JUMLAH HARGA BOBOT MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER
NO URAIAN PEKERJAAN
(Rp) (%) III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV
I Pekerjaan Persiapan
1 Papan Nama Pekerjaan 900,000.00 0.0110 0.0110
2 Pagar Sementara 174,188,990.45 2.1250 0.3542 0.3542 0.3542 0.3542 0.3542 0.3542
3 Pembuatan Direksi Keet (menjadi inventaris owner) 51,399,642.89 0.6270 0.1568 0.1568 0.1568 0.1568
4 Pembuatan Gudang Bahan (menjadi inventaris owner) 56,712,744.00 0.6918 0.1384 0.1384 0.1384 0.1384 0.1384
5 Pembuatan Barak Kerja (menjadi inventaris owner) 30,236,580.00 0.3689 0.0738 0.0738 0.0738 0.0738 0.0738
6 Listrik Kerja 11,764,200.00 0.1435 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048 0.0048
7 Air Kerja 9,300,000.00 0.1135 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038 0.0038
8 Pembersihan Lokasi (Menggunakan Alat Berat) 70,085,000.00 0.8550 0.1710 0.1710 0.1710 0.1710 0.1710
9 Dokumentasi, Pelaporan dan Asbuildrawing 14,500,000.00 0.1769 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059
10 Sistem Manajemen Keselamatan dan Kesehatan Kerja (SMK3) 35,640,000.00 0.4348 0.1087 0.1087 0.1087 0.1087

II Pekerjaan Elemen I
Devisi 1.0 Pekerjaan Drainase Luar
Section 7.1.1 Pekerjaan Awal 281,432.98 0.0034 0.0034
Section 1.1.2 Pekerjaan Drainase Baru 60,388,872.16 0.7367 0.2456 0.2456 0.2456
Section 1.1.3 Pekerjaan Penutup Drainase Lama 69,021,737.88 0.8420 0.2807 0.2807 0.2807

