NO ITEM PEKERJAAN BOBOT MG 1 MG 2 MG 3 MG 4 MG 5 MG 6 MG 7 MG 8 MG 9 MG 10 MG 11 MG 12 MG 13 MG 14 MG 15 MG 16 MG 17 MG 18 MG 19 MG 20 MG 21 MG 22 MG 23 MG 24 MG 25 MG 26 MG 27 MG 28 MG 29 MG 30 MG 31 MG 32 MG 33 MG 34 MG 35
25-Oct 30-Oct 6-Nov 13-Nov 20-Nov 27-Nov 4-Dec 11-Dec 18-Dec 25-Dec 1-Jan 8-Jan 15-Jan 22-Jan 29-Jan 5-Feb 12-Feb 19-Feb 26-Feb 4-Mar 11-Mar 18-Mar 25-Mar 1-Apr 8-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun
29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec 24-Dec 31-Dec 7-Jan 14-Jan 21-Jan 28-Jan 4-Feb 11-Feb 18-Feb 25-Feb 3-Mar 10-Mar 17-Mar 24-Mar 31-Mar 7-Apr 14-Apr 21-Apr 28-Apr 5-May 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 20-Jun

A PEKERJAAN PERSIAPAN DAN PENUNJANG 0,05% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002%
B PEKERJAAN GEDUNG C DAN E
B.1 PEKERJAAN STRUKTUR 0,75% 0,075% 0,075% 0,075% 0,075% 0,075% 0,075% 0,075% 0,075% 0,075% 0,075%
B.2 PEKERJAAN ARSITEKTUR

LIBUR HARI RAYA IDUL FITRI 1445 H


B.2.1 Pekerjaan Dinding 0,63% 0,063% 0,063% 0,063% 0,063% 0,063% 0,063% 0,063% 0,063% 0,063% 0,063%
B.2.2 Pekerjaan Pasangan Lantai 0,55% 0,110% 0,110% 0,110% 0,110% 0,110%
B.2.3 Pekerjaan Pasangan Plafound 0,26% 0,052% 0,052% 0,052% 0,052% 0,052%
B.2.4 Pekerjaan Pasangan Kusen, Daun Pintu dan Jendela 0,32% 0,040% 0,040% 0,040% 0,040% 0,040% 0,040% 0,040% 0,040%
B.2.5 Pekerjaan Pasangan Atap Bangunan 0,82% 0,164% 0,164% 0,164% 0,164% 0,164%
C PEKERJAAN BANGUNAN GEDUNG B
C.1 PEKERJAAN STRUKTUR 0,10% 0,013% 0,013% 0,013% 0,013% 0,013% 0,013% 0,013% 0,013%
C.2 PEKERJAAN ARSITEKTUR
C.2.1 Pekerjaan Dinding 0,06% 0,007% 0,007% 0,007% 0,007% 0,007% 0,007% 0,007% 0,007% 0,007%
C.2.2 Pekerjaan Pasangan Lantai 0,20% 0,051% 0,051% 0,051% 0,051%
C.2.3 Pekerjaan Pasangan Plafound 0,03% 0,007% 0,007% 0,007% 0,007%
C.2.4 Pasangan Pintu Type P3 Uk (2,1x0,79m) = 7 unit 0,04% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006%
C.2.5 Pekerjaan Perlengkapan Sanitery 0,13% 0,065% 0,065%
C.2.6 Pekerjaan Pasangan Atap Bangunan 0,06% 0,014% 0,014% 0,014% 0,014%
D PEKERJAAN HALAMAN DAN LINGKUNGAN
D.1 Pekerjaan Halaman 0,79% 0,265% 0,265% 0,265%
D.2 Pekerjaan Drainase 0,05% 0,023% 0,023%
D.3 Pekerjaan Pagar 0,04% 0,045%
D.4 Pekerjaan Halaman 0,24% 0,080% 0,080% 0,080%
D.5 Pekerjaan Signage 0,04% 0,018% 0,018%
D.6 Pekerjaan Pengecatan Ulang Bangunan Gedung Eksisting 0,26% 0,065% 0,065% 0,065% 0,065%
E PEKERJAAN MEKANIKAL, ELEKTRIKAL, DAN PLAMBING (MEP)
E.1 Pekerjaan Listrik Arus Kuat 0,12% 0,015% 0,015% 0,015% 0,015% 0,015% 0,015% 0,015% 0,015%
E.2 Pekerjaan Plambing 0,38% 0,063% 0,063% 0,063% 0,063% 0,063% 0,063%

RENCANA PROGRESS PER MINGGU 5,932% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,08% 0,08% 0,08% 0,15% 0,16% 0,16% 0,26% 0,28% 0,45% 0,46% 0,40% 0,38% 0,00% 0,00% 0,28% 0,52% 0,62% 0,63% 0,32% 0,36% 0,13% 0,09% 0,02%
KOMULATIF PROGRESS PER MINGGU 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,01% 0,01% 0,01% 0,01% 0,01% 0,09% 0,17% 0,25% 0,40% 0,56% 0,72% 0,98% 1,27% 1,72% 2,18% 2,58% 2,96% 2,96% 2,96% 3,24% 3,76% 4,38% 5,01% 5,33% 5,69% 5,83% 5,91% 5,93%