Anda di halaman 1dari 78

PERHITUNGAN KEBUTUHAN BETON DAN BESI

Kolom e
a
d BK b

Pondasi a
BP b

A. PADA PELAT PONDASI (L= 0.60 m) ; (P = 0.60 m ; Jumlah : 2.00 bh)


(T = 0.20 m)
VOL. BETON K-200 = 0.60 x 0.60 x 0.20 x 2.00 = 0.14

Panjang Panjang Panjang Panjang Panjang Panjang Diameter Berat Jumlah Jumlah Volume
Kode a b c d e Total (Ltot) Besi Per m' (W) batang (n) Pelat V = L.W
Tulangan (m) (m) (m) (m) (m) (m) (mm) (kg) (btg) (bh) (kg)

BP 0.55 0.36 - 0.91 12.00 0.888 8.00 2.00 12.93


bawah
BP 0.55 0.06 - 0.61 12.00 0.888 8.00 2.00 8.67
Atas

JUMLAH Besi Polos U24 21.60


Kwt ikat
Total 21.60

Kolom 1
BK 2.29 0.10 - 2.39 12.00 0.888 4.00 1.00 8.49
2.14 0.10 - 2.24 12.00 0.888 2.00 1.00 3.98
Begel 0.70 0.30 1.00 6.00 0.222 13.00 1.00 2.88

Kolom 2
BK 2.14 0.10 - 2.24 12.00 0.888 4.00 1.00 7.96
1.99 0.10 - 2.09 12.00 0.888 2.00 1.00 3.71
Begel 0.70 0.30 1.00 6.00 0.222 12.00 1.00 2.66

JUMLAH Besi Polos U24 29.69


Kwt ikat
Total 29.69
PERHITUNGAN KEBUTUHAN BESI BETON

Pelat Saluran tertutup


a
b
100
Besi Ø12 - 15

20
a
b Tula nga n Pokok

STA. 0+100
PADA PELAT (L= 1.00 m) ; (P = 5.00 m ; Jumlah : 1.00 bh)
(T = 0.20 m)

STA. 0+159
PADA PELAT (L= - m) ; (P = - m ; Jumlah : - bh)
(T = - m)

Panjang Panjang Panjang Panjang Panjang Panjang Diameter Berat Jumlah Jumlah Volume
Kode a b c d e Total (Ltot) Besi Per m' (W) batang (n) Pelat V = L.W
Tulangan (m) (m) (m) (m) (m) (m) (mm) (kg) (btg) (bh) (kg)

BB 0.95 0.38 - 1.33 12.00 0.888 33.00 1.00 38.99


Melintang
BA 0.95 0.08 - 1.03 12.00 0.888 33.00 1.00 30.19
Melintang

BB 4.95 0.08 - 5.03 12.00 0.888 7.00 1.00 31.28


Memanjang
BA 4.95 0.08 - 5.03 12.00 0.888 7.00 1.00 31.28
Memanjang

BB
Melintang
BA
Melintang

BB
Memanjang
BA

JUMLAH Besi Polos U24 131.74


Kwt ikat
Total 131.74
Panjang 5 M'

1
0.2 1 Cor Beton K200 1 M3

180
140
20 20 20 60 20 20 20

Pla t Deker 2 Pasangan Batu


20
1 Dinding 0.72 m2
50

60
3.6 m3
130

10

30 20

5 50 5 2 Pondasi 0.6 m2
60 60
180
60
3 m3

3 Lantai 0.114 m2
0.57 m3

1.434 M2
Total Vol. Pas Batu 7.17 m3
180

3 Galian Tanah 1.8 m2


80

Ga lia n
110

9 m3
30

60 60 60

4 Plester,Acian Lantai 0.6 Lebar

5 Bekisting Pelat 3.4 m2


GALIAN PAS. BATU 1:4 PLESTERAN URUGAN Kembali BETON K200 BETON K100 Bekisting Pelat
PATOK PJG
LUAS Luas rata2 VOL. LUAS VOL. LUAS VOL. LUAS VOL. LUAS VOL. LUAS VOL. LUAS VOL.
Lanjutan Saluran 2
P0 0.5082 12.79 0.6610 16.53 1.8000 45.00 0.02 0.62
25.0 0.5117
P1 0.5151
P1 0.5151 12.96 0.6610 16.53 1.8000 45.00 0.02 0.59
25.0 0.5183
P2 0.5215
P2 0.5215 13.18 0.6610 16.53 1.8000 45.00 0.03 0.80
25.0 0.5271
P3 0.5327
P3 0.5327 13.84 0.6610 15.20 1.8000 41.40 0.04 0.88
23.0 0.6017
P4 0.6707
P4 0.7885 3.15 0.6668 2.67 1.20 4.80 0.04 0.17 0.15 0.60 1.60 6.40
4.0 0.7885
P5 0.7885
P5 0.7885 17.82 0.6610 15.20 1.8000 41.40 0.04 0.95
23.0 0.7746
P6 0.7607
P6 0.7607 19.53 0.6610 16.53 1.8000 45.00 0.04 1.03
25.0 0.7811
P7 0.8014
P7 0.8014 3.97 0.6668 3.33 1.20 6.00 0.04 0.21 0.15 0.75 1.60 8.00
5.0 0.7950
P8 0.7885
P8 0.7885 14.23 0.6610 13.22 1.8000 36.00 0.03 0.65
20.0 0.7115
P9 0.6345
P9 0.6345 16.43 0.6610 16.53 1.8000 45.00 0.03 0.65
25.0 0.6573
P10 0.6800
P10 0.6800 17.11 0.6610 16.53 1.8000 45.00 0.02 0.62
25.0 0.6844
P11 0.6887
P11 0.6887 16.14 0.6610 16.53 1.8000 45.00 0.01 0.33
25.0 0.6454
P12 0.6021
P12 0.6021 13.75 0.6610 16.53 1.8000 45.00 0.00 0.06
25.0 0.5499
P13 0.4977
P13 0.4977 9.61 0.6610 12.76 1.8000 34.76 0.00 0.05
19.3 0.4977
P14 0.4977

Lanjutan Saluran 1
P0 0.6022 15.35 0.6610 16.53 1.8000 45.00 0.03 0.69
25.0 0.6139
P1 0.6255
P1 0.6255 15.46 0.6610 16.53 1.8000 45.00 0.04 0.88
25.0 0.6184
P2 0.6113
P2 0.6113 16.26 0.6610 16.53 1.8000 45.00 0.04 1.03
25.0 0.6505
25.0 0.6505
P3 0.6897
P3 0.6897 16.78 0.6610 16.53 1.8000 45.00 0.04 0.88
25.0 0.6713
P4 0.6529

tan Saluran 3/2016


P0 0.6036 15.58 0.6610 16.53 1.8000 45.00 0.03 0.69
25.0 0.6232
P1 0.6428
P1 0.6428 12.86 0.6610 13.22 1.8000 36.00 0.03 0.59
20.0 0.6428
P2 0.6428

Box Kontrol 1 0.67 0.94


Pondasi+Lantai 0.51 0.71 0.80 0.48 - -
Dinding box bagi 0.13 0.41 2.60 1.04
0.12

Box Kontrol 2 0.75 1.06


Pondasi+Lantai 0.59 0.83 0.80 0.48 - -
Dinding box bagi 0.13 0.41 2.60 1.04
0.12
439.3 278.8 292.8 788.6 12.4 1.4 14.4

Penyangga
Pondasi 0.98 0.676 0.28 0.20 0.72 0.144 0.98 0.05 2.40 0.48
Kolom1 0.83 0.165
Kolom2 0.77 0.153

0.676 - - 0.1971 0.462 0.049 0.480

439.3

Profil melintang 43.93


Pembersihan lok439.309

Total Sal.1 294.3 304.6


Total Sal.2 100.0 100.0
404.6 449.6

-
Bekisting Kolom Urugan Pasir
LUAS VOL. LUAS VOL.
-

0.98 0.05
1.26 2.5112
1.17 2.3312

4.842 0.049
PAKET PEKERJAAN :
REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE
RODA

LOKASI :
KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA

KABUPATEN MANGGARAI TIMUR


TAHUN ANGGARAN 2017

DIBUAT OLEH :
KONSULTAN PERENCANA
0.00
KONSULTAN PERENCANA & SUPERVISI
Kel. Rana Loba - Golo Karot - Borong
1 BANGUNAN TPT TYPE 1 3.00 M'

I GALIAN TANAH
1 0.60 0.60 0.36
30

0.360
140

II PASANGAN
II 1 0.45 1.40 0.63
2 0.6 0.6 0.36
I
60

0.990
60
III PLESTERAN
1 0.30
1.53

panjang gal tanah gal cds pas. Batu plesteran urugan kembali
luas volume luas volume luas volume luas volume luas volume
P0 - P1 EXT.
P7 - P8 TP 11.50 0.89 10.24 - 3.37 38.70 6.00 69.00 0.025 0.29
P8 - P9 TP 5.00 0.69 3.45 - 1.69 8.45 4.70 23.50 0.025 0.13
P9 - P11 SAL. BIASA 65.00 0.92 59.80 0.77 50.05 2.10 136.50 0.050 3.25
P11 - P13 SAL. BIASA 85.00 0.95 80.33 - 0.77 65.45 2.10 178.50 0.050 4.25
P13 - P14 SAL. BIASA 4.00 0.69 2.75 - 0.77 3.08 2.10 8.40 0.025 0.10
P14 - P15 SAL. BIASA 45.00 0.69 30.96 - 0.77 34.65 2.10 94.50 0.025 1.13
P15 - P16 TP, SAL. 1 SISI 5.00 0.34 1.70 - 1.09 5.43 3.00 15.00 -
P16 - P20 SAL. BIASA 148.36 0.63 93.47 - 0.77 114.24 2.10 311.56 0.025 3.71
P20 - - - - - -
- - - - - - -
- -
368.86 282.69 - 320.04 836.96 12.85
5.00
913,254,000.00 373.86 5.00
913,254,000.00
-
1 PASANGAN BARU TYPE 1 1.50 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I 0.18 2.00 0.35
II 0.56 1.00 0.56
III - 1.00 -

I I 0.91 1.365
I 0.70 I
2. PASANGAN
I 0.35 0.25 2 0.49
II 0.56 0.56 1 0.56
II II 0.20 1.050 1.58

- 3. PLESTERAN
0.40 2.00 0.40 I 2.70 1 2.700 4.05
2.80

4. URUGAN KEMBALI
I 0.035 1 0.035 0.05
1 PASANGAN BARU TYPE 1 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I 0.25 2.00 0.50
II 0.46 1.00 0.46
III - 1.00 -

I I 0.96
I 1.00 I
2. PASANGAN
I 0.35 0.35 2 0.70
II 0.46 0.46 1 0.46
IIII 0.20 1.160

- 3. PLESTERAN
0.40 1.50 0.40 I 3.60 1 3.600
2.30

4. URUGAN KEMBALI
I 0.05 2 0.100

2 PASANGAN BARU TYPE 2 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I 0.20 2.00 0.40
II 0.40 1.00 0.40
III - 1.00 -

I I 0.80
I 0.80 I
2. PASANGAN
I 0.35 0.28 2 0.56
II 0.4 0.4 1 0.40
IIII 0.20 0.960

- 3. PLESTERAN
0.40 1.20 0.40 I 3.00 1 3.000
2.00

4. URUGAN KEMBALI
I 0.04 2 0.080

3 PASANGAN BARU TYPE 3 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I 0.20 2.00 0.40
II 0.36 1.00 0.36
III - 1.00 -

I I 0.76
I 0.80 I
2. PASANGAN
I 0.35 0.28 2 0.56
II 0.36 0.36 1 0.36
IIII 0.20 0.920

- 3. PLESTERAN
0.40 1.00 0.40 I 3.00 1 3.000
1.80

4. URUGAN KEMBALI
I 0.04 2 0.080

7 REHAB. PAS. LAMA+TPT 14.70 M'

0.30 0.30 1. GALIAN TANAH


I - 1.00 -
II 0.20 1.00 0.20
III 0.20 1.00 0.20
IV 1.00 -
IV
IV 0.6 0.40
I 0.60
2. PASANGAN
I 0.40 1.40 0.56 0.56
I II 0.20 0.20 1.00 0.20
1.4
III III
0.2 III
IV
0.20
0.35
0.20
0.21
1.00
1.00
0.20
0.21
0.60 0.40 1.17
1.00

0.4
II
II 3. PLESTERAN
I 2.40 1 2.400
0.5

4. TIMBUNAN
I 0 1 -
8 BOX BAGI 1.00 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I - 1.00 -
II 0.16 2.00 0.32
III 0.12 1.00 0.12

I I 0.44
I 0.60 I
2. PASANGAN
I 0.35 0.21 2 0.42
II 0.16 0.16 2 0.32
IIIII III 0.12 0.12 1 0.12
0.40
II II 0.20 0.860

- 3. PLESTERAN
0.40 0.60 0.40 I 2.40 1 2.400

4. URUGAN KEMBALI
I 0.03 2 0.060
9 REHAB. PAS. LAMA 6.00 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH/BONGKAR PAS LAMA


I 0.15 2.00 0.30
II 0.28 1.00 0.28
III - 1.00 -

I I 0.58
I 0.60 I
2. PASANGAN
I 0.35 0.21 2 0.42
II 0.28 0.28 1 0.28
IIII 0.20 0.700

- 3. PLESTERAN
0.40 0.60 0.40 I 2.40 1 2.400
1.40

4. URUGAN KEMBALI
I 0.03 2 0.060

10 REHAB. PAS. LAMA+TPT 1.30 M'

0.30 0.30 1. GALIAN TANAH


I - 1.00 -
II 0.16 1.00 0.16
III 0.20 1.00 0.20
IV 1.00 -
IV
IV 0.6 0.36
I 0.60
2. PASANGAN
I 0.35 1.00 0.35 0.35
I II 0.16 0.16 1.00 0.16
1
III III
0.2 III
IV
0.20
0.35
0.20
0.21
1.00
1.00
0.20
0.21
0.60 0.40 0.92
1.00

0.4
II
II 3. PLESTERAN
I 2.40 1 2.400
0.4

4. TIMBUNAN
I 0 1 -
11 REHAB. PAS. LAMA 2.20 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH/BONGKAR PAS LAMA


I 0.15 2.00 0.30
II 0.28 1.00 0.28
III - 1.00 -

I I 0.58
I 0.60 I
2. PASANGAN
I 0.35 0.21 2 0.42
II 0.28 0.28 1 0.28
IIII 0.20 0.700

- 3. PLESTERAN
0.40 0.60 0.40 I 2.40 1 2.400
1.40

4. URUGAN KEMBALI
I 0.03 2 0.060

12 REHAB. PAS. LAMA+TPT 13.50 M'

0.30 0.30 1. GALIAN TANAH


I - 1.00 -
II 0.16 1.00 0.16
III 0.20 1.00 0.20
IV 1.00 -
IV
IV 0.6 0.36
I 0.60
2. PASANGAN
I 0.35 1.00 0.35 0.35
I II 0.16 0.16 1.00 0.16
1
III III
0.2 III
IV
0.20
0.35
0.20
0.21
1.00
1.00
0.20
0.21
0.60 0.40 0.92
1.00

