton 760 kg x Rp. 57.14 = Rp. 43,428.57
Kerikil (maksimum 30mm ) 1,029 kg x Rp. 85.19 = Rp. 87,655.56
Air 215 Ltr x Rp. 200.00 = Rp. 43,000.00
Jumlah = Rp. 581,584.13
Tenaga
Pekerja 1.650 Oh x Rp. 80,000.00 = Rp. 132,000.00
Tukang batu 0.275 Oh x Rp. 120,000.00 = Rp. 33,000.00
Kepala Tukang 0.028 Oh x Rp. 160,000.00 = Rp. 4,480.00
Mandor 0.083 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 169,480.00
Total = Rp. 751,064.13

A.4.1.1.17. Pembesian 10 kg dengan besi polos


Bahan
Besi beton polos 10.500 kg x Rp. 9,000.00 = Rp. 94,500.00
Kawat beton 0.150 kg x Rp. 18,500.00 = Rp. 2,775.00
Jumlah = Rp. 97,275.00
Tenaga
Pekerja 0.070 Oh x Rp. 80,000.00 = Rp. 5,600.00
Tukang besi 0.070 Oh x Rp. 120,000.00 = Rp. 8,400.00
Kepala Tukang 0.007 Oh x Rp. 160,000.00 = Rp. 1,120.00
Mandor 0.004 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 15,120.00
Total = Rp. 112,395.00
Pembesian per kg = Rp. 11,239.50
A.4.1.1.20. Memasang 1 m2 bekisting untuk pondasi
Bahan
Kayu Sembarang Keras 0.040 m3 x Rp. 5,600,000.00 = Rp. 224,000.00
Paku 5 cm-12 cm 0.300 kg x Rp. 15,600.00 = Rp. 4,680.00
Minyak bekisting 0.100 ltr x Rp. 7,000.00 = Rp. 700.00
Jumlah = Rp. 229,380.00
Tenaga
Pekerja 0.520 Oh x Rp. 80,000.00 = Rp. 41,600.00
Tukang kayu 0.260 Oh x Rp. 120,000.00 = Rp. 31,200.00
Kepala Tukang 0.026 Oh x Rp. 160,000.00 = Rp. 4,160.00
Mandor 0.026 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 76,960.00
Total = Rp. 306,340.00
3 x pakai = Rp. 102,113.33

A.4.1.1.21. Memasang 1 m2 bekisting untuk sloof


Bahan
Kayu Sembarang Keras 0.045 m3 x Rp. 5,600,000.00 = Rp. 252,000.00
Paku 5 cm-12 cm 0.300 kg x Rp. 15,600.00 = Rp. 4,680.00
Minyak bekisting 0.100 ltr x Rp. 7,000.00 = Rp. 700.00
Jumlah = Rp. 257,380.00
Tenaga
Pekerja 0.520 Oh x Rp. 80,000.00 = Rp. 41,600.00
Tukang kayu 0.260 Oh x Rp. 120,000.00 = Rp. 31,200.00
Kepala Tukang 0.026 Oh x Rp. 160,000.00 = Rp. 4,160.00
Mandor 0.026 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 76,960.00
Total = Rp. 334,340.00
3 x pakai = Rp. 111,446.67

A.4.1.1.22. Memasang 1 m2 bekisting untuk kolom


Bahan
Kayu Sembarang Keras 0.040 m3 x Rp. 5,600,000.00 = Rp. 224,000.00
Paku 5 cm-12 cm 0.400 kg x Rp. 15,600.00 = Rp. 6,240.00
Minyak bekisting 0.200 ltr x Rp. 7,000.00 = Rp. 1,400.00
Balok Kayu Sembarang Keras 0.015 m3 x Rp. 5,600,000.00 = Rp. 84,000.00
Plywood tebal 9 mm 0.350 Lbr x Rp. 162,500.00 = Rp. 56,875.00
Dolken kayu galam 2.000 btg x Rp. 20,000.00 = Rp. 40,000.00
Jumlah = Rp. 412,515.00
Tenaga
Pekerja 0.660 Oh x Rp. 80,000.00 = Rp. 52,800.00
Tukang kayu 0.330 Oh x Rp. 120,000.00 = Rp. 39,600.00
Kepala Tukang 0.033 Oh x Rp. 160,000.00 = Rp. 5,280.00
Mandor 0.033 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 97,680.00
Total = Rp. 510,195.00
3 x pakai = Rp. 170,065.00

A.4.1.1.23. Memasang 1 m2 bekisting untuk balok


Bahan
Kayu Sembarang Keras 0.040 m3 x Rp. 5,600,000.00 = Rp. 224,000.00
Paku 5 cm-12 cm 0.400 kg x Rp. 15,600.00 = Rp. 6,240.00
Minyak bekisting 0.200 ltr x Rp. 7,000.00 = Rp. 1,400.00
Balok Kayu Sembarang Keras 0.018 m3 x Rp. 5,600,000.00 = Rp. 100,800.00
Plywood tebal 9 mm 0.350 Lbr x Rp. 162,500.00 = Rp. 56,875.00
Dolken kayu galam 2.000 btg x Rp. 20,000.00 = Rp. 40,000.00
Jumlah = Rp. 429,315.00
Tenaga
Pekerja 0.660 Oh x Rp. 80,000.00 = Rp. 52,800.00
Tukang kayu 0.330 Oh x Rp. 120,000.00 = Rp. 39,600.00
Kepala Tukang 0.033 Oh x Rp. 160,000.00 = Rp. 5,280.00
Mandor 0.033 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 97,680.00
Total = Rp. 526,995.00
3 x pakai = Rp. 175,665.00
A.4.1.1.24. Memasang 1 m2 bekisting untuk lantai
Bahan
Kayu Sembarang Keras 0.040 m3 x Rp. 5,600,000.00 = Rp. 224,000.00
Paku 5 cm-12 cm 0.400 kg x Rp. 15,600.00 = Rp. 6,240.00
Minyak bekisting 0.200 ltr x Rp. 7,000.00 = Rp. 1,400.00
Balok Kayu Sembarang Keras 0.002 m3 x Rp. 5,600,000.00 = Rp. 8,400.00
Plywood tebal 9 mm 0.350 Lbr x Rp. 162,500.00 = Rp. 56,875.00
Dolken kayu galam 6.000 btg x Rp. 20,000.00 = Rp. 120,000.00
Jumlah = Rp. 416,915.00
Tenaga
Pekerja 0.660 Oh x Rp. 80,000.00 = Rp. 52,800.00
Tukang kayu 0.330 Oh x Rp. 120,000.00 = Rp. 39,600.00
Kepala Tukang 0.033 Oh x Rp. 160,000.00 = Rp. 5,280.00
Mandor 0.033 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 97,680.00
Total = Rp. 514,595.00
3x pakai = Rp. 171,531.67

