3
II Konstruksi Beton 0,840 M
1 Kolom
3
h = 8,00 V1 = t x b x L x n 0,84 M
b = 0,35
B = 0,30
h n = 1,00
B
b
12 63,936 KG
III Pekerjaan Pembesian BERAT BESI
8 24,885 KG
Besi Ø 12 6 Btg
a Kolom 8 Ø 12 Besi Ø 8 5,25 Btg
30
II Bekisting 11,200 M2
1 Kolom
Begesting L = t x b x L x n 11,20 M2
h = 8,00
t = 0,35
h n = 4,00 sisi
L = 1,00