0.4
II
II 3. PLESTERAN
I 2.40 1 2.400
0.4

4. TIMBUNAN
I 0 1 -
13 REHAB. PAS. LAMA 11.50 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH/BONGKAR PAS LAMA


I 0.15 2.00 0.30
II 0.28 1.00 0.28
III - 1.00 -

I I 0.58
I 0.60 I
2. PASANGAN
I 0.35 0.21 2 0.42
II 0.28 0.28 1 0.28
IIII 0.20 0.700

- 3. PLESTERAN
0.40 0.60 0.40 I 2.40 1 2.400
1.40

4. URUGAN KEMBALI
I 0.03 2 0.060

14 SAL. BARU 124.50 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I 0.10 2.00 0.20
II 0.24 1.00 0.24

I I
0.40
II 0.44

2. PASANGAN
I 0.35 0.14 2 0.28
II 0.24 0.24 1 0.24

II II 0.20 0.520

3. PLESTERAN
0.40 0.40 0.40 I 1.80 1 1.800
1.20

4. URUGAN KEMBALI
I 0.02 2 0.040
PERHITUNGAN KEBUTUHAN BETON DAN BESI

Saluran Tertutup 1

MB b
a

a
LA b

A. PADA PELAT (L= 3.00 m) ; (B = 1.10 m ; Jumlah Duikers : 3.00 bh)


STA 00+000 (T = 0.15 m)
VOL. BETON K-250 = 3.00 x 1.10 x 0.15 x 3.00 = 1.49

Panjang Panjang Panjang Panjang Panjang Panjang Diameter Berat Jumlah Jumlah Volume
Kode a b c d e Total (Ltot) Per m' (W) batang (n) Duikers V = L.W
Tulangan (m) (m) (m) (m) (m) (m) (mm) (kg) (btg) (bh) (kg)

LA 2.96 0.05 - 3.01 12.00 0.888 8.00 3.00 64.15


-
LB 2.96 - - 2.96 12.00 0.888 - 3.00 -
-
MA 1.06 - - 1.06 12.00 0.888 - 3.00 -

MB 1.06 0.05 - 1.11 12.00 0.888 34.00 3.00 100.54

JUMLAH Besi Ulir U24 164.69


Kwt ikat 1.50
Total 166.19
1.53

panjang gal tanah gal cds pas. Batu plesteran urugan kembali
luas volume luas volume luas volume luas volume luas volume
P0 - P1 EXT.
P7 - P8 SAL. BIASA 50.00 0.67 33.50 - 0.77 38.50 2.10 105.00 0.050 2.50
P8 - P9 SAL. BIASA 11.17 0.67 7.48 - 0.77 8.60 2.10 23.46 0.050 0.56
P9 - P11 SAL. BIASA - 0.67 - 0.77 - 2.10 - 0.050 -
P11 - P13 SAL. BIASA - 0.67 - - 0.77 - 2.10 - 0.050 -
P13 - P14 SAL. BIASA - 0.67 - - 0.77 - 2.10 - 0.050 -
P14 - P15 SAL. BIASA - 0.67 - - 0.77 - 2.10 - 0.050 -
P15 - P16 TP, SAL. 1 SISI - 0.67 - - 0.77 - 3.00 - -
P16 - P20 SAL. BIASA - 0.67 - - 0.77 - 2.10 - 0.025 -
P20 - - - - - -
- - - - - - -
- -
61.17 40.98 - 47.10 128.46 3.06
5.00
913,254,317.49 66.17 5.00
913,254,000.00
-
1.53

panjang gal tanah gal cds pas. Batu plesteran urugan kembali
luas volume luas volume luas volume luas volume luas volume
P0 - P1 EXT.
P0 - P1 SAL. BIASA 50.00 0.62 31.00 - 0.77 38.50 2.10 105.00 0.050 2.50
P1 - P3 TP 8.00 0.72 5.76 - 2.82 22.56 1.60 12.80 0.020 0.16
P3 - P6 SAL. BIASA 150.00 0.62 93.00 0.77 115.50 2.10 315.00 0.050 7.50
P6 - P8 SAL. BIASA 100.00 0.62 62.00 - 0.77 77.00 2.10 210.00 0.050 5.00
P6 - P9 SAL. BIASA 20.00 0.62 12.40 - 0.77 15.40 2.10 42.00 0.050 1.00
P9 - P10 TP 8.43 0.62 5.22 - 2.96 24.94 1.80 15.17 - -
P10 - P11 SAL. BIASA - 0.62 - - 0.77 - 2.10 - 0.050 -
P11 - P14 SAL. BIASA - - - - - -
P14 -
- -
- -
336.43 209.38 - 293.90 699.97 16.16
5.00
913,254,317.49 341.43 5.00
913,254,000.00
-
1.53

panjang gal tanah gal cds pas. Batu plesteran urugan kembali
luas volume luas volume luas volume luas volume luas volume
P0 - P1 SAL. BIASA 50.00
P1 - P5 SAL. BIASA 200.00 0.67 134.00 - 0.77 154.00 2.10 420.00 0.050 10.00
P5 - P6 SAL. BIASA 50.00 0.67 33.50 - 0.77 38.50 2.10 105.00 0.050 2.50
P6 - P10 SAL. BIASA 136.13 0.67 91.21 0.77 104.82 2.10 285.87 0.050 6.81
P10 - SAL. BIASA - - 0.77 - 2.10 - 0.050 -
- - SAL. BIASA - - 0.77 - 2.10 - 0.025 -
- - SAL. BIASA - - 0.77 - 2.10 - 0.025 -
- - TP, SAL. 1 SISI - - 0.77 - 3.00 - -
- - SAL. BIASA - - 0.77 - 2.10 - 0.025 -
- - - - - - -
- - - - - - -
- -
436.13 258.71 - 297.32 810.87 19.31
5.00
913,254,000.00 441.13 5.00
913,254,000.00
-
DAFTAR KUANTITAS DAN HARGA
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR / NORMALISASI
SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

Harga Jumlah
No Uraian Pekerjaan Volume Satuan Satuan Harga
(Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.000 Ls 5,100,000.00 5,100,000.00
2 Papan Nama Proyek 1.000 Ls 500,000.00 500,000.00
3 Pembersihan Lokasi 439.309 m² 4,917.00 2,160,082.35
4 Pemasangan Profil Melintang galian tanah 43.931 m' 46,247.58 2,031,697.59
5 Asbuilt Drawing 1.000 Ls 500,000.00 500,000.00
6 Dokumentasi 1.000 Ls 500,000.00 500,000.00
7 Pelaporan 1.000 Ls 500,000.00 500,000.00
Sub Jumlah I 11,291,779.95
II. PEKERJAAN SALURAN PASANGAN + BOX BAGI
1 Pek. Galian Tanah Biasa 278.7842 m³ 46,137.85 12,862,504.03
2 Pek. Urugan Kembali 12.3525 m³ 27,043.50 334,055.86
3 Pek. Pasangan Batu 1Pc : 4Psr 292.7864 m³ 1,123,664.30 328,993,635.32
4 Pek. Beton K200 1.3500 m³ 1,324,688.30 1,788,329.21
5 Pek. Baja Tulangan Pelat 131.7398 kg 17,020.85 2,242,323.94
6 Pek. Bekisting Pelat 14.4000 m2 127,777.21 1,839,991.82
7 Pek. Plesteran 1Pc : 3Psr dan Acian 788.6362 m2 56,736.24 44,744,252.72
Sub Jumlah II 392,805,092.90
II. PEKERJAAN PENYANGGA DAN TALANG PIPA
1 Pek. Galian Tanah Biasa 0.6762 m³ 46,137.85 31,198.41
2 Pek. Urugan Kembali 0.1971 m³ 27,043.50 5,330.81
3 Pek. Urugan Pasir 0.0490 m³ 403,700.00 19,781.30
4 Pek. Beton K100 0.0490 m³ 1,173,020.64 57,478.01
5 Pek. Beton K200 0.4622 m³ 1,324,688.30 612,323.92
6 Pek. Baja Tulangan Pelat Pondasi 21.6043 kg 17,020.85 367,722.98
7 Pek. Baja Tulangan Kolom 29.6866 kg 19,138.35 568,151.90
8 Pek. Bekisting Kolom 4.8424 m2 143,596.42 695,351.30
9 Pek. Pipa GIP Ø 4 " 16.6000 m1 68,346.67 1,134,554.67
Sub Jumlah III 3,491,893.32
Jumlah ( I s/d III ) 407,588,766.16

0.00
0.00
0.00
CV. DETAIL ENGINEERING DISAIN KONSULTAN

0.00
0.00
DAFTAR KUANTITAS DAN HARGA
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM
PROGRAM/KEGIATAN : PENGEMBANGAN DAN PENGELOLAAN JARINGAN IRIGASI, RAWA DAN JARINGAN
PENGAIRAN LAINNYA/REHABILITASI/PEMELIHARAAN JARINGAN IRIGASI (DAK)
PAKET : PENINGKATAN JARINGAN IRIGASI DI. WAE RINA
LOKASI : DESA ARUS, KECAMATAN POCO RANAKA TIMUR
TAHUN ANGGARAN : 2017

Harga Jumlah
No Uraian Pekerjaan Volume Satuan Satuan Harga
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi (Peralatan & Tenaga Kerja) 1.000 Ls 2,600,000.00 2,600,000.00
2 Pembuatan Base Camp 1.000 Ls 500,000.00 500,000.00
3 Biaya Pelaporan, Dokumentasi, Asbuilt Drawing 1.000 Ls 2,500,000.00 2,500,000.00
4 Papan Nama Proyek 1.000 Ls 500,000.00 500,000.00
5 Pembersihan Lapangan 20.390 m² 4,917.00 100,258.45
6 Pemasangan Profil Melintang 6.117 m' 46,247.58 282,898.73
Sub Jumlah I 6,483,157.18
II PEKERJAAN REHAB. SALURAN LAMA + TALANG PEMBAWA
1 Pek. Pembongkaran Pasangan Lama 0.600 m³ 100,732.50 60,439.50
2 Pek. Timbunan Batu Kosong 13.000 m³ 403,700.00 5,248,100.00
3 Pek. Beton K100 (Camp. 1Pc:2Psr:3Krl) 1.485 m³ 1,173,020.64 1,741,935.65
4 Pek. Pembesian dengan besi polos 166.188 Kg 17,020.85 2,828,669.19
5 Pek. Bekisting 9.900 m² 127,777.21 1,264,994.38
6 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr 119.520 m³ 1,123,664.30 134,300,357.14
7 Pek. Plesteran + Acian 1Pc : 3Psr 546.000 m² 56,736.24 30,977,987.04
Sub Jumlah II 176,422,482.90
III PEKERJAAN SALURAN PASANGAN
1 Pek. Galian Tanah Biasa 40.984 m³ 46,137.85 1,890,924.49
2 Pek. Urugan Kembali 3.059 m³ 27,043.50 82,713.22
3 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr 47.101 m³ 1,123,664.30 52,926,032.44
4 Pek. Plesteran + Acian 1Pc : 3Psr 128.458 m² 56,736.24 7,288,226.75

Sub Jumlah III 62,187,896.90


Jumlah ( I s/d III ) 245,093,536.97

0.00
DIBUAT OLEH :
KONSULTAN PERENCANA

DIDIMUS JEGAUT, ST
KEPALA PERWAKILAN
DAFTAR KUANTITAS DAN HARGA
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

Harga Jumlah
No Uraian Pekerjaan Volume Satuan Satuan Harga
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi (Peralatan & Tenaga Kerja) 1.000 Ls 2,600,000.00 2,600,000.00
2 Pembuatan Base Camp 1.000 Ls 500,000.00 500,000.00
3 Biaya Pelaporan, Dokumentasi, Asbuilt Drawing 1.000 Ls 2,500,000.00 2,500,000.00
4 Papan Nama Proyek 1.000 Ls 500,000.00 500,000.00
5 Pembersihan Lapangan 112.142 m² 4,917.00 551,401.89
6 Pemasangan Profil Melintang 11.214 m' 46,247.58 518,629.25
Sub Jumlah I 7,170,031.13
II PEKERJAAN SALURAN PASANGAN + TP & BOX BAGI
1 Pek. Galian Tanah Biasa 209.384 m³ 46,137.85 9,660,527.40
2 Pek. Urugan Kembali 16.160 m³ 27,043.50 437,022.96
3 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr 293.900 m³ 1,123,664.30 330,245,351.28
4 Pek. Plesteran + Acian 1Pc : 3Psr 699.966 m² 56,736.24 39,713,463.93

Sub Jumlah II 380,056,365.57


Jumlah ( I s/d II ) 387,226,396.70

0.00
DIBUAT OLEH :
KONSULTAN PERENCANA

DIDIMUS JEGAUT, ST
KEPALA PERWAKILAN
DAFTAR KUANTITAS DAN HARGA
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

Harga Jumlah
No Uraian Pekerjaan Volume Satuan Satuan Harga
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi (Peralatan & Tenaga Kerja) 1.000 Ls 2,500,000.00 2,500,000.00
2 Pembuatan Base Camp 1.000 Ls 500,000.00 500,000.00
3 Biaya Pelaporan, Dokumentasi, Asbuilt Drawing 1.000 Ls 2,500,000.00 2,500,000.00
4 Papan Nama Proyek 1.000 Ls 500,000.00 500,000.00
5 Pembersihan Lapangan 145.376 m² 4,917.00 714,815.43
6 Pemasangan Profil Melintang 43.613 m' 46,247.58 2,016,990.86
Sub Jumlah I 8,731,806.29
II PEKERJAAN REHAB BENDUNG

1 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr 17.400 m³ 1,123,664.30 19,551,758.82


2 Pek. Plesteran + Acian 1Pc : 3Psr 64.250 m² 56,736.24 3,645,303.42
Sub Jumlah II 23,197,062.24
III PEKERJAAN SALURAN PASANGAN + TP + BOX BAGI
1 Pek. Galian Tanah Biasa 258.706 m³ 46,137.85 11,936,158.46
2 Pek. Urugan Kembali 19.306 m³ 27,043.50 522,113.98
3 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr 297.319 m³ 1,123,664.30 334,087,116.82
4 Pek. Plesteran + Acian 1Pc : 3Psr 810.871 m² 56,736.24 46,005,765.99

Sub Jumlah III 392,551,155.25


Jumlah ( I s/d III ) 424,480,023.79

0.00
DIBUAT OLEH :
KONSULTAN PERENCANA

DIDIMUS JEGAUT, ST
KEPALA PERWAKILAN
DAFTAR KUANTITAS DAN HARGA
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM
PROGRAM/KEGIATAN : PENGEMBANGAN DAN PENGELOLAAN JARINGAN IRIGASI, RAWA DAN JARINGAN
PENGAIRAN LAINNYA/REHABILITASI/PEMELIHARAAN JARINGAN IRIGASI (DAK)
PAKET : PENINGKATAN JARINGAN IRIGASI DI. WAE GERONG
LOKASI : DESA PONG RUAN, KECAMATAN KOTA KOMBA
TAHUN ANGGARAN : 2017

