Anda di halaman 1dari 39

LAPORAN PROGRES PEKERJAAN

R E H A B I L I TA S I D A N
R E N O VA S I P R A S A R A N A
P E N D I D I K A N S E KO L A H
BANTEN 2
Pe r i o d e M i n g g u 1 5 ( 1 1 M a r e t 2 0 2 4 s / d 1 7 M a r e t 2 0 2 4 )

KONTRAKTOR
PROGRES

KURVA S

DOKUMENTASI
PEKERJA & ALAT

MASALAH & SARAN PEKERJAAN YANG DILAKUKAN


DAN RENCANA MINGGU DEPAN

TOPIK PEMBAHASAN
SDN 4 CIHAMBALI
PROGRES SDN 4 CIHAMBALI

1. RENCANA : 17,10 %
2. REALISASI : 43,25%
3. DEVIASI : 26,15%
REKAPITULASI PROGRES SDN 4 CIHAMBALI

PROGRES PEKERJAAN PERIODE : 11 Maret - 17 Maret 2024 MINGGU KE : 15


PRESTASI PEKERJAAN
BOBOT
NO URAIAN PEKERJAAN NILAI PEKERJAAN BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU INI DEVIASI
RENCANA
Prestasi Bobot Prestasi Bobot Prestasi Bobot

A PEKERJAAN SMKK 12,734,146.52 1.16% 34.10% 0.39% 1.57% 0.02% 35.67% 0.41% 0.66% -0.25%
B PEKERJAAN PEMBONGKARAN 51,257,014.41 4.66% 61.98% 2.89% 0.00% 0.00% 61.98% 2.89% 2.38% 0.51%
C PEKERJAAN TANAH 7,829,300.00 0.71% 18.59% 0.13% 0.00% 0.00% 18.59% 0.13% 0.23% -0.10%
D PEKERJAAN STRUKTUR 417,808,787.84 37.96% 84.77% 32.18% 7.57% 2.87% 92.34% 35.05% 10.84% 24.21%
E PEKERJAAN ARSITEKTUR 551,742,393.84 50.13% 9.43% 4.73% 0.08% 0.04% 9.52% 4.77% 2.83% 1.94%
F PEKERJAAN MEP 36,202,300.00 3.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% -0.15%
G PEKERJAAN LANDSCAPE 23,106,049.06 2.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TOTAL 1,100,679,992 100.00% 40.32% 2.93% 43.25% 17.10% 26.15%


KURVA S SDN 4 CIHAMBALI
WAKTU PELAKSANAAN
Dec/2023 Jan/2024 Feb/2024 Mar/2024 Apr/2024 May/2024 Jun/2024 Jul/2024
NO ITEM PEKERJAAN SATUAN BOBOT 04/Dec 11/Dec 18/Dec 25/Dec 01/Jan 08/Jan 15/Jan 22/Jan 29/Jan 05/Feb 12/Feb 19/Feb 26/Feb 04/Mar 11/Mar 18/Mar 25/Mar 01/Apr 08/Apr 15/Apr 22/Apr 29/Apr 06/May 13/May 20/May 27/May 03/Jun 10/Jun 17/Jun 24/Jun 01/Jul 08/Jul 15/Jul 22/Jul 29/Jul
10/Dec 17/Dec 24/Dec 31/Dec 07/Jan 14/Jan 21/Jan 28/Jan 04/Feb 11/Feb 18/Feb 25/Feb 03/Mar 10/Mar 17/Mar 24/Mar 31/Mar 07/Apr 14/Apr 21/Apr 28/Apr 05/May 12/May 19/May 26/May 02/Jun 09/Jun 16/Jun 23/Jun 30/Jun 07/Jul 14/Jul 21/Jul 28/Jul 30/Jul
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28 M-29 M-30 M-31 M-32 M-33 M-34 M-35

A SMKK 1.46% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%

B PEKERJAAN PEMBONGKARAN 2.38% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% L
E P
0.08% 0.08% 0.08%
H
C PEKERJAAN TANAH 0.23%
B
O
1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81%
A
D PEKERJAAN STRUKTUR 30.73%

E PEKERJAAN ARSITEKTUR 45.33% 2.83% 2.83%


R 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83%

F PEKERJAAN MEP 2.06% 0.15% 0.15% 0.15% 0.15% A 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%