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang


Bahan
Kayu Kelas III 0.002 m3 x Rp. 5,600,000.00 = Rp. 11,200.00
Paku 5 cm-12 cm 0.010 kg x Rp. 15,600.00 = Rp. 156.00
Minyak bekisting 0.000 ltr x Rp. 7,000.00 = Rp. 0.00
Besi Beton polos 3.000 Kg x Rp. 9,000.00 = Rp. 27,000.00
Kawat Beton 0.045 Kg x Rp. 18,500.00 = Rp. 832.50
Semen Forland 4.000 Kg x Rp. 1,250.00 = Rp. 5,000.00
Pasir 0.006 m3 x Rp. 80,000.00 = Rp. 480.00
Kerikil 0.009 m3 x Rp. 115,000.00 = Rp. 1,035.00
Jumlah = Rp. 45,703.50
Tenaga
Pekerja 0.180 Oh x Rp. 80,000.00 = Rp. 14,400.00
Tukang Batu 0.020 Oh x Rp. 120,000.00 = Rp. 2,400.00
Tukang kayu 0.020 Oh x Rp. 120,000.00 = Rp. 2,400.00
Tukang besi 0.020 Oh x Rp. 120,000.00 = Rp. 2,400.00
Kepala Tukang 0.006 Oh x Rp. 160,000.00 = Rp. 960.00
Mandor 0.009 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 22,560.00
Total = Rp. 68,263.50

A.4.1.1.36. Membuat 1 m’ balok praktis beton bertulang


Bahan
Kayu Kelas III 0.003 m3 x Rp. 5,600,000.00 = Rp. 16,800.00
Paku 5 cm-12 cm 0.020 kg x Rp. 15,600.00 = Rp. 312.00
Minyak bekisting 0.000 ltr x Rp. 7,000.00 = Rp. 0.00
Besi Beton polos 3.600 Kg x Rp. 9,000.00 = Rp. 32,400.00
Kawat Beton 0.050 Kg x Rp. 18,500.00 = Rp. 925.00
Semen Forland 5.500 Kg x Rp. 1,250.00 = Rp. 6,875.00
Pasir 0.009 m3 x Rp. 80,000.00 = Rp. 720.00
Kerikil 0.015 m3 x Rp. 115,000.00 = Rp. 1,725.00
Jumlah = Rp. 59,757.00
Tenaga
Pekerja 0.297 Oh x Rp. 80,000.00 = Rp. 23,760.00
Tukang Batu 0.033 Oh x Rp. 120,000.00 = Rp. 3,960.00
Tukang kayu 0.033 Oh x Rp. 120,000.00 = Rp. 3,960.00
Tukang besi 0.033 Oh x Rp. 120,000.00 = Rp. 3,960.00
Kepala Tukang 0.010 Oh x Rp. 160,000.00 = Rp. 1,600.00
Mandor 0.015 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 37,240.00
Total = Rp. 96,997.00
PEKERJAAN KERAMIK & BATU ALAM
A.4.4.3.35.b. Pemasangan 1 m2 Lantai Granit Tile Uk. 60 x 60 cm
Bahan
Granite Tile 60x60cm 2.917 bh x Rp. 45,000.00 = Rp. 131,250.00
Porland cement 10.000 kg x Rp. 1,585.00 = Rp. 15,850.00
Pasir pasang 0.045 m3 x Rp. 110,890.00 = Rp. 4,990.05
Semen warna 1.500 kg x Rp. 3,125.00 = Rp. 4,687.50
Jumlah = Rp. 203,261.93
Tenaga
Pekerja 0.700 Oh x Rp. 80,000.00 = Rp. 56,000.00
Tukang batu 0.350 Oh x Rp. 120,000.00 = Rp. 42,000.00
Kepala tukang 0.035 Oh x Rp. 160,000.00 = Rp. 5,600.00
Mandor 0.035 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 129,675.00
Total = Rp. 332,936.93
A.4.4.3.36. Pemasangan 1 m2 lantai keramik uk. 25 x 25 cm
Bahan
Keramik 16.800 bh x Rp. 2,768.00 = Rp. 46,502.40
Porland cement 10.400 kg x Rp. 1,585.00 = Rp. 16,484.00
Pasir pasang 0.045 m3 x Rp. 110,890.00 = Rp. 4,990.05
Semen warna 1.620 kg x Rp. 3,125.00 = Rp. 5,062.50
Jumlah = Rp. 73,038.95
Tenaga
Pekerja 0.700 Oh x Rp. 80,000.00 = Rp. 56,000.00
Tukang batu 0.350 Oh x Rp. 120,000.00 = Rp. 42,000.00
Kepala Tukang 0.035 Oh x Rp. 160,000.00 = Rp. 5,600.00
Mandor 0.035 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 103,600.00
Total = Rp. 176,638.95
A.4.4.3.54.a Pemasangan 1 m2 dinding keramik uk. 25 x 40 cm
Bahan
Keramik 13.125 bh x Rp. 6,250.00 = Rp. 82,031.25
Porland cement 10.400 kg x Rp. 1,585.00 = Rp. 16,484.00
Pasir pasang 0.045 m3 x Rp. 110,890.00 = Rp. 4,990.05
Semen warna 1.620 kg x Rp. 3,125.00 = Rp. 5,062.50
Jumlah = Rp. 108,567.80
Tenaga
Pekerja 0.600 Oh x Rp. 80,000.00 = Rp. 48,000.00
Tukang batu 0.350 Oh x Rp. 120,000.00 = Rp. 42,000.00
Kepala Tukang 0.035 Oh x Rp. 160,000.00 = Rp. 5,600.00
Mandor 0.300 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 95,600.00
Total = Rp. 204,167.80

PEKERJAAN PLAFOND & SEKAT PARTISI


A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran 120 x 240 x 9 mm, tebal 9 mm
Bahan
Gypsum Board 0.364 Lbr x Rp. 86,400.00 = Rp. 31,449.60
Paku Gypsum 0.110 kg x Rp. 25,000.00 = Rp. 2,750.00
Jumlah = Rp. 34,199.60
Tenaga
Pekerja 0.100 Oh x Rp. 80,000.00 = Rp. 8,000.00
Tukang batu 0.050 Oh x Rp. 120,000.00 = Rp. 6,000.00
Kepala Tukang 0.005 Oh x Rp. 160,000.00 = Rp. 800.00
Mandor 0.005 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 14,800.00
Total = Rp. 48,999.60
Dihitung 3 100 m2 Ceiling Frame / Metal Furing
Bahan
C-Channel PN 260 74.000 m x Rp. 28,325.00 = Rp. 2,096,050.00
Connector PN 261 170.000 bh x Rp. 1,925.00 = Rp. 327,250.00
Hanger Clip PN 262 85.000 bh x Rp. 962.50 = Rp. 81,812.50
Suspension Rod PN 227 M4 26.000 bh x Rp. 7,975.00 = Rp. 207,350.00
Angel Bracket PN 220 N 85.000 bh x Rp. 1,512.50 = Rp. 128,562.50
Wall Angel PN 252 FX 7.000 m x Rp. 13,475.00 = Rp. 94,325.00
Paku Mesiu 85.000 bh x Rp. 1,562.50 = Rp. 132,812.50
Concrete Nails 74.000 bh x Rp. 125.00 = Rp. 9,250.00
Alat Bantu 0.300 923,223.75
Jumlah = Rp. 4,000,636.25
1 m2 Ceiling Frame = Rp. 40,006.36
Tenaga
Upah Pemasangan / m2 (30% bahan) x Rp. 12,001.91 = Rp. 12,001.91
Jumlah = Rp. 12,001.91
Total = Rp. 52,008.27