II Pekerjaan Elemen II
Devisi 1.0 Pekerjaan Tangga
Section 1.1.1 Pekerjaan Awal 2,877,399.25 0.0351 0.0351
Section 1.1.2 Pekerjaan Tangga Tipe 8 438,446,986.58 5.3487 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.1198 0.6119 0.6119 0.6119 0.6119 0.6119 0.6119
Devisi 2.0 Pekerjaan Ramp
Section 2.1.1 Pekerjaan Awal 1,586,813.07 0.0194 0.0194
Section 2.1.2 Pekerjaan Ramp Tipe 7 69,772,968.43 0.8512 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.0109 0.1163 0.1163 0.1163 0.1163 0.1163 0.1163
Devisi 3.0 Pekerjaan Planter Box
Section 3.1.1 Pekerjaan Awal 359,979.13 0.0044 0.0044
Section 3.1.2 Pekerjaan Planter Box Tipe 12 10,789,157.45 0.1316 0.0061 0.0061 0.0061 0.0061 0.0061 0.0061 0.0316 0.0316 0.0316
Devisi 4.0 Pekerjaan Tiang Bendera (Retractable) 8,454,779.40 0.1031 0.0129 0.0129 0.0129 0.0129 0.0129 0.0129 0.0129 0.0129
Devisi 5.0 Pekerjaan Talud
Section 5.1.1 Pekerjaan Awal 834,944.00 0.0102 0.0102
Section 5.1.2 Pekerjaan Pondasi Batu Kali
1 Pekerjaan Talud C 28,901,329.33 0.3526 0.1175 0.1175 0.1175
2 Pekerjaan Talud D 24,276,555.60 0.2962 0.0987 0.0987 0.0987
Devisi 6.0 Pekerjaan Kanstin
Section 6.1.1 Pekerjaan Awal 672,929.40 0.0082 0.0082
Section 6.1.2 Pekerjaan Pasangan Kanstin 9,472,448.70 0.1156 0.1156
Devisi 7.0 Pekerjaan Drainase Luar
Section 7.1.1 Pekerjaan Awal 313,720.00 0.0038 0.0038
Section 7.1.2 Pekerjaan Drainase Baru 59,702,508.09 0.7283 0.3642 0.3642
Divisi 8.0 Pekerjaan Drainase Dalam
Section 8.1.1 Pekerjaan Awal 1,236,579.67 0.0151 0.0151
Section 8.1.2 Pekerjaan Drainase Baru 436,964,915.74 5.3306 0.7615 0.7615 0.7615 0.7615 0.7615 0.7615 0.7615
Devisi 9.0 Pekerjaan Lansekap
Section 9.1.1 Pekerjaan Hardscape
1 Zona Fleksibel Untuk Event 1,652,466,576.76 20.1587 0.8063 0.8063 0.8063 0.8063 0.8063 0.8063 0.8063 0.8063 0.8063 1.0751 1.0751 1.0751 1.0751 1.0751 1.0751 1.0751 1.0751 1.0751 1.0751 1.0751 1.0751
2 Plaza Eksibisi 585,730,704.23 7.1454 0.1327 0.1327 0.1327 0.1327 0.1327 0.1327 0.1327 0.5180 0.5180 0.5180 0.5180 0.5180 0.5180 0.5180 0.5180 0.5180 0.5180 0.5180 0.5180
3 Titik Tiang Bendera (Retractable) 227,819,646.56 2.7792 0.3970 0.3970 0.3970 0.3970 0.3970 0.3970 0.3970
4 Zona Taman Batu 54,207,268.14 0.6613 0.0945 0.0945 0.0945 0.0945 0.0945 0.0945 0.0945
5 Joging Track 92,336,195.52 1.1264 0.1024 0.1024 0.1024 0.1024 0.1024 0.1024 0.1024 0.1024 0.1024 0.1024 0.1024
Section 9.1.2 Pekerjaan softsscape 10,310,322.55 0.1258 0.0157 0.0157 0.0157 0.0157 0.0157 0.0157 0.0157 0.0157
Section 9.1.3 Pekerjaan Furnitur 41,674,979.28 0.5084 0.1271 0.1271 0.1271 0.1271

III Pekerjaan Elemen IV


Devisi 1.0 Pekerjaan Lansekap
Section 1.1.1 Pekerjaan Furnitur
Section 1.1.1.1 Pekerjaan Fitness Outdoor 171,801,355.00 2.0958 0.5240 0.5240 0.5240 0.5240