Harga Jumlah
No Uraian Pekerjaan Volume Satuan Satuan Harga
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi (Peralatan & Tenaga Kerja) 1.000 Ls 2,500,000.00 2,500,000.00
2 Pembuatan Base Camp 1.000 Ls 500,000.00 500,000.00
3 Biaya Pelaporan, Dokumentasi, Asbuilt Drawing 1.000 Ls 2,500,000.00 2,500,000.00
4 Papan Nama Proyek 1.000 Ls 500,000.00 500,000.00
5 Pembersihan Lapangan 122.954 m² 4,917.00 604,566.46
6 Pemasangan Profil Melintang 36.886 m' 46,247.58 1,705,901.93
Sub Jumlah I 8,310,468.38
II PEKERJAAN SALURAN PASANGAN + TP & BOX BAGI
1 Pek. Galian Tanah Biasa 282.691 m³ 46,137.85 13,042,740.65
2 Pek. Urugan Kembali 12.847 m³ 27,043.50 347,416.35
3 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr 320.042 m³ 1,123,664.30 359,619,781.14
4 Pek. Plesteran + Acian 1Pc : 3Psr 836.962 m² 56,736.24 47,486,093.92

Sub Jumlah II 420,496,032.06


Jumlah ( I s/d II ) 428,806,500.45

0.00
DIBUAT OLEH :
KONSULTAN PERENCANA

DIDIMUS JEGAUT, ST
KEPALA PERWAKILAN
7 REHAB. PAS. LAMA+TPT 14.70 M'

0.30 0.30 1. GALIAN TANAH


I - 1.00 -
II 0.20 1.00 0.20
III 0.20 1.00 0.20
IV 1.00 -
IV
IV 0.6 0.40
I 0.60
2. PASANGAN
I 0.40 1.40 0.56 0.56
I II 0.20 0.20 1.00 0.20
1.4
III III
0.2 III
IV
0.20
0.35
0.20
0.21
1.00
1.00
0.20
0.21
0.60 0.40 1.17
1.00

0.4
II
II 3. PLESTERAN
I 2.40 1 2.400
0.5

4. TIMBUNAN
I 0 1 -
2 Bh
1 PASANGAN BARU TYPE 1 2.00 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I 0.15 2.00 0.30
II 0.44 1.00 0.44
III - 1.00 -

I I 1.48 2.96
I 0.60 I
2. PASANGAN
I 0.35 0.21 2 0.42
II 0.44 0.44 1 0.44
II II 0.20 1.720 3.44

- 3. PLESTERAN
0.40 1.40 0.40 I 3.20 1 6.400 12.80
2.20

4. URUGAN KEMBALI
I 0.03 1 0.030 0.06

80 80
30 40 30
+0.40

+0.40
±0.00

50
+0.40

30 40 30
+0.50

±0 .0 0
140

-0.1
+0.40

50
±0.00
+0.50
+0.50

30 50 30
75 75
1 PASANGAN BARU TYPE 1 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I 0.10 2.00 0.20
II 0.24 1.00 0.24
III - 1.00 -

I I 0.44
I 0.40 I
2. PASANGAN
I 0.35 0.14 2 0.28
II 0.24 0.24 1 0.24
IIII 0.20 0.520

- 3. PLESTERAN
0.40 0.40 0.40 I 1.80 1 1.800
1.20

4. URUGAN KEMBALI
I 0.02 1 0.020
1 REHAB TYPE 1 M'

0 0.30 - 0 1. GALIAN TANAH


I - 2.00 -
II - 1.00 -
III - 1.00 -

I I -
I 0.50 I
2. PASANGAN
I - 2 -
II 0 1 -
IIII - -

- 3. PLESTERAN
- 0.50 - I 1.30 1 1.300
-

4. URUGAN KEMBALI
I 0 1 -

2 REHAB TYPE 2 M'

0 0.30 - 0 1. GALIAN TANAH


I - 2.00 -
II - 1.00 -
III - 1.00 -

I I -
I 0.50 I
2. PASANGAN
I 0 - 2 -
II 0 0 1 -
IIII - -

- 3. PLESTERAN
- - - I 0.80 1 0.800
-

4. URUGAN KEMBALI
I 0 1 -

3 PASANGAN BARU TYPE 3 M'

0 0.30 - 0 1. GALIAN TANAH


I - 2.00 -
II - 1.00 -
III - 1.00 -

I I -
I 0.80 I
2. PASANGAN
I 0 - 2 -
II 0 0 1 -
IIII - -

- 3. PLESTERAN
- - - I 1.10 1 1.100
-

4. URUGAN KEMBALI
I 0 1 -
4 PASANGAN BARU TYPE 4 M'

0 0.30 - 0 1. GALIAN TANAH


I - 2.00 -
II - 1.00 -
III - 1.00 -

I I -
I 0.45 I
2. PASANGAN
I 0 - 2 -
II 0 0 1 -
IIII - -

- 3. PLESTERAN
- - - I 0.75 1 0.750
-

4. URUGAN KEMBALI
I 0 2 -

5 PASANGAN BARU TYPE 5 M'

0 0.30 - 0 1. GALIAN TANAH


I - 2.00 -
II - 1.00 -
III - 1.00 -

I I -
I 0.60 I
2. PASANGAN
I 0 - 2 -
II 0 0 1 -
IIII - -

- 3. PLESTERAN
- - - I 0.90 1 0.900
-

4. URUGAN KEMBALI
I 0 2 -

6 PASANGAN BARU TYPE 6 M'

0 0.30 - 0 1. GALIAN TANAH


I - 2.00 -
II - 1.00 -
III - 1.00 -

I I -
I 0.67 I
2. PASANGAN
I 0 - 2 -
II 0 0 1 -
IIII - -

- 3. PLESTERAN
- - - I 0.97 1 0.970
-

4. URUGAN KEMBALI
I 0 2 -
7 PASANGAN BARU TYPE 7 M'

0 - 0.30 0 1. GALIAN TANAH


I - 2.00 -
II - 1.00 -
III - 1.00 -

I I -
I 0.64 I
2. PASANGAN
I 0.35 0.22 1 0.22
II 1.02 0.204 1 0.20
IIII 0.20 0.428

- 3. PLESTERAN
- 0.62 0.40 I 1.56 1 1.560
-

4. URUGAN KEMBALI
I 0 2 -

8 PASANGAN BARU TYPE 8 M'

0 0.30 0.30 0 1. GALIAN TANAH


I - 2.00 -
II - 1.00 -
III - 1.00 -

I I -
I 0.55 I
2. PASANGAN
I 0 - 1 -
II - 0 1 -
IIII - -

- 3. PLESTERAN
- - - I 1.70 1 1.700
-

4. URUGAN KEMBALI
I 0 2 -

9 PASANGAN BARU TYPE 9 M'

0 0.30 - 0 1. GALIAN TANAH


I 0.11 2.00 0.22
II - 1.00 -
III - 1.00 -

I I 0.22
I 0.55 I
2. PASANGAN
I 0.35 0.19 1 0.19
II 0.40 0.08 1 0.08
IIII 0.20 0.273

- 3. PLESTERAN
0.40 - - I 0.85 1 0.850
-

4. URUGAN KEMBALI
I 0 2 -
1 PASANGAN BARU TYPE 1 M'

0.1 0.30 0.30 0.1 1. GALIAN TANAH


I 0.13 2.00 0.25
II 0.26 1.00 0.26
III - 1.00 -

I I 0.51
I 0.50 I
2. PASANGAN
I 0.35 0.18 2 0.35
II 0.26 0.26 1 0.26
IIII 0.20 0.610

- 3. PLESTERAN
0.40 0.50 0.40 I 2.10 1 2.100
1.30

4. URUGAN KEMBALI
I 0.025 1 0.025
1.53

panjang gal tanah gal cds pas. Batu plesteran urugan kembali
SALURAN PRIMER luas volume luas volume luas volume luas volume Siaran volume luas volume
P0 - P1 TYPE 1 600.50 0.510 306.255 - 0.610 366.305 2.100 1,261.050 0.025 15.013
- - - - - - -
- - - - - - - - -

TOTAL JUMLAH 600.50 306.26 - 366.31 1,261.05 - 15.01

SALURAN SKUNDER
P0 - P1 TYPE 1 420.00 0.440 184.800 - 0.520 218.400 1.800 756.000 0.020 8.400
- - - - - - - - -

TOTAL JUMLAH 420.00 184.80 - 218.40 756.00 - 8.40

PEKERJAAN BANGUNAN PELIMPAS


500 - 505 TYPE 1 5.00 1.800 9.000 - 1.434 7.170 0.600 3.000 0.053 0.263
- - - - - -
TOTAL JUMLAH 5.00 9.00 - - 7.17 3.00 - 0.26
- - - - - -
TEMBOK PENAHAN TANAH (TPT)
TYPE 1 3.00 0.36 1.080 - 0.99 2.970 0.30 0.900
- - - - - -
- - - - - -

TOTAL JUMLAH 3.00 1.08 - 2.97 0.90 - -


BANGUNAN SADAP
TYPE 1 1.50 1.365 2.048 - 1.575 2.363 4.050 6.075 - -
- - - - - -
- - - - - -

TOTAL JUMLAH 1.50 2.05 - 2.36 6.08 - -

BANGUNAN BOKS PEMBAGI


TYPE 1 2.00 1.480 2.960 - 1.720 3.440 6.400 12.800 - -
- - - - - -
- - - - - -

TOTAL JUMLAH 2.00 2.96 - 3.44 12.80 - -

REHAB. SALURAN PRIMER


TYPE 1 26.00 - - - 1.300 33.800 -
TYPE 2 9.00 - - - 0.800 7.200 -
TYPE 3 14.00 1.100 15.400
TYPE 4 1.64 0.750 1.230
TYPE 5 14.00 0.900 12.600
TYPE 6 8.00 0.970 7.760
TYPE 7 9.30 - - 0.428 3.980 1.560 14.508 -
TYPE 8 2.40 1.700 4.080
TYPE 9 4.60 0.273 1.254 0.850 3.910

TOTAL JUMLAH 88.94 - - 5.23 100.49 - -


- - - - -

5.00
913,254,317.49 5.00 #REF!
913,254,000.00 5.00 ### -
-
1 LANTAI BELAKANG BENDUNG 24.00 M'

0 - 1. GALIAN TANAH
I
II 0.50 1.00

2. PASANGAN
I 0.9 1.00
II 0.5 0.5
I
II 0.30

II 1.00

0.50
- 3. PLESTERAN
3.00 I 3.30 1

4. URUGAN KEMBALI
I 0 1

2 SAYAP KIRI 6.00 M'

0 - 1. GALIAN TANAH
0.50 I
II 1.00 1.00

1.50

I 2. PASANGAN
I 0.75 1.13
II 1 1

II 1.00

1.00
- 3. PLESTERAN
I 2.00 1

4. URUGAN KEMBALI
I 0 1

3 MERCU 24.00 M'


3. PLESTERAN
I 2.50 1

4 BRONJONG 100.00 M' 1. GALIAN TANAH

I 0.50 1.00
3. PAS. BRONJONG
I 2.00 2
0.50

0.50 12.00

1 1.00
1 0.50

1.500 36.00

3.300 79.20

GAN KEMBALI
- -

1.00

1.00 6.00

1 1.13
1 1.00

2.125 12.75

2.000 12.00

GAN KEMBALI
- -

2.500 60.00

0.50

0.50 50.00
4.000 400.00
PAKET PEKERJAAN :

REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA

LOKASI :
KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA

KABUPATEN MANGGARAI TIMUR


TAHUN ANGGARAN 2023

0.00
0.00
KONSULTAN PERENCANA & SUPERVISI
Kel. Rana Loba - Golo Karot - Borong
ENGINEERING ESTIMATE
(EE)
REKAPITULASI
DAFTAR KUANTITAS DAN HARGA

PEMERINTAH : KABUPATEN MANGGARAI TIMUR


DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

JUMLAH
KETERANGA
NO. URAIAN KEGIATAN HARGA
N
(Rp)

I. PEKERJAAN PERSIAPAN 17,037,442.89

II. PEKERJAAN REHAB. SALURAN PRIMER 11,377,161.51

III. PEKERJAAN BANGUNAN PELIMPAS 12,362,338.53

IV. PEKERJAAN TEMBOK PENAHAN TANAH (TPT) 3,321,678.13

V. PEKERJAAN SALURAN PASANGAN PRIMER 482,912,956.60

VI. PEKERJAAN BOX PEMBAGI 4,593,265.32

VII. PEKERJAAN SADAP 2,886,238.39

A JUMLAH TOTAL I s/d VII 822,751,637.38


B PPN ( 10% x A ) 90,502,680.11
C JUMLAH A + B 913,254,317.49
DIBULATKAN 913,254,000.00

SEMBILAN RATUS TIGA BELAS JUTA DUA RATUS LIMA PULUH


TERBILANG :
EMPAT RIBU 0 RUPIAH
DAFTAR KUANTITAS DAN HARGA
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR / NORMALISASI
SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

Harga Jumlah
No Uraian Pekerjaan Volume Satuan Satuan Harga
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 372.980 m² 4,917.00 1,833,942.66
2 Pemasangan Profil Melintang 103.000 m' 46,247.58 4,763,500.23
3 Keselamatan dan Kesehatan Kerja 1.000 Ls 10,440,000.00 10,440,000.00
Sub Jumlah I 17,037,442.89
II PEKERJAAN REHAB. SALURAN PRIMER
1 Pek. Plesteran + Acian 1Pc : 3Psr 100.488 m² 56,736.24 5,701,311.29
2 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr (Pakai Molen) 5.234 m3 1,084,439.94 5,675,850.23
Sub Jumlah II 11,377,161.51
III PEKERJAAN BANGUNAN PELIMPAS
1 Pek. Galian Tanah 9.000 m³ 46,137.85 415,240.65
2 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr (Pakai Molen) 7.170 m³ 1,084,439.94 7,775,434.40
3 Pekerjaan Beton K200 1.000 m3 1,324,688.30 1,324,688.30
4 Pekerjaan Besi Polos 131.740 Kg 17,020.85 2,242,323.94
5 Pekerjaan Bekisting Pelat 3.400 m² 127,777.21 434,442.51
6 Pek. Plesteran + Acian 1Pc : 3Psr 3.000 m² 56,736.24 170,208.72
Sub Jumlah III 12,362,338.53
IV PEKERJAAN TEMBOK PENAHAN TANAH (TPT)
1 Pek. Galian Tanah 1.080 m³ 46,137.85 49,828.88
2 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr (Pakai Molen) 2.970 m³ 1,084,439.94 3,220,786.64
3 Pek. Plesteran + Acian 1Pc : 3Psr 0.900 m² 56,736.24 51,062.62
Sub Jumlah IV 3,321,678.13
V PEKERJAAN SALURAN PASANGAN PRIMER
1 Pek. Galian Tanah 306.26 m³ 46,137.85 14,129,947.25
2 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr (Pakai Molen) 366.31 m³ 1,084,439.94 397,235,773.90
3 Pek. Plesteran + Acian 1Pc : 3Psr 1,261.05 m² 56,736.24 71,547,235.45
Sub Jumlah V 482,912,956.60
VI PEKERJAAN BOX PEMBAGI
1 Pek. Galian Tanah 2.96 m³ 46,137.85 136,568.04
2 Pekerjaan Pas. Batu/Mortar, Camp 1 Pc : 4 Psr (Pakai Molen) 3.44 m³ 1,084,439.94 3,730,473.41
3 Pek. Plesteran 1 pc : 3 psr 12.80 m² 56,736.24 726,223.87
Sub Jumlah VI 4,593,265.32
VII PEKERJAAN SADAP
1 Pek. Galian tanah biasa 2.05 m³ 46,137.85 94,467.25
2 Pek. Pasangan Batu 1 pc : 4 Psr (Pakai Molen) 2.36 m³ 1,084,439.94 2,561,989.37
3 Pek. Plesteran + Acian 1 pc : 3 psr 4.05 m² 56,736.24 229,781.77
Sub Jumlah VII 2,886,238.39
VIII PEKERJAAN SALURAN PASANGAN SKUNDER
1 Pek. Galian tanah biasa 184.80 m³ 46,137.85 8,526,274.68
2 Pek. Pasangan Batu 1 pc : 4 Psr (Pakai Molen) 218.40 m³ 1,084,439.94 236,841,683.90
3 Pek. Plesteran + Acian 1 pc : 3 psr 756.00 m² 56,736.24 42,892,597.44
Sub Jumlah VIII 288,260,556.02
Jumlah ( I s/d VIII ) 822,751,637.38
0.00
DIBUAT OLEH :
KONSULTAN PERENCANA

