TIME SCHEDULLE / KURVA S

PEKERJAAN : RUMKIT Tk.IV ATAMBUA KESDAM IX/UDY


LOKASI : ATAMBUA, PROVINSI NTT
TAHUN : 2022

REKAPITULASI

WAKTU PELAKSANAAN (210 HARI)


NO URAIAN PEKERJAAN BOBOT (%) KET.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

I. PEKERJAAN PERSIAPAN 0.813% 0.0024 0.0057

II. BIAYA PENERAPAN KESELAMATAN KONSTRUKSI / SMKKK 0.152% 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001

III. PEKERJAAN PENYIAPAN LAHAN 1.880% 0.0038 0.0075 0.0075

IV. PEKERJAAN STRUKTUR 37.967%


PEKERJAAN GALIAN TANAH DAN PONDASI 6.387% 0.0064 0.0192 0.0192 0.0192
PEKERJAAN STRUKTUR BETON LANTAI 1 7.497% 0.0075 0.0225 0.0225 0.0225
PEKERJAAN STRUKTUR BETON LANTAI 2 12.377% 0.0124 0.0371 0.0371 0.0371
PEKERJAAN STRUKTUR BETON LANTAI ATAP 7.568% 0.0303 0.0303 0.0076 0.0076
PEKERJAAN ATAP 2.377% 0.0024 0.0071 0.0071 0.0071
PEKERJAAN BETON RAMP 1.761% 0.0106 0.0070

V. PEKERJAAN ARSITEKTUR 29.916%


PEKERJAAN PASANGAN DINDING 5.652% 0.0057 0.0057 0.0057 0.0057 0.0057 0.0057 0.0057 0.0057 0.0057 0.0057
PEKERJAAN PASANGAN LANTAI DAN DINDING KERAMIK 11.096% 0.0111 0.0111 0.0111 0.0111 0.0111 0.0111 0.0111 0.0111 0.0111 0.0111
PEKERJAAN PLAFOND DAN PARTISI 4.675% 0.0117 0.0117 0.0117 0.0117
PEKERJAAN PINTU DAN JENDELA 5.241% 0.0087 0.0087 0.0087 0.0087 0.0087 0.0087
PEKERJAAN CAT DINDING DAN PLAFOND 1.872% 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031
PEKERJJAAN SANITAIR 0.645% 0.0032 0.0032
PEKERJAAN ARSITEKTUR RAMP 0.735% 0.0037 0.0037

VI. PEKERJAAN MEP 24.783%


PEKERJAAN PLUMBING 1.746% 0.0009 0.0009 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017
PEKERJAAN ELEKTRIKAL 13.656% 0.0205 0.0205 0.0137 0.0137 0.0137 0.0137 0.0137 0.0137 0.0137
PEKERJAAN ELEKTRONIKA 1.598% 0.0024 0.0024 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016
PEKERJAAN PENANGKAL PETIR 0.323% 0.0008 0.0008 0.0008 0.0008
PEKERJAAN INSTALASI IPAL 1.720% 0.0043 0.0043 0.0043 0.0043
PEKERJAAN INSTALASI RUMAH POMPA-GROUND TANK 1.521% 0.0038 0.0038 0.0038 0.0038
PEKERJAAN INSTALASI GAS MEDIK 0.775% 0.0009 0.0009 0.0009 0.0009 0.0009 0.0009 0.0009 0.0009 0.0009
PEKERJAAN INSTALASI GENSET 3.445% 0.0086 0.0086 0.0086 0.0086

VII. PEKERJAAN GEDUNG PENUNJANG DAN SARANA PRASARANA 4.489%


PEKERJAAN GWT KAP 112 M3 DAN RUANG POMPA 2.722% 0.0068 0.0068 0.0068 0.0068
PEMBANGUNAN IPAL 0.887% 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015
PEKERJAAN JALAN DAN SALURAN 0.879% 0.0029 0.0029 0.0029

RENCANA MINGGUAN 100.000% 0.6251 1.3264 0.7572 0.6437 1.9210 1.9210 2.5736 1.4073 4.1037 4.1037 7.6296 7.6812 7.0931 10.9937 7.6786 6.4023 6.2494 5.9681 5.9148 2.7114 1.6720 1.6720 1.6624 0.9787 1.1266 1.1266 1.0142 1.0142 1.0142 1.0142
AKUMULASI RENCANA MINGGUAN 0.000% 0.6251 1.9515 2.7087 3.3525 5.2735 7.1945 9.7681 11.1754 15.2791 19.3829 27.0124 34.6937 41.7868 52.7805 60.4590 66.8613 73.1107 79.0787 84.9935 87.7049 89.3768 91.0488 92.7113 93.6900 94.8165 95.9431 96.9573 97.9715 98.9858 100.0000

Atambua, 14 Oktober 2022


PT.DARMA SIPON

CHARISTO KENEN BUDY


Direktur Cabang