PEKERJAAN : PEMBANGUNAN WORKSHOP - BLK KOMUNITAS

PEMBERI TUGAS : KEMNAKER RI


KEJURUAN : TEKNIK INFORMATIKA
GROUP : B
NAMA LEMBAGA : PONPES ALFALAH DUKUHJATI
KOTAMADYA / KABUPATEN : INDRAMAYU
PROVINSI : JAWA BARAT
TAHUN : 2020
TANGGAL MULAI PEKERJAAN : 15 September 2020
TANGGAL SELESAI PEKERJAAN : 02 November 2020

MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8 MINGGU 9 MINGGU 10 MINGGU 11 MINGGU 12 MINGGU 13 MINGGU 14 MINGGU 15 MINGGU 16 MINGGU 17

NO. URAIAN PEKERJAAN VOLUME SAT. %


PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS

(%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%)
A PEKERJAAN PERSIAPAN
1 Papan Proyek 1,00 unt 0,12 100
2 Pek. Laporan & Dokumentasi 1,00 ls 0,11
B PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi 82,80 m3 1,42 100
2 Pek. Urug Tanah Kembali 27,60 m3 0,10 100
3 Pek. Urug Tanah Peninggian Peil Lantai (t = 10 cm) 19,55 m3 0,50 100
4 Pek. Pasir Urug
- Bawah Pondasi 11,83 m3 0,56 100
- Bawah Lantai 15,06 m3 0,71 100
C PEKERJAAN PONDASI
5 Pek. Pondasi Tapak P1 (100x100x20) 16,80 m2 1,65 100
6 Pek. Pondasi Batu Belah P2 19,29 m3 2,36 100
7 Pek. Sloof Beton (15/30) 52,58 m2 2,76 100
C PEKERJAAN STRUKTUR
C.1 STRUKTUR BETON
1 Pek. Kolom Beton K1 (30/30) 16,00 bh 7,30 100
2 Pek. Kolom Praktis KP (15/15) 11,00 bh 0,81 100
3 Pek. Balok Beton B1,B2 (20/30) 49,20 m2 3,36 100
4 Pek. Beton Balok Lintel BL (15/15), RB (15/15) 43,82 m2 2,89 100
5 Pek. Ramp Beton T = 10 cm 0,69 m2 0,15 100
6 Pek. Kolom Sopi Sopi 30/30) 26,46 m2 1,59 100
7 Pek. Balok B4 Sopi Sopi (15/20) 17,56 m2 1,21 100
8 Pek. Plat Beton Topi Topi (10/60) 21,06 m2 1,50 100
C.2 PEKERJAAN ATAP
Rangka Atap
1 L 40.40.4 366,65 kg 1,60 100
2 2 X L 50,50,5 946,30 kg 4,13 100
3 Kuda Kuda 2 x C 100.50.20.2,3 32,50 kg 0,12 100
4 Gording C 125.50.20.2,3 875,00 kg 3,19 100
5 L 50,50,5 dudukan gording 49,80 kg 0,22 100
6 Trekstang Ø12 49,65 kg 0,18 100
7 Ikatan angin Ø16 166,60 kg 0,61 100
8 Pelat sambung T 10mm 377,10 kg 1,56 100
9 Angkur Ø16 x 300 mm 64,00 bh 0,25 100
10 Bout M12 x 30 mm 608,00 bh 0,93 100
11 Cat Sincromat Rangka baja 150,00 m2 0,66 100
Penutup Atap
1 Atap Spandek t = 0.35 mm 223,19 m2 3,95 100
2 Pasang Aluminium Foil, Glaswool, Roofmesh 140,00 m2 2,77 100
3 Listplank GRC 74,60 m' 1,12
4 Plashing/ban banan atap (plester, aci, waterprofing) 6,00 m1 0,09 100
D PEKERJAAN PLAFOND
1 Plafond Gipsum 9 mm + Rangka Hollow 4/4 ; t = 0.35 116,49 m2 2,41 25
2 Plafond Calsiboard 4,5 mm + Rangka 55,51 m2 1,09 25
3 Lis Gipsum 5 cm 94,85 m' 0,35
E PEKERJAAN PASANGAN
1 Pasangan Dinding Bata 275,37 m2 5,35 50 50
2 Plester + Acian 545,45 m3 7,43 50 50
3 Pasangan Rolaag Bata 19,80 m' 0,35 100
4 Pekerjaan Lapis cor Beton t = 5 cm bawah lantai keramik 7,53 m3 1,22
5 Pekerjaan Rabat Beton t = 5 cm keliling bang lbr = 100 cm 2,43 m3 0,39
6 Pekerjaan Meja Beton Wastafel t = 8 cm 0,12 m3 0,08
7 Pasangan Keramik Lantai 40/40 Polished 136,40 m2 2,64
8 Pasangan Keramik Lantai 30/30 UnPolished (rabat) 52,00 m2 0,98
9 Pasangan Keramik Lantai 20/20 Unpolished 3,04 m2 0,06
10 Pasangan Plint Keramik Lantai 40/10 polished 97,40 m' 0,97
MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8 MINGGU 9 MINGGU 10 MINGGU 11 MINGGU 12 MINGGU 13 MINGGU 14 MINGGU 15 MINGGU 16 MINGGU 17