G PEKERJAAN LANDSCAPE 17.81%


N 1.98% 1.98% 1.98% 1.98% 1.98% 1.98% 1.98% 1.98% 1.98%

TOTAL 100.00% 0.04% 0.04% 0.31% 0.31% 0.31% 0.31% 0.31% 0.31% 0.39% 2.19% 2.19% 1.85% 1.85% 1.85% 4.83% 4.83% 2.00% 2.00% 0.00% 0.00% 4.83% 4.83% 4.83% 4.83% 4.83% 4.83% 6.81% 6.81% 5.00% 5.00% 4.86% 4.86% 4.86% 4.86% 2.02%
INCLUDE PPN 11%
PROGRES MINGGUAN 0.04% 0.04% 0.31% 0.31% 0.31% 0.31% 0.31% 0.31% 0.39% 2.19% 2.19% 1.85% 1.85% 1.85% 4.83% 4.83% 2.00% 2.00% 0.00% 0.00% 4.83% 4.83% 4.83% 4.83% 4.83% 4.83% 6.81% 6.81% 5.00% 5.00% 4.86% 4.86% 4.86% 4.86% 2.02%
PROGRES MINGGUAN KUMULATIF - 0.04% 0.09% 0.40% 0.71% 1.01% 1.32% 1.63% 1.94% 2.32% 4.52% 6.71% 8.56% 10.42% 12.27% 17.10% 21.93% 23.93% 25.93% 25.93% 25.93% 30.76% 35.60% 40.43% 45.26% 50.09% 54.93% 61.74% 68.55% 73.55% 78.55% 83.41% 88.27% 93.12% 97.98% 100.00%
PROGRES BULANAN 0.71% 1.62% 9.94% 13.66% 9.66% 19.33% 28.48% 16.59%
PROGRES BULANAN KUMULATIF 0.71% 2.32% 12.27% 25.93% 35.60% 54.93% 83.41% 100.00%
REALISASI PROGRES MINGGUAN 0.00% 0.14% 0.03% 1.33% 0.00% 1.24% 0.89% 0.93% 3.41% 0.71% 3.14% 7.79% 16.39% 4.34% 2.93%
REALISASI PROGRES MINGGUAN KUMULATIF - 0.00% 0.14% 0.17% 1.49% 1.49% 2.73% 3.62% 4.55% 7.96% 8.67% 11.81% 19.60% 35.98% 40.32% 43.25%
DEVIASI -0.04% 0.05% -0.23% 9.05% 0.48% 1.41% 1.99% 2.61% 5.63% 4.15% 5.10% 11.03% 25.57% 28.05% 26.15%
MASALAH & SARAN SDN 4 CIHAMBALI
MASALAH :
1. APD tidak lengkap
2. APAR tidak ada
3. P3K tidak ada
4. Ada pekerjaan yang harus diinput ke CCO karena tidak terwakili di
MC0 sedangkan pekerjaan tersebut penting (galian tanah, turap,
kolom dan balok selasar, kolom, balok ampig dan foldinggate)
5. Jenis bouvenlight cuma ada satu sedangkan dilapangan harus ada
2 jenis karena dibutuhkan diarea toilet

SARAN :
1. APD dan kewajiban item SMKK lainnya segera dipenuhi
2. CCO segera diselesaikan
DOKUMENTASI
Gedung A Gedung B

Gedung A Gedung B

Gedung A Gedung B
PEKERJA & ALAT SDN 4 CIHAMBALI
PEKERJA :
1. Tukang = 7 OH
2. Kenek = 8 OH
3. Mandor = 1 OH
4. Pelaksana = 1 OH
ALAT :
1. Selang timbangan 9. Roskam
2. Waterpas 10. Gerinda potong
3. Meteran 11. Impact wrench/Pengencang
baut
4. Palu
5. Pahat
6. Cangkul
7. Ember
8. Sendok semen
PEKERJAAN YANG TELAH DILAKUKAN DAN RENCANA
MINGGU DEPAN SDN 4 CIHAMBALI

PEKERJAAN YANG TELAH DILAKUKAN :


1. Bongkaran dinding bata (kusen pintu dan jendela) gedung A dan B
2. Bongkaran keramik gedung A dan B
3. Bongkaran genteng, rangka atap dan lisplank gedung A dan B
4. Bongkaran plafond gedung A dan B
5. Bongkaran plesteran gedung A dan B
6. Pemasangan balok lintel gedung A dan B
7. Plesteran dan acian gedung A dan B
8. Pemasangan dinding bata merah gedung A dan B
9. Galian tanah gedung B
10. Pemasangan kolom dan balok selasar gedung B
11. Pemasangan rangka atap baja ringan kanal C75 gedung A dan B
12. Pemasangan turap gedung B
13. Pemasangan atap genteng metal gedung A dan B
14. Pemasangan nok genteng metal gedung A dan B
15. Pemasangan lisplank gedung dan B
16. Pengerokan cat lama gedung A dan B
RENCANA MINGGU DEPAN :
1. Pemasangan lisplank gedung A
2. Pemasangan Plafond gedung A dan B
5. Rabat beton selasar gedung A dan B
6. Acian gedung A dan B
7. Pekerjaan MEP gedung A dan B
SMP 9 SATAP CIBEBER
PROGRES SMP 9 SATAP CIBEBER