PENGECATAN
A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Bahan
Plamur 0.10 Kg x Rp. 27,000.00 = Rp. 2,700.00
Cat Dasar 0.10 Kg x Rp. 28,300.00 = Rp. 2,830.00
Cat Tembok 0.26 Kg x Rp. 24,000.00 = Rp. 6,240.00
Jumlah = Rp. 11,770.00
Tenaga
Pekerja 0.02 OH x Rp. 80,000.00 = Rp. 1,600.00
Tukang Cat 0.063 OH x Rp. 120,000.00 = Rp. 7,560.00
Kepala Tukang 0.0063 OH x Rp. 160,000.00 = Rp. 1,008.00
Mandor 0.003 OH x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 10,168.00
Total = Rp. 21,938.00

A.4.7.1.4. Pengecatan 1 m2 cat bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Bahan
Cat Manie 0.20 Kg x Rp. 29,400.00 = Rp. 5,880.00
Plamur 0.15 Kg x Rp. 27,000.00 = Rp. 4,050.00
Cat Dasar 0.17 Kg x Rp. 28,300.00 = Rp. 4,811.00
Cat Kilat 0.26 Kg x Rp. 65,000.00 = Rp. 16,900.00
Kuas 0.01 Bh x Rp. 20,000.00 = Rp. 200.00
Thineer 0.03 Kg x Rp. 15,000.00 = Rp. 450.00
Kertas Pasir 0.20 Lbr x Rp. 2,950.00 = Rp. 590.00
Jumlah = Rp. 32,881.00
Tenaga
Pekerja 0.07 OH x Rp. 80,000.00 = Rp. 5,600.00
Tukang Cat 0.009 OH x Rp. 120,000.00 = Rp. 1,080.00
Kepala Tukang 0.006 OH x Rp. 160,000.00 = Rp. 960.00
Mandor 0.003 OH x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 7,640.00
Total = Rp. 40,521.00

A.4.7.1.5. Pengecatan 1 m2 cat bidang besi baru (1 lapis cat dasar, 2 lapis cat penutup)
Bahan
Cat Manie 0.20 Kg x Rp. 29,400.00 = Rp. 5,880.00
Cat Dasar 0.17 Kg x Rp. 28,300.00 = Rp. 4,811.00
Cat Kilat 0.26 Kg x Rp. 65,000.00 = Rp. 16,900.00
Kuas 0.01 Bh x Rp. 20,000.00 = Rp. 200.00
Thineer 0.03 Kg x Rp. 15,000.00 = Rp. 450.00
Kertas Pasir 0.20 Lbr x Rp. 2,950.00 = Rp. 590.00
Jumlah = Rp. 28,831.00
Tenaga
Pekerja 0.07 OH x Rp. 80,000.00 = Rp. 5,600.00
Tukang Cat 0.009 OH x Rp. 120,000.00 = Rp. 1,080.00
Kepala Tukang 0.006 OH x Rp. 160,000.00 = Rp. 960.00
Mandor 0.003 OH x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 7,640.00
Total = Rp. 36,471.00

PINTU & JENDELA


A.4.6.1.2. Pembuatan dan Pemasangan 1 m3 kusen pintu dan jendela, kayu kelas I
Bahan
Balok kayu meranti 1.2 m3 x Rp. 13,145,000.00 = Rp. 15,774,000.00
Paku Biasa cm 1.25 kg x Rp. 15,600.00 = Rp. 19,500.00
Lem Kayu 1 kg x Rp. 25,000.00 = Rp. 25,000.00
Jumlah = Rp. 15,818,500.00
Tenaga
Pekerja 6 Oh x Rp. 80,000.00 = Rp. 480,000.00
Tukang Kayu 18 Oh x Rp. 120,000.00 = Rp. 2,160,000.00
Kepala Tukang 1.8 Oh x Rp. 160,000.00 = Rp. 288,000.00
Mandor 0.3 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 2,928,000.00
Total = Rp. 18,746,500.00

A.4.6.1.5.a Pembuatan dan Pemasangan 1 m2 daun pintu panel, kayu kelas I


Bahan
Papan kayu meranti 0.04 m3 x Rp. 13,145,000.00 = Rp. 525,800.00
Lem Kayu 0.5 kg x Rp. 25,000.00 = Rp. 12,500.00
Jumlah = Rp. 538,300.00
Tenaga
Pekerja 1 Oh x Rp. 80,000.00 = Rp. 80,000.00
Tukang Kayu 1.5 Oh x Rp. 120,000.00 = Rp. 180,000.00
Kepala Tukang 0.3 Oh x Rp. 160,000.00 = Rp. 48,000.00
Mandor 0.05 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 308,000.00
Total = Rp. 846,300.00

A.4.6.1.6. Pembuatan dan Pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau I
Bahan
Papan kayu meranti 0.024 m3 x Rp. 13,145,000.00 = Rp. 315,480.00
Lem Kayu 0.3 kg x Rp. 25,000.00 = Rp. 7,500.00
Jumlah = Rp. 322,980.00
Tenaga
Pekerja 0.8 Oh x Rp. 80,000.00 = Rp. 64,000.00
Tukang Kayu 1.2 Oh x Rp. 120,000.00 = Rp. 144,000.00
Kepala Tukang 0.24 Oh x Rp. 160,000.00 = Rp. 38,400.00
Mandor 0.04 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 246,400.00
Total = Rp. 569,380.00

A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa


Bahan
Kunci tanam 1.0000 Bh x Rp. 110,000.00 = Rp. 110,000.00
Jumlah = Rp. 110,000.00
Tenaga
Pekerja 0.010 Oh x Rp. 80,000.00 = Rp. 800.00
Tukang Kayu 0.500 Oh x Rp. 120,000.00 = Rp. 60,000.00
Kepala Tukang 0.050 Oh x Rp. 160,000.00 = Rp. 8,000.00
Mandor 0.005 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 68,800.00
Total = Rp. 178,800.00

A.4.6.2.5. Pemasangan 1 buah engsel pintu


Bahan
Engsel Pintu 4" 1.0000 Bh x Rp. 10,600.00 = Rp. 10,600.00
Jumlah = Rp. 10,600.00
Tenaga
Pekerja 0.015 Oh x Rp. 80,000.00 = Rp. 1,200.00
Tukang Kayu 0.150 Oh x Rp. 120,000.00 = Rp. 18,000.00
Kepala Tukang 0.015 Oh x Rp. 160,000.00 = Rp. 2,400.00
Mandor 0.0008 Oh x Rp. 0.00 = Rp. 0.00
Jumlah = Rp. 21,600.00
Total = Rp. 32,200.00

A.4.6.2.6. Pemasangan 1 buah engsel jendela


Bahan
Engsel Jendela 3" 1.0000 Ps x Rp. 4,500.00 = Rp. 4,500.00
Jumlah = Rp. 4,500.00
Tenaga
Pekerja 0.015 Oh x Rp. 100,000.00 = Rp. 1,500.00
Tukang Kayu 0.150 Oh x Rp. 140,000.00 = Rp. 21,000.00
Kepala Tukang 0.015 Oh x Rp. 175,000.00 = Rp. 2,625.00
Mandor 0.0008 Oh x Rp. 130,000.00 = Rp. 104.00
Jumlah = Rp. 25,229.00
Total = Rp. 29,729.00

A.4.6.2.7 Pemasangan 1 buah kait angin


Bahan
Kait Angin 1.0000 Ps x Rp. 18,000.00 = Rp. 18,000.00
Jumlah = Rp. 18,000.00
Tenaga
Pekerja 0.015 Oh x Rp. 100,000.00 = Rp. 1,500.00
Tukang Kayu 0.150 Oh x Rp. 140,000.00 = Rp. 21,000.00
Kepala Tukang 0.015 Oh x Rp. 175,000.00 = Rp. 2,625.00
Mandor 0.0008 Oh x Rp. 130,000.00 = Rp. 104.00
Jumlah = Rp. 25,229.00
Total = Rp. 43,229.00

