1 PONDASI BATU BELAH (DPT) 81.40 4.07 12.21 16.28 24.42 4.88 4.88 4.88 4.88 2.44 0.81 0.81 0.81
2 GALIAN DENGAN ALAT BERAT 18.60 3.72 3.72 3.72 3.72 0.74 0.74 0.74 0.74 0.37 0.19 0.09 0.09
TOTAL 100.00
RENCANA MINGGUAN 7.79 15.93 20.00 28.14 5.63 5.63 5.63 5.63 2.81 1.00 0.91 0.91
RENCANA MINGGUAN KOMULATIF 7.79 23.72 43.72 71.86 77.49 83.12 88.74 94.37 97.19 98.19 99.09 100.00
REALISASI 1.05 5.32 9.90 10.32 8.51 3.15 12.26 3.38 - - 0.68 4.27
REALISASI KOMULATIF 1.05 6.37 16.27 26.59 35.10 38.24 50.51 53.89 53.89 53.89 54.57 58.84
DEVIASI (+/-) (6.74) (17.35) (27.45) (45.27) (42.39) (44.87) (38.24) (40.48) (43.30) (44.30) (44.52) (41.16)
SCHEDULE
PEKERJAAN DPT DAN SALURAN - SECTION C
PROGRESS PEKERJAAN PAGAR PANEL– SECTION C
PROGRESS 20 – 26 JANUARI 2024
1 PAGAR PRECAST T = 2 m, K-225 100.00 5.00 5.00 10.00 10.00 10.00 15.00 15.00 10.00 10.00 3.00 3.00 4.00
TOTAL 100.00
RENCANA MINGGUAN 5.00 5.00 10.00 10.00 10.00 15.00 15.00 10.00 10.00 3.00 3.00 4.00
RENCANA MINGGUAN KOMULATIF 5.00 10.00 20.00 30.00 40.00 55.00 70.00 80.00 90.00 93.00 96.00 100.00
REALISASI - - - - - 7.09 - - - - 2.67 1.38
REALISASI KOMULATIF - - - - - 7.09 7.09 7.09 7.09 7.09 9.77 11.14
DEVIASI (+/-) (5.00) (10.00) (20.00) (30.00) (40.00) (47.91) (62.91) (72.91) (82.91) (85.91) (86.23) (88.86)
SCHEDULE
PEKERJAAN PAGAR PANEL - SECTION C
PROGRESS PEKERJAAN INFRASTRUKTUR – JALAN UTAMA (TAHAP 1)
PROGRESS 20 – 26 JANUARI 2024
HARGA BOBOT FISIK PROGRESS (%)
NO. URAIAN PEKERJAAN VOLUME SATUAN
SATUAN (%) YANG LALU SAAT INI S/D SAAT INI YANG LALU SAAT INI S/D SAAT INI
1 Galian badan jalan termasuk pemadatan t = 70 cm 50,470.00 2,837.00 m2 8.66 2,837.00 - 2,837.00 8.66 - 8.66
Beton K-300, t = 15 cm (termasuk Bekisting,
2 216,820.00 2,241.00 m2 29.40 1,464.00 - 1,464.00 19.21 - 19.21
Grooving, Cutting, Curing dan joint sealant)
3 Plastik Cor 6,054.00 2,241.00 m2 0.82 1,464.00 - 1,464.00 0.54 - 0.54
4 Wiremesh M5 1 lapis 55,850.00 2,241.00 m2 7.57 1,464.00 - 1,464.00 4.95 - 4.95
5 Basecourse kasar t = 15 cm (Pemadatan) 46,469.00 2,837.00 m2 7.97 2,837.00 - 2,837.00 7.97 - 7.97
6 Limestone t = 40 cm (Pemadatan) 123,916.00 2,837.00 m2 21.26 2,837.00 - 2,837.00 21.26 - 21.26
7 Kansteen slipform, L=20cm 107,540.00 726.00 m' 4.72 144.00 206.00 350.00 0.94 1.34 2.28
8 Pekerjaan Galian Saluran 45,103.00 198.00 m2 0.54 171.52 - 171.52 0.47 - 0.47
9 Pasir Urug 31,583.00 198.00 m2 0.38 43.70 6.30 50.00 0.08 0.01 0.10
10 Saluran U-ditch 400 (Termasuk Tutup t=10cm) 749,830.00 395.00 m' 17.91 46.00 54.00 100.00 2.09 2.45 4.53
Bak Kontrol 60x60 per 30m (Tulangan Ø8, Tutup,
11 811,000.00 14.00 titik 0.69 - - - - - -
t=10cm)
12 Galian Bak Kontrol 95,154.00 6.00 m3 0.03 2.00 - 2.00 0.01 - 0.01
13 Lantai Kerja, t=10cm 850,000.00 1.00 m3 0.05 - - - - - -
TOTAL 100.00 66.16 3.80 69.96
4 Wiremesh M5 1 lapis 7.57 0.28 0.74 1.72 1.56 1.43 0.98 0.87
5 Basecourse kasar t = 15 cm (Pemadatan) 7.97 0.29 0.78 1.81 1.64 1.51 1.03 0.92
6 Limestone t = 40 cm (Pemadatan) 21.26 0.78 2.07 4.82 4.38 4.02 2.74 2.44
7 Kansteen slipform, L=20cm 4.72 0.17 0.46 1.07 0.97 0.89 0.61 0.54
8 Pekerjaan Galian Saluran 0.54 0.01 0.01 0.14 0.12 0.12 0.12
10 Saluran U-ditch 400 (Termasuk Tutup t=10cm) 17.91 0.49 0.42 4.72 4.09 4.09 4.09
12 Galian Bak Kontrol 0.03 0.00 0.00 0.01 0.01 0.01 0.01
