Anda di halaman 1dari 1

MINGGU KE 7 PERIODE : 5 OKTOBER 2021 S/D 11 OKTOBER 2021

NOMOR SPK : 445/75.a/KONTRAK-TK.PANAS/DISPAR-TW/VIII/2021


TANGGAL SPK : 24 AGUSTUS 2021
PENGAWAS : CV. RELOKA KARYA KONSULTAN
TERHITUNG : 24 AGUSTUS 2021
LAPORAN REALISASI MINGGUAN MASSA KONTRAK : 120 (SERATUS DUA PULUH) HARI KALENDER ATAU 17 MING.
PAKET : PEMBANGUNAN TALUD MINGGU LALU = 8.24%
LOKASI : ROSWAR MINGGU INI = 5.84%
T.A : 2020 KOMULATIF = 14.08%

REALISASI S/D REALISASI S/D KOMULATIF S/D


HARGA. SATUAN JUMLAH HARGA
NO DAFTAR ITEM PEKERJAAN SAT VOL. RIL BOBOT MINGGU LALU MINGGU INI MINGGU INI
(Rp) SATUAN (Rp)
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pas. Bouwplank M 250.00 25,700.00 6,425,000 0.69% 250 0.689% 0 0.00% 250 0.689%
2 Papan Nama Pekerjaan Ls 1.00 500,000.00 500,000 0.05% 1 0.05% 0 0.00% 1 0.05%
3 Gudang Semen dan Peralatan M2 9.00 755,200.00 6,796,800 0.73% 9 0.73% 0 0.00% 9 0.73%
2 Administrasi, Dokumen dan Pelaporan Ls 1.00 5,500,000.00 5,500,000 0.59% 0.25 0.15% 0.05 0.03% 0.3 0.18%
3 Keselamatan Dan kesehatan Kerja (K3) Ls 1.00 19,094,124.45 19,094,124 2.05% 0.16 0.33% 0.08 0.16% 0.24 0.49%

Jumlah Pekerjaan Persiapan 38,315,924.45 4.11% 1.95% 0.19% 2.14%


III PEKERJAAN PASANGAN DAN BETON
1 Galian Tanah M3 220.00 227,920.00 50,142,400.00 5.38% 85 2.077% 15.00 0.37% 100 2.44%
2 Urugan Pasir Bawah pondasi M3 10.00 813,933.56 8,139,336 0.87% 2 0.17% 2.00 0.17% 4 0.35%
3 Pasangan Batu Kosong M3 40.00 1,017,416.95 40,696,678.00 4.36% 8 0.87% 8.00 0.87% 16 1.75%
4 Pas. Batu Kali Talud 1 Pc 3 Psr M3 325.00 1,972,460.66 641,049,715 68.73% 15 3.17% 20.00 4.23% 35 7.40%
5 Urugan Tanah Kembali M3 70.12 122,375.00 8,581,052.47 0.92% 0 0.00% 0.00 0.00% 0 0.00%
6 Cor Beton Tulangan 1 2 3 M3 25.00 2,900,677.45 72,516,936 7.77% 0 0.000% 0.00 0.00% 0 0.00%
7 Plesteran Mata Sapi 1 2 M2 480.00 142,230.59 68,270,685 7.32% 0 0.00% 0.00 0.00% 0 0.00%
Jumlah Pekerjaan Pas. & Beton 889,396,802.82 95.36% 6.30% 5.64% 11.94%
II PEKERJAAN AKHIR
1 Pek. Pembersihan Akhir Ls 1.00 5,000,000.00 5,000,000.00 0.54% 0 0.00% 0 0.00% 0 0.00%
Jumlah Pekerjaan Akhir 5,000,000.00 0.54% 0.00% 0.00% 0.00%
Jumlah Bobot 100.00% 8% 5.84% 14%

MENGETAHUI; DIPERISKA; DIBUAT;


PEJABAT PEMBUAT KOMITMEN CV. RELOKA KARYA KONSULTAN CV. MEYAK INDAH

DIANA ARMAYANTI, S. KOM Reinhaed Gloria Ba'ka, St. SIPORA B. MANDACAN


Konsultan Pengawas DITREKTRIS