NAMA PEKERJAAN : PEMBANGUNAN JALUR KA ELEVATED ANTARA SOLO BALAPAN - KADIPIRO KM. 104+700 SD KM. 107+000 (TAHAP 1)
LOKASI PEKERJAAN : SIMPANG JOGLO LINTAS SOLO - KADIPIRO

KODE BULAN KE -
NO. SPESIFIKAS URAIAN PEKERJAAN SATUAN VOLUME Bobot
I TEKNIK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
I. UMUM
1 Mobilisasi dan Demobilisasi Peralatan kerja ton 50.00 0.046% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Angkutan Rel R.54 dari Gudang ke Lokasi ton 155.52 0.041% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
3 Pengukuran dan staking out m2 36,000.00 0.041% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Sewa direksi keet (container 20 ft) 3bh bln 25.00 0.060% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Penyelidikan Tanah (uji sondir) titik 14.00 0.008% 0.00% 0.00%
6 Penyelidikan Tanah (uji boring) titik 4.00 0.032% 0.02% 0.02%
7 Patok km/hm bh 14.00 0.004% 0.00%
8 Tanda lintas/marka/rambu bh 10.00 0.002% 0.00%
9 Manajemen dan keselamatan lalu lintas ls 1.00 0.167% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
10 Keamanan dan Kesehatan Kerja serta keselamatan kontruksi ls 1.00 0.363% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
JUMLAH : I. 0.76%
II. SIPIL
1 Stripping/pembersihan lahan m2 14,400.00 0.085% 0.01% 0.03% 0.04%
2 Bongkar Pasangan Batu kali m3 100.00 0.003% 0.00% 0.00% 0.00%
3 Bongkar Beton m3 100.00 0.005% 0.00% 0.00% 0.00%
4 Bongkar Aspal m2 200.00 0.002% 0.00% 0.00% 0.00%
5 Galian tanah termasuk buangan m3 18,000.00 0.303% 0.06% 0.12% 0.12%
6 Timbunan dengan materal tanah pilihan m3 13,500.00 0.676% 0.11% 0.23% 0.34%
7 Timbunan dengan material berbutir m3 3,870.00 0.433% 0.43%
8 Perbaikan tanah dasar dengan Material berbutir dibungkus Geotekstile m3 2,700.00 0.533% 0.13% 0.13% 0.27%
9 Pemasangan geotextile Sebagai Separator m2 6,750.00 0.103% 0.05% 0.05%
10 Pekerjaan Jalan akses m 1,440.00 0.367% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
11 Pagar panel dengan sloof dan ring balk m 640.00 0.343% 0.11% 0.11% 0.11%
12 Saluran pracetak uk. 60x70x120 cm dengan lantai kerja m 940.00 0.446% 0.11% 0.11% 0.11% 0.11%
JUMLAH : II 3.30%
III. PEKERJAAN TRACK
1 Pengadaan dan pengeceran Balas kricak m3 3,312.00 0.685% 0.08% 0.16% 0.16% 0.16% 0.07% 0.07%
2 Pengadaan Bantalan beton dan sistem penambat btg 2,380.00 0.570% 0.07% 0.13% 0.13% 0.13% 0.06% 0.06%
3 Angkutan bantalan beton ke lokasi pekerjaan btg 2,380.00 0.035% 0.01% 0.01% 0.01% 0.00% 0.00%
4 Memasang MJ berikut bahan (bantalan kayu dan plat sambung lengkap) @4 bantalan titik 5.00 0.030% 0.01% 0.01%
5 Memasang Jalur KA rel R.54, balas, bantalan beton, serta Pemadatan awal (HTT) msp 1,440.00 0.329% 0.13% 0.13% 0.03% 0.03%
6 Mengelas rel R.54 dengan las thermit menjadi panjang menerus. titik 106.00 0.085% 0.07% 0.02%
7 Relokasi utilitas/ detour (PLN, Kabel, FO, Jalan dan saluran, JPL termasuk palang pintunya) untuk LS 1.00 0.559% 0.06% 0.12% 0.12% 0.12% 0.12%
8 Angkat listring dengan alat berat (MTT) msp 1,440.00 0.128% 0.10% 0.03%
9 Switch Over titik 2.00 0.126% 0.13%
JUMLAH : III. 2.55%
IV. JEMBATAN
1 Pekerjaan Sipil
Sewa SSP untuk Perkuatan Shoring penahan tanah (m dalam) m 3,360.00 0.395% 0.10% 0.10% 0.10% 0.10%
Pancang SSP untuk Perkuatan Shoring penahan tanah (m dalam) m 3,360.00 0.152% 0.04% 0.04% 0.04% 0.04%
Mencabut SSP untuk Shoring m 3,360.00 0.152% 0.08% 0.08%
Pekerjaan bracing untuk perkuatan shoring (m keliling) m 672.00 0.103% 0.03% 0.03% 0.03% 0.03%
Galian tanah termasuk buangan m3 2,366.00 0.040% 0.04%
Timbunan dengan tanah bekas galian termasuk pemadatan m3 788.67 0.025% 0.01% 0.01%
2 Pekerjaan Pier Stuktur
Beton fc' 15 Mpa Lantai kerja berikut bekisting m3 98.60 0.041% 0.04%
Beton fc' 30 Mpa pada Pilecap dan Slab berikut bekisting m3 4,042.17 3.415% 0.85% 0.85% 0.85% 0.85%