DIDIMUS JEGAUT, ST
KEPALA PERWAKILAN
ANALISA HARGA SATUAN PEKERJAAN
( SNI 2016 )
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

T.01.a 1 m2 pembersihan lokasi pekerjaan

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.060 65,000.00 3,900.00
2 Mandor L.04 OH 0.006 95,000.00 570.00
Jumlah Harga Tenaga Kerja 4,470.00
B Bahan
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 4,470.00
E Overhead + Profit ( 10% x D ) 447.00
F Harga Satuan Pekerjaan per - m2 (D+E) 4,917.00

T.02.b.1) Pasang 1 m' profil melintang galian tanah

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.060 65,000.00 3,900.00
2 Tukang Kayu L.02 OH 0.020 95,000.00 1,900.00
3 Mandor L.04 OH 0.006 95,000.00 570.00
4 Juru Ukur L.11 OH 0.020 85,000.00 1,700.00
5 Pembantu Juru Ukur L.12 OH 0.020 65,000.00 1,300.00
Jumlah Harga Tenaga Kerja 9,370.00
B Bahan
1 Kaso 4/6 cm M.05 m3 0.0025 3,093,700.00 7,734.25
2 Papan 2/20 M.04 m3 0.0042 3,795,000.00 15,939.00
3 Paku 5 cm dan 7 cm M.06 kg 0.200 45,000.00 9,000.00
Jumlah Harga Bahan 32,673.25
C Peralatan
1 Water Pas E.03 Sewa-hari - 500,000 -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 42,043.25
E Overhead + Profit ( 10% x D ) 4,204.33
F Harga Satuan Pekerjaan per - m' (D+E) 46,247.58
TM.02.a 1 m3 galian tanah dengan Excavator

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.1630 65,000.00 10,595.00
2 Mandor L.04 OH 0.0163 95,000.00 1,548.50
Jumlah Harga Tenaga Kerja 12,143.50
B Bahan
Jumlah Harga Bahan
C Peralatan
1 arm) E.11.c Jam 0.0372 459,382.45 17,098.21

Jumlah Harga Peralatan 17,098.21


D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 29,241.71
E Overhead + Profit ( 10% x D ) 2,924.17
F Harga Satuan Pekerjaan per - m3 (D+E) 32,165.89

T.06.a.1) 1 m3 galian tanah biasa sedalam ≤ 1 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.5630 65,000.00 36,595.00
2 Mandor L.04 OH 0.0563 95,000.00 5,348.50
Jumlah Harga Tenaga Kerja 41,943.50
B Bahan
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 41,943.50
E Overhead + Profit ( 10% x D ) 4,194.35
F Harga Satuan Pekerjaan per - m3 (D+E) 46,137.85

T.14.a 1 m3 Timbunan tanah atau urugan tanah kembali

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.330 65,000.00 21,450.00
2 Mandor L.04 OH 0.033 95,000.00 3,135.00
Jumlah Harga Tenaga Kerja 24,585.00
B Bahan
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 24,585.00
E Overhead + Profit ( 10% x D ) 2,458.50
F Harga Satuan Pekerjaan per - m3 (D+E) 27,043.50

T.14.c 1 m3 Timbunan batu sebagai bahan pengisi

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.400 65,000.00 26,000.00
2 Mandor L.04 OH 0.040 95,000.00 3,800.00
Jumlah Harga Tenaga Kerja 29,800.00
B Bahan
1 Batu Kali M.02 m3 1.200 281,000.00 337,200.00
Jumlah Harga Bahan 337,200.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 367,000.00
E Overhead + Profit ( 10% x D ) 36,700.00
F Harga Satuan Pekerjaan per - m3 (D+E) 403,700.00
T.15 Angkutan Material dan/atau hasil galian
T.15.a.2) Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 10 m
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga Kerja
1 Pekerja L.01 OH 0.2720 65,000.00 17,680.00
2 Mandor L.04 OH 0.0136 95,000.00 1,292.00
Jumlah Harga Tenaga Kerja 18,972.00
B Bahan
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 18,972.00

T.15.a.6) Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 100 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga Kerja
1 Pekerja L.01 OH 0.6000 65,000.00 39,000.00
2 Mandor L.04 OH 0.0300 95,000.00 2,850.00
Jumlah Harga Tenaga Kerja 41,850.00
B Bahan
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 41,850.00

P.01 Pasangan Batu dengan Mortar Jenis PC - PP (1 m3)


P.01.c Mortar Tipe N (Setara campuran 1 PC : 4 PP)
P.01.c.1) Manual
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga Kerja
1 Pekerja L.01 OH 2.700 65,000.00 175,500.00
2 Tukang Batu L.02 OH 0.900 95,000.00 85,500.00
3 Mandor L.04 OH 0.270 95,000.00 25,650.00
Jumlah Harga Tenaga Kerja 286,650.00
B Bahan
1 Batu Belah M.02 m3 1.200 281,000.00 337,200.00
2 Pasir Pasang M.03 m3 0.520 349,400.00 181,688.00
3 Portland Cement M.01.a kg 163 1,325.00 215,975.00
Jumlah Harga Bahan 734,863.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 1,021,513.00
E Overhead + Profit ( 10% x D ) 102,151.30
F Harga Satuan Pekerjaan per - m3 (D+E) 1,123,664.30

P.01.c.2) Menggunakan Molen


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 1.800 65,000.00 117,000.00
2 Tukang Batu L.02 OH 0.900 95,000.00 85,500.00
3 Mandor L.04 OH 0.180 95,000.00 17,100.00
Jumlah Harga Tenaga Kerja 219,600.00
B Bahan
1 Batu Belah M.02 m3 1.200 281,000.00 337,200.00
2 Pasir Pasang M.03 m3 0.520 349,400.00 181,688.00
3 Portland Cement M.01.a kg 163 1,325.00 215,975.00
Jumlah Harga Bahan 734,863.00
C Peralatan
1 0,3 m3 E.29.b Sewa-hari 0.0760 413,045.99 31,391.50

Jumlah Harga Peralatan 31,391.50


D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 985,854.50
E Overhead + Profit ( 10% x D ) 98,585.45
F Harga Satuan Pekerjaan per - m3 (D+E) 1,084,439.94
P.04 1 m2 Pekerjaan Plesteran dengan Mortar Jenis PC - PP (1 m2)
P.04.b Plesteran tebal 1 cm, dengan mortar tipe S (Setara campuran 1 PC : 3 PP) dan Acian

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga Kerja
1 Pekerja L.01 OH 0.300 65,000.00 19,500.00
2 Tukang Batu L.02 OH 0.150 95,000.00 14,250.00
3 Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
4 Mandor L.04 OH 0.030 95,000.00 2,850.00
Jumlah Harga Tenaga Kerja 38,250.00
B Bahan
1 Pasir Pasang M.03 m3 0.016 349,400.00 5,590.40
2 Portland Cement M.01.a kg 5.840 1,325.00 7,738.00
Jumlah Harga Bahan 13,328.40
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 51,578.40
E Overhead + Profit ( 10% x D ) 5,157.84
F Harga Satuan Pekerjaan per - m2 (D+E) 56,736.24

P.03.b Siaran dengan mortar tipe S (setara campuran 1 PC:3 PP) + Acian

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.300 65,000.00 19,500.00
2 Tukang Batu L.02 OH 0.150 95,000.00 14,250.00
3 Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
4 Mandor L.04 OH 0.030 95,000.00 2,850.00
Jumlah Harga Tenaga Kerja 38,250.00
B Bahan
1 Pasir Pasang M.01.a m3 0.018 349,400.00 6,289.20
2 Portland Cement M.01.a kg 4.840 1,325.00 6,413.00
Jumlah Harga Bahan 12,702.20
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 50,952.20
E Overhead + Profit ( 10% x D ) 5,095.22
F Harga Satuan Pekerjaan per - m2 (D+E) 56,047.42

B.02 1 m3 Beton Mutu, f'c = 7,4 Mpa (K100), slump (12±2) cm, w/c = 0,87
B.02.a Manual
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 1.650 65,000.00 107,250.00
2 Tukang Batu L.02 OH 0.275 95,000.00 26,125.00
3 Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
4 Mandor L.04 OH 0.165 95,000.00 15,675.00
Jumlah Harga Tenaga Kerja 152,130.00
B Bahan
1 Portland Cement M.01.a kg 247 1,325.00 327,275.00
2 Pasir Beton M.03 m3 0.621 349,400.00 216,977.40
3 Krikil M.04 m3 0.74 500,000.00 370,000.00
4 Air Liter 215 0.00 0.00
Jumlah Harga Bahan 914,252.40
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 1,066,382.40
E Overhead + Profit ( 10% x D ) 106,638.24
F Harga Satuan Pekerjaan per - m3 (D+E) 1,173,020.64
B.06 1 m3 Beton Mutu, f'c = 16,9 Mpa (K200), slump (12±2) cm, w/c = 0,61
B.06.a Manual
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 1.650 65,000.00 107,250.00
2 Tukang Batu L.02 OH 0.275 95,000.00 26,125.00
3 Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
4 Mandor L.04 OH 0.165 95,000.00 15,675.00
Jumlah Harga Tenaga Kerja 152,130.00
B Bahan
1 Portland Cement M.01.a kg 352 1,325.00 466,400.00
2 Pasir Beton M.03.a kg 731 258.81 189,193.63
3 Krikil M.04.a kg 1031 384.62 396,538.46
4 Air Liter 215 0.00 0.00
Jumlah Harga Bahan 1,052,132.09
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 1,204,262.09
E Overhead + Profit ( 10% x D ) 120,426.21
F Harga Satuan Pekerjaan per - m3 (D+E) 1,324,688.30

B.17 Pembesian 1 kg dengan besi polos atau ulir


B.17.a Untuk pembesian pelat
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga Kerja
1 Pekerja L.01 OH 0.007 65,000.00 455.00
2 Tukang Besi L.02 OH 0.007 85,000.00 595.00
3 Kepala Tukang L.03 OH 0.001 110,000.00 77.00
4 Mandor L.04 OH 0.001 95,000.00 66.50
Jumlah Harga Tenaga Kerja 1,193.50
B Bahan
1 Besi Beton (polos/ulir) M.05 kg 1.050 13,100.00 13,755.00
2 Kawat Ikat M.06 kg 0.015 35,000.00 525.00
Jumlah Harga Bahan 14,280.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 15,473.50
E Overhead + Profit ( 10% x D ) 1,547.35
F Harga Satuan Pekerjaan per - 1 kg (D+E) 17,020.85

B.17.b Untuk pembesian kolom


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga Kerja
1 Pekerja L.01 OH 0.021 65,000.00 1,365.00
2 Tukang Besi L.02 OH 0.014 85,000.00 1,190.00
3 Kepala Tukang L.03 OH 0.001 110,000.00 154.00
4 Mandor L.04 OH 0.002 95,000.00 199.50
Jumlah Harga Tenaga Kerja 2,908.50
B Bahan
1 Besi Beton (polos/ulir) M.05 kg 1.050 13,100.00 13,755.00
2 Kawat Ikat M.06 kg 0.021 35,000.00 735.00
Jumlah Harga Bahan 14,490.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 17,398.50
E Overhead + Profit ( 10% x D ) 1,739.85
F Harga Satuan Pekerjaan per - 1 kg (D+E) 19,138.35
B.21.c 1 m2 Bekisting Lantai beton biasa menggunakan kayu papan 3/20 (TP)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga Kerja
1 Pekerja L.01 OH 0.300 65,000.00 19,500.00
2 Tukang Kayu L.02 OH 0.150 95,000.00 14,250.00
3 Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
4 Mandor L.04 OH 0.030 95,000.00 2,850.00
Jumlah Harga Tenaga Kerja 38,250.00
B Bahan
1 Papan 3/20 cm kayu kelas II M.07 m3 0.014 3,795,000.00 53,130.00
2 Kaso 5/7 cm M.08 m3 0.003 3,093,700.00 9,281.10
3 Paku 5 cm dan 7 cm M.09 kg 0.300 45,000.00 13,500.00
4 Minyak bekisting M.14 Liter 0.200 10,000.00 2,000.00
Jumlah Harga Bahan 77,911.10
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 116,161.10
E Overhead + Profit ( 10% x D ) 11,616.11
F Harga Satuan Pekerjaan per - m2 (D+E) 127,777.21

B.24.c 1 m2 Bekisting kolom beton biasa menggunakan kayu papan 3/20 (TP)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.340 65,000.00 22,100.00
2 Tukang Kayu L.02 OH 0.170 95,000.00 16,150.00
3 Kepala Tukang L.03 OH 0.017 110,000.00 1,870.00
4 Mandor L.04 OH 0.034 95,000.00 3,230.00
Jumlah Harga Tenaga Kerja 43,350.00
B Bahan
1 Papan 3/20 cm kayu kelas II M.07 m3 0.014 3,795,000.00 53,130.00
2 Kaso 5/7 cm M.08 m3 0.006 3,093,700.00 18,562.20
3 Paku 5 cm dan 7 cm M.09 kg 0.300 45,000.00 13,500.00
4 Minyak bekisting M.14 Liter 0.200 10,000.00 2,000.00
Jumlah Harga Bahan 87,192.20
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 130,542.20
E Overhead + Profit ( 10% x D ) 13,054.22
F Harga Satuan Pekerjaan per - m2 (D+E) 143,596.42

