1 Pekerja Oh Rp 46,000.00
2 Mandor Oh Rp 58,000.00
3 Kepala Tukang Oh Rp 67,000.00
4 Tukang Batu Oh Rp 58,000.00
5 Tukang Besi Oh Rp 58,000.00
6 Tukang Kayu Oh Rp 58,000.00
7 Tukang Cat Oh Rp 58,000.00
KETERANGAN :
1 M3 Pasir Beton = 1400 kg / m3 ( harga 1 m3 pasir / 1400 )
1 M3 Kerikil = 1350 kg / m3 ( harga 1 m3 kerikil / 1350 )
1 zak semen 40 kg = ( harga 1 zak semen / 40 kg )
RENCANA ANGGARAN BIAYA
NO. JENIS PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA JML. HARGA TOTAL
B. PEKERJAAN PERSIAPAN
1 Langsiran 1.00 ls 1,000,000.00 1,000,000.00
2 Bongkaran 1.00 ls 1,500,000.00 1,500,000.00
3 Pembersihan lapangan 1.00 ls 150,000.00 150,000.00
4 Utzet / Bowplank 1.00 ls 200,000.00 200,000.00
2,850,000.00
V. PEKERJAAN ATAP
1 Kuda - kuda baja ringan 108.09 m2 160,000.00 17,294,080.00
2 Listplank GRC 41.92 m' 25,000.00 1,048,000.00
3 Genteng kodok ( lama pasang kembali ) 108.09 m2 12,250.00 1,324,078.00
4 Bubungan genteng kodok 11.80 m' 71,912.00 848,561.60
5 Pasang plastik bawah genteng 108.09 m2 5,000.00 540,440.00
21,055,159.60
NO. JENIS PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA JML. HARGA TOTAL
X. PEKERJAAN SANITASI
1 Klosed jongkok 1.00 bh 200,000.00 200,000.00
2 Floor drain 1.00 bh 25,000.00 25,000.00
3 Kran 2.00 bh 30,000.00 60,000.00
4 Pipa penguras bak 1.00 bh 15,000.00 15,000.00
5 Kitchen zink 1.00 unit 300,000.00 300,000.00
6 Pipa PVC AW 3/4" ( air bersih dari pipa 1" tower ke rumah ) 7.72 m' 17,267.40 133,304.33
7 Pipa PVC AW 2" ( pipa air kotor ) 3.10 m' 32,106.80 99,531.08
8 Pipa PVC AW 4" ( dari klosed ke septick tank ) 7.50 m' 43,731.80 327,988.50
1,160,823.91
NO. JENIS PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA JML. HARGA TOTAL
B. PEKERJAAN PERSIAPAN
1 Langsiran 1.00 ls 1,000,000.00 1,000,000.00
2 Bongkaran 1.00 ls 1,500,000.00 1,500,000.00
3 Pembersihan lapangan 1.00 ls 150,000.00 150,000.00
4 Utzet / Bowplank 1.00 ls 200,000.00 200,000.00
2,850,000.00
V. PEKERJAAN ATAP
1 Kuda - kuda baja ringan 108.09 m2 160,000.00 17,294,080.00
2 Listplank GRC 41.92 m' 25,000.00 1,048,000.00
3 Genteng kodok baru 108.09 m2 62,250.00 6,728,478.00
4 Bubungan genteng kodok 11.80 m' 71,912.00 848,561.60
5 Pasang plastik bawah genteng 108.09 m2 5,000.00 540,440.00
26,459,559.60
X. PEKERJAAN SANITASI
1 Klosed jongkok 1.00 bh 200,000.00 200,000.00
2 Floor drain 1.00 bh 25,000.00 25,000.00
3 Kran 2.00 bh 30,000.00 60,000.00
4 Pipa penguras bak 1.00 bh 15,000.00 15,000.00
5 Kitchen zink 1.00 unit 300,000.00 300,000.00
6 Pipa PVC AW 3/4" ( air bersih menyambung dari bangunan sebelah ) 8.72 m' 17,267.40 150,571.73
7 Pipa PVC AW 2" ( pipa air kotor ) 3.10 m' 32,106.80 99,531.08
8 Pipa PVC AW 4" ( dari klosed ke septick tank ) 2.00 m' 43,731.80 87,463.60
9 Saluran U 20 42.65 m' 84,256.06 3,593,521.13
10 Saluran gorong -gorong O 20 7.72 m' 66,980.80 517,091.78
11 Bak kontrol 5.00 bh 40,444.45 202,222.27
12 Grill penutup saluran U 20 7.33 m' 206,262.18 1,511,901.75
13 Grill penutup bak kontrol 2.00 bh 80,590.25 161,180.50
14 Septick tank dan resapan 1.00 unit 3,500,000.00 3,500,000.00
10,423,483.84
BULAN
Nilai
No. Uraian Pekerjaan JUNI JULI AGUSTUS SEPTEMBER KET
Bobot
01-09 10-16 17-23 24-30 01-07 08-14 15-21 22-28 29-04 05-11 12-18 19-25 26-01 02-08 09-15 16-22 23-28
A. PEKERJAAN ADMINISTRASI & DOKUMENTASI 0.089 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005
B. PEKERJAAN PERSIAPAN 1.016 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060
A. PEKERJAAN ADMINISTRASI & DOKUMENTASI 0.089 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005
B. PEKERJAAN PERSIAPAN 1.016 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060