1. RENCANA : 20,67 %
2. REALISASI : 33,32%
3. DEVIASI : 12,65%
REKAPITULASI PROGRES SMP 9 SATAP CIBEBER

PROGRES PEKERJAAN PERIODE : 11 Maret - 17 Maret 2024 MINGGU KE : 15


PRESTASI PEKERJAAN
BOBOT
NO URAIAN PEKERJAAN NILAI PEKERJAAN BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU INI DEVIASI
RENCANA
Prestasi Bobot Prestasi Bobot Prestasi Bobot

A PEKERJAAN SMKK 12,734,146.52 1.77% 31.44% 0.56% 2.69% 0.05% 34.14% 0.60% 0.73% -0.13%
B PEKERJAAN PEMBONGKARAN 35,760,394.30 4.97% 69.83% 3.47% 0.00% 0.00% 69.83% 3.47% 2.59% 0.88%
C PEKERJAAN TANAH 13,065,547.06 1.81% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.49% -0.49%
D PEKERJAAN STRUKTUR 294,664,953.34 40.92% 52.94% 21.66% 7.27% 2.97% 60.21% 24.64% 13.93% 10.71%
E PEKERJAAN ARSITEKTUR 310,263,493.79 43.09% 6.56% 2.83% 4.14% 1.78% 10.70% 4.61% 2.77% 1.84%
F PEKERJAAN MEP 42,066,150.00 5.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.16% -0.16%
G PEKERJAAN LANDSCAPE 11,543,500.00 1.60% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TOTAL 720,098,185 100.00% 28.52% 4.81% 33.32% 20.67% 12.65%


KURVA S SMP 9 CIBEBER
WAKTU PELAKSANAAN
Dec/2023 Jan/2024 Feb/2024 Mar/2024 Apr/2024 May/2024 Jun/2024 Jul/2024
NO ITEM PEKERJAAN SATUAN BOBOT 04/Dec 11/Dec 18/Dec 25/Dec 01/Jan 08/Jan 15/Jan 22/Jan 29/Jan 05/Feb 12/Feb 19/Feb 26/Feb 04/Mar 11/Mar 18/Mar 25/Mar 01/Apr 08/Apr 15/Apr 22/Apr 29/Apr 06/May 13/May 20/May 27/May 03/Jun 10/Jun 17/Jun 24/Jun 01/Jul 08/Jul 15/Jul 22/Jul 29/Jul
10/Dec 17/Dec 24/Dec 31/Dec 07/Jan 14/Jan 21/Jan 28/Jan 04/Feb 11/Feb 18/Feb 25/Feb 03/Mar 10/Mar 17/Mar 24/Mar 31/Mar 07/Apr 14/Apr 21/Apr 28/Apr 05/May 12/May 19/May 26/May 02/Jun 09/Jun 16/Jun 23/Jun 30/Jun 07/Jul 14/Jul 21/Jul 28/Jul 30/Jul
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28 M-29 M-30 M-31 M-32 M-33 M-34 M-35

A SMKK 1.60% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%

B PEKERJAAN PEMBONGKARAN 2.59% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% L
P
C PEKERJAAN TANAH 0.49% 0.16% 0.16% 0.16% E
B H
D PEKERJAAN STRUKTUR 39.47% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32%

A O
E PEKERJAAN ARSITEKTUR 44.40% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77% 2.77%
R
0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16%
A
F PEKERJAAN MEP 2.27%

