LAPORAN BIM BULAN JUNI - JULl 2020

PROYEK SEMARANG DEMAK


DIVISI INFRASTRUKTUR 1
LAPORAN PERHITUNGAN VOLUME (BIM VS QS)
➢ Pekerjaan Civil Mainroad
Timbunan
Sta No Mata Pembayaran Item Pekerjaan Total Kuantitas BIM Total Kuantitas QS Deviasi Presentasi Progress (%) Satuan Status
PEKERJAAN TANAH
17+325 S/D 27+000 SK. 4.2 Timbunan Tanah Untuk Preloading 550.875 442.485,83 108.389 0,80% m3
17+325 S/D 27+000 4.05 (1) Timbunan Tanah Biasa (Borrow Material) 1.446.566 1.903.178,85 - 456.613 1,32% m3
PERKERASAN
17+325 S/D 27+000 9.07 (1) Asphalt Concrete Base Course (AC Base) 8.056,04 8.931,45 - 875 1,11% m3
17+325 S/D 27+000 9.08 (1) Perkerasan Beton Tebal 30 cm 147.430,00 144.693,00 2.737 0,98% m2
17+325 S/D 27+000 9.08 (2) Lean Concrete (t = 10 cm) 150.638,10 147.839,00 2.799 0,98% m2 Update Optimasi 19 Maret 2020
17+325 S/D 27+000 9.08 (3) Lapis Drainase 23.317,19 22.176,00 1.141,19 0,95% m3

LAPIS PONDASI AGREGAT (SUBBASE)


17+325 S/D 27+000 8.01 (1) Lapis Pondasi Agregat Kelas A 6.573,74 6.373,99 199,75 0,97% m3
17+325 S/D 27+000 8.01 (2) Lapis Pondasi Agregat Kelas B 18.630,35 19.074,76 - 444 1,02% m3

Catatan :
- Perhitungan ini update per 19 Maret 2020 (Mainroad)
- Desain gambar masih desain Optimasi, gambar desain dari perencana (DED) belum fix
LAPORAN PERHITUNGAN VOLUME (BIM VS QS)
➢ Pekerjaan Jembatan Buyaran
LAPORAN PERHITUNGAN VOLUME (BIM VS QS)
➢ Pekerjaan Box
BOX
Sta No Mata Pembayaran Item Pekerjaan Total Kuantitas BIM Total Kuantitas QS Deviasi Presentasi Progress (%) Satuan

22+400 (3x3) 10.01 (11) Beton Struktur Kelas C-2 (Gorong - gorong kotak) 357,0 0 357 0,00% m3
Tul Ulir D13 3.459,0 0 3.459 0,00% kg
Batang Baja T ulangan Ulir
10.02 (2) Tul Ulir D19 21.965,0 0 21.965 0,00% kg
BJT D-40
Tul Ulir D22 35.487,0 0 35.487 0,00% kg
26+797 (3x3) 10.01 (11) Beton Struktur Kelas C-2 (Gorong - gorong kotak) 390,6 0 391 0,00% m3
Tul Ulir D13 4.796,0 0 4.796 0,00% kg
Batang Baja T ulangan Ulir
10.02 (2) Tul Ulir D19 23.960,0 0 23.960 0,00% kg
BJT D-40
Tul Ulir D22 38.290,0 0 38.290 0,00% kg
24+400 (7x4,6) 10.01 (11) Beton Struktur Kelas C-2 (Gorong - gorong kotak) 390,6 0 391 0,00% m3
Tul Ulir D13 10.458,0 0 10.458 0,00% kg
Batang Baja T ulangan Ulir
10.02 (2) Tul Ulir D16 827,0 0 827 0,00% kg
BJT D-40
Tul Ulir D25 12.000,0 0 12.000 0,00% kg
18+376 (3x3) 10.01 (11) Beton Struktur Kelas C-2 (Gorong - gorong kotak) 298,6 0 299 0,00% m3
Tul Ulir D13 3.661,0 0 3.661 0,00% kg
Batang Baja T ulangan Ulir
10.02 (2) Tul Ulir D19 18.082,0 0 18.082 0,00% kg
BJT D-40
Tul Ulir D22 29.103,0 0 29.103 0,00% kg
22+250 (3x3) 10.01 (11) Beton Struktur Kelas C-2 (Gorong - gorong kotak) 390,6 0 391 0,00% m3
Tul Ulir D13 4.758,0 0 4.758 0,00% kg
Batang Baja T ulangan Ulir
10.02 (2) Tul Ulir D19 23.915,0 0 23.915 0,00% kg
BJT D-40
Tul Ulir D22 38.733,0 0 38.733 0,00% kg
19+976 (2x2) 10.01 (11) Beton Struktur Kelas C-2 (Gorong - gorong kotak) 234,2 0 234 0,00% m3
Tul Ulir D13 3.799,0 0 3.799 0,00% kg
Batang Baja T ulangan Ulir
10.02 (2) Tul Ulir D16 11.953,0 0 11.953 0,00% kg
BJT D-40
Tul Ulir D19 18.660,0 0 18.660 0,00% kg

Catatan :
- Desain gambar masih desain Optimasi, gambar desain dari perencana (DED) belum fix
LAPORAN VISUAL BIM & LAPANGAN

NO DATE ITEM PEKEREJAAN VISUAL LAPANGAN VISUAL BIM 3D


1 20-07-20 PEMBESIAN PILE CAP
JEMBATAN BUYARAN
LAPORAN VISUAL BIM & LAPANGAN

NO DATE ITEM PEKEREJAAN VISUAL LAPANGAN VISUAL BIM 3D


1 25-07-20 PVD Sta 19+150
LAPORAN APPROVAL GAMBAR KERJA (KENDALA)
NO GAMBAR 2D GAMBAR 3D
1

Lokas Kerja : Sta 20 Tantangan:


Item pekerjaan : PILE CAP dan KOLOM Perbedaan dimensi kolom dan pembesian antara
konsultan perencana dan optimasi Jembatan
Status : Open / Closed Buyaran
LAPORAN APPROVAL GAMBAR KERJA (KENDALA)
NO GAMBAR 2D GAMBAR 3D
1

Lokas Kerja : Sta 19+550 Tantangan:


Item pekerjaan : PILE CAP, KOLOM dan Adanya indikasi clash pada Abutment,Kolom dan
PIERHEAD Pierhead P4 dengan tanggul sungai
Gumayang/Wonokerto
Status : Open / Closed
LAPORAN METODE PELAKSANAAN
Visual Metode Pelaksanaan:

Lokasi Kerja : Sta. 19+550 Metode yang dilakukan:


Item pekerjaan : Pekerjaan Pile Cap Proses metode Sheet pile Jembatan Gumayang
Status : Open / Closed / Revisi
Contact us at:
Biro Sekretaris Perusahaan
PT PP (Persero) Tbk
Plaza PP – Wisma Subiyanto
Jl. Letjend. TB. Simatupang No 57
Pasar Rebo, Jakarta 13760 – Indonesia
website : www.ptpp.co.id

10