A.8.4.1.34. (K3) Pemasangan 1 m Pipa GIP Ø 100 mm / 4 dim


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja L.01 OH 0.400 65,000.00 26,000.00
2 Tukang Pipa L.02 OH 0.200 95,000.00 19,000.00
3 Mandor L.04 OH 0.040 95,000.00 3,800.00
Jumlah Harga Tenaga Kerja 48,800.00
B Bahan
1 Pipa GIP Ø 100 mm / 4 dim M.15.a m 1.000 13,333.33 13,333.33
Jumlah Harga Bahan 13,333.33
C Peralatan
1 Sewa Tripot/Tackel & handle crane 2 T hari - - 0.00
Jumlah Harga Peralatan 0.00
D Jumlah Harga Tenaga, Bahan dan Peralatan (A+B+C) 62,133.33
E Overhead + Profit ( 10% x D ) 6,213.33
F Harga Satuan Pekerjaan per - m2 (D+E) 68,346.67
P.01.e.2). Bongkar 1 m3 pasangan batu (manual)
Biaya Jumlah
No Uraian Satuan Kuantitas Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 Pekerja OH 1.2000 65,000.00 78,000.00
2 Mandor OH 0.1200 95,000.00 11,400.00

B Bahan
1 Batu M3 0.0000 281,000.00 0.00
2 Pasir M3 0.0000 349,400.00 0.00
C Alat
1 Palu/Godam (baja keras) buah 0.0060 75,000.00 450.00
2 Pahat Beton (baja keras) buah 0.0090 25,000.00 225.00
3 Linggis (baja keras) buah 0.0200 75,000.00 1,500.00

D Jumlah (A+B+C) 91,575.00


E Overhead & Profit ( 10% x D ) 9,157.50
F Total ( D + E ) 100,732.50

P.06 Pasangan batu bronjong kawat (SNI 03-0090-1999)


P.06.a.7) bronjong)
Biaya Jumlah
No Uraian Satuan Kuantitas Satuan Harga
(Rp) (Rp)

A Tenaga Kerja
1 pasang) OH 0.2500 65,000.00 16,250.00
2 Mandor OH 0.0250 95,000.00 2,375.00

B Bahan
1 BatuBatu / batu belah m3 1.3000 281,000.00 365,300.00
2 Kawat bronjong bh 1.0000 595,400.00 595,400.00

C Alat

D Jumlah (A+B+C) 979,325.00


E Overhead & Profit ( 10% x D ) 97,932.50
F Total ( D + E ) 1,077,257.50
LAMPIRAN : KEPUTUSAN BUPATI MANGGARAI TIMUR
NOMOR : HK/ /TAHUN 2019
TANGGAL :
TENTANG : PENETAPAN NORMALISASI DAN STANDARDISASI HARGA KOMODITI, BARANG,
PERALATAN DAN JASA DI KABUPATEN MANGGARAI TIMUR TAHUN 2020

