RENCANA PEMBUATAN TEMPAT BUDIDAYA UDANG

NO URAIAN BIAYA BOBOT


M1
1 DESAIN 1,500,000 3.2% 3.2%

2 PEMBELIAN BAHAN 18,000,000 38.7%

3 PENGADAAN PERALATAN K3 3,000,000 6.5%

4 PENGUKURAN KAYU 1,000,000 2.2%

5 PEMOTONGAN KAYU 4,000,000 8.6%

6 PELUBANGAN KAYU 1,000,000 2.2%

7 PEMASANGAN KERANGKA 6,000,000 12.9%

8 PEMASANGAN PELAMPUNG 3,000,000 6.5%

9 PEMASANGAN PAPAN 6,000,000 12.9%

10 PEMASANGAN JARING 3,000,000 6.5%


46,500,000 100.0%
PROGES MINGGUAN 3.2%
AKUMULASI PROGES 3.2%
M2 M3 M4 M5 M6 M7 M8 M9

7.7% 7.7% 7.7% 7.7% 7.7%

2.2% 2.2% 2.2%

1.1% 1.1%

2.9% 2.9% 2.9%

1.1% 1.1%

2.6% 2.6%

2.2% 9.9% 9.9% 11.7% 11.7% 10.6% 1.1% 1.1% 2.6% 2.6%
5.4% 15.3% 25.2% 36.8% 48.5% 59.1% 60.2% 61.3% 63.9% 66.5%
2.6% 2.6% 2.6%

2.2% 2.2% 2.2%

4.3% 4.3% 4.3%

1.6%

2.6% 2.6% 2.6% 2.2% 2.2% 2.2% 4.3% 4.3% 4.3% 1.6%
69.0% 71.6% 74.2% 76.3% 78.5% 80.6% 84.9% 89.2% 93.5% 95.2%
1.6% 1.6% 1.6%

1.6% 1.6% 1.6%


96.8% 98.4% 100.0%