A.4.6.2.11 Pemasangan 1 buah kunci slot


Bahan
Kunci Slot 1.0000 Ps x Rp. 4,700.00 = Rp. 4,700.00
Jumlah = Rp. 4,700.00
Tenaga
Pekerja 0.020 Oh x Rp. 100,000.00 = Rp. 2,000.00
Tukang Kayu 0.200 Oh x Rp. 140,000.00 = Rp. 28,000.00
Kepala Tukang 0.020 Oh x Rp. 175,000.00 = Rp. 3,500.00
Mandor 0.0010 Oh x Rp. 130,000.00 = Rp. 130.00
Jumlah = Rp. 33,630.00
Total = Rp. 38,330.00

A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm


Bahan
Kaca 5 MM 1.1000 m2 x Rp. 68,888.89 = Rp. 75,777.78
Silikon 0.0150 Kg x Rp. 64,000.00 = Rp. 960.00
Jumlah = Rp. 76,737.78
Tenaga
Pekerja 0.020 Oh x Rp. 100,000.00 = Rp. 2,000.00
Tukang Kayu 0.200 Oh x Rp. 140,000.00 = Rp. 28,000.00
Kepala Tukang 0.020 Oh x Rp. 175,000.00 = Rp. 3,500.00
Mandor 0.0010 Oh x Rp. 130,000.00 = Rp. 130.00
Jumlah = Rp. 33,630.00
Total = Rp. 110,367.78

SANITAIR
A.5.1.1.2. Pemasangan 1 buah closet jongkok
Bahan
Closet jongkok 1.00 Bh x Rp. 242,000.00 = Rp. 242,000.00
Semen Portland 6.00 Kg x Rp. 1,585.00 = Rp. 9,510.00
Pasir Pasang 0.01 M3 x Rp. 110,890.00 = Rp. 1,108.90
Jumlah = Rp. 252,618.90
Tenaga
Pekerja 1.000 Oh x Rp. 100,000.00 = Rp. 100,000.00
Tukang Batu 1.500 Oh x Rp. 140,000.00 = Rp. 210,000.00
Kepala Tukang 0.150 Oh x Rp. 175,000.00 = Rp. 26,250.00
Mandor 0.160 Oh x Rp. 130,000.00 = Rp. 20,800.00
Jumlah = Rp. 357,050.00
Total = Rp. 609,668.90

A.5.1.1.19. Pemasangan 1 buah kran diameter 3/4"


Bahan
Kran Air 1.00 Bh x Rp. 25,000.00 = Rp. 25,000.00
Sealtape 0.025 Bh x Rp. 3,000.00 = Rp. 75.00
Jumlah = Rp. 25,075.00
Tenaga
Pekerja 0.010 Oh x Rp. 100,000.00 = Rp. 1,000.00
Tukang Batu 0.400 Oh x Rp. 140,000.00 = Rp. 56,000.00
Kepala Tukang 0.040 Oh x Rp. 175,000.00 = Rp. 7,000.00
Mandor 0.005 Oh x Rp. 130,000.00 = Rp. 650.00
Jumlah = Rp. 64,650.00
Total = Rp. 89,725.00

A.5.1.1.26. Pemasangan 1 m' pipa PVC tipe AW diameter 3/4"


Bahan
Pipa PVC 3/4" 1.20 M x Rp. 9,166.67 = Rp. 11,000.00
Perlengkapan 15.00 % x Rp. = Rp. 1,650.00
Jumlah = Rp. 12,650.00
Tenaga
Pekerja 0.036 Oh x Rp. 100,000.00 = Rp. 3,600.00
Tukang Batu 0.060 Oh x Rp. 140,000.00 = Rp. 8,400.00
Kepala Tukang 0.006 Oh x Rp. 175,000.00 = Rp. 1,050.00
Mandor 0.002 Oh x Rp. 130,000.00 = Rp. 260.00
Jumlah = Rp. 13,310.00
Total = Rp. 25,960.00

A.5.1.1.32. Pemasangan 1 m' pipa PVC tipe AW diameter 4"


Bahan
Pipa PVC 4" 1.20 M x Rp. 44,166.67 = Rp. 53,000.00
Perlengkapan 5.00 % x Rp. = Rp. 2,650.00
Jumlah = Rp. 55,650.00
Tenaga
Pekerja 0.081 Oh x Rp. 100,000.00 = Rp. 8,100.00
Tukang Batu 0.135 Oh x Rp. 140,000.00 = Rp. 18,900.00
Kepala Tukang 0.0135 Oh x Rp. 175,000.00 = Rp. 2,362.50
Mandor 0.004 Oh x Rp. 130,000.00 = Rp. 520.00
Jumlah = Rp. 29,882.50
Total = Rp. 85,532.50

A.5.1.1.19.a Pemasangan 1 buah floor drain


Bahan
Floor drain 1.00 Bh x Rp. 25,000.00 = Rp. 25,000.00
Perlengkapan 15.00 % x Rp. = Rp. 3,750.00
Jumlah = Rp. 28,750.00
Tenaga
Pekerja 0.010 Oh x Rp. 100,000.00 = Rp. 1,000.00
Tukang Batu 0.040 Oh x Rp. 140,000.00 = Rp. 5,600.00
Kepala Tukang 0.004 Oh x Rp. 175,000.00 = Rp. 700.00
Mandor 0.005 Oh x Rp. 130,000.00 = Rp. 650.00
Jumlah = Rp. 7,950.00
Total = Rp. 36,700.00

PK Supl. 1 Pemasangan 1 Buah Lampu Downlight 18 Watt


Bahan
Armatur Downlight 3 inci 1.000 bh x Rp. 56,250.00 x Rp. 56,250.00
Bola Lampu SL 18 Watt 1.000 bh x Rp. 49,450.00 x Rp. 49,450.00
Alat Bantu 1.000 Ls x Rp. 1,000.00 x Rp. 1,000.00
Jumlah x Rp. 106,700.00
Tenaga
Pekerja 0.300 oh x Rp. 100,000.00 x Rp. 30,000.00
Tukang 0.200 oh x Rp. 140,000.00 x Rp. 28,000.00
Kepala Tukang 0.010 oh x Rp. 175,000.00 x Rp. 1,750.00
Mandor 0.010 oh x Rp. 130,000.00 x Rp. 1,300.00
Jumlah x Rp. 61,050.00
Total x Rp. 167,750.00

PK Supl. 2 Pemasangan 1 Buah Lampu Downlight 8 Watt


Bahan
Armatur Downlight 3 inci 1.000 bh x Rp. 56,250.00 x Rp. 56,250.00
Bola Lampu SL 8 Watt 1.000 bh x Rp. 27,600.00 x Rp. 27,600.00
Alat Bantu 1.000 Ls x Rp. 1,000.00 x Rp. 1,000.00
Jumlah x Rp. 84,850.00
Tenaga
Pekerja 0.300 oh x Rp. 100,000.00 x Rp. 30,000.00
Tukang 0.200 oh x Rp. 140,000.00 x Rp. 28,000.00
Kepala Tukang 0.010 oh x Rp. 175,000.00 x Rp. 1,750.00
Mandor 0.010 oh x Rp. 130,000.00 x Rp. 1,300.00
Jumlah x Rp. 61,050.00
Total x Rp. 145,900.00