NORMALISASI DAN STANDARDISASI HARGA KOMODITI, BARANG, PERALATAN DAN JASA


DI KABUPATEN MANGGARAI TIMUR TAHUN 2020

X. DAFTAR HARGA UPAH DAN BAHAN BANGUNAN

HargaSatuan Jam
No Jenis Barang Merk/Type Ukuran Satuan Ket
2020 (Rp) Efektif
1 2 3 4 5 6 7 8
A UPAH
1 Pekerja OH 65,000 7 5.800/jam
2 Tukang Gali OH 65,000 7 6.800/jam
3 Tukang Cat OH 66,000 7 5.800/jam
4 Tukang Batu OH 95,000 7 7.200/jam
5 Tukang Batu/Pipa OH 85,000 7 7.200/jam
6 Tukang Besi OH 85,000 7 7.200/jam
7 Tukang Besi Konstruksi OH 85,000 7 7.200/jam
8 Tukang Kayu OH 95,000 7 7.200/jam
9 Tukang Las OH 85,000 7 7.200/jam
10 Mandor OH 95,000 7 9.000/jam
11 Kepala tukang OH 110,000 7 10.200/jam
12 Mandor lapangan OH 95,000 7 8.200/jam
13 Operator OH 95,000
14 Pembantu Operator OH 75,000
15 Mekanik OH 110,000
16 Pembantu Mekanik OH 85,000
17 Sopir OH 85,000
18 Pembantu Sopir OH 65,000
B BAHAN LOKAL
1 Batu Kali / Gunung 10/15 1 M3 120,000
2 Batu Belah 5/7 cm 1 M3 275,000
3 Batu Pecah 3/5 cm 1 M3 385,000
4 Batu Pecah 2/3 cm 1 M3 495,000
5 Batu Pecah 1/2 cm 1 M3 715,000
6 Bataco Ukuran Besar 10x20x30 1 Buah 3,500
7 Bataco Standar 1 Buah 7,200.00
8 Bata Merah Standar 1 Buah 2,500.00 Belum
9 Pasir Pasang/Beton 1 M3 139,500 Termasuk
10 Pasir Urug 1 M3 80,000 Pajak dan
11 Tanah Timbun 1 M3 60,500 Ongkos
12 Tanah Timbun/Liat 1 M3 80,000 Angkut
13 Timbunan Pilihan 1 M3 160,000
14 Urugan Pilihan 1 M3 110,000
15 Tanah Liat 1 M3 72,500
16 Kerikil Alam 1 M3 180,000
C BAHAN NON LOKAL
1 Asphal 1 Kg 45,000
2 Afdunner / Tinner A (Emco) 1 Ltr 37,500
3 Afdunner / Tinner B (Emco) 1 Ltr 25,000
4 Amplas 1 Lbr 12,650
5 Besi Beton 6 mm 1 Kg 38,000
6 Besi Beton 8 mm 1 Kg 58,000
7 Besi Beton 10 mm 1 Kg 80,000
8 Besi Beton 12 mm 1 Kg 117,000
9 Besi Beton 16 mm 1 Kg 220,000
10 Besi Beton 19 mm 1 Kg
11 Besi Beton 25 mm 1 Kg
12 Besi Beton 32 mm 1 Kg
13 Cat kayu kwalitet baik (Emco) 1 Kg 86,200
14 Cat tembok (Decoplus) 1 Kg 86,200
15 Cat Tembok (Vitex) 1 Kg 71,500
16 Closet duduk (INA) 1 Bh 1,815,000
17 Closet jongkok (INA) 1 Bh 187,000
18 Deak standar 1 Bh 162,769
19 Dumpul 1 Kg 48,000
20 Ember coor 1 Bh 11,667
21 Fiber air 650 liter 1 Bh 1,500,000
22 Fiber air 1100 liter 1 Bh 1,800,000
23 Rool matex 1 Bh 25,700
24 Gemuk 1 Kg 44,000
25 Grendel pintu jendela 1 Bh 22,000
26 Genteng semen 1 Bh 15,000
27 Gergaji kayu 1 Bh 57,000
28 Gagang + Gergaji besi 1 Bh 41,667
29 Hengsel 88x55 1 Bh 17,667
30 Hengsel 110x55 1 Bh 19,500
31 Hengsel 140x60 1 Bh 25,000
32 Kait angin 1 Bh 13,750
33 Hamer 10 P 1 Bh 117,500
34 Hamer 8P 1 Bh 93,500
35 Hamer 6P 1 Bh 77,000
36 Hamer 4P 1 Bh 66,000
37 Hamer 2P 1 Bh 35,750
38 Overval 1 1 Bh 11,000
39 Globe Besar 1 Bh 37,000
40 Globe Sedang 1 Bh 27,500
41 Globe Kecil 1 Bh 16,500
42 Kawat beton 1 Kg 24,750
43 Kwt. bronjong 2.7 mm (diameter lubang..) 1 1 Unit 15,000
44 Kunci laci kings 1 Bh 20,200
45 Kunci tanam jangkar 1 Bh 200,000
46 Kunci tanam union 1 Bh 500,000
47 Kunci Yalle 1 Bh 302,500
48 Kunci tanam anchor 1 Bh 440,000
49 Kuas cat 2 1 Bh 11,000
50 Kuas cat 3 1 Bh 15,400
51 Kuas cat 4 1 Bh 20,200
52 Kaca bening 3 1 M2 200,000
53 Kaca bening 5 1 M2 250,000
54 Kaca reben 3 1 M2 250,000
55 Kaca reben 5 1 M2 257,500
56 Kaca Es 3 1 M2 250,000
57 Kaca Es 5 1 M2 300,000
58 Linggis 1 Btg 78,900
59 Menie 1 Kg 69,600
60 Minyak Tanah Subsidi 1 Ltr -
61 Minyak Tanah Industri 1 Ltr -
62 Minyak Premium Subsidi 1 Ltr -
63 Minyak Premium Industri 1 Ltr -
64 Minyak Diesel Subsidi 1 Ltr -
65 Minyak Diesel Industri 1 Ltr -
66 Teac Oil 1 Ltr 26,667
67 Paku 2cm 1 Kg 27,500
68 Paku 3cm 1 Kg 27,500
69 Paku 4cm 1 Kg 25,700
70 Paku 5cm 1 Kg 21,300
71 Paku 10-15 cm 1 Kg 21,300
72 Rangka naco + Trali 7 daun Daun 75,000
73 Pikwel / ganco Bh 96,250
74 Pahat kayu 1,2 Bh 21,500
75 Pahat kayu 1,0 Bh 27,500
76 Pahat kayu 1,5 Bh 30,000
77 Pahat kayu 2 Bh 35,000
78 Pahat besi Bh 40,000
79 Semen Kupang 40 kg Zak
80 Semen Tonasa 40 kg Zak 57,600
81 Semen Tiga Roda 40 kg Zak 56,650
82 Semen Warna Kg 23,800
83 Sanyo tipe kecil Bh
84 Sanyo tipe sedang Bh
85 Sanyo tipe besar Bh
86 Kapur Zak 96,250
87 Triplex 2 mm Lbr 55,000
88 Triplex 3 mm Lbr 57,900
89 Triplex 6 mm Lbr 85,000
90 Triplex 9 mm Lbr 126,500
91 Teakwood m2 104,500
92 Tegel Mozaik m2 65,000
93 Tegel Porselin 11x11 cm m2 120,000
94 Tegel Porselin 15x15 cm m2 110,000
95 Tegel Porselin 20x20 cm m2 78,800
96 Tegel Porselin 30x30 cm m2 75,000
97 Wastafel KIA, INA Buah 825,000
98 Zink gelombang Berwarna Lbr 54,000
99 Zink gelombang BJLS 0.20 Lbr 86,000
100 Zink gelombang BJLS 0.30 Lbr 93,500
101 Zink Plat 0.30 (Lebar 30X100 cm) M 18,333
102 Zink Plat 0.30 (Lebar 40X100 cm) M 22,500
103 Zink Plat 0.30 (Lebar 50X100 cm) M 27,500
104 Zink Plat 0.30 (Lebar 60X100 cm) M 32,500
105 Zink Plat 0.30 (Lebar 70X100 cm) M 38,333
106 Zink Plat 0.30 (Lebar 90X100 cm) M 50,000
107 Paku Zink Kg 20,000
D PIPA GIP (TT)SNI 07-0039-1987/BS 1387 : 1985
1 Pipa GIP 0,5" (2.42) 1 Btg 150,000
2 Pipa GIP 0,75"(2.65) 1 Btg 160,000
3 Pipa GIP 0 1,0" (3.25) 1 Btg 240,000
4 Pipa GIP 0 1,5" (3.25) 1 Btg 350,000
5 Pipa GIP ukuran 0 2,0" (3.65) 1 Btg 425,000
6 Pipa GIP ukuran 0 3,0" (4.05) 1 Btg 1,811,802
7 Pipa GIP ukuran 0 4,0" (4.50) 1 Btg 2,286,108
8 Pipa GIP 0 6,0" (4.85) 1 Btg 3,020,958
E PIPA PVC MASPION
1 PIPA PVC 1/2 dim S-8 Mof 1 Btg 57,750
2 Pipa PVC 3/4 dim S-8 Mof 1 Btg 74,250
3 Pipa PVC 1 dim S-10 Mof 1 Btg 88,000
4 Pipa PVC 1 1/4 dim S-10 Mof 1 Btg 44,000
5 Pipa PVC 1 1/5 dim S-10 Mof 1 Btg 55,000
6 Pipa PVC 2 dim S-10 RR 1 Btg 77,000
7 Pipa PVC 2 1/2 dim S-10 (RR) 1 Btg 121,000
8 Pipa PVC 3 dim S-10 (RR) 1 Btg 126,500
9 Pipa PVC 4 dim S-10 (RR) 1 Btg 159,500
10 Pipa PVC 6 DIM S-10 (RR) 1 Btg 187,000
11 Pipa PVC 8 dim S-10 (RR) 1 Btg 200,000
F PIPA CLASS MEDIUM SIO- SNI
1 Pipa GIP 1/2 Inch (15) 1 Btg 321,345
2 Pipa GIP 3/4 Inch (20) 1 Btg 430,307
3 Pipa GIP 1 Inch (25) 1 Btg 491,422
4 Pipa GIP 1 1/4 Inch (32) 1 Btg 628,680
5 Pipa GIP 1 1/2 Inch (40) 1 Btg 706,492
6 Pipa GIP 2 Inch (50) 1 Btg 912,212
7 Pipa GIP 2 1/2 Inch (65) 1 Btg 986,184
8 Pipa GIP 3 Inch (80) 1 Btg 1,953,666
9 Pipa GIP 4 Inch (100) 1 Btg 2,448,094
10 Pipa GIP 5 Inch (125) 1 Btg 3,035,696
11 Pipa GIP 6 Inch (150) 1 Btg 3,646,175
12 Pipa GIP 8 Inch (200) 1 Btg 8,774,632
G PIPA PVC CLASS-AW-SNI
1 Pipa PVC 1/2 dim Mof 1 Btg 45,000
2 Pipa PVC 3/4 dim Mof 1 Btg 55,000
3 Pipa PVC 1 dim Mof 1 Btg 67,500
4 Pipa PVC 1 1/4 dim Mof 1 Btg 97,500
5 Pipa PVC 1 1/5 dim Mof 1 Btg 125,000
6 Pipa PVC 2 dim Rubber Ring (RR) 1 Btg 200,000
7 Pipa PVC 2 1/2 dim (RR) 1 Btg 515,133
8 Pipa PVC 3 dim (RR) 1 Btg 718,014
9 Pipa PVC 4 dim (RR) 1 Btg 1,042,289
10 Pipa PVC 6 dim (RR) 1 Btg 1,873,557
11 Pipa PVC 8 dim (RR) 1 Btg 2,794,500
H PIPA PE - SDR 17/PN - 10
1 Pipa PE 1/2 Inch (15) 1 mtr 10,382
2 Pipa PE 3/4 Inch (20) 1 mtr 12,000
3 Pipa PE 1 Inch (25) 1 mtr 19,200
4 Pipa PE 1 1/4 Inch (32) 1 mtr 30,000
5 Pipa PE 1 1/2 Inch (40) 1 mtr 46,800
6 Pipa PE 2 Inch (50) 1 mtr 74,400
7 Pipa PE 2 1/2 Inch (65) 1 mtr 105,600
8 Pipa PE 3 Inch (80) 1 mtr 150,000
9 Pipa PE 4 Inch (100) 1 btg 224,400
10 Pipa PE 5 Inch (125) 1 btg 360,000
11 Pipa PE 6 Inch (150) 1 btg 607,200
12 Pipa PE 8 Inch (225) 1 btg 932,400
13 Pipa PE 10 Inch 1 btg 1,064,400
J ACCSESOREIS
1 Socket GIP 0 0,5" 1 Buah 15,000
2 Socket GIP 0 0,75" 1 Buah 20,000
3 Socket GIP 0 1,0" 1 Buah 25,000
4 Socket GIP 0 1,5" 1 Buah 30,000
5 Socket GIP 0 2,0" 1 Buah 40,000
6 Socket GIP 0 3,0" 1 Buah 80,000
7 Socket GIP 0 4,0" 1 Buah 120,000
8 Socket GIP 0 6,0" 1 Buah 223,146
9 Socket GIP 0 0,5" x 45 1 Buah 15,000
10 Socket GIP 0 0,5" x 90 1 Buah 19,279
11 Socket GIP 0 3/4 x 45 1 Buah 20,000
12 Socket GIP 0 3/4 x 90 1 Buah 34,914
13 Boog GIP 0 1x 11,25 1 Buah 25,000
14 Boog GIP 0 1x 22,5 1 Buah 44,629
15 Boog GIP 0 1x 45 1 Buah 44,629
16 Boog GIP 0 1x 90 1 Buah 44,629
17 Boog GIP 0 1,5"x 11,2 1 Buah 58,139
18 Boog GIP 0 1,5x 22,5 1 Buah 58,139
19 Boog GIP 0 1,5x 45 1 Buah 30,000
20 Boog GIP 0 1,5x 90 1 Buah 58,139
21 Boog GIP 0 2x 11,5 1 Buah 87,285
22 Boog GIP 0 2x 22,5 1 Buah 87,285
23 Boog GIP 0 2x 45 1 Buah 40,000
24 Boog GIP 0 2x 90 1 Buah 87,285
25 Boog GIP 0 3x 11,25 1 Buah 116,431
26 Boog GIP 0 3x 22,5 1 Buah 116,431
27 Boog GIP 0 3x 45 1 Buah 116,431
28 Boog GIP 0 3x 90 1 Buah 116,431
29 Boog GIP 0 4x 11,5 1 Buah 164,855
30 Boog GIP 0 4x 45 1 Buah 164,855
31 Boog GIP 0 4x 90 1 Buah 164,855
32 Boog GIP 0 6x 11,5 1 Buah 223,146
33 Boog GIP 0 6x 45 1 Buah 223,146
34 Boog GIP 0 6x 90 1 Buah 223,146
35 Kopling GIP 0 0,5" 1 Buah 15,000
36 Kopling GIP 0 0,75" 1 Buah 20,000
37 Kopling GIP 0 1,0" 1 Buah 25,000
38 Kopling GIP 0 1,5" 1 Buah 30,000
39 Kopling GIP 0 2,0" 1 Buah 35,000
40 Kopling GIP 0 3,0" 1 Buah 261,855
41 Kopling GIP 0 4,0" 1 Buah 436,577
42 Kopling GIP 0 6,0" 1 Buah 630,577
43 Reduser socket 1 1/2 x 1/2 1 Buah 30,000
44 Reduser socket GIP 1 1/2 x 3/4 1 Buah 30,000
45 Reduser socket GIP 1 1/2 x 1 1 Buah 30,000
46 Reduser socket GIP 1 1/2 x 1 1 Buah 30,000
47 Reduser socket GIP 2 x 1/2 1 Buah 40,000
48 Reduser socket GIP 2 x 3/4 1 Buah 40,000
49 Reduser socket GIP 2x1 1 Buah 40,000
50 Reduser socket GIP 2 x 1 1/2 1 Buah 40,000
51 Reduser socket GIP 3 x 3/4 1 Buah 82,427
52 Reduser socket GIP GIP 3 x 1 1 Buah 82,427
53 Reduser socket GIP 3 x 1 1/2 1 Buah 87,285
54 Reduser socket GIP 3x2 1 Buah 87,285
55 Reduser socket GIP 4x1 1 Buah 91,080
56 Reduser socket GIP 4 x 1 1/2 1 Buah 97,000
57 Reduser socket GIP 4x2 1 Buah 97,000
58 Reduser socket GIP 4x3 1 Buah 1,164,306
59 Reduser socket GIP 6 x 1 1/2 1 Buah 145,424
60 Reduser socket GIP 6x2 1 Buah 1,454,244
61 Reduser socket GIP 6x3 1 Buah 145,424
62 Reduser socket GIP 6x4 1 Buah 145,424
63 Reduser Tee GIP 1/2 x 1/2 1 Buah 28,994
64 Reduser Tee GIP 3/4 x 1/2 1 Buah 28,994
65 Reduser Tee GIP 3/4 x 3/4 1 Buah 32,941
66 Reduser Tee GIP 1 x 1/2 1 Buah 32,941
67 Reduser Tee GIP 1 x 3/4 1 Buah 32,941
68 Reduser Tee GIP 1x1 1 Buah 32,941
69 Reduser Tee GIP 1 1/2 x 1/2 1 Buah 54,193
70 Reduser Tee GIP 1 1/2 x 3/4 1 Buah 54,193
71 Reduser Tee GIP 1 1/2 x 1 1 Buah 54,193
72 Reduser Tee GIP 1 1/2 x 1 1/2 1 Buah 54,193
73 Reduser Tee GIP 2 x 1/2 1 Buah 67,855
74 Reduser Tee GIP GIP 2 x 3/4 1 Buah 77,570
75 Reduser Tee GIP 2x1 1 Buah 77,570
76 Reduser Tee GIP 2 x 1 1/2 1 Buah 77,570
77 Reduser Tee GIP 2x2 1 Buah 77,570
78 Reduser Tee GIP 3 x 1 1/2 1 Buah 87,285
79 Reduser Tee GIP 3 x 3/4 1 Buah 87,285
80 Reduser Tee GIP 3x1 1 Buah 97,000
81 Reduser Tee GIP 3 x 1 1/2 1 Buah 145,424
82 Reduser Tee GIP 3x2 1 Buah 145,424
83 Reduser Tee GIP 3x3 1 Buah 145,424
84 Kran dorong 0 0,5" 1 Buah 28,994
85 Kran putar 0 0,5" 1 Buah 23,225
86 Stop kran KITZ 1/2 1 Buah 87,285
87 Stop kran KITZ 3/4 1 Buah 120,226
88 Stop kran KITZ 1 1 Buah 174,570
89 Stop kran KITZ 1 1/2 1 Buah 242,576
90 Stop kran KITZ 2 1 Buah 388,001
91 Stop kran KITZ 3 1 Buah 543,292
92 Stop kran KITZ 4 1 Buah 679,153
93 Stop kran KITZ 6 1 Buah 970,306
94 Water meter 1/2 1 Buah 349,292
95 Water meter 3/4 1 Buah 523,862
96 Water meter 1 1 Buah 679,153
97 Water meter 1 1/2 1 Buah 892,584
98 Water meter 2 1 Buah 1,406,882
99 Water meter 3 1 Buah 1,795,035
100 Water meter 4 1 Buah 3,396,070
101 Water meter 6 1 Buah 3,881,222
102 Double nipel 1/2 1 Buah 18,000
103 Double nipel 3/4 1 Buah 20,000
104 Double nipel 1 1 Buah 25,000
105 Double nipel 1 1/2 1 Buah 30,000
106 Double nipel 2 1 Buah 54,193
107 Double nipel 3 1 Buah 67,855
108 Double nipel 4 1 Buah 77,570
109 Double nipel 6 1 Buah 87,423
110 Valve socket 1/2 1 Buah 9,563
111 Valve socket 3/4 1 Buah 14,421
112 Valve socket 1 1 Buah 19,279
113 Valve socket 1 1/2 1 Buah 28,994
114 Valve socket 2 1 Buah 38,709
115 Valve socket 3 1 Buah 54,193
116 Valve socket 4 1 Buah 77,570
117 Valve socket 6 1 Buah 116,431
118 Doop GIP 1/2 1 Buah 135,709
119 Doop GIP 3/4 1 Buah 19,182
120 Doop GIP 1 1 Buah 26,358
121 Doop GIP 1 1/2 1 Buah 35,190
122 Doop GIP 2 1 Buah 49,266
123 Doop GIP 3 1 Buah 70,518
124 Doop GIP 4 1 Buah 105,846
125 Doop GIP 6 1 Buah 123,372
126 Taping Sadle (Clem Sadle) 3x3/4 1 Buah 276,000
127 Taping Sadle (Clem Sadle) 3x 1 1/2 1 Buah 291,001
128 Taping Sadle (Clem Sadle) 4x3/4 1 Buah 291,001
129 Taping Sadle (Clem Sadle) 4x1 4x1 1 Buah 310,431
130 Taping Sadle (Clem Sadle) 4x2 1 Buah 339,577
131 Taping Sadle (Clem Sadle) 6x1/2 1 Buah 485,153
132 Taping Sadle (Clem Sadle) 6x2 1 Buah 543,292
133 Gilboult Joint 1 1 Buah 87,285
134 Gilboult Joint 1 1/2 1 Buah 116,431
135 Gilboult Joint 2 1 Buah 145,424
136 Gilboult Joint 3 1 Buah 194,000
137 Gilboult Joint 4 1 Buah 533,577
138 Gilboult Joint 6 1 Buah 1,455,458
139 Boog PVC 1/2 x 90 1 Buah 13,510
140 Boog PVC 3/4 x 90 1 Buah 23,225
141 Boog PVC 1 x 90 1 Buah 32,941
142 Boog PVC 1 1/2 x 90 1 Buah 38,709
143 Boog PVC 2 x 90 1 Buah 97,000
144 Boog PVC 3 x 90 1 Buah 135,709
145 Boog PVC 4 x 90 1 Buah 203,716
146 Boog PVC 6 x 90 1 Buah 339,577
147 Reducer Tee PVC 1/2x1/2 1 Buah 17,457
148 Reducer Tee PVC 3/4x1/2 1 Buah 19,279
149 Reducer Tee PVC 3/4x3/4 1 Buah 23,225
150 Reducer Tee PVC 1x1/2 1 Buah 23,225
151 Reducer Tee PVC 1x3/4 1 Buah 24,136
152 Reducer Tee PVC 1x1 1 Buah 28,994
153 Reducer Tee PVC 1 1/2x1/2 1 Buah 44,629
154 Reducer Tee PVC 1 1/2x3/4 1 Buah 8,000
155 Reducer Tee PVC 1 1/2x1 1 Buah 8,000
156 Reducer Tee PVC 1 1/2x1 1/2 1 Buah 10,000
157 Reducer Tee PVC 2x3/4 1 Buah 10,000
158 Reducer Tee PVC 2x1 1 Buah 10,000
159 Reducer Tee PVC 2x2 1 Buah 10,000
160 Reducer Tee PVC 3x1 1 Buah 15,000
161 Reducer Tee PVC 3x1 1/2 1 Buah 15,000
162 Reducer Tee PVC 3x2 1 Buah 15,000
163 Reducer Tee PVC 3x3 1 Buah 15,000
164 Reducer Tee PVC 4x1 1 Buah 25,000
165 Reducer Tee PVC 4x2 1 Buah 25,000
166 Reducer Tee PVC 4x3 1 Buah 25,000
167 Reducer Tee PVC 4x4 1 Buah 25,000
168 Reducer Tee PVC 6x6 1 Buah 25,000
169 Faucet Socket 1/2 1 Buah 3,000
170 Faucet Socket 3/4 1 Buah 4,000
171 Faucet Socket 1 1 Buah 5,000
172 Faucet Socket 1 1/2 1 Buah 8,000
173 Faucet Socket 2 1 Buah 10,000
174 Faucet Socket 3 1 Buah 15,000
175 Faucet Socket 4 1 Buah 20,000
176 Faucet Socket 6 1 Buah 77,570
177 Doop PVC 1/2 1 Buah 3,000
178 Doop PVC 3/4 1 Buah 4,000
179 Doop PVC 1 1 Buah 5,000
180 Doop PVC 1 1/2 1 Buah 8,000
181 Doop PVC 2 1 Buah 10,000
182 Doop PVC 3 1 Buah 15,000
183 Doop PVC 4 1 Buah 20,000
184 Doop PVC 6 1 Buah 58,139
185 Reducer Sock PVC 3/4x1/2 1 Buah 4,000
186 Reducer Sock PVC 1x1/2 1 Buah 5,000
187 Reducer Sock PVC 1x3/4 1 Buah 5,000
188 Reducer Sock PVC 1 1/2x1/2 1 Buah 8,000
189 Reducer Sock PVC 1 1/2x3/4 1 Buah 8,000
190 Reducer Sock PVC 1 1/2x1 1 Buah 8,000
191 Reducer Sock PVC 2x1/2 1 Buah 10,000
192 Reducer Sock PVC 2x3/4 1 Buah 10,000
193 Reducer Sock PVC 2x1 1 Buah 10,000
194 Reducer Sock PVC 2x1 1/2 1 Buah 10,000
195 Reducer Sock PVC 3x1/2 1 Buah 15,000
196 Reducer Sock PVC 3x3/4 1 Buah 15,000
197 Reducer Sock PVC 3x1 1 Buah 15,000
198 Reducer Sock PVC 3x1 1/2 1 Buah 15,000
199 Lem Pipa PVC Stiki 3x2 1 Buah 15,000
200 Kotak Meteran 1 Buah 131,307
201 Lem Pipa PVC Stiki 1 1 Kg 71,500
K MULTIROOOF
1 Genteng Multiroof 2 susun (2x5
Genteng) (77 cm x 100 cm) Stone 1 m2 = 1,3 lembar 1 lembar 106,920
tebal 0,40 mm Disesuiakan
2 Genteng Multicolor 2 susun (2x5 dengan
Genteng) (77 cm x 100 cm) Polos harga Pabrik
1 m2 = 1,3 lembar 1 lembar 95,040
tebal 0,40 mm
DAFTAR HARGA SATUAN DASAR UPAH DAN BAHAN

PEMERINTAH : KABUPATEN MANGGARAI TIMUR


DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN :
PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR / NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

Harga Total
No Uraian Pekerjaan Kode Satuan Satuan Harga Satuan Keterangan
(Rp) (Rp)
I UPAH
1 Pekerja L.01 OH 65,000.00 65,000.00 Org/Hari
2 Mandor Lapangan L.04 OH 95,000.00 95,000.00 Org/Hari
3 Tukang Gali OH 65,000.00 65,000.00 Org/Hari
4 Tukang Batu OH 95,000.00 95,000.00 Org/Hari
L.02
5 Tukang Besi OH 85,000.00 85,000.00 Org/Hari
6 Tukang Kayu OH 95,000.00 95,000.00 Org/Hari
7 Kepala Tukang L.03 OH 110,000.00 110,000.00 Org/Hari
8 Operator L.05 OH 95,000.00 95,000.00 Org/Hari
9 Pembantu Operator L.06 OH 75,000.00 75,000.00 Org/Hari
10 Sopir / Driver L.07 OH 85,000.00 85,000.00 Org/Hari
11 Pembantu Sopir / Driver L.08 OH 65,000.00 65,000.00 Org/Hari
12 Mekanik L.09 OH 110,000.00 110,000.00 Org/Hari
13 Pembantu Mekanik L.10 OH 85,000.00 85,000.00 Org/Hari
14 Juru Ukur L.11 OH 85,000.00 85,000.00 Org/Hari
15 Pembantu Juru Ukur L.12 OH 65,000.00 65,000.00 Org/Hari

