Anda di halaman 1dari 6

KEGIATAN

SALURAN DRAINASE RT 1 RW 1 PEMBANGUNAN SARANA


PRASARANA DESA TA
PANJANG (M): 100.0
2017

PROPINSI
Sulawesi tengah
KABUPATEN
0.30 Morowali utara
PLASTERAN 1:4 KECAMATAN
Mori atas
DESA
Ensa
LOKASI
SULING- SULING
RT 1 RW 1
0.30
JENIS SARANA
0.50 PAS. BATU BELAH 1:5
Saluran Drainase

0.20 GAMBAR
PASIR URUG
POTONGAN
0.05
DIBUAT OLEH

0.35 PELAKSNA KEGIATAN


DIPERIKSA OLEH

DETAIL SALURAN DRAINASE DPL


IRNOVIA
B.PAKPAHAN,ST.,M.Eng
DIKETAHUI OLEH

KADES
Kabupaten :Morowali utara Jenis Prasaran Saluran Drainase
Kecamatan :Mori atas Take Off Sheet Lokasi RT 1 RW 1
Desa :Ensa Volume 100 M

a Volume galian tanah


Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar = 0.35 m
Tebal = 0.20 m
Volume galian
= 100 X 0.35 X 0.2 = 7.0 m³
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar = 0.35 m
Tebal = 0.20 m
Volume galian
= 100 X 0.35 X 0.2 = 7.0 m³
Volume galian total = 14.0 m³

b Volume urugan pasir


Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar = 0.35 m
Tebal = 0.05 m
Volume urugan
= 100 X 0.35 X 0.05 = 1.8 m³
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar = 0.35 m
Tebal = 0.05 m
Volume urugan
= 100 X 0.35 X 0.05 = 1.8 m³
Volume urugan total = 3.5 m³

c Volume batu belah


Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar atas = 0.30 m
Lebar bawah = 0.35 m
Tinggi talud = 0.30 m
Tinggi pondasi = 0.20 m
Volume batu belah
{(0.3 + 0.35)/2} x 0.3 x 100 = 9.8 m³
0.35 x 0.2 x 100 = 7.0 m³
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar atas = 0.30 m
Lebar bawah = 0.35 m
Tinggi talud = 0.30 m
Tinggi pondasi = 0.20 m
Volume batu belah
{(0.3 + 0.35)/2} x 0.3 x 100 = 9.8 m³
0.35 x 0.2 x 100 = 7.0 m³
Volume total = 33.5 m³

d Volume plesteran
Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar = 0.30 m
Volume plesteran
(0,1 + 0.3) x 100 = 40.0 m²
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar = 0.30 m
Volume plesteran
(0,1 + 0.3) x 100 = 40.0 m²
Volume plesteran total = 80.0 m²

f Langsiran material
Pekerja langsiran (1 m³ = 0,5 HOK)
Bahan = 64.3 m³
Pekerja = 32.1 HOK

Tanggal Survei :02-Okober-2022 Dibuat oleh :


Mahasiswa KKPT
PERHITUNGAN VOLUME PEKERJAAN, ANALISA HARGA SATUAN &
BIAYA
Uraian Pekerjaan Volume Satuan Harga Satuan Total Biaya

I Pekerjaan galian tanah 14.0 m³


(Analisa P.02.a)
0.563 Pekerja 7.9 HOK 120,000 948,000
0.025 Mandor 0.4 HOK 150,000 60,000
Total biaya 1,008,000

II Pekerjaan urugan pasir 3.5 m³


(Analisa T.14.c)
1.2 Pasir urug 4.2 m³ -
0.4 Pekerja 1.4 HOK 120,000 168,000
0.04 Mandor 0.14 HOK 150,000 21000
Total biaya 189,000

III Pasangan batu belah 1 : 5 33.5 m³


(Analisa P.01.C.a.1)
1.17 Batu belah 39.2 m³ 290,000 11,366,550
2.352 Semen 50 Kg 78.8 Zak 63,000 4,963,896
0.5654 Pasir muntilan 18.9 m³ 360,000 6,818,724
1.18 Pekerja 39.5 HOK 120,000 4.740.000
0.59 Tukang 19.8 HOK 150,000 2.970.000
0.1 Kepala tukang 3.4 HOK 180,000 612,000
0.1 Mandor 3.4 HOK 150,000 510,000
Total biaya 1.152,85917

IV Plesteran 1 PC : 4 PS, 15 mm 80.0 m²


(SNI 03 - 2837 - 2008)
0.125 Semen 50 Kg 10.0 Zak 63,000 630,000
0.024 Pasir muntilan 1.9 m³ 360,000 691,200
0.3 Pekerja 24.0 HOK 120,000 2.880.000
0.15 Tukang 12.0 HOK 150,000 1.800.000
0.015 Kepala tukang 1.2 HOK 180,000 216.000
0.015 Mandor 1.2 HOK 150,000 180,000
Total biaya 810.910,08
REKAP KEBUTUHAN BAHAN, ALAT DAN UPAH
No Uraian Volume Satuan

1 Pasir urug 4.2 = 5.0 m³


2 Batu belah 39.2 = 40.0 m³
3 Semen 50 Kg 88.8 = 89.0 Zak
4 Pasir muntilan 20.9 = 21.0 m³
5 Pekerja 72.8 = 73.0 HOK
6 Tukang 31.8 = 32.0 HOK
7 Kepala tukang 4.6 = 5.0 HOK
8 Mandor 5.0 = 6.0 HOK
9 Pekerja langsiran 32.1 = 33.0 HOK
RENCANA ANGGARAN BIAYA
DESA ENSA KECAMATAN MORI ATAS TAHUN
ANGGARAN 2022

Bidang : Pelaksanaan Pembangunan Desa


Kegiatan : Saluran Drainase
Lokasi : Desa Ensa

Rincian Pendanaan

Harga Satuan Jumlah


Uraian Volume Satuan
Rp Rp
Saluran Drainase RT 1 RW 1 Vol= 100 m 35,143,000

Belanja Barang dan Jasa 8,990,000


Upah Tenaga Kerja 8,990,000
Pekerja 73.0 HOK 120,000 8.760.000
Tukang 32.0 HOK 150,000 4.800.000
Kepala tukang 5.0 HOK 180,000 900.000
Mandor 6.0 HOK 150,000 900.000
Pekerja langsiran 33.0 HOK 100,000 3.300.000
1.800.016,86
Belanja Modal 26,153,000
Matrial 25,617,000
Pasir urug 5.0 m³ 170,000 850,000
Batu belah 40.0 m³ 290,000 11,600,000
Semen 50 Kg 89.0 Zak 63,000 5,607,000
Pasir muntilan 21.0 m³ 360,000 7,560,000

Alat 216,000
Cetok 1.0 Set 14,000 14,000
Ember plastik (5 liter) 2.0 Buah 10,000 20,000
Sekop 1.0 Buah 91,000 91,000
Cangkul 1.0 Buah 91,000 91,000

Sewa molen Hari 250,000 -


Prasasti 1.0 Ls 300,000 300,000
Papan Proyek 1.0 Ls 20,000 20,000
87,129,00