PEMERINTAH PROVINSI SULAWESI SELATAN

DINAS PEKERJAAN UMUM DAN TATA RUANG


Jalan Andi Pangeran Petterani No, 90 Telp (0411) 448309
Makassar - 90222

REKAPITULASI MONTHLY CERTIFICATE

NAMA PAKET : PENANGANAN PASCA BENCANA RUAS PALANGGA - SAPAYA 360 KM 1 PAKET MONTHLY CERTIFICATE (MC) - 02
NOMOR KONTRAK : 602.1/271/DPUTR-BM/V/2020 SERTIFIKAT : 02 (DUA)
TANGGAL KONTRAK : 13 MEI 2020 BULAN : JUNI
NILAI KONTRAK : Rp. 4.380.250.400,- TANGGAL : 30 Juni 2020
SUMBER DANA : APBD.I PERIODE : 02 Juni 2020 s/d 30 Juni 2020
PENYEDIA JASA : CV. TIQA CEMERLANG HALAMAN : 1 dari 7

ITEM NILAI KONTRAK JUMLAH PEMBAYARAN BOBOT


PEMB URAIAN PEKERJAAN KONTRAK AWAL BOBOT S/D BULAN BULAN INI S/D BULAN S/D BULAN ITEM PEKERJAAN
. (Rp.) (%) LALU (Rp.) (Rp.) INI (Rp.) INI (%) (%)
1 2 3 4 5 6 7 = (5+6) 8 9

1 DIVISI 1. UMUM 156,181,496.48 3.922% 35,493,828.90 6,690,000.00 42,183,828.90 1.059% 4.28%


2 DIVISI 2. DRAINASE 1,142,247,217.51 28.686% 1,932,361.60 147,845,160.55 149,777,522.15 3.761% 12.94%
3 DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 513,332,111.57 12.892% 5,523,170.94 77,023,379.99 82,546,550.93 2.073% 15.00%
4 DIVISI 7. STRUKTUR 2,097,070,520.52 52.665% - - - - -
5 DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN 73,097,969.00 1.836% - - - - -

A SUB TOTAL 3,981,929,315.08 100% 42,949,361.43 231,558,540.55 274,507,901.98 S/D BULAN LALU

B PPN (10%) X A 398,192,931.51 4,294,936.14 23,155,854.05 27,450,790.20 6.894%


1.079%
C JUMLAH TOTAL A + B 4,380,122,246.59 47,244,297.57 254,714,394.60 301,958,692.18

D DIBULATKAN C 4,380,122,000.00 47,244,000.00 254,714,000.00 301,958,000.00 BULAN INI

E MATERIAL ON SITE (MOS) Rp. -


5.815%
F JUMLAH KOTOR SERTIFIKAT BULAN INI Rp. 301,958,000.00

G POTONGAN - POTONGAN S/D BULAN INI

1 SERTIFIKAT S/D BULAN LALU (KOMULATIF) Rp. 47,244,000.00


6.894%
2 5 % JAMINAN PEMELIHARAAN ( 5% X D ) Rp. 12,735,700.00
PEMERINTAH PROVINSI SULAWESI SELATAN
DINAS PEKERJAAN UMUM DAN TATA RUANG
Jalan Andi Pangeran Petterani No, 90 Telp (0411) 448309
Makassar - 90222
NAMA PAKET : PENANGANAN PASCA BENCANA RUAS PALANGGA - SAPAYA 360 KM 1 PAKET MONTHLY CERTIFICATE (MC) - 02
NOMOR KONTRAK : 602.1/271/DPUTR-BM/V/2020 SERTIFIKAT : 02 (DUA)
TANGGAL KONTRAK : 13 MEI 2020 BULAN : JUNI
NILAI KONTRAK : Rp. 4.380.250.400,- TANGGAL : 30 Juni 2020
SUMBER DANA : APBD.I PERIODE : 02 Juni 2020 s/d 30 Juni 2020
PENYEDIA JASA : CV. TIQA CEMERLANG HALAMAN : 2 dari 7

3 30 % PENGEMBALIAN UANG MUKA Rp. 76,414,200.00 TERSISA

H JUMLAH POTONGAN ( 1 + 2 + 3 ) Rp. 136,393,900.00


93.106%
I JUMLAH BERSIH SERTIFIKAT BULAN INI TERMASUK PPN 10% (F-H) Rp. 165,564,100.00

Terbilang : #NAME?