G PEKERJAAN LANDSCAPE 9.19%


N 1.02% 1.02% 1.02% 1.02% 1.02% 1.02% 1.02% 1.02% 1.02%

TOTAL PEKERJAAN LANDSCAPE


TOTAL 100.00% 0.05% 0.05% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.50% 2.82% 2.82% 2.37% 2.37% 2.37% 5.31% 5.31% 2.53% 2.53% 0.00% 0.00% 5.31% 5.31% 5.31% 5.31% 5.31% 5.31% 6.33% 6.33% 4.01% 4.01% 3.84% 3.84% 3.84% 3.84% 1.07%
INCLUDE PPN 11%
PROGRES MINGGUAN 0.05% 0.05% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.50% 2.82% 2.82% 2.37% 2.37% 2.37% 5.31% 5.31% 2.53% 2.53% 0.00% 0.00% 5.31% 5.31% 5.31% 5.31% 5.31% 5.31% 6.33% 6.33% 4.01% 4.01% 3.84% 3.84% 3.84% 3.84% 1.07%
PROGRES MINGGUAN KUMULATIF - 0.05% 0.10% 0.43% 0.77% 1.11% 1.44% 1.78% 2.11% 2.61% 5.43% 8.26% 10.63% 13.00% 15.37% 20.67% 25.98% 28.51% 31.04% 31.04% 31.04% 36.35% 41.66% 46.96% 52.27% 57.58% 62.88% 69.21% 75.54% 79.55% 83.55% 87.40% 91.24% 95.09% 98.93% 100.00%
PROGRES BULANAN 0.77% 1.84% 12.75% 15.68% 10.61% 21.23% 24.51% 12.60%
PROGRES BULANAN KUMULATIF 0.77% 2.61% 15.37% 31.04% 41.66% 62.88% 87.40% 100.00%
REALISASI PROGRES MINGGUAN 0.00% 0.15% 0.03% 0.49% 2.23% 0.00% 0.81% 1.31% 1.65% 0.31% 0.11% 9.15% 5.39% 6.88% 4.81%
REALISASI PROGRES MINGGUAN KUMULATIF - 0.00% 0.15% 0.18% 0.67% 2.90% 2.90% 3.71% 5.02% 6.67% 6.98% 7.09% 16.25% 21.63% 28.52% 33.32%
DEVIASI -0.05% 0.05% -0.25% 11.99% 1.79% 1.46% 1.93% 2.90% 4.06% 1.55% -1.16% 5.62% 8.64% 13.15% 12.65%
MASALAH & SARAN SMP 9 SATAP CIBEBER
MASALAH :
1. APD tidak lengkap
2. APAR tidak ada
3. P3K tidak ada
4. Ada pekerjaan yang harus diinput ke CCO karena tidak terwakili di MC0
sedangkan pekerjaan tersebut penting (galian tanah, pile cap, sloof, kolom, kolom
praktis, turap dan foldinggate)
5. Ada kesalahan penghitungan volume rangka atap di MC0 karena dilapangan
tidak ada penggantian/pembongkaran rangka atap kecuali toilet itupan terlalu
besar volumenya
6. Jenis bouvenlight hanya ada satu jenis sedangkan dilapangan harus ada 2 jenis
karena dibutuhkan di area toilet
7. Kurangnya komunikasi pada saat pengadaan material

SARAN :
1. APD dan kewajiban item SMKK lainnya segera dipenuhi
2. CCO segera diselesaikan
3. Perbaiki hitungan volume di CCO
4. Idealnya diterapkan form request
DOKUMENTASI
Ruang kelas Ruang guru

Ruang kelas Ruang guru

Ruang kelas Ruang kelas


PEKERJA & ALAT SMP 9 SATAP CIBEBER
PEKERJA :
1. Tukang = 4 OH
2. Kenek = 5 OH
3. Mandor = 1 OH
4. Pelaksana = 1 OH
ALAT :
1. Selang timbangan 9. Roskam
2. Waterpas 10. Gerinda potong
3. Meteran 11. Impact wrench/Pengencang
baut
4. Palu
5. Pahat
6. Cangkul
7. Ember
8. Sendok semen
PEKERJAAN YANG TELAH DILAKUKAN DAN RENCANA
MINGGU DEPAN SMP 9 SATAP CIBEBER

PEKERJAAN YANG TELAH DILAKUKAN :


1. Bongkaran dinding bata (kusen pintu dan jendela) ruang guru dan kelas
2. Bongkaran keramik ruang guru dan kelas
3. Bongkaran genteng, dan lisplank ruang guru dan kelas
4. Bongkaran plafond ruang guru dan kelas
5. Bongkaran plesteran ruang guru dan kelas
6. Pemasangan balok lintel ruang guru dan kelas
7. Plesteran dan acian ruang guru dan kelas
8. Pemasangan dinding bata merah ruang guru dan kelas
9. Galian tanah ruang kelas
10. Pemasangan turap ruang kelas
11. Pemasangan pile cap ruangkelas
12. Penyuntikan sloof dan kolom ruang kelas
13. Pemasangan kolom praktis ruang kelas
14. Pengerokan cat lama ruang guru dan kelas
15. Pemasangan atap genteng metal ruang guru dan kelas
16. Pemasangan nok genteng metal ruang guru dan kelas
RENCANA MINGGU DEPAN :
1. Pemasangan lisplank ruang guru dan kelas
2. Pengerokan cat lama ruang guru dan kelas
3. Pemasangan Plafond ruang guru dan kelas
4. Rabat beton selasar ruang guru dan kelas
5. Pekerjaan MEP ruang guru dan kelas
SDN 1 NEGLASARI
PROGRES SDN 1 NEGLASARI