IV Pekerjaan Elemen V
Devisi 1.0 Pekerjaan Tangga
Section 1.1.1 Pekerjaan Awal 2,496,834.27 0.0305 0.0305
Section 1.1.2 Pekerjaan Tangga Tipe 9 270,812,840.55 3.3037 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.9691 0.9691 0.9691
Devisi 2.0 Pekerjaan Ramp
Section 2.1.1 Pekerjaan Awal 646,902.30 0.0079 0.0079
Section 2.1.2 Pekerjaan Ramp Tipe 11 10,197,705.24 0.1244 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089 0.0089
Section 2.1.3 Pekerjaan Ramp Tipe 12 9,147,406.18 0.1116 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080 0.0080
Devisi 3.0 Pekerjaan Planter Box
Section 3.1.1 Pekerjaan Awal 2,320,073.25 0.0283 0.0283
Section 3.1.2 Pekerjaan Planter Box Tipe 18 9,842,197.34 0.1201 0.0054 0.0054 0.0054 0.0054 0.0054 0.0054 0.0292 0.0292 0.0292
Section 3.1.3 Pekerjaan Planter Box Tipe 19 18,107,870.63 0.2209 0.0099 0.0099 0.0099 0.0099 0.0099 0.0099 0.0538 0.0538 0.0538
Section 3.1.4 Pekerjaan Planter Box Tipe 20 34,987,959.80 0.4268 0.0164 0.0164 0.0164 0.0164 0.0164 0.0164 0.1096 0.1096 0.1096
Section 3.1.5 Pekerjaan Planter Box Tipe 21 13,538,647.21 0.1652 0.0110 0.0110 0.0110 0.0110 0.0110 0.0110 0.0330 0.0330 0.0330
Devisi 4.0 Pekerjaan Talud
Section 4.1.1 Pekerjaan Awal 1,464,630.93 0.0179 0.0179
Section 4.1.2 Pekerjaan Pondasi Batu Kali
1 Pekerjaan Talud D 125,210,344.42 1.5275 0.3055 0.3055 0.3055 0.3055 0.3055
Devisi 5.0 Pekerjaan Kanstin
Section 5.1.1 Pekerjaan Awal 1,553,436.87 0.0190 0.0190
Section 5.1.2 Pekerjaan Pasangan Kanstin 21,866,857.10 0.2668 0.2668
Devisi 6.0 Pekerjaan Drainase Luar
Section 6.1.1 Pekerjaan Awal 1,201,939.75 0.0147 0.0147
Section 6.1.2 Pekerjaan Drainase Baru 228,737,680.71 2.7904 0.5581 0.5581 0.5581 0.5581 0.5581
Divisi 7.0 Pekerjaan Drainase Dalam
Section 7.1.1 Pekerjaan Awal 979,852.13 0.0120 0.0120
Section 7.1.2 Pekerjaan Drainase Baru 159,847,144.93 1.9500 0.3900 0.3900 0.3900 0.3900 0.3900
Devisi 8.0 Pekerjaan Lansekap
Section 8.1.1 Pekerjaan Hardscape
1 Urugan Pasir T = 7 cm 5,129,251.05 0.0626 0.0313 0.0313
2 Urugan Pasir T = 10 cm 12,918,178.35 0.1576 0.1576
3 Lantai Kerja K. 100, T = 7 cm 26,208,561.85 0.3197 0.0400 0.0400 0.0400 0.0400 0.0400 0.0400 0.0400 0.0400
4 Batu Bata Tempel (BB) 8,511,525.69 0.1038 0.0346 0.0346 0.0346
5 Batu Andesit 30 x 30 cm (AN3) 69,945,573.50 0.8533 0.0853 0.0853 0.0853 0.0853 0.0853 0.0853 0.0853 0.0853 0.0853 0.0853
6 Batu Sikat (Batu Mangga Besar) 15,870,476.88 0.1936 0.0194 0.0194 0.0194 0.0194 0.0194 0.0194 0.0194 0.0194 0.0194 0.0194
7 Batu Sikat (Batu Mangga Kecil) 4,310,348.63 0.0526 0.0053 0.0053 0.0053 0.0053 0.0053 0.0053 0.0053 0.0053 0.0053 0.0053
8 EPDM granules tipe Rubber cor (EPDM 1) 228,782,269.10 2.7909 0.9303 0.9303 0.9303
9 Lantai Paving Bata K. 300 Uk 21 x 10,5 x 8 Cm (PEX) 69,758,617.06 0.8510 0.1418 0.1418 0.1418 0.1418 0.1418 0.1418
10 Lantai Paving seling rumput jepang (PRJ) 77,709,234.63 0.9480 0.1580 0.1580 0.1580 0.1580 0.1580 0.1580
11 Joging Track 71,651,337.06 0.8741 0.0795 0.0795 0.0795 0.0795 0.0795 0.0795 0.0795 0.0795 0.0795 0.0795 0.0795
Section 8.1.2 Pekerjaan softsscape 65,654,014.12 0.8009 0.1001 0.1001 0.1001 0.1001 0.1001 0.1001 0.1001 0.1001
Section 8.1.3 Pekerjaan Furnitur
Section 8.1.3.1 Pekerjaan Playground dan Flying Fox 118,250,000.00 1.4425 0.2885 0.2885 0.2885 0.2885 0.2885
Section 8.1.3.2 Pekerjaan Furnitur Pendukung 69,819,750.00 0.8517 0.2129 0.2129 0.2129 0.2129