DISETUJUI OLEH : DIPERIKSA OLEH : DIAJUKAN OLEH :


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN SUPERVISI PENYEDIA BARANG/JASA
PT. NAFA AIRFINDO KONSULTAN CV. TIQA CEMERLANG

Dr. Ir. H. ANUGRAH YASIN, ST, M.Si Ir. H. IBRAHIM PAKKI MUHAMMAD RAHUD
SITE ENGINEER DIREKTUR UTAMA
NIP. 19750824 200902 1 001
PEMERINTAH PROVINSI SULAWESI SELATAN
DINAS PEKERJAAN UMUM DAN TATA RUANG
Jalan Andi Pangeran Petterani No, 90 Telp (0411) 448309
Makassar - 90222

MONTHLY CERTIFICATE
NAMA PAKET : PENANGANAN PASCA BENCANA RUAS PALANGGA - SAPAYA 360 KM 1 PAKET MONTHLY CERTIFICATE (MC) - 02
NOMOR KONTRAK : 602.1/271/DPUTR-BM/V/2020 SERTIFIKAT : 02 (DUA)
TANGGAL KONTRAK : 13 MEI 2020 BULAN : JUNI
NILAI KONTRAK : Rp. 4.380.250.400,- TANGGAL : 30 Juni 2020
SUMBER DANA : APBD.I PERIODE : 02 Juni 2020 s/d 30 Juni 2020
PENYEDIA JASA : CV. TIQA CEMERLANG HALAMAN : 3 Dari 7

DIVISI 1. UMUM JUMLAH KONTRAK AWAL Rp 156,181,496.48


KONTRAK AWAL REALISASI
ITEM S/D BULAN LALU BULAN INI S/D BULAN INI
URAIAN PEKERJAAN SAT.
PEMB. VOLUME HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.) BOBOT % JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME BOBOT %
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6=4x5 7 8 9=5x8 10 11 = 5 x 10 12 = 8 + 10 13 = 9 + 11 14

1.2 Mobilisasi LS 1.00 48,620,000.00 48,620,000.00 1.221% 0.30 14,586,000.00 - - 0.30 14,586,000.00 0.366%
1.8 Manajemen dan Keselamatan Lalu Lintas LS 1.00 40,772,763.00 40,772,763.00 1.024% 0.30 12,231,828.90 - - 0.30 12,231,828.90 0.307%
1.17 Pengaman Lingkungan Hidup -
1.17.(2a) Pengujian Vibrasi Lingkungan Hidup bh 9.00 250,000.00 2,250,000.00 0.057% - - 3.00 750,000.00 3.00 750,000.00 0.00
1.17.(2b) Pengujian tingkat getaran kendaraan bermotor bh 9.00 250,000.00 2,250,000.00 0.057% - - 3.00 750,000.00 3.00 750,000.00 0.00
1.17.(3a) Pengujian NoX bh 9.00 340,000.00 3,060,000.00 0.077% - - 3.00 1,020,000.00 3.00 1,020,000.00 0.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) bh 9.00 340,000.00 3,060,000.00 0.077% - - 3.00 1,020,000.00 3.00 1,020,000.00 0.00
1.17.(3c) Pengujian Karbondioksida (CO2) bh 9.00 340,000.00 3,060,000.00 0.077% - - 3.00 1,020,000.00 3.00 1,020,000.00 0.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu bh 9.00 340,000.00 3,060,000.00 0.077% - - 3.00 1,020,000.00 3.00 1,020,000.00 0.00
1.17.(3g) Pengujian Timah Hitam (Pb) bh 9.00 370,000.00 3,330,000.00 0.084% - - 3.00 1,110,000.00 3.00 1,110,000.00 0.00
1.19 Keselamatan dan Kesehatan Kerja LS 1.00 28,920,000.00 28,920,000.00 0.726% 0.30 8,676,000.00 - - 0.30 8,676,000.00 0.218%
1.2 Pengujian Tanah -
1.20.(2) Sondir termasuk Laporan M1 66.00 269,677.78 17,798,733.48 0.447% - - - - - - -