1. RENCANA : 18,38 %
2. REALISASI : 18,97%
3. DEVIASI : 0,59%
REKAPITULASI PROGRES SDN 1 NEGLASARI

PROGRES PEKERJAAN PERIODE : 11 Maret - 17 Maret 2024 MINGGU KE : 15


PRESTASI PEKERJAAN
BOBOT
NO URAIAN PEKERJAAN NILAI PEKERJAAN BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU INI DEVIASI
RENCANA
Prestasi Bobot Prestasi Bobot Prestasi Bobot

A PEKERJAAN SMKK 12,734,146.52 1.25% 34.37% 0.43% 0.00% 0.00% 34.37% 0.43% 0.51% -0.08%
B PEKERJAAN PEMBONGKARAN 23,626,435.69 2.32% 67.67% 1.57% 0.00% 0.00% 67.67% 1.57% 2.30% -0.73%
C PEKERJAAN TANAH 20,083,307.98 1.97% 0.94% 0.02% 0.00% 0.00% 0.94% 0.02% 1.38% -1.36%
D PEKERJAAN STRUKTUR 404,733,086.97 39.78% 35.52% 14.13% 0.00% 0.00% 35.52% 14.13% 11.45% 2.68%
E PEKERJAAN ARSITEKTUR 461,891,491.88 45.40% 6.21% 2.82% 0.00% 0.00% 6.21% 2.82% 2.49% 0.32%
F PEKERJAAN MEP 60,774,550.00 5.97% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.25% -0.25%
G PEKERJAAN LANDSCAPE 33,480,407.06 3.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TOTAL 1,017,323,426 100.00% 18.97% 0.00% 18.97% 18.38% 0.59%


KURVA S SDN 1 NEGLASARI
WAKTU PELAKSANAAN
Dec/2023 Jan/2024 Feb/2024 Mar/2024 Apr/2024 May/2024 Jun/2024 Jul/2024
NO ITEM PEKERJAAN SATUAN BOBOT 04/Dec 11/Dec 18/Dec 25/Dec 01/Jan 08/Jan 15/Jan 22/Jan 29/Jan 05/Feb 12/Feb 19/Feb 26/Feb 04/Mar 11/Mar 18/Mar 25/Mar 01/Apr 08/Apr 15/Apr 22/Apr 29/Apr 06/May 13/May 20/May 27/May 03/Jun 10/Jun 17/Jun 24/Jun 01/Jul 08/Jul 15/Jul 22/Jul 29/Jul
10/Dec 17/Dec 24/Dec 31/Dec 07/Jan 14/Jan 21/Jan 28/Jan 04/Feb 11/Feb 18/Feb 25/Feb 03/Mar 10/Mar 17/Mar 24/Mar 31/Mar 07/Apr 14/Apr 21/Apr 28/Apr 05/May 12/May 19/May 26/May 02/Jun 09/Jun 16/Jun 23/Jun 30/Jun 07/Jul 14/Jul 21/Jul 28/Jul 30/Jul
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28 M-29 M-30 M-31 M-32 M-33 M-34 M-35

A SMKK 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
L
B PEKERJAAN PEMBONGKARAN 0.00% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26%
E
0.46% 0.46% 0.46%
B P
C PEKERJAAN TANAH 0.00%

1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91% 1.91%
A H
D PEKERJAAN STRUKTUR 0.00%

R
2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49% 2.49%
O
E PEKERJAAN ARSITEKTUR 0.00%