V Pekerjaan Elemen VI
Devisi 1.0 Pekerjaan Tangga
Section 1.1.1 Pekerjaan Awal 1,919,741.27 0.0234 0.0234
Section 1.1.2 Pekerjaan Tangga Tipe 6 28,430,730.81 0.3468 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0102 0.0341 0.0341 0.0341 0.0341 0.0341 0.0341
Section 1.1.3 Pekerjaan Tangga Tipe 7 56,172,735.14 0.6853 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0186 0.0708 0.0708 0.0708 0.0708 0.0708 0.0708
Devisi 2.0 Pekerjaan Ramp
Section 2.1.1 Pekerjaan Awal 2,535,029.93 0.0309 0.0309
Section 2.1.2 Pekerjaan Ramp Tipe 8c 1,752,015.76 0.0214 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015
Section 2.1.3 Pekerjaan Ramp Tipe 8d 1,752,015.76 0.0214 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015
Section 2.1.4 Pekerjaan Ramp Tipe 8e 1,752,015.76 0.0214 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015 0.0015
Section 2.1.5 Pekerjaan Ramp Tipe 9 9,802,037.96 0.1196 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085 0.0085
Section 2.1.6 Pekerjaan Ramp Tipe 10 8,665,306.11 0.1057 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076 0.0076
Devisi 3.0 Pekerjaan Balustrade
Section 3.1.1 Pekerjaan Awal 1,359,453.33 0.0166 0.0166
Section 3.1.2 Pekerjaan Beton 14,177,112.95 0.1729 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216
Section 3.1.3 Pekerjaan Pasangan, Plesteran dan Acian 38,273,284.65 0.4669 0.1167 0.1167 0.1167 0.1167
Devisi 4.0 Pekerjaan Planter Box
Section 4.1.1 Pekerjaan Awal 2,726,501.43 0.0333 0.0333
Section 4.1.2 Pekerjaan Planter Box Tipe 13 41,842,735.31 0.5104 0.0230 0.0230 0.0230 0.0230 0.0230 0.0230 0.1242 0.1242 0.1242
Section 4.1.3 Pekerjaan Planter Box Tipe 14 31,075,174.99 0.3791 0.0171 0.0171 0.0171 0.0171 0.0171 0.0171 0.0922 0.0922 0.0922
Section 4.1.4 Pekerjaan Planter Box Tipe 15 49,326,278.93 0.6017 0.0271 0.0271 0.0271 0.0271 0.0271 0.0271 0.1464 0.1464 0.1464
Section 4.1.5 Pekerjaan Planter Box Tipe 16 10,557,080.10 0.1288 0.0058 0.0058 0.0058 0.0058 0.0058 0.0058 0.0313 0.0313 0.0313
Section 4.1.6 Pekerjaan Planter Box Tipe 17 22,161,958.88 0.2704 0.0122 0.0122 0.0122 0.0122 0.0122 0.0122 0.0658 0.0658 0.0658
Devisi 5.0 Pekerjaan Talud
Section 5.1.1 Pekerjaan Awal 2,064,210.68 0.0252 0.0252
Section 5.1.2 Pekerjaan Pondasi Batu Kali
1 Pekerjaan Talud C 27,655,477.58 0.3374 0.0843 0.0843 0.0843 0.0843
2 Pekerjaan Talud D 103,323,691.78 1.2605 0.2521 0.2521 0.2521 0.2521 0.2521
Devisi 6.0 Pekerjaan Kanstin
Section 6.1.1 Pekerjaan Awal 1,441,020.53 0.0176 0.0176
Section 6.1.2 Pekerjaan Pasangan Kanstin 20,284,435.60 0.2475 0.2475
Devisi 7.0 Pekerjaan Drainase Luar
Section 7.1.1 Pekerjaan Penutup Drainase Lama 1,947,795.95 0.0238 0.0238
Divisi 8.0 Pekerjaan Drainase Dalam
Section 8.1.1 Pekerjaan Awal 340,647.63 0.0042 0.0042
Section 8.1.2 Pekerjaan Drainase Baru 185,273,216.04 2.2602 0.4520 0.4520 0.4520 0.4520 0.4520
Devisi 9.0 Pekerjaan Lansekap
Section 9.1.1 Pekerjaan Hardscape
1 Urugan Pasir T = 7 cm 18,384,031.05 0.2243 0.1121 0.1121
2 Urugan Pasir T = 10 cm 10,148,626.95 0.1238 0.1238
3 Lantai Kerja K. 100, T = 7 cm 93,935,549.27 1.1459 0.1432 0.1432 0.1432 0.1432 0.1432 0.1432 0.1432 0.1432
4 Lantai Batu Bata Tempel (BB) 10,819,179.94 0.1320 0.0440 0.0440 0.0440
5 Batu Andesit 30 x 30 cm (AN3) 151,667,046.58 1.8502 0.1850 0.1850 0.1850 0.1850 0.1850 0.1850 0.1850 0.1850 0.1850 0.1850
6 Acian Lantai 54,784,820.06 0.6683 0.0668 0.0668 0.0668 0.0668 0.0668 0.0668 0.0668 0.0668 0.0668 0.0668
7 High Duty Floor Paint (FP) 52,826,363.54 0.6444 0.0644 0.0644 0.0644 0.0644 0.0644 0.0644 0.0644 0.0644 0.0644 0.0644
8 Lantai Paving Bata K. 300 Uk 21 x 10,5 x 8 Cm (PEX) 49,524,034.18 0.6042 0.0604 0.0604 0.0604 0.0604 0.0604 0.0604 0.0604 0.0604 0.0604 0.0604
9 Lantai Paving Bata K. 300 Uk 21 x 10,5 x 8 Cm (PBS) 69,587,598.30 0.8489 0.0849 0.0849 0.0849 0.0849 0.0849 0.0849 0.0849 0.0849 0.0849 0.0849
10 Joging Track 83,622,267.97 1.0201 0.1020 0.1020 0.1020 0.1020 0.1020 0.1020 0.1020 0.1020 0.1020 0.1020
Section 9.1.2 Pekerjaan softsscape 29,892,223.79 0.3647 0.0456 0.0456 0.0456 0.0456 0.0456 0.0456 0.0456 0.0456
Section 9.1.3 Pekerjaan Furnitur 96,769,200.00 1.1805 0.2951 0.2951 0.2951 0.2951