TOTAL HARGA 156,181,496.48 3.922% - - - -


DIVISI 1. UMUM TOTAL PEMBAYARAN - - 35,493,828.90 6,690,000.00 42,183,828.90 1.059%
PERSENTASE 100% 100% 0.23 4.28% 27.01% 27.01%
DISETUJUI OLEH : DIPERIKSA OLEH : DIAJUKAN OLEH :
DIREKSI PENGAWAS TEKNIS LAPANGAN KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN PT. NAFA AIRFINDO KONSULTAN CV. TIQA CEMERLANG

JEFRI, ST Ir. NUR ALIMUDDIN USMAN, ST


NIP. 19680815 20071 1 042 QUANTITY ENGINEER GENERAL SUPRIMENTENDENT
PEMERINTAH PROVINSI SULAWESI SELATAN
DINAS PEKERJAAN UMUM DAN TATA RUANG
Jalan Andi Pangeran Petterani No, 90 Telp (0411) 448309
Makassar - 90222

MONTHLY CERTIFICATE
NAMA PAKET : PENANGANAN PASCA BENCANA RUAS PALANGGA - SAPAYA 360 KM 1 PAKET MONTHLY CERTIFICATE (MC) - 02
NOMOR KONTRAK : 602.1/271/DPUTR-BM/V/2020 SERTIFIKAT : 02 (DUA)
TANGGAL KONTRAK : 13 MEI 2020 BULAN : JUNI
NILAI KONTRAK : Rp. 4.380.250.400,- TANGGAL : 30 Juni 2020
SUMBER DANA : APBD.I PERIODE : 02 Juni 2020 s/d 30 Juni 2020
PENYEDIA JASA : CV. TIQA CEMERLANG HALAMAN : 4 dari 7

DIVISI 2. DRAINASE JUMLAH KONTRAK AWAL Rp. 1,142,247,217.51


KONTRAK AWAL REALISASI
S/D BULAN LALU BULAN INI S/D BULAN INI
ITEM PEMB. URAIAN PEKERJAAN SAT. HARGA SATUAN
VOLUME JUMLAH HARGA (Rp.) BOBOT % JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
(Rp.) VOLUME VOLUME VOLUME BOBOT %
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6=4x5 7 8 9=5x8 10 11 = 5 x 10 12 = 8 + 10 13 = 9 + 11 14

2.1.(1) Galian Untuk Selokan Drainase dan Saluran Air M3 2,854.80 48,299.38 137,885,070.02 3.463% 40.01 1,932,361.60 775.45 37,453,850.82 815.46 39,386,212.41 0.989%
2.2.(2) Pasangan Batu dengan Mortar M3 1,538.31 636,481.26 979,105,487.07 24.589% - - 173.44 110,391,309.73 173.44 110,391,309.73 0.03
2.3.(10) Gorong-gorong Pipa Baja Bergelombang Ton 31.04 813,681.07 25,256,660.41 0.634% - - - - - - -

TOTAL HARGA 1,142,247,217.51 28.686% - - - -


DIVISI 2. DRAINASE TOTAL PEMBAYARAN - - 1,932,361.60 147,845,160.55 149,777,522.15 3.761%
PERSENTASE 100% 100% 0.00 12.94% 13.11% 13.11%
DISETUJUI OLEH : DIPERIKSA OLEH : DIAJUKAN OLEH :
DIREKSI PENGAWAS TEKNIS LAPANGAN KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN PT. NAFA AIRFINDO KONSULTAN CV. TIQA CEMERLANG

JEFRI, ST Ir. NUR ALIMUDDIN USMAN, ST


NIP. 19680815 20071 1 042 QUANTITY ENGINEER GENERAL SUPRIMENTENDENT
PEMERINTAH PROVINSI SULAWESI SELATAN
DINAS PEKERJAAN UMUM DAN TATA RUANG
Jalan Andi Pangeran Petterani No, 90 Telp (0411) 448309
Makassar - 90222

MONTHLY CERTIFICATE
NAMA PAKET : PENANGANAN PASCA BENCANA RUAS PALANGGA - SAPAYA 360 KM 1 PAKET MONTHLY CERTIFICATE (MC) - 02
NOMOR KONTRAK : 602.1/271/DPUTR-BM/V/2020 SERTIFIKAT : 02 (DUA)
TANGGAL KONTRAK : 13 MEI 2020 BULAN : JUNI
NILAI KONTRAK : Rp. 4.380.250.400,- TANGGAL : 30 Juni 2020
SUMBER DANA : APBD.I PERIODE : 02 Juni 2020 s/d 30 Juni 2020
PENYEDIA JASA : CV. TIQA CEMERLANG HALAMAN : 5 dari 7

DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK JUMLAH KONTRAK AWAL Rp. 513,332,111.57
KONTRAK AWAL REALISASI
ITEM S/D BULAN LALU BULAN INI S/D BULAN INI
URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA
PEMB. VOLUME BOBOT % JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
(Rp.) (Rp.) VOLUME VOLUME VOLUME BOBOT %
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6=4x5 7 8 9=5x8 10 11 = 5 x 10 12 = 8 + 10 13 = 9 + 11 14

3.1.(1) Galian Biasa M3 3,652.10 23,011.78 84,041,321.74 2.111% 231.03 5,316,422.64 2,660.19 61,215,775.25 2,891.22 66,532,197.89 1.671%
3.1.(3) Galian Batu M3 878.13 99,989.86 87,804,095.76 2.205% - - 151.89 15,187,359.85 151.89 15,187,359.85 0.00
3.1.(9) Galian Perkerasan berbutir M3 697.60 116,772.29 81,460,349.50 2.046% - - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 1,820.65 37,606.76 68,468,747.59 1.719% - - - - - - -
3.3.(1) Penyiapan Badan Jalan M2 2,675.00 4,675.27 12,506,347.25 0.314% - - - - - - -
3.4.(2) Pemotongan Pohon Pilihan diameter 15 - 30 cm Buah 6.00 206,748.30 1,240,489.80 0.031% 1.00 206,748.30 3.00 620,244.90 4.00 826,993.20 0.021%
3.5.(3) Geotekstil Stabilisator (Kelas 1) M2 5,427.77 32,759.45 177,810,759.93 4.465% - - - - - - -

TOTAL HARGA 513,332,111.57 12.892% - - - -


DIVISI 3. PEKERJAAN TANAH DAN
TOTAL PEMBAYARAN - - 5,523,170.94 77,023,379.99 82,546,550.93 2.073%
GEOSINTETIK PERSENTASE 100% 100% 0.01 15.00% 16.08% 16.08%
DISETUJUI OLEH : DIPERIKSA OLEH : DIAJUKAN OLEH :
DIREKSI PENGAWAS TEKNIS LAPANGAN KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN PT. NAFA AIRFINDO KONSULTAN CV. TIQA CEMERLANG

JEFRI, ST Ir. NUR ALIMUDDIN USMAN, ST


NIP. 19750824 200902 1 001 QUANTITY ENGINEER GENERAL SUPRIMENTENDENT
PEMERINTAH PROVINSI SULAWESI SELATAN
DINAS PEKERJAAN UMUM DAN TATA RUANG
Jalan Andi Pangeran Petterani No, 90 Telp (0411) 448309
Makassar - 90222

MONTHLY CERTIFICATE
NAMA PAKET : PENANGANAN PASCA BENCANA RUAS PALANGGA - SAPAYA 360 KM 1 PAKET MONTHLY CERTIFICATE (MC) - 02
NOMOR KONTRAK : 602.1/271/DPUTR-BM/V/2020 SERTIFIKAT : 02 (DUA)
TANGGAL KONTRAK : 13 MEI 2020 BULAN : JUNI
NILAI KONTRAK : Rp. 4.380.250.400,- TANGGAL : 30 Juni 2020
SUMBER DANA : APBD.I PERIODE : 02 Juni 2020 s/d 30 Juni 2020
PENYEDIA JASA : CV. TIQA CEMERLANG HALAMAN : 6 dari 7

DIVISI 7. STRUKTUR JUMLAH KONTRAK AWAL


KONTRAK AWAL REALISASI
S/D BULAN LALU BULAN INI S/D BULAN INI
ITEM PEMB. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA
VOLUME BOBOT % JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
(Rp.) (Rp.) VOLUME VOLUME VOLUME BOBOT %
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6=4x5 7 8 9=5x8 10 11 = 5 x 10 12 = 8 + 10 13 = 9 + 11 14

7.1.(7a) Beton struktur, fc'20 Mpa M3 389.56 1,250,545.04 487,162,325.78 12.234% - - - - - - -


