JADWAL PELAKSANAAN PEKERJAAN

PEMBANGUNAN RUMAH TINGGAL


YOGYAKARTA

NO. URAIAN PEKERJAAN BOBOT MGG 1 MGG 2 MGG 3 MGG 4 MGG 5 MGG 6 MGG 7 MGG 8 MGG 9 MGG 10 MGG 11 MGG 12

I PEKERJAAN TANAH 3.65% 3.65%


II PEKERJAAN STRUKTUR UTAMA
PEKERJAAN BETON PONDASI 18.89% 3.15% 3.15% 3.15% 3.15% 3.15% 3.15%
PEKERJAAN ATAP 8.59% 4.30% 4.30%
III PEKERJAAN ARSITEKTUR
LANTAI 1
PEKERJAAN PASANGAN & PLESTERAN 13.34% 6.67% 6.67%
LANTAI 2
PEKERJAAN PASANGAN & PLESTERAN 9.41% 3.14% 3.14% 3.14%
LANTAI 1
PEKERJAAN KERAMIK 4.99% 2.50% 2.50%
LANTAI 2
PEKERJAAN KERAMIK 0.27% 0.14% 0.14%
LANTAI 1
PEKERJAAN PLAFOND 3.05% 3.05%
LANTAI 2
PEKERJAAN PLAFOND 6.03% 3.01% 3.01%
LANTAI 1
PEKERJAAN PINTU DAN JENDELA DAN ASESORIES 6.95% 3.48% 3.48%
LANTAI 2
PEKERJAAN PINTU DAN JENDELA DAN ASESORIES 2.79% 1.40% 1.40%
LANTAI 1
PEKERJAAN PENGECATAN 2.42% 1.21% 1.21%
LANTAI 2
PEKERJAAN PENGECATAN 2.79% 1.39% 1.39%
IV PEKERJAAN MEKANIKAL ELEKTRIKAL
LANTAI 1
PEKERJAAN INSTALASI LISTRIK 3.32% 1.66% 1.66%
LANTAI 2
PEKERJAAN INSTALASI LISTRIK 1.90% 0.95% 0.95%
V PEKERJAAN SANITAIR
LANTAI 1
PEKERJAAN SANITAIR & INSTALASI AIR 6.98% 1.16% 1.16% 1.16% 1.16% 1.16% 1.16%
VI PEKERJAAN ASESORIS
4.62% 1.54% 1.54% 1.54%

6.80% 4.31% 4.31% 7.84% 10.15% 11.33% 11.65% 12.69% 10.13% 10.01% 6.89% 3.88%
100.00%
PROGRESS RENCANA 6.80% 11.11% 15.43% 23.26% 33.41% 44.74% 56.39% 69.08% 79.21% 89.23% 96.12% 100.00%