F PEKERJAAN MEP 0.00% 0.25% 0.25% 0.25% 0.25%


A 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25%

G PEKERJAAN LANDSCAPE 0.00% N 2.16% 2.16% 2.16% 2.16% 2.16% 2.16% 2.16% 2.16% 2.16%

TOTAL 100.00% 0.03% 0.03% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.75% 2.66% 2.66% 1.94% 1.94% 1.94% 4.68% 4.68% 2.19% 2.19% 0.00% 0.00% 4.68% 4.68% 4.68% 4.68% 4.68% 4.68% 6.84% 6.84% 4.93% 4.93% 4.68% 4.68% 4.68% 4.68% 2.19%
INCLUDE PPN 11%
PROGRES MINGGUAN 0.03% 0.03% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.75% 2.66% 2.66% 1.94% 1.94% 1.94% 4.68% 4.68% 2.19% 2.19% 0.00% 0.00% 4.68% 4.68% 4.68% 4.68% 4.68% 4.68% 6.84% 6.84% 4.93% 4.93% 4.68% 4.68% 4.68% 4.68% 2.19%
PROGRES MINGGUAN KUMULATIF - 0.03% 0.07% 0.36% 0.65% 0.94% 1.23% 1.52% 1.80% 2.55% 5.21% 7.87% 9.81% 11.76% 13.70% 18.38% 23.06% 25.25% 27.44% 27.44% 27.44% 32.12% 36.80% 41.49% 46.17% 50.85% 55.53% 62.37% 69.21% 74.14% 79.07% 83.76% 88.44% 93.13% 97.81% 100.00%
PROGRES BULANAN 0.65% 1.91% 11.14% 13.74% 9.36% 18.73% 28.22% 16.24%
PROGRES BULANAN KUMULATIF 0.65% 2.55% 13.70% 27.44% 36.80% 55.53% 83.76% 100.00%
REALISASI PROGRES MINGGUAN 0.00% 0.11% 0.02% 0.91% 1.48% 0.00% 0.00% 0.00% 1.43% 1.74% 0.00% 4.66% 1.19% 7.42% 0.00%
REALISASI PROGRES MINGGUAN KUMULATIF - 0.00% 0.11% 0.13% 1.03% 2.52% 2.52% 2.52% 2.52% 3.95% 5.69% 5.69% 10.36% 11.55% 18.97% 18.97%
DEVIASI -0.03% 0.04% -0.23% 8.33% 1.58% 1.29% 1.00% 0.71% 1.39% 0.48% -2.18% 0.54% -0.21% 5.27% 0.59%
MASALAH & SARAN SDN 1 NEGLASARI
MASALAH :
1. APD tidak lengkap
2. APAR tidak ada
3. P3K tidak ada
4. Ada pekerjaan yang harus diinput ke CCO karena tidak terwakili di MC0
sedangkan pekerjaan tersebut penting (galian tanah, pile cap, sloof, kolom, kolom
praktis )
5. Dimensi besi kolom dan pile cap tidak sesuai juknis
6. Jenis bouvenlight hanya ada satu jenis sedangkan dilapangan harus ada 2 jenis
karena dibutuhkan di area toilet

SARAN :
1. APD dan kewajiban item SMKK lainnya segera dipenuhi
2. CCO segera diselesaikan
3. Perbaiki hitungan volume di CCO
DOKUMENTASI
Gedung B Gedung A

Gedung B Gedung A

Gedung B Gedung A
PEKERJA & ALAT SDN 1 NEGLASARI
PEKERJA :
1. Tukang = 8 OH
2. Kenek = 9 OH
3. Mandor = 1 OH
4. Pelaksana = 1 OH
ALAT :
1. Selang timbangan 9. Roskam
2. Waterpas 10. Gerinda potong
3. Meteran 11. Alat bending besi
4. Palu 12.Impact
wrench/Pengencang baut
5. Pahat
6. Cangkul
7. Ember
8. Sendok semen
PEKERJAAN YANG TELAH DILAKUKAN DAN RENCANA
MINGGU DEPAN SDN 1 NEGLASARI

PEKERJAAN YANG TELAH DILAKUKAN :


1. Bongkaran dinding bata (kusen pintu dan jendela) gedung A dan B
2. Bongkaran keramik gedung A dan B
3. Bongkaran genteng, dan lisplank gedung A dan B
4. Bongkaran rangka atap gedung B
4. Bongkaran plafond gedung A dan B
5. Bongkaran plesteran gedung B
6. Pemasangan balok lintel gedung A dan B
7. Plesteran dan acian gedung A dan B
8. Pemasangan dinding bata merah gedung A dan B
9. Galian tanah gedung A
10. Pemasangan kolom ampig gedung B
11. Pekerjaan sloof, kolom dan ring balk gedung A
12. Pemasangan batu bata ringan gedung A
13. Pemasangan genteng metal berpasir gedung B
14. Pemasangan nok genteng B
15. Pengerokan cat lama
RENCANA MINGGU DEPAN :
1. Pemasangan lisplank gedung A dan B
2. Acian gedung A dan B
3. Pemasangan genteng metal gedung A
4. Pemasangan Plafond gedung A dan B
5. Pemasangan jaringan listrik
6. Rabat beton selasar keliling
SDN 3 CIJENGKOL
PROGRES SDN 3 CIJENGKOL