Medan. Desember 2017


Rekapitulasi Rencana Anggaran Biaya
Pengembangan Rumah Bogor

NO URAIAN PEKERJAAN JUMLAH HARGA


1 2 3
I PEKERJAAN PERSIAPAN Rp 2,000,000.00
II PEKERJAAN BANGUNAN LANTAI 1 Rp 59,192,408.61
1 PEKERJAAN TANAH Rp 726,444.00
2 PEKERJAAN PONDASI DAN BETON Rp 29,369,470.77
3 PEKERJAAN DINDING DAN PLASTERAN Rp 4,415,138.50
4 PEKERJAAN FINSH. LANTAI & DINDING Rp 9,928,761.10
5 PEKERJAAN PINTU DAN JENDELA Rp 7,171,000.00
6 PEKERJAAN PLAFOND Rp 2,227,223.56
7 PEKERJAAN PENGECATAN Rp 1,202,421.78
8 PEKERJAAN SANITASI Rp 2,511,948.90
9 PEKERJAAN INSTALASI LISTRIK Rp 1,640,000.00

TOTAL BIAYA = Rp 61,192,408.61

Medan. Desember 2016


Rencana Anggaran Biaya
Pengembangan Rumah Bogor

NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 2 3 4 5 6 7=4x6
I PEKERJAAN PERSIAPAN
a Pembersihan lokasi pekerjaan Taksir 1.00 Ls 500,000.00 500,000.00
b Mobilisasi, Demobilisasi, Air Kerja & Listrik Kerja Taksir 1.00 Ls 1,000,000.00 1,000,000.00
c Pemasangan Bowplank Taksir 1.00 Ls 500,000.00 500,000.00
Jumlah I Rp 2,000,000.00
II PEKERJAAN BANGUNAN LANTAI 1
1 PEKERJAAN TANAH
a Galian Tanah Pondasi dan Sloof A.2.3.1.1. 6.45 M3 60,000.00 387,240.00
b Urugan Pasir A.2.3.1.11. 2.36 M3 84,000.00 197,904.00
c Mengurug kembali Tanah Galian A.2.3.1.9. 3.53 M3 40,000.00 141,300.00
Jumlah = Rp 726,444.00
2 PEKERJAAN PONDASI DAN BETON
a Lantai Kerja A.4.1.1.2. 1.68 M3 691,001.69 1,160,882.84
b Pekerjaan Pondasi Tapak 80x80x30 Cm
- Beton K.225 A.4.1.1.5. 1.54 M3 751,064.13 1,153,634.50
- Pembesian A.4.1.1.17. 105.16 Kg 11,239.50 1,181,940.17
c Pekerjaan Sloof 15x30 Cm
- Beton K.225 A.4.1.1.5. 1.13 M3 751,064.13 848,326.93
- Pembesian A.4.1.1.17. 185.75 Kg 11,239.50 2,087,719.64
d Pekerjaan Kolom Praktis A.4.1.1.35. 7.00 M' 68,263.50 477,844.50
e Pekerjaan Kolom 15x30 Cm
- Beton K.225 A.4.1.1.5. 1.30 M3 751,064.13 973,379.11
- Pembesian A.4.1.1.17. 244.79 Kg 11,239.50 2,751,353.21
- Bekisting A.4.1.1.22. 12.96 M2 170,065.00 2,204,042.40
f Pekerjaan Balok Lateh 10x13 Cm A.4.1.1.36. 18.20 M' 96,997.00 1,765,345.40
g Pekerjaan Balok 15x30 Cm
- Beton K.225 A.4.1.1.5. 1.12 M3 751,064.13 838,187.57
- Pembesian A.4.1.1.17. 189.69 Kg 11,239.50 2,131,988.17
- Bekisting A.4.1.1.23. 16.32 M2 175,665.00 2,866,852.80
j Pekerjaan Plat Lantai T-12 Cm
- Beton K.225 A.4.1.1.5. 2.65 M3 751,064.13 1,987,315.68
- Pembesian A.4.1.1.17. 281.01 Kg 11,239.50 3,158,384.60
- Bekisting A.4.1.1.24. 22.05 M2 171,531.67 3,782,273.25

Jumlah = Rp 29,369,470.77
3 PEKERJAAN DINDING DAN PLASTERAN
a Pasangan Batu Batu 1 : 2 A.4.4.1.7. 3.00 M2 108,077.50 324,232.50
b Pasangan Batu-Bata 1 : 4 A.4.4.1.9. 21.20 M2 99,165.00 2,102,298.00
c Plasteran 1 : 2 Tebal 1,5 cm A.4.4.2.2. 4.00 M2 58,780.00 235,120.00
d Plasteran 1 : 4 Tebal 1,5 cm A.4.4.2.4. 32.40 M2 54,120.00 1,753,488.00

Jumlah = Rp 4,415,138.50
4 PEKERJAAN FINSH. LANTAI & DINDING
a Pasangan Lantai Granite Uk. 60 x 60 Cm A.4.4.3.35.b. 16.80 M2 332,936.93 5,593,340.34
b Pasangan Lantai Keramik KM Uk. 25x25 Cm A.4.4.3.36. 3.60 M2 176,638.95 635,900.22
c Pasangan Dinding Keramik 25x40 Cm KM A.4.4.3.54.a 18.12 M2 204,167.80 3,699,520.54

Jumlah = Rp 9,928,761.10
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 2 3 4 5 6 7=4x6
5 PEKERJAAN PINTU DAN JENDELA
a Pintu Alumunium KM Taksir 1.00 Unit 850,000.00 850,000.00
b Pekerjaan Jendela PJ1 UPVC Taksir 6.02 M2 1,050,000.00 6,321,000.00

Jumlah = Rp 7,171,000.00
6 PEKERJAAN PLAFOND
a Rangka Metal furing Dihitung 3 22.05 M2 52,008.27 Rp 1,146,782.38
b Plafond Gybsum 9 mm A.4.5.1.7. 22.05 M2 48,999.60 Rp 1,080,441.18

Jumlah = Rp 2,227,223.56
7 PEKERJAAN PENGECATAN
a Cat Tembok Baru A.4.7.1.10. 32.76 M2 21,938.00 718,688.88
b Cat Plafond A.4.7.1.10. 22.05 M2 21,938.00 483,732.90

Jumlah = Rp 1,202,421.78
8 PEKERJAAN SANITASI
a Kloset Jongkok A.5.1.1.2. 1.00 Bh 609,668.90 609,668.90
b Pemasangan Kran 3/4" A.5.1.1.19. 2.00 Bh 89,725.00 179,450.00
c Floordrain A.5.1.1.19.a 2.00 Bh 36,700.00 73,400.00
d Instalasi Air Bersih pipa PVC dia. 3/4" A.5.1.1.26. 24.00 M' 25,960.00 623,040.00
e Instalasi Air Kotor pipa PVC dia. 4" A.5.1.1.32. 6.00 M' 85,532.50 513,195.00
f Instalasi Tinja pipa PVC dia. 4" A.5.1.1.32. 6.00 M' 85,532.50 513,195.00