NO. URAIAN PEKERJAAN VOLUME SAT. %


PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS

(%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%)
11 Pasangan Keramik Bak & Meja Wastafel 20/20 Polished 1,77 m2 0,03
12 Pasangan Keramik Dinding 30/60 Polished 5,29 m2 0,22
13 Pasangan keramik dinding 40 x40 cm Kolom Entrace 5,12 m2 0,10
14 Pek. Logo & Tulisan 1,00 ls 0,54
15 Tali Air 25,00 m1 0,07
16 List Profil Dinding 27,90 m1 0,29
F PEKERJAAN KUSEN PINTU & JENDELA
1 Kusen/Pintu type P1 1,00 unt 0,93
2 Kusen/Pintu type P2 4,00 unt 1,75
3 Kusen/Pintu type P3 (Spandrel) 1,00 unt 0,45
4 Kusen/Jendela type J1 1,00 unt 0,42
5 Kusen/Jendela type J2 9,00 unt 4,10
6 Kusen/Jendela type J3 1,00 unt 0,24
7 Kusen/Jendela type BV 4,00 unt 0,19
8 Tralis Jendela (Besi begel) 34,10 m2 1,59
G PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Interior 272,73 m2 1,40
2 Pek. Pengecatan Dinding Exterior 272,73 m2 1,20
3 Pek. Pengecatan Plafond 172,00 m2 0,58
4 Pek. Pengecatan Listplank 22,38 m2 0,13
H PEKERJAAN PLUMBING & SANITAIR
1 Instalasi Pipa PVC AW 4" 16,00 m' 0,42 100
2 Instalasi Pipa PVC AW 2" 12,00 m' 0,11 100
3 Instalasi Pipa PVC AW 3/4" 20,00 m' 0,08 100
4 Instalasi Pipa PVC AW 1/2" 15,00 m' 0,05 100
5 Septic Tank dan Rembesan 1,00 unt 1,12 100
6 Pemasangan Closed Jongkok 1,00 bh 0,11
7 Pemasangan Kran Air 2,00 bh 0,04
8 Pemasangan Wastafel + Kran 2,00 bh 0,53
9 Pemasangan Cermin Wastafel 100x200 1,00 unt 0,05
I PEKERJAAN LISTRIK
1 Penyambungan Daya Listrik 5500,00 VA 1,79
2 Perijinan Sertifikat Layak Operasi (SLO) 5500,00 VA 0,42
3 Panel Listrik (Panel terbuat dari Besi dan isi 11 MCB) 1,00 unt 0,28
4 Pek. Instalasi Kabel Feeder NYY 4x10 mm2 2,00 m' 0,04 50
5 Pek. Instalasi Penerangan & Power NYM 3x2,5 mm2 + conduit 66,00 ttk 2,46 50
6 Pek. Instalasi Power AC 2,00 ttk 0,07
7 Pemasangan Lampu TKI 2x36W 16,00 bh 1,19
8 Pemasangan Lampu Baret Kotak 18/22W 7,00 bh 0,31
9 Pemasangan Lampu E27ESS 8 Watt + DL 4'' 3,00 bh 0,11
10 Pemasangan Saklar Engkle 5,00 bh 0,05
11 Pemasangan Saklar Double 4,00 bh 0,04
12 Pemasangan Stop Kontak Single 9,00 bh 0,08
13 Pemasangan Stop Kontak Ganda 16,00 bh 0,14
14 Pemasangan Stop Kontak AC 2,00 bh 0,03
15 Pemasangan AC split wall 2 PK 2,00 unit 2,16
16 Grounding (max 2 Ohm) 1,00 lot 0,29
100 500