JADWAL PELAKSANAAN PEKERJAAN

PROGRAM : PENGELOLAAN DAN PENGEMBAGAN SISTIM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KABUPATEN/KOTA
KEGIATAN : PERLUASAN SPAM JARINGAN PERPIPAAN DI KAWASAN PERDESAAN
PEKERJAAN : PENGEMBANGAN JARINGAN DISTRIBUSI DAN SR NAGARI SUNGAI SIRAH AIR HAJI
LOKASI : KECAMATAN LINGGO SARI BAGANTI, KABUPATEN PESISIR SELATAN
TAHUN : 2021

Kemajuan Pekerjaan Per MingguBulan(%)


No Uraian Pekerjaan Bobot(%) Bulan Ke-1 Bulan Ke-2 Bulan Ke-2 Bulan Ke-3 KET.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
100%
I
PEKERJAAN PERSIAPAN
Los Kerja / Gudang (Sewa) 0.37% 0.18% 0.18%
Pengukuran Ulang, Dokumentasi dan Pelaporan 0.22% 0.22%
Pengadaan Perlengkapan Penanganan COVID -19
- Rambu - Rambu 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
II - Helm Proyek 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 90%
- Sepatu Boat 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- P3K 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Masker 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Rompi 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI RENCANA RENCANA
PEKERJAAN TANAH
Galian Tanah Biasa untuk Pemasangan Pipa
- ND 150 mm 1.59% 0.79% 0.79%
- ND 100 mm 0.78% 0.39% 0.39% 80%
- ND 75 mm 0.00% 0.00% 0.00%
- ND 50 mm 0.63% 0.32% 0.32%
- ND 40 mm
Galian Tanah Keras (Berbatu) untuk Pemasangan Pipa
- ND 150 mm 0.64% 0.32% 0.32%
- ND 100 mm 0.49% 0.25% 0.25% 70%
- ND 75 mm 1.10% 0.55% 0.55%
- ND 50 mm 0.87% 0.44% 0.44%
- ND 40 mm 0.67% 0.67%
Penimbunan Bekas Galian dengan Tanah Timbunan yang Bersih/Tidak
Mengandung Kotoran & Batuan (Tanah Terpilih)
- ND 150 mm 1.69% 0.85% 0.85%
- ND 100 mm 0.00% 0.00% 0.00%
- ND 75 mm 0.00% 0.00% 0.00%
- ND 50 mm 0.00% 0.00% 0.00% 60%
- ND 40 mm 17.20% 2.46% 2.46% 2.46% 2.46% 2.46% 2.46% 2.46%
PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA DAN ACCESSORIES
Pengadaan dan Pemasangan Pipa PVC Lengkap dengan Accessories :
SNI 06 0084 2002
- ND 150 mm S-12,5 (RRJ) 13.80% 4.60% 4.60% 4.60%
- ND 100 mm S-12,5 (RRJ) 8.46% 2.82% 2.82% 2.82%
- ND 75 mm S-12,5 (RRJ) 11.72% 3.91% 3.91% 3.91%
50%
- ND 50 mm S-12,5 (RRJ) 5.99% 2.99% 2.99%
- ND 40 mm S-10 (SCJ) 4.51% 2.26% 2.26%
Pengadaan dan Pemasangan Reducer PVC (RRJ)
- ND 150 mm x 100 mm 0.02% 0.01% 0.01% 0.01%
- ND 100 mm x 75 mm 0.03% 0.01% 0.01% 0.01%
- ND 75 mm x 50 mm 0.03% 0.01% 0.01% 0.01%
- ND 50 mm x 40 mm 0.03% 0.01% 0.01%
Pengadaan dan Pemasangan Koneksi PVC Tee (RRJ)
- ND 75 mm x 75 mm x 75 mm 0.02% 0.01% 0.01% 40%
- ND 50 mm x 50 mm x 50 mm 0.01% 0.01% 0.01%
Pengadaan dan Pemasangan Bend PVC (RRJ)
- ND 75 mm - 90⁰ 0.01% 0.01% 0.01%
Pengadaan dan Pemasangan Gate Valve
- ND 150 mm 0.18% 0.06% 0.06% 0.06%
- ND 100 mm 0.11% 0.05% 0.05%
- ND 75 mm 0.09% 0.09%
30%
Pengadaan dan Pemasangan Box Street
- ND 100 mm 0.10% 0.10%
Pengadaan dan Pemasangan Dop PVC
- ND 50 mm 0.00% 0.00%
- ND 40 mm 0.00% 0.00%
PEKERJAAN PELENGKAP JARINGAN PIPA DISTRIBUSI DAN TERSIER
20%
Pekerjaan Pembuatan Jembatan Pipa GIP
- ND 100 mm Bentangan 18 M' 1.10% 0.37% 0.37% 0.37%
- ND 75 mm Bentangan 18 M' 1.07% 0.53% 0.53%
Pekerjaan Crossing Pipa PVC Pada Jalan Aspal / Beton
- ND 75 mm Bentangan 6 M' 0.51% 0.26% 0.26%
Pembuatan Wash Out
- ND 50 mm Pada Jalur Pipa 0.34% 0.17% 0.17%
Pengadaan dan Pemasangan Air Valve ND 25 mm Pada Jalur Pipa / Jembatan 0.06% 0.06%
Flushing (Pencucian) dan Pengetesan Pipa
- Pipa PVC ND 150 mm 0.13% 0.04% 0.04% 0.04% 10%
- Pipa PVC ND 100 mm 0.12% 0.04% 0.04% 0.04%
- Pipa PVC ND 75 mm 0.20% 0.07% 0.07% 0.07%
- Pipa PVC ND 50 mm 0.12% 0.06% 0.06%
- Pipa PVC ND 40 mm 0.11% 0.05% 0.05%
PEKERJAAN PENGADAAN DAN PEMASANGAN SAMBUNGAN RUMAH
PEKERJAAN SAMBUNGAN RUMAH
- Pengadaan dan Pemasangan Sambungan Rumah Pada Pipa ND 100 mm 4.12% 1.03% 1.03% 1.03% 1.03%
0%
- Pengadaan dan Pemasangan Sambungan Rumah Pada Pipa ND 75 mm 6.08% 2.03% 2.03% 2.03%
- Pengadaan dan Pemasangan Sambungan Rumah Pada Pipa ND 50 mm 5.31% 1.77% 1.77% 1.77%
- Pengadaan dan Pemasangan Sambungan Rumah Pada Pipa ND 40 mm 9.22% 2.30% 2.30% 2.30% 2.30%
JUMLAH 100.00%
1 Bobot Rencana Per Minggu 1.53% 2.49% 6.55% 8.85% 11.34% 6.74% 9.17% 5.28% 0.04% 3.34% 5.45% 5.05% 9.08% 9.82% 8.75% 6.54%
2 Bobot Rencana Komulatif 1.53% 4.02% 10.57% 19.42% 30.75% 37.49% 46.66% 51.94% 51.98% 55.32% 60.77% 65.82% 74.89% 84.71% 93.46% 100.00%
3 Bobot Realisasi Per Minggu - - - - - - - - - - - - - - - -
Bobot Realisasi Komulatif - - - - - - - - - - - - - - - -
4 Deviasi - - - - - - - - - - - - - - - -

Jangka waktu pelaksanaan pekerjaan pisik = 120 (Seratus Dua Puluh ) hari kalender
Solok, 23 Juni 2021
Hormat Kami
CV SANSALAK PERKASA

Ttd

DASRIANTO
Kuasa Direktur