II BAHAN
1 Semen @ 40 kg M.01 Zak 53,000.00
2 Semen @ 40 kg M.01.a Kg 1,325.00
3 Batu Kali/belah M.02 M3 281,000.00
4 Pasir Pasang/Beton M.03 M3 349,400.00
5 Pasir Pasang/Beton M.03.a Kg 258.81
6 Kerikil Pecah 2/3 M.04 M3 500,000.00
7 Kerikil Pecah 2/3 M.04.a Kg 384.62
8 Besi Beton Polos M.05 Kg 13,100.00
9 Kawat Ikat M.06 Kg 35,000.00
10 Kayu Papan 2/20 x 300 cm M.07 M3 3,795,000.00
11 Kaso/Usuk 5/7 & 4/6 x 300 cm M.08 M3 3,093,700.00
12 Paku Kayu 5 cm dan 7 cm M.09 Kg 45,000.00
13 Bahan Bakar Solar M.10 Liter 10,200.00
14 Bahan Bakar Bensin M.11 Liter 9,000.00
15 Minyak Pelumas/Oli M.12 Liter 25,000.00
16 Minyak Tanah M.13 Liter 5,000.00
17 Minyak Begisting M.14 Liter 10,000.00
18 Pipa PVC Maspion dia. 2 dim M.15 Btg 80,000.00
19 Pipa PVC Maspion dia. 2 dim M.15.a M' 13,333.33
20 Palu/Godam (Baja keras) M.16 Bh 75,000.00
21 Pahat Beton (Baja keras) M.17 Bh 25,000.00
22 Linggis (Baja keras) M.18 Bh 75,000.00
23 Bronjong/Gabion 3.0mm (mess =10x12 cm)-0.3 x 1.0 x M.19 Unit/Bh 595,400.00
0.5 Berat 23 kg

III ALAT
1 WATER PAS E.03 Sewa-Hari 500,000.00
2 DUMP TRUCK 5 TON E.08 Jam 290,503.37
3 DUMP TRUCK 8 TON E.09 Jam 350,447.94
4 FLAT BED TRUCK 3-4 M3 E.10 Jam 309,971.08
5 EXCAVATOR 80-140 HP E.11.c Jam 459,382.45
6 STAMPER E.25 Jam 39,803.74
7 CONCRETE MIXER 0.3-0.6 M3 E.29.b Sewa-Hari 413,045.99

0.00
0.00
0.00
0.00

0.00
0.00
PERHITUNGAN BIAYA ANGKUT BAHAN DAN MATERIAL

PEMERINTAH : KABUPATEN MANGGARAI TIMUR


DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

* SEMEN
- Harga Semen di Pasaran = Rp. 55,000.00 /Zak
- Ongkos Angkut ke Lokasi = Rp. 2,278.47 /Zak
- Ongkos Bongkar Muat = Rp. 316.95 /Zak
- Ongkos angkut dari Ujung Jalan ke Lokasi pekerjaan = Rp. /Zak
Jumlah = Rp. 57,595.42 /Zak
Dibulatkan = Rp. 57,500.00 /Zak
Analisa Angkutan
a- Jarak Angkut L= 17.00 km PP = 2 x L = 34.00 Km
b- Kecepatan Rata-rata = V = 25.00 km/jam
c- Lamanya waktu muat/bongkar = 1.20 Jam
d- Waktu per trip = 34 / 25 + 1.20 = 2.56 Jam
e- Jumlah trip per hari = 7 / 2.56 = 2.73 Trip
f- Kapasitas angkut per trip = 150.00 Zak
g- Biaya transport truck per hari = Rp. 934,528
h- Produksi per hari = 2.73 x 150 Zak = 410.16 Zak
i- Ongkos angkut = 934,528 / 410.16 = Rp. 2,278.47 /Zak
- Analisa Bongkar Muat dengan 2 org Pekerja x 65,000.00 = Rp. 316.95 /Zak
410.16
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
0.04 = Rp. 689.89
- HSP Angkut 1 Zak Semen 40 Kg = 1.00 x x (A)
1.10

* BATU KALI
- Harga Batu Kali di Tempat = Rp. 175,000.00 /M3
- Ongkos Angkut ke Lokasi = Rp. 62,301.86 /M3
Ongkos Bongkar Muat = Rp. /M3
- Pajak Galian Gol. C = Rp. 43,750.00 /M3
- Ongkos angkut dari Ujung Jalan ke Lokasi pekerjaan = Rp. /M3
Jumlah = Rp. 281,051.86 /M3
Dibulatkan = Rp. 281,000.00 /M3
Analisa Angkutan
a - Jarak Angkut L= 5.00 km PP = 2 x L = 10.00 Km
b - Kecepatan Rata-rata = V = 25.00 km/jam
c- Lamanya waktu muat/bongkar = 1.00 Jam
d- Waktu per trip = 10 / 25.00 + 1.00 = 1.40 Jam
e- Jumlah trip per hari = 7 / 1.40 = 5.00 Trip
f- Kapasitas angkut per trip = 3.00 /M3
g- Biaya transport truck per hari = Rp. 934,528
h - Produksi per hari = 5.00 x 3.00 M3 = 15.00 M3
i - Ongkos angkut = 934,528 / 15.00 = Rp. 62,301.86 /M3
- Analisa Bongkar Muat dengan 4 org Pekerja x = Rp. /M3
15.00
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
0.97 = Rp. 16,729.85
- HSP Angkut 1 m3 Batu Kali = 1.00 x x (A)
1.10
* PASIR PASANG/BETON / M3
- Harga Pasir di Tempat = Rp. 150,000.00 /M3
- Ongkos Angkut ke Lokasi = Rp. 161,984.83 /M3
Ongkos Bongkar Muat = Rp. - /M3
- Pajak Galian Gol. C = Rp. 37,500.00 /M3
- Ongkos angkut dari Ujung Jalan ke Lokasi pekerjaan = Rp. /M3
Jumlah = Rp. 349,484.83 /M3
Dibulatkan = Rp. 349,400.00 /M3
Analisa Angkutan
a- Jarak Angkut L= 33.00 km PP = 2 x L = 66.00 Km
b- Kecepatan Rata-rata = V = 25.00 km/jam
c- Lamanya waktu muat/bongkar = 1.00 Jam
d- Waktu per trip = 66.00 / 25.00 + 1.00 = 3.64 Jam
e- Jumlah trip per hari = 7 / 3.64 = 1.92 Trip
f- Kapasitas angkut per trip = 3.00 /M3
g- Biaya transport truck per hari = Rp. 934,528
h- Produksi per hari = 1.92 x 3.00 M3 = 5.77 M3
i - Ongkos angkut = 934,528 / 5.77 = Rp. 161,984.83 /M3

- Analisa Bongkar Muat dengan 4 org Pekerja x - = Rp. /M3


5.77
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
1.28 = Rp. 22,076.51
- HSP Angkut 1 m3 Pasir = 1.00 x x (A)
1.10

* BATU PECAH 2/3 KERIKIL


- Harga Batu Pecah di Tempat = Rp. 400,000.00 /M3
- Ongkos Angkut ke Lokasi = Rp. -
Ongkos Bongkar Muat = Rp.
- Pajak Galian Gol. C = Rp. 100,000.00
- Ongkos angkut dari Ujung Jalan ke Lokasi pekerjaan = Rp. /M3
Jumlah = Rp. 500,000.00 /M3
Dibulatkan = Rp. 500,000.00 /M3
Analisa Angkutan
a- Jarak Angkut L= 5.00 km PP = 2 x L = 10.00 Km
b- Kecepatan Rata-rata = V = 25.00 km/jam
c- Lamanya waktu muat/bongkar = 1.20 Jam
d- Waktu per trip = 10.00 / 25.00 + 1.20 = 1.60 Jam
e- Jumlah trip per hari = 7 / 1.60 = 4.38 Trip
f- Kapasitas angkut per trip = 3.00 /M3
g- Biaya transport truck per hari = Rp. 934,528
h- Produksi per hari = 4.38 x 3.00 M3 = 13.13 M3
i- Ongkos angkut = 934,528 / 13.13 = Rp. /M3
- Analisa Bongkar Muat dengan 4 org Pekerja x 65,000.00 = Rp. /M3
13.13
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
1.25 = Rp. 21,559.09
- HSP Angkut 1 m3 Kerikil = 1.00 x x (A)
1.10
* BESI BETON
- Harga Besi beton di Pasaran = Rp. 13,100.00 /kg
- Ongkos Angkut ke Lokasi = Rp. 78.77 /kg
- Ongkos Bongkar Muat = Rp. 10.96 /kg
- Ongkos angkut dari Ujung Jalan ke Lokasi = Rp. /kg
Jumlah = Rp. 13,189.72 /kg
Dibulatkan = Rp. 13,100.00 /kg
Analisa Angkutan
a- Jarak Angkut L= 17.00 km PP = 2 x L = 34.00 Km
b- Kecepatan Rata-rata = V = 25.00 km/jam
c- Lamanya waktu muat/bongkar = 1.00 Jam
d- Waktu per trip = 34.00 / 25 + 1.00 = 2.36 Jam
e- Jumlah trip per hari = 7 / 2.36 = 2.97 Trip
f- Kapasitas angkut per trip = 4,000.00 /kg
g- Biaya transport truck per hari = Rp. 934,528
h- Produksi per hari = 2.97 x 4,000.00 kg = 11,864.41 /kg
i- Ongkos angkut = 934,528 / 11,864.41 = Rp. 78.77 /kg
- Analisa Bongkar Muat dengan 2 org Pekerja x 65,000.00 = Rp. 10.96 /kg
11,864.41
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
0.001 = Rp. 12.07
- HSP Angkut 1 kg besi beton = 0.70 x x (A)
1.10

* PAKU
- Harga Paku di Pasaran = Rp. 45,000.00 /Kg
- Ongkos Angkut ke Lokasi = Rp. 78.77 /Kg
- Ongkos Bongkar Muat = Rp. 0.07 /Kg
- Ongkos angkut dari Ujung Jalan ke Lokasi = Rp. /kg
Jumlah = Rp. 45,078.84 /Kg
Dibulatkan = Rp. 45,000.00 /Kg
Analisa Angkutan
a- Jarak Angkut L= 17.00 km PP = 2 x L = 34.00 Km
b- Kecepatan Rata-rata = V = 25.00 km/jam
c- Lamanya waktu muat/bongkar = 1.00 Jam
d- Waktu per trip = 34 / 25 + 1.00 = 2.36 Jam
e- Jumlah trip per hari = 7 / 2.36 = 2.97 Trip
f- Kapasitas angkut per trip = 4,000.00 Kg
g- Biaya transport truck per hari = Rp. 934,528
h- Produksi per hari = 2.97 x 4,000.00 kg = 11,864.41 /Kg
i- Ongkos angkut = 934,528 / 11,864.41 = Rp. 78.77 /Kg
- Analisa Bongkar Muat dengan 1 org Pekerja x 65,000.00 = Rp. 0.07 /Kg
934,527.85
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
0.001 = Rp. 12.07
- HSP Angkut 1 kg paku = 0.70 x x (A)
1.10
* KAWAT BETON
- Harga Kawat beton di Pasaran = Rp. 35,000.00 /kg
- Ongkos Angkut ke Lokasi = Rp. 78.77 /kg
- Ongkos Bongkar Muat = Rp. /kg
- Ongkos angkut dari Ujung Jalan ke Lokasi = = Rp. /kg
Jumlah = Rp. 35,078.77 /kg
Dibulatkan = Rp. 35,000.00 /kg
Analisa Angkutan
a- Jarak Angkut L= 17.00 km PP = 2 x L = 34.00 Km
b- Kecepatan Rata-rata = V = 25.00 km/jam
c- Lamanya waktu muat/bongkar = 1.00 Jam
d- Waktu per trip = 34 / 25 + 1.00 = 2.36 Jam
e- Jumlah trip per hari = 7 / 2.36 = 2.97 Trip
f- Kapasitas angkut per trip = 4,000.00 kg
g- Biaya transport truck per hari = Rp. 934,528
h- Produksi per hari = 2.97 x 4000 kg = 11,864.41 /kg
i- Ongkos angkut = 934,528 / 11,864.41 = Rp. 78.77 /kg
- Analisa Bongkar Muat dengan org Pekerja x 65,000.00 = Rp. /kg

Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
0.001 = Rp. 12.07
- HSP Angkut 1 kg kawat beton = 0.70 x x (A)
1.10

* KASO/USUK 5/7 CM
- Harga kayu perancah di Pasaran = Rp. 3,080,000.00 /m3
- Ongkos angkut dari Quary ke Lokasi = Rp. 13,797.82 /m3
Jumlah = Rp. 3,093,797.82 /m3
Dibulatkan = Rp. 3,093,700.00 /m3
Analisa Angkutan
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
0.80 = Rp. 13,797.82
- HSP Angkut 1 m3 Kaso 5/7 cm = 1.00 x x (A)
1.10

* PAPAN 2/20 CM
- Harga kayu perancah di Pasaran = Rp. 3,781,250.00 /m3
- Ongkos angkut dari Quary ke Lokasi = Rp. 13,797.82 /m3
Jumlah = Rp. 3,795,047.82 /m3
Dibulatkan = Rp. 3,795,000.00 /m3
Analisa Angkutan
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
0.80 = Rp. 13,797.82
- HSP Angkut 1 m3 Papan 2/20 cm = 1.00 x x (A)
1.10
* PIPA GIP Ø 100 mm / 4 " (Class Medium SIO-SNI)
- Harga Pipa GIP Ø 100 mm di Pasaran = Rp. 2,139,000.00 /Btg
- Ongkos Angkut ke Lokasi = Rp. 7,684.62 /Btg
- Ongkos Bongkar Muat = Rp. 1,068.99 /Btg
- Ongkos angkut dari Ujung Jalan ke Lokasi = = Rp. /Btg
Jumlah = Rp. 2,147,753.61 /Btg
Dibulatkan = Rp. 2,147,700.00 /Btg
Analisa Angkutan
a- Jarak Angkut L= 17.00 km PP = 2 x L = 34.00 Km
b- Kecepatan Rata-rata = V = 25.00 km/jam
c- Lamanya waktu muat/bongkar = 1.00 Jam
d- Waktu per trip = 34 / 25 + 1.00 = 2.36 Jam
e- Jumlah trip per hari = 7 / 2.36 = 2.97 Trip
f- Kapasitas angkut per trip = 41.00 Btg
g- Biaya transport truck per hari = Rp. 934,528
h- Produksi per hari = 2.97 x 41 kg = 121.61 /Btg
i- Ongkos angkut = 934,528 / 121.61 = Rp. 7,684.62 /Btg
- Analisa Bongkar Muat dengan 2 org Pekerja x 65,000.00 = Rp. 1,068.99 /Btg
121.61
Pemindahan Bahan/ Material ke lokasi Site (Dengan Tenaga Manusia)
- Jarak angkut 500.00 m'
- HSP Angkut 1 m3 Material (Analisa T.15.a.2) = (A) = Rp. 18,972.00
0.001 = Rp. 13.80 (B)
- HSP Angkut 1 Kg Pipa GIP = 0.80 x x (A)
1.10
- Berat Pipa GIP 4 dim untuk 1 batang = 74.40 Kg (C)
- HSP Angkut Pipa GIP 4 dim untuk 1 batang = (B) x (C) = Rp. 1,026.56