7.1.(8) Beton, fc'15 Mpa M3 87.19 1,182,145.00 103,071,222.55 2.588% - - - - - - -
7.1.(9) Beton Siklop, fc'15 Mpa M3 54.75 728,039.61 39,860,168.65 1.001% - - - - - - -
7.1.(10) Beton, fc'10 Mpa M3 36.48 821,711.67 29,976,041.72 0.753% - - - - - - -
7.1.(12a) Penyediaan Panel Full Depth Slab Buah 125.00 145,344.34 18,168,042.50 0.456% - - - - - - -
7.1.(12b) Pemasangan Panel Full Depth Slab Buah 125.00 24,297.19 3,037,148.75 0.076% - - - - - - -
7.3.(3) Baja Tulangan Sirip BjTS 420A Kg 56,513.65 16,076.50 908,541,694.23 22.817% - - - - - - -
7.6.(8b) Penyedian Tiang Pancang Baja Diameter 152 mm tebal 4,8 mm M1 456.00 620,083.78 282,758,203.68 7.101% - - - - - - -
7.6.(14b) Pemancangan Tiang Pancang Baja Diameter 152 mm M1 456.00 259,225.56 118,206,855.36 2.969% - - - - - - -
7.9.(1) Pasangan Batu M3 173.90 611,206.54 106,288,817.31 2.669% - - - - - - -

TOTAL HARGA 2,097,070,520.52 52.665% - - - -


DIVISI 7. STRUKTUR TOTAL PEMBAYARAN - - - - - -
PERSENTASE 100% 100% - - - -
DISETUJUI OLEH : DIPERIKSA OLEH : DIAJUKAN OLEH :
DIREKSI PENGAWAS TEKNIS LAPANGAN KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN PT. NAFA AIRFINDO KONSULTAN CV. TIQA CEMERLANG

JEFRI, ST Ir. NUR ALIMUDDIN USMAN, ST


NIP. 19680815 20071 1 042 QUANTITY ENGINEER GENERAL SUPRIMENTENDENT
PEMERINTAH PROVINSI SULAWESI SELATAN
DINAS PEKERJAAN UMUM DAN TATA RUANG
Jalan Andi Pangeran Petterani No, 90 Telp (0411) 448309
Makassar - 90222

MONTHLY CERTIFICATE
NAMA PAKET : PENANGANAN PASCA BENCANA RUAS PALANGGA - SAPAYA 360 KM 1 PAKET MONTHLY CERTIFICATE (MC) - 02
NOMOR KONTRAK : 602.1/271/DPUTR-BM/V/2020 SERTIFIKAT : 02 (DUA)
TANGGAL KONTRAK : 13 MEI 2020 BULAN : JUNI
NILAI KONTRAK : Rp. 4.380.250.400,- TANGGAL : 30 Juni 2020
SUMBER DANA : APBD.I PERIODE : 02 Juni 2020 s/d 30 Juni 2020
PENYEDIA JASA : CV. TIQA CEMERLANG HALAMAN : 7 Dari 7

DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN JUMLAH KONTRAK AWAL


KONTRAK AWAL REALISASI
ITEM S/D BULAN LALU BULAN INI S/D BULAN INI
URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA
PEMB. VOLUME BOBOT % JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
(Rp.) (Rp.) VOLUME VOLUME VOLUME BOBOT %
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6=4x5 7 8 9=5x8 10 11 = 5 x 10 12 = 8 + 10 13 = 9 + 11 14

9.2.(5) Patok Pengarah Buah 350.00 208,851.34 73,097,969.00 1.836% - - - - - - -

TOTAL HARGA 73,097,969.00 1.836% - - - -


DIVISI 9. PEKERJAAN HARIAN &
TOTAL PEMBAYARAN - - - - - -
PEKERJAAN LAIN-LAIN PERSENTASE 100% 100% - - - -
DISETUJUI OLEH : DIPERIKSA OLEH : DIAJUKAN OLEH :
DIREKSI PENGAWAS TEKNIS LAPANGAN KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN PT. NAFA AIRFINDO KONSULTAN CV. TIQA CEMERLANG

JEFRI, ST Ir. NUR ALIMUDDIN USMAN, ST


NIP. 19680815 20071 1 042 QUANTITY ENGINEER GENERAL SUPRIMENTENDENT

Anda mungkin juga menyukai