MAINTENANCE BUILDING MCC-03 CPP
WEEKLY REPORT (W-9)
DOC. NO. :
Periode: 24 s/d 30 Juni 2023
DATE PIC CHKD APVD
30/06/2023 Eric Bagus S. 0 0
1. PROGRESS KESELURUHAN
» Pencapaian progress pekerjaan pada Weeks ke-9 sebesar 11.84% dari target 16.25%.
Dimana Total pencapaian progress komulatifnya saat ini sebesar 80.62% dari rencanaan target 87.30%, sehingga pencapaian minggu ini
TERDEVIASI negatif sebesar -6.68%.
Dan untuk rencana target pencapaian di minggu ke-10 (W-10) sebesar 8.99%
PROJECT HEALTH:
100.00%
96.30%
87.30%
80.62%
71.05%
68.7…
48.47%
51.99%
37.80%
39.93%
26.99%
27.46%
17.85%
21.08%
10.01%
5.74% 9.14%
2.33% 5.74%
2.33%
2/9
REV
MAINTENANCE BUILDING MCC-03 CPP
WEEKLY REPORT (W-9)
DOC. NO. :
Periode: 24 s/d 30 Juni 2023
DATE PIC CHKD APVD
30/06/2023 Eric Bagus S. 0 0
TOTAL 8.99%
3/9
REV
MAINTENANCE BUILDING MCC-03 CPP
WEEKLY REPORT (W-9)
DOC. NO. :
Periode: 24 s/d 30 Juni 2023
DATE PIC CHKD APVD
30/06/2023 Eric Bagus S. 0 0
4. MANAJEMEN PROYEK:
- Man power HO.
Project Director 1 Org - Total hari kerja : 61 hari = 61 Man/days.
Procurement Manager 1 Org - Total hari kerja : 61 hari = 61 Man/days.
Accounting 1 Org - Total hari kerja : 61 hari = 61 Man/days.
TOTAL-1: 3 org 45,290 Man/days.
4/9
REV
MAINTENANCE BUILDING MCC-03 CPP
WEEKLY REPORT (W-9)
DOC. NO. :
Periode: 24 s/d 30 Juni 2023
DATE PIC CHKD APVD
30/06/2023 Eric Bagus S. 0 0
Direct Labour:
Structure: Welder 1 Org - Total hari kerja : 48 hari = 48 Man/days.
Fitter 1 Org - Total hari kerja : 48 hari = 48 Man/days.
Fitter 2 Org - Total hari kerja : 38 hari = 76 Man/days.
Scaffolder 1 Org - Total hari kerja : 38 hari = 38 Man/days.
Sipil: Mandor 1 Org - Total hari kerja : 42 hari = 42 Man/days.
Tukang 2 Org - Total hari kerja : 42 hari = 84 Man/days.
Helper 7 Org - Total hari kerja : 42 hari = 294 Man/days.
TOTAL-3: 15 org 630 Man/days.
GRAND TOTAL: 21 org 46,051 Man/days.
LIST VAKSINASI:
5. FABRICATION REPORT
5A. - Man power :. Man/day.
Fitter Org
Welder Org
Helper Org
TOTAL: 0 org
5/9
REV
MAINTENANCE BUILDING MCC-03 CPP
WEEKLY REPORT (W-9)
DOC. NO. :
Periode: 24 s/d 30 Juni 2023
DATE PIC CHKD APVD
30/06/2023 Eric Bagus S. 0 0
6. SAFETY REPORT
- Man power average consumption this week : 147 Man/day.
- Keterlambatan kedatangan material fabrikasi. 7 hari
- HSE Statistik :
DESCRIPTION
CLEAR V V V V V V V
CLOUD
RAINY
7. MASALAH DILAPANGAN
6/9
REV
MAINTENANCE BUILDING MCC-03 CPP
WEEKLY REPORT (W-9)
DOC. NO. :
Periode: 24 s/d 30 Juni 2023
DATE PIC CHKD APVD
30/06/2023 Eric Bagus S. 0 0
PHOTOGRAPH REPORT
7/9
REV
MAINTENANCE BUILDING MCC-03 CPP
WEEKLY REPORT (W-9)
DOC. NO. :
Periode: 24 s/d 30 Juni 2023
DATE PIC CHKD APVD
30/06/2023 Eric Bagus S. 0 0
PHOTOGRAPH REPORT
ELEK
8/9
REV
MAINTENANCE BUILDING MCC-03 CPP
WEEKLY REPORT (W-9)
DOC. NO. :
Periode: 24 s/d 30 Juni 2023
DATE PIC CHKD APVD
30/06/2023 Eric Bagus S. 0 0
PHOTOGRAPH REPORT
P5M
INSTAL SCAFFOLDING
9/9