Jumlah = Rp 2,511,948.90
9 PEKERJAAN INSTALASI LISTRIK
a Instalasi Titik Lampu + kabel Taksir 3.00 Ttk 200,000.00 600,000.00
b Instalasi Stop Kontak + kabel Taksir 3.00 Ttk 200,000.00 600,000.00
c Lampu Down Ligh + LED 8 Watt Harga Satuan 2.00 Bh 115,000.00 230,000.00
d Lampu Down Ligh + LED 3 Watt Harga Satuan 1.00 Bh 105,000.00 105,000.00
e Saklar Tunggal Harga Satuan 1.00 Bh 20,000.00 20,000.00
f Saklar Double Harga Satuan 1.00 Bh 22,000.00 22,000.00
g Stop Kontak Harga Satuan 3.00 Bh 21,000.00 63,000.00

Jumlah = Rp 1,640,000.00
T O T A L = Rp 61,192,408.61

Medan. Maret 2018


BACKUP VOLUME
Pengembangan Rumah Bogor

KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
1 2 3 4 5 6 7 8 9 10 11 12

I PEKERJAAN PERSIAPAN
a Pembersihan lokasi pekerjaan 1.00 1.00 Ls
b Mobilisasi, Demobilisasi, Air Kerja & Listrik Kerja 1.00 1.00 Ls
c Pemasangan Bowplank 1.00 1.00 Ls

II PEKERJAAN BANGUNAN LANTAI 1

1 PEKERJAAN GALIAN DAN URUGAN


a Galian Tanah Pondasi dan Sloof 6.45 6.45 M3
Sloof arah 4 6.10 0.30 0.40 1.00 0.73
Sloof arah 6 8.60 0.20 0.35 1.00 0.60
Pondasi Tapak 0.80 0.80 1.00 8.00 5.12

b Urugan Pasir 2.36 2.36 M3


Bawah Pondasi Tapak 0.80 0.80 0.05 8.00 0.26
Bawah Lantai 0.10 21.00 2.10

c Mengurug kembali Tanah Galian 3.53 3.53 M3


Total Galian 6.45
Penurangan 2.92
Pasir Urug Bawah Pondasi 0.26
Pondasi Tapak 1.54
Sloof 1.13

2 PEKERJAAN PONDASI DAN BETON


a Lantai Kerja 0.08 21.0000 1.68 1.68 M3

b Pekerjaan Pondasi Tapak 80x80x30 Cm


- Beton K.175 0.80 0.80 0.30 8.00 1.54 1.54 M3

- Pembesian 105.16 Kg
Tulangan Utama Ø 12 1.85 8.00 8.00 0.00 7,850.00 105.16

- Bekisting 3.20 0.30 8.00 7.6800 0.50 3.84 M2

c Pekerjaan Sloof 15x30 Cm


- Beton K.175 1.13 1.13 M3
Arah 4 11.30 0.15 0.30 0.51
Arah 6 13.80 0.15 0.30 0.62

- Pembesian 185.75 Kg
Tulangan Utama Ø 12 27.50 6.00 0.00 7,850.00 146.55
Begel Ø 8 0.65 152.78 0.00 7,850.00 39.20

- Bekisting 25.10 0.30 2.00 15.0600 0.50 7.53 M2

d Pekerjaan Kolom Praktis 7.00 3.50 2.00 7.00 M'

e Pekerjaan Kolom 15x30 Cm


- Beton K.175 0.30 0.15 3.60 8.00 1.30 1.30 M3

- Pembesian 244.79 Kg
Tulangan Utama Ø 12 4.60 8.00 6.00 0.00 7,850.00 196.11
Begel Ø 8 0.75 8.00 20.56 0.00 7,850.00 48.68

- Bekisting 0.30 0.15 3.60 8.00 25.9200 0.50 12.96 M2

f Pekerjaan Balok Lateh 10x13 Cm 18.20 18.20 M'


Arah 4 9.20
Arah 6 9.00

g Pekerjaan Balok 15x30 Cm


- Beton K.175 1.12 1.12 M3
Arah 4 11.00 0.15 0.30 0.50
Arah 6 13.80 0.15 0.30 0.62

- Pembesian 189.69 Kg
Tulangan Utama Ø 12 27.20 6.00 0.00 7,850.00 144.95
Begel Ø 8 0.75 151.11 0.00 7,850.00 44.74

- Bekisting 27.20 0.60 1.00 16.3200 16.32 M2

vol Page 17
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
1 2 3 4 5 6 7 8 9 10 11 12

h Pekerjaan Cor Plat Lantai


- Beton K.175 2.65 2.65 M3
Utuh 4.00 6.00 0.12 2.88
Penurangan Tangga
Taman 2.60 0.75 0.12 0.23

- Pembesian 281.01 281.01 Kg


Besi Ø 10 Pjg 6 6.30 3.20 32.00 1.00 0.00 7,850.00 124.34
Besi Ø 10 Pjg 3 3.20 4.00 40.00 1.00 0.00 7,850.00 78.95
Besi Ø 10 Pjg 4 4.20 3.00 30.00 1.00 0.00 7,850.00 77.72

- Bekisting 22.0500 22.05 M2


Utuh 6.00 4.00 24.0000
Penurangan Tangga
Taman 2.60 0.75 1.9500

3 PEKERJAAN DINDING DAN PLASTERAN


a Pasangan Hebel 1 : 2 3.0000 3.00 M2
Arah 4 0.50 1.50 0.7500
Arah 6 1.50 1.50 2.2500

b Pasangan Hebel 1 : 4 21.2000 21.20 M2


Arah 4
Tinggi 1 m 4.00 1.00 2.00 8.0000
Tinggi 1,5 m 1.20 1.50 2.00 3.6000
Arah 6
Tinggi 1 m 6.00 1.00 1.00 6.0000
Tinggi 1,5 m 1.80 1.50 1.00 2.7000
Tinggi 0,3 m 3.00 0.30 1.00 0.9000

d Plasteran 1 : 2 Tebal 1,5 cm 4.0000 4.00 M2


Total 3.0000 2.00 6.00
Pengurangan Keramik KM
Dinding Km 2.00 1.00 2.0000

e Plasteran 1 : 4 Tebal 1,5 cm 32.4000 32.40 M2


Total 42.4000 2.00
Pengurangan
Keramik CUCI 3.00 2.00 6.0000
Plester 1:2 4.0000

4 PEKERJAAN LANTAI
a Pasangan Lantai Geranite Uk. 60 x 60 Cm 16.8000 16.80 M2
Utuh 6.00 2.80 1.00 16.8000

b Pasangan Lantai Keramik KM Uk. 25x25 Cm 3.6000 3.60 M2


KM Lurah 3.00 1.20 3.6000

c Pasangan Dinding Keramik 25x40 Cm KM 18.12 18.12 M2


KM 5.30 2.40 12.7200
Cuci 3.90 2.00 7.8000
Pengurangan
Pintu 1 0.80 3.00 2.4000

5 PEKERJAAN PINTU DAN JENDELA


c Pintu KM 1.00 1.00 Unit

d Pekerjaan Jendela PJ1 2.80 2.15 1.00 6.0200 6.02 M2

6 PEKERJAAN PLAFOND
a Pemasangan Rangka Furing Plafond 22.0500 22.05 M2
Banunan Utama 6.00 4.00 24.0000
Pengurangan
Tangga 2.60 0.75 1.9500

b Pemasangan Plafond Gypsum tebal 9 mm 22.0500 22.05 M2

7 PEKERJAAN PENGECATAN
a Cat Tembok Baru 32.7600 32.76 M2
Pass 1:2 4.0000
Pass 1:4 32.4000

b Cat Plafond 22.0500 22.05 M2

8 PEKERJAAN SANITASI

vol Page 18
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
1 2 3 4 5 6 7 8 9 10 11 12

a Kloset Jongkok 1.00 1.00 Bh

b Pemasangan Kran 3/4" 2.00 2.00 Bh

c Floordrain 2.00 2.00 Bh

d Instalasi Air Bersih pipa PVC dia. 3/4" 24.00 24.00 M'

e Instalasi Air Kotor pipa PVC dia. 4" 6.00 6.00 M'

f Instalasi Tinja pipa PVC dia. 4" 6.00 6.00 M'

