SCHEDULE KURVA - S

Proyek : Pembangunan Rumah Tinggal 2 Lantai


Pemilik : Bp. Sunyoto
Lokasi : Jl. Cipinang Muara 3 No.34 RT.09/15 Jakarta Timur

Maret 2019 Apr-19 Mei 2019 Juni 2019 Juli 2019 Agustus 2019
NO. URAIAN PEKERJAAN BOBOT MG-1 MG-2 MG-3 MG-4 MG-5 MG-6 MG-7 MG-8 MG-9 MG-10 MG-11 MG-12 MG-13 MG-14 MG-15 MG-16 MG-17 MG-18 MG-19 MG-20 KET
27-30 31-06 07-13 14-20 21-27 28-04 05-11 12-18 19-25 26-31 1-07 08-15 16-22 23-29 30-06 07-13 14-20 21-27 28-31 1-7

I PEKERJAAN PERSIAPAN 2.39% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%

II PEKERJAAN TANAH 0.67% 0.112% 0.112% 0.112% 0.112% 0.112% 0.112%

III PEKERJAAN PONDASI 2.03% 0.675% 0.675% 0.675%

IV PEKERJAAN BETON 25.45% 5.090% 5.090% 5.090% 5.090% 5.090%

V PEKERJAAN DINDING 23.26% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551% 1.551%

LIBUR IDUL FITRI


VI PEKERJAAN KERAMIK 10.88% 1.813% 1.813% 1.813% 1.813% 1.813% 1.813%

VII PEKERJAAN KUSEN PINTU, JENDELA DAN PARTISI 6.67% 0.952% 0.952% 0.952% 0.952% 0.952% 0.952% 0.952%

VIII PEKERJAAN ATAP 7.12% 1.425% 1.425% 1.425% 1.425% 1.425%

IX PEKERJAAN PLAFOND 3.57% 0.715% 0.715% 0.715% 0.715% 0.715%

X PEKERJAAN SANITAIR DAN PEMIPAAN 3.57% 0.446% 0.446% 0.446% 0.446% 0.446% 0.446% 0.446% 0.446%

XI PEKERJAAN KUNCI, KACA DAN PENGGANTUNG 0.62% 0.205% 0.205% 0.205%

XII PEKERJAAN PENGECATAN 7.38% 1.475% 1.475% 1.475% 1.475% 1.475%

XIII PEKERJAAN LISTRIK 2.78% 0.398% 0.398% 0.398% 0.398% 0.398% 0.398% 0.398%

XIV PEKERJAAN WATER PROOFING 0.45% 0.149% 0.149% 0.149%

XV PEKERJAAN BESI 3.17% 1.057% 1.057% 1.057%

BOBOT 100.000% 0.000% 6.276% 3.182% 8.151% 3.061% 7.705% 7.593% 2.503% 5.632% 5.632% 8.477% 8.923% 7.460% 6.184% 3.926% 5.197% 3.424% 0.399%

PROGRES RENCANA 6.276% 12.551% 15.734% 23.885% 26.946% 34.651% 42.244% 44.748% 50.379% 56.011% 56.011% 56.011% 64.488% 73.410% 80.871% 87.055% 90.980% 96.177% 99.601% 100.000%

PROGRES ACTUAL 2.250% 5.500% 9.157% 11.520% 16.670% 19.820% 26.070% 31.320% 35.170% 53.220% 61.870% 61.870% 61.870% 65.120% 65.120% 65.120% 65.120% 65.120% 65.120% 65.120%

BOBOT AKTUAL 3.250% 3.657% 2.363% 5.150% 3.150% 6.250% 5.250% 3.850% 18.050% 8.650% 0.000% 0.000% 3.250% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

Jakarta, 26 Juni 2019


Dibuat oleh,
Kontraktor

( Ferdy Ardiansyah )
CV. Kirana Satu Persada