0.00
0.00
0.00
CV. DETAIL ENGINEERING DISAIN KONSULTAN

0.00
0.00
HARGA & JARAK RATA-RATA
DARI SUMBER BAHAN (QUARRY)

PEMERINTAH : KABUPATEN MANGGARAI TIMUR


DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR / NORMALISASI SALURAN
SUNGAI

PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

HARGA JARAK JARAK DARI


No. URAIAN SATU ROYALTY LOKASI QUARRY UJUNG JLN KET.
AN (Rp) ( Km ) KE LOKASI PEK.
(M)

1. Pasir Pasang/Beton M3 150,000.00 Bondo/Wae Musur 33.00 500.00 Ke Lokasi Pek.

2. Batu Kali/Belah M3 175,000.00 Wae Reno 5.00 500.00 Ke Lokasi Pek.

3. Kaso/Usuk 5/7 cm M3 3,080,000.00 Sekitar Lokasi 5.00 500.00 Ke Lokasi Pek.

4. Papan 2/20 cm M3 3,781,250.00 Sekitar Lokasi 5.00 500.00 Ke Lokasi Pek.

5. Kerikil Pecah 2/3 M3 400,000.00 Wae Reno 5.00 500.00 Ke Lokasi Pek.

6. Pasir Urug M3 150,000.00 Wae Reno 5.00 500.00 Ke Lokasi Pek.

7. Semen Zak 55,000.00 Ruteng 17.00 500.00 Ke Base Camp

8. Paku Kayu Kg 45,000.00 Ruteng 17.00 500.00 Ke Base Camp

9. Besi Beton Kg 13,100.00 Ruteng 17.00 500.00 Ke Base Camp

10. Kawat Beton Kg 35,000.00 Ruteng 17.00 500.00 Ke Base Camp

11. Pipa GIP Ø 100 mm / 4 " (Class Medium A) Btg 2,139,000.00 Ruteng 17.00 500.00 Ke Base Camp

12. Bronjong/Gabion 3.0mm (mess =10x12 cm)-0.3 x


1.0 x 0.5 Berat 23 kg Unit 595,400.00 Ruteng 17.00 500.00 Ke Base Camp

Catatan : Harga Royalty belum termasuk retribusi .

0.00
0.00
0.00
CV. DETAIL ENGINEERING DISAIN KONSULTAN

0.00
0.00
ANALISA BIAYA PERALATAN

PEMERINTAH : KABUPATEN MANGGARAI TIMUR


DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3-4 M3
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 5.0 Ton
4. Alat Yang Dipakai : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 280,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 28,000,000 Rupiah
i x (1 + i)^A
2. Faktor Angsuran Modal = ---------- D 0.28085 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
(B-C)xD
a. Biaya Pengembalian Modal = - - - - - - - -- - E 35,387.61 Rupiah
W
0.002 x B
b. Asuransi, dll = ----------- F 280.00 Rupiah
W

Biaya Pasti per Jam = (E+F) G 35,667.61 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 191,250.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,875.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 21,000.00 Rupiah


perbaikan = ------- -------
W'

4. Operator = ( 1 Orang / Jam ) x U1 L 12,142.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,285.71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 280,553.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 316,221.18 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 12.50 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 12,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 9,285.71 Rp./Jam
4. Bahan Bakar Bensin Mb 9,000.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan LIGHT TRUCK 3-4 M3
2 Tenaga Pw 125.0 HP
3 Kapasitas Cp 4.0 M3
4 Alat Yang Dipakai : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat (*) B 220,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 22,000,000 Rupiah
i x (1 + i)^A
2. Faktor Angsuran Modal = ---------- D 0.28085 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
(B-C)xD
a. Biaya Pengembalian Modal = - - - - - - - - - - E 27,804.55 Rupiah
W
0.002 x B
b. Asuransi, dll = ----------- F 220.00 Rupiah
W

Biaya Pasti per Jam = (E+F) G 28,024.55 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 191,250.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,875.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 16,500.00 Rupiah


perbaikan = -----------------
W

4. Operator = ( 1 Orang / Jam ) x U1 L 12,142.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,285.71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 276,053.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 304,078.12 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 12.50 % / Tahun
2. Upah Operator / Sopir U1 12,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 9,285.71 Rp./Jam
4. Bahan Bakar Bensin Mb 9,000.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06
2. Tenaga Pw 15.0 HP
3. Kapasitas Cp 300.0 Liter
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 8,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam Alat Baru
c. Harga Alat (*) B' 8,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 800,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.33271 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 1,197.75 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 8.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 1,205.75 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 22,950.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 5,625.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 600.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 11,875.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,375.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 50,425.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 51,630.75 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 12.50 % / Tahun
2. Upah Operator / Sopir U1 11,875.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 9,375.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,000.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 5 TON E08
2. Tenaga Pw 110.0 HP
3. Kapasitas Cp 5.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 295,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam Alat Baru
c. Harga Alat (*) B' 295,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 29,500,000 Rupiah 290,503.37

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.28085 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 37,283.37 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 295.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 37,578.37 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 168,300.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 41,250.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 22,125.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 11,875.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,375.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 252,925.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 290,503.37 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 12.50 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 11,875.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 9,375.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,000.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 8 TON E09
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 450,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam Alat Baru
c. Harga Alat (*) B' 450,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 45,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.28085 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 56,872.94 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 450.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 57,322.94 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 191,250.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,875.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 33,750.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 11,875.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,375.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 293,125.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 350,447.94 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 12.50 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 11,875.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 9,375.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,000.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 145.0 HP
3. Kapasitas Cp 0.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 800,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam Alat Baru
c. Harga Alat (*) B' 800,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 80,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.28085 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 101,107.45 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 800.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 101,907.45 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 221,850.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 54,375.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 60,000.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 11,875.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,375.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 357,475.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 459,382.45 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 12.50 % / Tahun
2. Upah Operator / Sopir U1 11,875.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 9,375.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,000.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan FLAT BED TRUCK 3-4 M3 E11
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 4.0 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 250,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam Alat Baru
c. Harga Alat (*) B' 250,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 25,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.28085 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 31,596.08 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 250.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 31,846.08 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 191,250.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,875.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 18,750.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 11,875.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,375.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 278,125.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 309,971.08 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 12.50 % / Tahun
2. Upah Operator / Sopir U1 11,875.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 9,375.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,000.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
PEMERINTAH : KABUPATEN MANGGARAI TIMUR
DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan STAMPER E25
2. Tenaga Pw 5.0 HP
3. Kapasitas Cp 0.200 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 20,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 1,000.0 Jam Alat Baru
c. Harga Alat (*) B' 20,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 2,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.33271 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 5,988.74 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 40.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 6,028.74 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 7,650.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 1,875.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 3,000.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 11,875.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9,375.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 33,775.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 39,803.74 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 12.50 % / Tahun
2. Upah Operator / Sopir U1 11,875.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 9,375.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,000.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
SATUAN KERJA : DINAS PERTANIAN
PROGRAM : PENINGKATAN PRODUKSI PERTANIAN
PAKET : PEMBANGUNAN JALAN USAHA TANI (JUT) BUGIS-GOLO KACA
LOKASI : BORONG, KELURAHAN RANA LOBA KEC. BORONG
SUMBER DANA : DANA ALOKASI UMUM (DAU)
TAHUN ANGGARAN : 2017
JENIS KONSTRUKSI : LAPEN

DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA


BIAYA
No. URAIAN ALAT KO HP KAP. HARGA SEWA KET.
DE ALAT 1 ALAT/JAM
(Rp.) (di luar PPN)

1 ASPHALT MIXING PLANT E01 220.0 50.0 T/Jam 2,750,000,000 #REF! #REF!

2 ASPHALT FINISHER E02 50.0 5.0 Ton 950,000,000 #REF! #REF!

3 ASPHALT SPRAYER E03 15.0 800.0 Liter 60,000,000 #REF! #REF!

4 BULLDOZER 100-150 HP E04 140.0 - - 1,200,000,000 #REF! #REF!

5 COMPRESSOR 4000-6500 L\M E05 80.0 - - 275,000,000 #REF! Alat Baru

6 CONCRETE MIXER 0.3-0.6 M3 E06 15.0 300.0 Liter 8,000,000 52,129.86 Alat Baru

7 CRANE 10-15 TON E07 150.0 25.0 Ton 500,000,000 #REF! Alat Baru

8 DUMP TRUCK 5 TON E08 110.0 5.0 Ton 295,000,000 288,508.73 Alat Baru

9 DUMP TRUCK 8 TON E09 125.0 8.0 Ton 450,000,000 348,059.55 Alat Baru

10 EXCAVATOR 80-140 HP E10 145.0 0.5 M3 800,000,000 456,469.06 #REF!

11 FLAT BED TRUCK 3-4 M3 E11 125.0 4.0 M3 250,000,000 307,582.69 #REF!

12 GENERATOR SET E12 220.0 180.0 KVA 325,000,000 #REF! #REF!

13 MOTOR GRADER >100 HP E13 125.0 - - 1,425,000,000 #REF! Alat Baru

14 TRACK LOADER 75-100 HP E14 95.0 1.5 M3 1,350,000,000 #REF! Alat Baru

15 WHEEL LOADER 1.0-1.6 M3 E15 125.0 1.5 M3 1,250,000,000 509,967.00 #REF!

16 THREE WHEEL ROLLER 6-8 T E16 60.0 8.0 Ton 250,000,000 185,463.94 #REF!

17 TANDEM ROLLER 6-8 T. E17 60.0 8.0 Ton 500,000,000 #REF! #REF!

18 TIRE ROLLER 8-10 T. E18 60.0 10.0 Ton 825,000,000 #REF! Alat Baru

19 VIBRATORY ROLLER 5-8 T. E19 60.0 8.0 Ton 915,000,000 #REF! #REF!

20 CONCRETE VIBRATOR E20 3.0 - - 7,500,000 31,164.89 #REF!

21 STONE CRUSHER E21 125.0 15.0 T/Jam 250,000,000 #REF! #REF!

22 WATER PUMP 70-100 mm E22 6.0 - - 7,500,000 #REF! #REF!

23 WATER TANKER 3000-4500 L. E23 125.0 4,000.0 Liter 200,000,000 #REF! Alat Baru

24 PEDESTRIAN ROLLER E24 11.0 1.0 Ton 90,000,000 #REF! #REF!

25 STAMPER E25 5.0 0.2 Ton 20,000,000 40,565.35 #REF!


ANALISA LUMP SUM UNTUK MOBILISASI

PEMERINTAH : KABUPATEN MANGGARAI TIMUR


DINAS : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
PROGRAM/KEGIATAN : PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR /
NORMALISASI SALURAN SUNGAI
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
LOKASI : KELURAHAN NGGALAK LELENG , KECAMATAN POCO RANAKA
TAHUN ANGGARAN : 2023

Jenis Pekerjaan : Mobilisasi dan Demobilisasi


Satuan Pekerjaan : Ls

Prakiraan Harga Jumlah


No Komponen Satuan Kwantitas Satuan Harga
Rp Rp

A FASILITAS KONTRAKTOR
1 Base Camp Ls 1.00 500,000.00 500,000.00

B MOBILISASI
1 Mobilisasi Personil Ls 1.00 300,000.00 300,000.00
2 Mobilisasi Alat Ls 1.00 2,000,000.00 2,000,000.00

C DEMOBILISASI ls 1.00 2,300,000.00 2,300,000.00

Jumlah Harga Satuan 5,100,000.00


ANALISA LUMPSUM PENYELENGGARAAN SMK3 KONSTRUKSI

SATUAN KERJA : PEKERJAAN UMUM DAN PERUMAHAN RAKYAT


PROGRAM / KEGIATAN PEMBANGUNAN DAN REHABILITASI INFRASTRUKTUR SUMBER DAYA AIR / NORMALISASI SALURAN SUNGAI
:
PAKET : REHABILITASI JARINGAN IRIGASI DI. WAE REBAK DAN DI. WAE RODA
TAHUN ANGGARAN : 2023
ITEM PEKERJAAN : BIAYA SMK3 KONSTRUKSI
SATUAN PEMBAYARAN : LS

Harga Satuan Jumlah


No. Komponen Satuan Volume Komponen Harga Satuan Keterangan
( Rupiah ) ( Rupiah )

A. PENYIAPAN RK3K
1. Pembuatan manual, prosedur, instruksi kerja LS 1.00 500,000.00 500,000.00

B. SOSIALISASI DAN PROMOSI K3


1. Pengarahan K3 ( Safety Briefing ) LS 1.00 1,000,000.00 1,000,000.00

C. ALAT PELINDUNG KERJA


1. Pembatas Area ( Restricted Area ) LS 1.00 1,000,000.00 1,000,000.00

D. ALAT PELINDUNG DIRI


1. Topi Pelindung ( Safety Helmet ) bh 20.00 70,000.00 1,400,000.00
2. Pelindung Mata ( Goggles, Spectacles ) bh 150,000.00 -
3. Pelindung Pernapasan dan mulut ( Masker ) bh 20.00 2,000.00 40,000.00
4. Sarung Tangan ( Safety Gloves ) bh 20.00 10,000.00 200,000.00
5. Sepatu Keselamatan ( Safety Shoes ) bh 20.00 100,000.00 2,000,000.00
6. Rompi Keselamatan ( Safety Vest ) bh 20.00 65,000.00 1,300,000.00

E. ASURANSI DAN PERIJINAN


1. BPJS Ketenagakerjaan dan Kesehatan Kerja Ls 1,245,346 - Tabel 1

F. PERSONIL K3
1. Petugas P3K OB 1.00 1,000,000.00 1,000,000.00
2. Petugas pengatur lalu lintas OB 0.00 400,000.00 -

G. FASILITAS SARANA KESEHATAN


1. Peralatan P3K ( Kotak P3K, obat luka, perban,Masker dl Ls 1.00 1,000,000.00 1,000,000.00

H. RAMBU - RAMBU
1. Rambu Peringatan bh 140,000.00 -
2. Rambu Informasi bh 140,000.00 -
3. Tongkat pengatur lalu lintas (Warning Lights Stick) bh 200,000.00 -
4. Kerucut lalu lintas ( Traffic Cone ) bh 175,000.00 -

I. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO K3


1. Pelaporan dan penyelidikan insiden bh 1.00 1,000,000.00 1,000,000.00

JUMLAH HARGA SATUAN ( A + B + C + D + E + F + G + H + I ) 10,440,000.00