9 PEKERJAAN INSTALASI LISTRIK


a Instalasi Titik Lampu + kabel 3.00 3.00 Ttk
b Instalasi Stop Kontak + kabel 3.00 3.00 Ttk
c Lampu Down Ligh + PCL 18 Watt 2.00 2.00 Bh
d Lampu Down Ligh + PCL 11 Watt 1.00 1.00 Bh
e Saklar Tunggal 1.00 1.00 Bh
f Saklar Double 1.00 1.00 Bh
g Stop Kontak 3.00 3.00 Bh

Medan. Maret 2018

vol Page 19
PERHITUNGAN MATERIAL
Pengembangan Rumah Bogor

NO JENIS BAHAN VOLUME SAT KOEVISIEN KONVERSI SATUAN

1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
a Pembersihan lokasi pekerjaan
b Mobilisasi, Demobilisasi, Air Kerja & Listrik Kerja
c Pemasangan Bowplank 1.00 Ls
Benag 2.00 2.00 Gulung
Paku 1.00 1.00 Kg
Kayu 1x2 inc 4.00 4.00 Btg
Kayu 2x2 inc 2.00 2.00 Btg

II PEKERJAAN BANGUNAN LANTAI 1


1 PEKERJAAN TANAH
a Galian Tanah Pondasi dan Sloof
b Urugan Pasir 2.36 M3 1.20 2.83 M3
c Mengurug kembali Tanah Galian

2 PEKERJAAN PONDASI DAN BETON


a Lantai Kerja 1.68 M3
Porland cement 276.00 11.59 Sak
Pasir beton 828.00 0.99 m3
Kerikil (maksimum 30mm ) 1,012.00 1.26 m3

b Pekerjaan Pondasi Tapak 80x80x30 Cm


- Beton K.225 1.54 M3
Porland cement 326.00 12.52 Sak
Pasir beton 760.00 0.83 m3
Kerikil (maksimum 30mm ) 1,029.00 1.17 m3

- Pembesian 105.16 Kg
Besi beton polos D 12 1.05 10.36 Btg
Kawat beton 0.02 1.58 Kg

c Pekerjaan Sloof 15x30 Cm


- Beton K.225 1.13 M3
Porland cement 326.00 9.21 Sak
Pasir beton 760.00 0.61 M3
Kerikil (maksimum 30mm ) 1,029.00 0.86 M3

- Pembesian 185.75 Kg
Besi beton polos D 12 146.55 0.89 13.75 Btg
Besi beton polos D 8 39.20 0.39 9.93 Btg
Kawat beton 0.02 2.79 Kg
NO JENIS BAHAN VOLUME SAT KOEVISIEN KONVERSI SATUAN

1 2 3 4 5 6 7
d Pekerjaan Kolom Praktis 7.00 M'
Kayu Kelas III 0.0020 0.014 M3
Paku 5 cm-12 cm 0.0100 0.070 Kg
Minyak bekisting -
Besi Beton polos 3.0000 21.000
Besi D 8 1.6579 2.940 Btg
Besi D 6 9.3258 7.000 Btg
Kawat Beton 0.0450 0.315 Kg
Semen Forland 4.0000 0.700 Sak
Pasir 0.0060 0.042 m3
Kerikil 0.0090 0.063 m3

e Pekerjaan Kolom 15x30 Cm


- Beton K.225 1.30 M3
Porland cement 326.00 10.56 Sak
Pasir beton 760.00 0.70 M3
Kerikil (maksimum 30mm ) 1,029.00 0.99 M3

- Pembesian 244.79 Kg
Besi beton polos D 12 196.11 0.89 18.40 Btg
Besi beton polos D 8 48.68 0.39 12.33 Btg
Kawat beton 0.02 3.67 Kg

- Bekisting 12.96 M2
Kayu Sembarang Keras 0.04 0.52 m3
Paku 5 cm-12 cm 0.40 5.18 kg
Minyak bekisting 0.20 2.59 ltr
Balok Kayu Sembarang Keras 0.02 0.19 m3
Plywood tebal 9 mm 0.35 4.54 Lbr
Dolken kayu galam 2.00 25.92 btg

f Pekerjaan Balok Lateh 10x13 Cm 18.20 M'


Kayu Kelas III 0.00 0.05 M3
Paku 5 cm-12 cm 0.02 0.36 Kg
Minyak bekisting - -
Besi Beton polos 3.60 65.52
Besi D 8 9.14 0.3947 2.316 Btg
Besi D 6 2.83 0.2220 2.121 Btg
Kawat Beton 0.05 0.91 Kg
Semen Forland 5.50 2.50 Sak
Pasir 0.01 0.16 M3
Kerikil 0.02 0.27 m3

g Pekerjaan Balok 15x30 Cm


- Beton K.225 1.12 M3
Porland cement 326.00 9.10 Sak
Pasir beton 760.00 0.61 M3
Kerikil (maksimum 30mm ) 1,029.00 0.85 M3

- Pembesian 189.69 Kg
Besi beton polos D 12 144.95 0.89 13.60 Btg
Besi beton polos D 8 44.74 0.39 11.33 Btg
Kawat beton 0.02 2.85 Kg
NO JENIS BAHAN VOLUME SAT KOEVISIEN KONVERSI SATUAN

1 2 3 4 5 6 7
- Bekisting 16.32 M2
Kayu Sembarang Keras 0.04 0.65 m3
Paku 5 cm-12 cm 0.40 6.53 kg
Minyak bekisting 0.20 3.26 ltr
Balok Kayu Sembarang Keras 0.02 0.29 m3
Plywood tebal 9 mm 0.35 5.71 Lbr
Dolken kayu galam 2.00 32.64 btg

j Pekerjaan Plat Lantai T-12 Cm


- Beton K.225 2.65 M3
Porland cement 326.00 21.56 Sak
Pasir beton 760.00 1.44 M3
Kerikil (maksimum 30mm ) 1,029.00 2.02 M3

- Pembesian 281.01 Kg
Besi beton polos D 10 281.01 0.62 45.56 Btg
Kawat beton 0.02 4.22 Kg

- Bekisting 22.05 M2
Kayu Sembarang Keras 0.04 0.88 m3
Paku 5 cm-12 cm 0.40 8.82 kg
Minyak bekisting 0.20 4.41 ltr
Balok Kayu Sembarang Keras 0.00 0.03 m3
Plywood tebal 9 mm 0.35 7.72 Lbr
Dolken kayu galam 6.00 132.30 btg