13 Lantai Kerja, t=10cm 0.05 0.00 0.00 0.01 0.01 0.01 0.01
TO TAL 100.00
RENCANA MINGGUAN 2.89 5.53 10.40 16.74 19.95 18.05 13.72 12.72
RENCANA MINGGUAN KOMULATIF 2.89 8.42 18.82 35.56 55.51 73.56 87.28 100.00
REALISASI 23.93 20.92 4.27 1.29 15.76 3.80
REALISASI KOMULATIF 23.93 44.84 49.11 50.40 66.16 69.96
DEVIASI (+/-) 21.04 36.42 30.29 14.84 10.65 (3.60)
PROGRESS PEKERJAAN SALURAN U-DITCH ASRAMA HAJI
PROGRESS 20 – 26 JANUARI 2024
BOBOT FISIK PROGRESS (%)
NO. URAIAN PEKERJAAN VOLUME SATUAN
(%) YANG LALU SAAT INI S/D SAAT INI YANG LALU SAAT INI S/D SAAT INI
1 Pekerjaan Tanah
Galian Jalur Box Culvert 500.50 m3 1.98 220.00 130.35 350.35 0.87 0.51 1.38
2 Pekerjaan Bongkar Pagar Pembatas Asrama Haji
Pembongkaran Dinding Pas. Bata 13.50 m2 0.06 - - - - - -
Pembongkaran Beton Bertulang 0.38 m3 0.00 - - - - - -
Pembongkaran Pondasi Batu Kali 2.03 m3 0.01 - - - - - -
Pekerjaan Pemasangan Saluran Box Culvert 100 x
3
100
Pasir Urug t = 10 cm 42.00 m3 1.15 - 11.44 11.44 - 0.31 0.31
Pemasangan Box Culvert 350.00 m' 94.52 - 44.00 44.00 - 11.88 11.88
Backfill Jalur Box Culvert 115.50 m3 1.23 - - - - - -
4 Pekerjaan Perbaikan Pagar Pembatas Asrama Haji
4.1. Pekerjaan Pondasi Batu Kali
Pasangan Batu Kali 1 Pc : 5 Ps 2.03 m3 0.12 - - - - - -
Besi Angkur Ø10 32.50 Kg 0.03 - - - - - -
Pasir Urug 0.30 m3 0.01 - - - - - -
4.2. Pekerjaan Sloof
Bekisting 1.20 0.01 - - - - - -
Pembesian 150.00 0.13 - - - - - -
Cor Beton Site Mix K-225 0.09 0.01 - - - - - -
4.3. Pekerjaan Kolom 150 x 150
Bekisting 5.40 0.05 - - - - - -
Pembesian 150.00 0.13 - - - - - -
Cor Beton Site Mix K-225 0.20 0.01 - - - - - -
4.4. Pekerjaan Ring Balok
Bekisting 1.20 0.01 - - - - - -
Pembesian 150.00 0.13 - - - - - -
Cor Beton Site Mix K-225 0.09 0.01 - - - - - -
4.5. Pekerjaan Dinding Pasangan Bata Ringan
Pemasangan Dinding Bata Ringan 13.50 0.16 - - - - - -
Plesteran dengan Mortar setara 1 pc : 4 pp 27.00 0.11 - - - - - -
Pemasangan Acian dengan Mortar 13.50 0.05 - - - - - -
Pengecatan Dinding Eksterior 13.50 0.03 - - - - - -
Pemasangan List Profil 3.00 0.05 - - - - - -
1. Leveling Elevasi Zona 1 1. Pasang DPT & Saluran P33 - 1. Pasang pagar panel P29 –
2. Pemadatan tanah Zona 1 P35 P30
2. Pasang DPT & Saluran P50 –
P52
3. Finishing saluran
REALISASI PEKERJAAN MINGGU INI
PEKERJAAN TANAH
PEKERJAAN TANAH PEKERJAAN DPT PEKERJAAN SALURAN
SALURAN PEKERJAAN PAGAR PANEL
1. Leveling Elevasi Zona 1 - 3 1. Pasang DPT & Saluran P61 – 1. Pasang pagar panel P32 –
2. Pemadatan tanah Zona 1 - 3 P77 P47
RENCANA PEKERJAAN MINGGU DEPAN
PEKERJAAN TANAH
PEKERJAAN TANAH PEKERJAAN DPT PEKERJAAN SALURAN
SALURAN PEKERJAAN PAGAR PANEL
PEKERJAAN TANAH
PEKERJAAN TANAH PEKERJAAN DPT PEKERJAAN SALURAN
SALURAN PEKERJAAN PAGAR PANEL
Pekerjaan DPT Saluran terkendala aliran air dari saluran Terapkan sistem buka tutup saluran air dibantu dengan
1 Open
eksisting dan warga pompa
2
DOKUMENTASI
PEKERJAAN TANAH
DOKUMENTASI
PEKERJAAN DPT & SALURAN – SECTION C
DOKUMENTASI
PEKERJAAN PAGAR PANEL PRECAST – SECTION C
DOKUMENTASI
PEKERJAAN INFRASTRUKTUR – JALAN UTAMA (TAHAP 1)
DOKUMENTASI
PEKERJAAN SALURAN U-DITCH ASRAMA HAJI
DOKUMENTASI
PEKERJAAN PEMBENTUKAN KAVLING – TAHAP 1
DOKUMENTASI
PEKERJAAN TOTEM
DOKUMENTASI
PEKERJAAN PEMANCANGAN MINI PILE
DOKUMENTASI
PEKERJAAN PAGAR DEPAN (SAMPING TOTEM)