CONTOH REKAPITULASI RAB

JUMLAH HARGA BOBOT


NO URAIAN PEKERJAAN
(RP) %

A PEKERJAAN PENDAHULUAN 26,651,680.00 7.61


B PEKERJAAN PONDASI 53,663,264.00 15.32
C PEKERJAAN STRUKTUR 100,000,000.00 28.55
D PEKERJAAN DINDING BATA 40,000,000.00 11.42
E PEK. KUSEN, OINTU, JENDELA, DAN AKSESORIS 25,000,000.00 7.14
F PEKERJAAN INSTALASIS LISTRIK 10,000,000.00 2.85
G PEKERJAAN SANITAIR 15,000,000.00 4.28
H PEKERJAAN ATAP BETON 60,000,000.00 17.13
I PEKERJAAN FINISHING 20,000,000.00 5.71
JUMLAH= 350,314,944.00 100.00

TIME SCHEDULE MINGGUAN

JUMLAH HARGA BOBOT


NO URAIAN PEKERJAAN MAR'17
(RP) %
1 2
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.61 3.75 3.75

B PEKERJAAN PONDASI 53,663,264.00 15.32

C PEKERJAAN STRUKTUR 100,000,000.00 28.55

D PEKERJAAN DINDING BATA 40,000,000.00 11.42

E PEK. KUSEN, OINTU, JENDELA, DAN AKSESORIS 25,000,000.00 7.14

F PEKERJAAN INSTALASIS LISTRIK 10,000,000.00 2.85

G PEKERJAAN SANITAIR 15,000,000.00 4.28

H PEKERJAAN ATAP BETON 60,000,000.00 17.13

I PEKERJAAN FINISHING 20,000,000.00 5.71


JUMLAH= 350,314,944.00 100.00
RENCANA PROGRES MINGGUAN (%)= 0.00 3.75 3.75
RENCANA PROGRES KOMULATIF (%)= 0.00 3.75 7.50

REALISASI PROGRES MINGGUAN (%)=


REALISASI PROGRES KOMULATIF MINGGUAN (%)=

SELISIH (DEVIASI) MINGGUAN (%)=


SELISISIH (DEVIASI) KOMULATIF (%)=
WAKTU PELAKSANAAN PEKERJAAN = 4 BULAN
MAR'17 APR'17 MEI'17
3 4 1 2 3 4 1 2 3 4

5.03 5.03 5.03

7.04 7.04 7.04 7.04

2.81 2.81 2.81 2.81

1.41 1.41 1.41 1.41 1.41 1.41

0.6 0.6 0.6 0.6 0.6

0.53 0.53 0.53 0.53 0.53


3.10 3.10 3.10 3.10

1.13

5.03 5.03 12.07 11.26 11.26 12.39 8.45 5.64 5.64 5.36
12.53 17.56 29.63 40.89 52.15 64.54 72.99 78.63 84.27 89.63
JUN'17 KET
1 2 3 4

0.6 0.6

0.53 0.53 0.53


3.10

1.13 1.13 1.13 1.13

5.36 2.26 1.66 1.13


94.99 97.25 98.91 100.0