3 PEKERJAAN DINDING DAN PLASTERAN


a Pasangan Batu Batu 1 : 2 3.00 M2
Hebel 1.05 3.15 m2
Porland cement 18.95 1.42 Sak
Pasir pasang 0.04 0.11 m3

b Pasangan Batu-Bata 1 : 4 21.20 M2


Hebel 1.05 22.26 m2
Porland cement 11.50 6.10 Sak
Pasir pasang 0.04 0.91 m3

c Plasteran 1 : 2 Tebal 1,5 cm 4.00 M2


Porland cement 10.22 1.02 Sak
Pasir pasang 0.02 0.08 M3

d Plasteran 1 : 4 Tebal 1,5 cm 32.40 M2


Porland cement 6.24 5.05 Sak
Pasir pasang 0.02 0.78 M3

4 PEKERJAAN FINSH. LANTAI & DINDING


a Pasangan Lantai Granite Uk. 60 x 60 Cm 16.80 M2
Granite Tile 60x60cm 2.92 12.25 Ktk
Porland cement 10.00 4.20 Sak
Pasir pasang 0.05 0.76 m3
Semen warna 0.50 8.40 kg
NO JENIS BAHAN VOLUME SAT KOEVISIEN KONVERSI SATUAN

1 2 3 4 5 6 7
b Pasangan Lantai Keramik KM Uk. 25x25 Cm 3.60 M2
Keramik 16.80 3.78 Ktk
Porland cement 10.40 0.94 Sak
Pasir pasang 0.05 0.16 m3
Semen warna 0.50 1.80 kg

c Pasangan Dinding Keramik 25x40 18.12 M2


Cm KM Keramik 11.00 19.93 Ktk
Porland 10.40 4.71 Sak
cement
Pasir 0.05 0.82 m3
pasang
Semen 0.50 9.06 kg
warna

5 PEKERJAAN PINTU DAN JENDELA


a Pintu Alumunium KM 1.00 Unit 1.00 1.00 Unit
b Pekerjaan Jendela PJ1 UPVC 6.02 M2 1.00 6.02 M2

6 PEKERJAAN PLAFOND
a Rangka Metal furing 22.05 M2 1.00 22.05 M2
b Plafond Gybsum 9 mm 22.05 M2 1.00 22.05 M2

7 PEKERJAAN PENGECATAN
a Cat Tembok Baru 32.76 M2
Plamur 0.10 3.28 Kg
Cat Dasar 0.10 3.28 Kg
Cat Tembok 0.26 8.52 Kg

b Cat Plafond 22.05 M2


Plamur 0.10 2.21 Kg
Cat Dasar 0.10 2.21 Kg
Cat Tembok 0.26 5.73 Kg

8 PEKERJAAN SANITASI
a Kloset Jongkok 1.00 Bh 1.00 1.00 Bh
b Pemasangan Kran 3/4" 2.00 Bh 1.00 2.00 Bh
c Floordrain 2.00 Bh 1.00 2.00 Bh
d Instalasi Air Bersih pipa PVC dia. 3/4" 24.00 M' 1.00 24.00 M'
e Instalasi Air Kotor pipa PVC dia. 4" 6.00 M' 1.00 6.00 M'
f Instalasi Tinja pipa PVC dia. 4" 6.00 M' 1.00 6.00 M'

9 PEKERJAAN INSTALASI LISTRIK


a Instalasi Titik Lampu + kabel 3.00 Ttk
Kabel 0,25 mm 12.00 36.00 M
Pipa Conduit 6.00 18.00 M

b Instalasi Stop Kontak + kabel 3.00 Ttk


Kabel 0,25 mm 1.00 3.00 M
Pipa Conduit 1.00 3.00 M

c Lampu Down Ligh + LED 8 Watt 2.00 Bh


Bola Lampu LED 8 Watt 1.00 2.00 Bh
Armature Dowlight 4 Inc 1.00 2.00 Bh

d Lampu Down Ligh + LED 3 Watt 1.00 Bh


NO JENIS BAHAN VOLUME SAT KOEVISIEN KONVERSI SATUAN

1 2 3 4 5 6 7
Bola Lampu LED 3 Watt 1.00 1.00 Bh
Armature Dowlight 4 Inc 1.00 1.00 Bh

e Saklar Tunggal 1.00 Bh 1.00 1.00 Bh


f Saklar Double 1.00 Bh 1.00 1.00 Bh
g Stop Kontak 3.00 Bh 1.00 3.00 Bh
REKAP MATERIAL
Pengembangan Rumah Bogor

NO JENIS PEKERJAAN VOLUME SAT PEMBULATAN SATUAN HARGA SATUAN JUMLAH HARGA

1 2 3 4 5 6 7 8
I Bahan Galian
1 Pasir urug 2.83 M3 3.00 M3
2 Pasir pasang/ Pasir Beton 8.97 M3 9.00 M3
3 Kerikil 2-3 cm / Batu Pecah 2-3 7.48 M3 7.00 M3

II Pabrikan
1 Semen @ 40 Kg/ Sak 100.48 Sak 100 Sak
2 Semen warna 19.26 Kg 15.00 Kg
3 Besi D 12 56.11 Btg 55.00 Btg
4 Besi D 10 45.56 Btg 45.00 Btg
5 Besi D 8 38.85 Btg 38.00 Btg
6 Besi D 6 9.12 Btg 9.00 Btg
7 Paku 21.97 Kg 15.00 Kg
8 Hebel 20x60 Cm 198.08 Bh 198.00 Bh
9 Granite 60x60 Cm 12.25 Ktk 12.00 Ktk
10 Kayu Kelas 3 2.12 M3 1.50 M3
11 Multipleks 9 MM 17.97 Lbr 15.00 Lbr
12 Keramik 25x25 Cm 3.78 Ktk 4.00 Ktk
13 Keramik 25x40 Cm 19.93 Ktk 20.00 Ktk
14 Pintu Km 1.00 Bh 1.00 Bh
15 Kusen PJ (UPVC/ Alumunium) Pinti Sorong 6.02 m2 6.02 m2
16 Rangka Metal furing 22.05 M2 22.00 M2
17 Plafond Gybsum 9 mm 22.05 m2 22.00 m2
18 Plamur 5.48 Kg 5.00 Kg
19 Cat Dasar 5.48 Kg 5.00 Kg
20 Cat Tembok 14.25 Kg 15.00 Kg
21 Kloset Jongkok 1.00 Bh 1.00 Bh
22 Pemasangan Kran 3/4" 2.00 Bh 2.00 Bh
23 Floordrain 2.00 Bh 2.00 Bh
24 Instalasi Air Bersih pipa PVC dia. 3/4" 24.00 M' 24.00 M'
25 Instalasi Air Kotor pipa PVC dia. 4" 6.00 M' 6.00 M'
26 Instalasi Tinja pipa PVC dia. 4" 6.00 M' 6.00 M'
27 Kabel 0,25 mm 39.00 M' 1.00 Rol
28 Pipa Conduit 21.00 M' 4.00 Btg
29 Bola Lampu LED 8 Watt 2.00 Bh 2.00 Bh
30 Bola Lampu LED 3 Watt 1.00 Bh 1.00 Bh
31 Armature Dowlight 4 Inc 3.00 Bh 3.00 Bh
32 Saklar Tunggal 1.00 Bh 1.00 Bh
33 Saklar Double 1.00 Bh 1.00 Bh
34 Stop Kontak 3.00 Bh 3.00 Bh
35 Rangka Metal furing 22.05 m2 22.00 m2
36 Plafond Gybsum 9 mm 22.05 m2 22.00 m2