1. RENCANA : 19,69 %
2. REALISASI : 26,88%
3. DEVIASI : 7,19%
REKAPITULASI PROGRES SDN 3 CIJENGKOL

PROGRES PEKERJAAN PERIODE : 11 Maret - 17 Maret 2024 MINGGU KE : 15


PRESTASI PEKERJAAN
BOBOT
NO URAIAN PEKERJAAN NILAI PEKERJAAN BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU INI DEVIASI
RENCANA
Prestasi Bobot Prestasi Bobot Prestasi Bobot

A PEKERJAAN SMKK 12,734,146.52 1.17% 34.84% 0.41% 0.00% 0.00% 34.84% 0.41% 0.49% -0.08%
B PEKERJAAN PEMBONGKARAN 45,038,732.59 4.15% 61.29% 2.55% 0.00% 0.00% 61.29% 2.55% 2.02% 0.53%
C PEKERJAAN TANAH 15,205,106.48 1.40% 4.38% 0.06% 0.00% 0.00% 4.38% 0.06% 0.83% -0.77%
D PEKERJAAN STRUKTUR 482,802,861.56 44.52% 46.56% 20.73% 0.00% 0.00% 46.56% 20.73% 13.24% 7.49%
E PEKERJAAN ARSITEKTUR 474,496,968.42 43.76% 7.16% 3.13% 0.00% 0.00% 7.16% 3.13% 2.84% 0.30%
F PEKERJAAN MEP 46,891,940.00 4.32% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.28% -0.28%
G PEKERJAAN LANDSCAPE 7,243,300.00 0.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TOTAL 1,084,413,056 100.00% 26.88% 0.00% 26.88% 19.69% 7.19%


KURVA S SDN 3 CIJENGKOL
WAKTU PELAKSANAAN
Dec/2023 Jan/2024 Feb/2024 Mar/2024 Apr/2024 May/2024 Jun/2024 Jul/2024
NO ITEM PEKERJAAN SATUAN BOBOT 04/Dec 11/Dec 18/Dec 25/Dec 01/Jan 08/Jan 15/Jan 22/Jan 29/Jan 05/Feb 12/Feb 19/Feb 26/Feb 04/Mar 11/Mar 18/Mar 25/Mar 01/Apr 08/Apr 15/Apr 22/Apr 29/Apr 06/May 13/May 20/May 27/May 03/Jun 10/Jun 17/Jun 24/Jun 01/Jul 08/Jul 15/Jul 22/Jul 29/Jul
10/Dec 17/Dec 24/Dec 31/Dec 07/Jan 14/Jan 21/Jan 28/Jan 04/Feb 11/Feb 18/Feb 25/Feb 03/Mar 10/Mar 17/Mar 24/Mar 31/Mar 07/Apr 14/Apr 21/Apr 28/Apr 05/May 12/May 19/May 26/May 02/Jun 09/Jun 16/Jun 23/Jun 30/Jun 07/Jul 14/Jul 21/Jul 28/Jul 30/Jul
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28 M-29 M-30 M-31 M-32 M-33 M-34 M-35

A SMKK 1.08% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%

B PEKERJAAN PEMBONGKARAN 2.02% 0.22% 0.22% 0.22% 0.22% 0.22% 0.22% 0.22% 0.22% 0.22% L
E P
C PEKERJAAN TANAH 0.83% 0.28% 0.28% 0.28%
B H
2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21% 2.21%
A
D PEKERJAAN STRUKTUR 37.50%

O
E PEKERJAAN ARSITEKTUR 45.36% 2.84% 2.84%
R 2.84% 2.84% 2.84% 2.84% 2.84% 2.84% 2.84% 2.84% 2.84% 2.84% 2.84% 2.84% 2.84% 2.84%

F PEKERJAAN MEP 3.89% 0.28% 0.28% 0.28% 0.28% A 0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28%

