JADWAL WAKTU PELAKSANAAN (TIME SCHEDULE)

Nama Proyek : Pembangunan Rumah Dinas Wakil Bupati Nias Utara


TAHUN 2022 ( 130 HARI KALENDER )
HARGA BOBOT
NO JENIS PEKERJAAN BULAN KE - 1 BULAN KE - 2 BULAN KE - 3 BULAN KE - 4 BULAN KE - 5
MG - 19
( Rp ) % MG - 1 MG - 2 MG - 3 MG - 4 MG - 5 MG - 6 MG - 7 MG - 8 MG - 9 MG - 10 MG - 11 MG - 12 MG - 13 MG - 14 MG - 15 MG - 16 MG - 17 MG - 18
(4 Hari)

DEVISI 1

I PERSIAPAN LAPANGAN 276,141,870.00 8.844% 0.277% 0.277% 0.277% 0.277% 0.604% 0.604% 0.604% 0.604% 0.604% 0.604% 0.604% 0.604% 0.604% 0.604% 0.604% 0.277% 0.277% 0.277% 0.259%

DEVISI 2

II PENERAPAN SMKK 6,190,000.00 0.198% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010%

DEVISI 3

MASA RETENSI / PEMELIHARAAN


III PEKERJAAN STRUKTURAL 398,653,900.00 12.768% 1.592% 3.184% 3.184% 3.184% 1.624%

DEVISI 4

IV PEKERJAAN ARSITEKTUR 1,741,696,840.00 55.784% 2.323% 2.323% 2.323% 4.181% 4.181% 4.181% 4.181% 4.181% 4.181% 4.181% 4.181% 4.181% 4.181% 2.323% 2.323% 2.361%

DEVISI 5

V PEKERJAAN PLUMBING 91,257,000.00 2.923% 0.366% 0.732% 0.732% 0.732% 0.363%

DEVISI 6

VI PEKERJAAN ELEKTRIKAL 33,156,700.00 1.062% 0.133% 0.267% 0.267% 0.267% 0.129%

DEVISI 9

IX FASILITAS EKSTERIOR BANGUNAN 570,503,690.00 18.272% 0.763% 0.763% 0.763% 1.717% 1.717% 1.717% 1.717% 1.717% 1.717% 1.717% 1.717% 0.763% 0.763% 0.720%

DEVISI 10

X PEKERJAAN LAIN-LAIN 4,600,000.00 0.147% 0.005% 0.005% 0.005% 0.005% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.005% 0.005% 0.005% 0.004%

TOTAL 3,122,200,000.00 100.00%


RENCANA KEMAJUAN PEKERJAAN / MINGGU 0.292% 1.884% 5.799% 6.165% 6.997% 8.191% 6.567% 6.198% 6.652% 6.523% 6.523% 6.523% 6.523% 6.523% 6.523% 4.332% 3.378% 3.417% 0.992%
RENCANA KEMAJUAN PEKERJAAN KOMULATIF / MINGGU 0.292% 2.176% 7.975% 14.140% 21.136% 29.327% 35.894% 42.092% 48.744% 55.267% 61.790% 68.313% 74.835% 81.358% 87.881% 92.213% 95.591% 99.008% 100.000%

Asumsi : 1 Bulan = 4 Minggu Lotu, 03 Agustus 2022


1 Minggu = 7 Hari Dibuat oleh :
CV. NUNUT

FEBER VIANUS ZEBUA


Wakil Direktur - II