VI Pekerjaan Mekanikal dan Elektrikal Dalam Site


Devisi 1.0 Pekerjaan Mekanikal 10,720,215.00 0.1308 0.0654 0.0654
Devisi 2.0 Pekerjaan Elektrikal
Section 2.1.1 Pekerjaan Penarikan Kabel 27,402,375.00 0.3343 0.1114 0.1114 0.1114
Section 2.1.2 Pekerjaan Penerangan 497,692,772.50 6.0714 0.7589 0.7589 0.7589 0.7589 0.7589 0.7589 0.7589 0.7589
JUMLAH 8,197,297,732.7 100.00 0.6451 0.8462 1.0172 1.0172 0.7518 0.8362 4.5053 4.1415 5.2251 4.2013 4.1971 2.1280 2.1662 1.3881 1.5880 1.5220 2.0910 2.7451 2.9141 2.8355 4.5931 4.5931 5.8616 5.1444 5.0277 5.3162 7.2229 6.5484 6.5484 2.3824
PPN 11 % 901,702,750.60 0.65 1.49 2.51 3.53 4.28 5.11 9.62 13.76 18.99 23.19 27.38 29.51 31.68 33.07 34.65 36.18 38.27 41.01 43.93 46.76 51.35 55.95 61.81 66.95 71.98 77.30 84.52 91.07 97.62 100.0
JUMLAH TOTAL 9,099,000,483.33

Palu, 19 Mei 2023


CV. INTAN KARYA AGUNG