G PEKERJAAN LANDSCAPE 9.32% N 1.04% 1.04% 1.04% 1.04% 1.04% 1.04% 1.04% 1.04% 1.04%

TOTAL 100.00% 0.03% 0.03% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.54% 2.74% 2.74% 2.24% 2.24% 2.24% 5.35% 5.35% 2.52% 2.52% 0.00% 0.00% 5.35% 5.35% 5.35% 5.35% 5.35% 5.35% 6.39% 6.39% 4.18% 4.18% 3.90% 3.90% 3.90% 3.90% 1.07%
INCLUDE PPN 11%
PROGRES MINGGUAN 0.03% 0.03% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.54% 2.74% 2.74% 2.24% 2.24% 2.24% 5.35% 5.35% 2.52% 2.52% 0.00% 0.00% 5.35% 5.35% 5.35% 5.35% 5.35% 5.35% 6.39% 6.39% 4.18% 4.18% 3.90% 3.90% 3.90% 3.90% 1.07%
PROGRES MINGGUAN KUMULATIF - 0.03% 0.07% 0.32% 0.58% 0.84% 1.09% 1.35% 1.61% 2.14% 4.88% 7.62% 9.86% 12.10% 14.34% 19.69% 25.04% 27.56% 30.08% 30.08% 30.08% 35.43% 40.78% 46.13% 51.48% 56.83% 62.19% 68.57% 74.96% 79.14% 83.32% 87.22% 91.13% 95.03% 98.93% 100.00%
PROGRES BULANAN 0.58% 1.56% 12.20% 15.74% 10.70% 21.41% 25.04% 12.78%
PROGRES BULANAN KUMULATIF 0.58% 2.14% 14.34% 30.08% 40.78% 62.19% 87.22% 100.00%
REALISASI PROGRES MINGGUAN 0.00% 0.10% 1.85% 0.36% 0.00% 0.00% 0.01% 0.03% 1.50% 1.77% 0.00% 1.22% 8.71% 11.34% 0.00%
REALISASI PROGRES MINGGUAN KUMULATIF - 0.00% 0.10% 1.95% 2.31% 2.31% 2.31% 2.32% 2.34% 3.84% 5.62% 5.62% 6.83% 15.54% 26.88% 26.88%
DEVIASI -0.03% 0.04% 1.63% 9.87% 1.47% 1.21% 0.97% 0.74% 1.70% 0.73% -2.01% -3.03% 3.44% 12.54% 7.19%
MASALAH & SARAN SDN 3 CIJENGKOL
MASALAH :
1. APD tidak lengkap
2. APAR tidak ada
3. P3K tidak ada
4. Ada pekerjaan yang harus diinput ke CCO karena tidak terwakili di MC0
sedangkan pekerjaan tersebut penting ( pile cap, sloof, kolom, kolom praktis dan
ring balk)
5. Ada kesalahan penghitungan volume rangka atap di MC0 karena dilapangan ada
penggantian rangka atap hanya satu gedung yaitu gedung B kecuali toilet itupan
terlalu besar volumenya
6. Jenis bouvenlight hanya ada satu jenis sedangkan dilapangan harus ada 2 jenis
karena dibutuhkan di area toilet
7. Pekerjaan rabat beton jadi screed karena tidak menggunakan batu kerikil/split

SARAN :
1. APD dan kewajiban item SMKK lainnya segera dipenuhi
2. CCO segera diselesaikan
3. Perbaiki hitungan volume dan item pekerjaan di CCO
DOKUMENTASI
Gedung B Gedung B

Gedung B Gedung B

Gedung B Gedung A
Gedung A Gedung A

Gedung A Gedung A

Gedung A
PEKERJA & ALAT SDN 3 CIJENGKOL
PEKERJA :
1. Tukang = 6 OH
2. Kenek = 7 OH
3. Mandor = 1 OH
4. Pelaksana = 1 OH
ALAT :
1. Selang timbangan 9. Roskam
2. Waterpas 10. Gerinda potong
3. Meteran 11. Alat bending besi
4. Palu 12. Impact
wrench/pengencang sekrup
5. Pahat
6. Cangkul
7. Ember
8. Sendok semen
PEKERJAAN YANG TELAH DILAKUKAN DAN RENCANA
MINGGU DEPAN SDN 3 CIJENGKOL

PEKERJAAN YANG TELAH DILAKUKAN :


1. Bongkaran dindinga bata (kusen pintu dan jendela)
2. Bongkaran keramik
3. Bongkaran genteng, dan lisplank
4. Bongkaran plafond
5. Bongkaran plesteran
6. Pemasangan balok lintel
7. Plesteran dan acian
8. Pemasangan dinding bata merah
9. Galian tanah
10. Pemasangan kolom ampig
11. Pemasangan balok ampig
12. Pemasangan rangka atap baja ringan canal C75
13. Pemasangan genteng metal
14. Screed selasar
RENCANA MINGGU DEPAN :
1. Pemasangan lisplank Gedung A dan B
2. Pengerokan cat lama Gedung A dan B
3. Pemasangan plafond Gedung A dan B
4. Acian gedung A dan B
5. Pemasangan instalasi listrik
6. Saluran drainase keliling bangunan gedung A dan B