Pembesian baja ulir BJTS-420B pada Pilecap dan Slab kg 1,637,097.68 10.946% 0.24% 0.24% 0.49% 0.73% 0.73% 0.12% 0.12% 0.24% 0.24% 0.49% 0.49% 0.73% 2.03% 2.03% 2.03%
Beton fc' 35 Mpa pada Pier, Pier head, balok berikut bekisting m3 2,129.63 2.180% 0.44% 0.44% 0.44% 0.44% 0.44%
Pengeboran dan pengecoran Bore Pile dia.150 cm fc30 Mpa m 2,542.00 4.058% 1.62% 1.62% 0.81%
Pembesian baja ulir BJTS-420B pada Borepile kg 736,924.11 4.927% 1.97% 1.97% 0.99%
Memotong /bobok borepile dia. 150 cm titik 74.00 0.044% 0.04%
Pengadaan dan pemasangan tendon kg 56,503.98 1.297% 0.65% 0.65%
3 Jembatan Baja
Pengadaan jembatan rangka baja pipa dia 1.200 mm tebal 22mm dan 800mm tebal 14 mm
kg 2,623,907.20 38.487% 0.05% 0.05% 0.15% 0.30% 1.40% 2.90% 2.50% 2.50% 3.05% 3.37% 3.67% 4.30% 4.00% 4.00% 4.00% 2.25%
SMA 490
Angkutan jembatan rangka baja pipa dia 1.200 mm tebal 22mm dan 800mm tebal 14 mm SMA
kg 2,623,907.20 2.269% 0.05% 0.05% 0.10% 0.10% 0.15% 0.15% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.42%
490
Pemasangan dan penyetelan jembatan rangka baja pipa dia 1.200 mm tebal 22mm dan
kg 2,623,907.20 10.211% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85%
800mm tebal 14 mm SMA 490
4 Beton Barrier
Beton fc30 pada Barrier berikut bekisting m3 395.45 0.398% 0.20% 0.20%
Pembesian baja ulir BJTS-420B pada barrier kg 59,317.63 0.397% 0.20% 0.20%
5 Pengujian
Statik aksial loading test 3000 ton buah 2.00 0.620% 0.62%
Pengujian Pembebanan Pada Tiang Dengan Diameter 1500 mm (PDA) tes buah 4.00 0.018% 0.02%
Pengujian Keutuhan Tiang dengan Pile Integrated Test (PIT) buah 74.00 0.038% 0.04%
Pengujian Lateral Loading Test titik 2.00 0.046% 0.05%
Sambungan Siar Muai Expansion Joint Tipe Modular 15 cm m 25.00 0.072% 0.07%
Pengujian jembatan dengan item sebagai berikut Set 1.00 0.947% 0.95%
Pengamatan regangan dengan VWSG titik 36.00
Pengamatan dengan Tilmeter titik 23.00
Laser distance meter titik 19.00
Displacement Tranducer titik 20.00
Accelerometer titik 21.00
Vibrometer titik 5.00
Shaker titik 2.00
Pekerjaan ME (Penangkal petir dan pencahayaan) dan Landscape dengan spesifikasi Set 1.00 1.175% 0.59% 0.59%
Pekerjaan pemeliharaan kinerja (SHMS) Set 1.00 1.628% 0.81% 0.81%
6 Bearing
GG-04 (Vmax = 8000 kN) unit 1.00 0.282% 0.01% 0.01% 0.03% 0.03% 0.09% 0.09%
FX (Vmax = 8000 kN) unit 1.00 0.207% 0.01% 0.01% 0.02% 0.02% 0.07% 0.07%
GL-02 (Vmax = 20000 kN) unit 2.00 0.142% 0.01% 0.01% 0.02% 0.02% 0.05% 0.05%
GG-02 (Vmax = 20000 kN) unit 2.00 0.235% 0.01% 0.01% 0.03% 0.03% 0.08% 0.08%
GL-03 (Vmax = 45000 kN) unit 2.00 0.416% 0.02% 0.02% 0.05% 0.05% 0.14% 0.14%
GG-03 (Vmax = 45000 kN) unit 2.00 0.645% 0.03% 0.03% 0.08% 0.08% 0.22% 0.22%
GL-01 (Vmax = 8000 kN) unit 1.00 0.039% 0.00% 0.00% 0.00% 0.00% 0.01% 0.01%
GG-01 (Vmax = 8000 kN) unit 1.00 0.042% 0.00% 0.00% 0.00% 0.00% 0.01% 0.01%
Instalasi Pot Bearing Ls 1.00 0.075% 0.04% 0.04%
Pengujian Pot Bearing Ls 1.00 0.205% 0.04% 0.04% 0.04% 0.04% 0.04%
STU 4000/100 unit 24.00 6.241% 0.10% 0.10% 0.10% 0.10% 0.21% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47%
STU 3000/100 unit 2.00 0.374% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.05% 0.05% 0.05% 0.01% 0.01% 0.02% 0.14%
Expansion Joint SX 80 m 24.60 0.099% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
Instalasi STU Ls 1.00 0.043% 0.02% 0.02%
Instalasi SX 80 Ls 1.00 0.049% 0.05%
Pengujian STU&SX80 Ls 1.00 0.214% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
JUMLAH : IV. 93.39%
Jumlah Total Progress 100.00%
Rencana Progress Per Bulan 0.06% 0.22% 0.87% 1.17% 1.86% 4.93% 5.70% 5.50% 5.48% 5.93% 5.91% 5.82% 5.71% 5.48% 6.11% 6.10% 6.10% 6.34% 6.09% 4.27% 4.46% 2.76% 2.02% 1.10%
Rencana Komulatif Progress Per Bulan 0.06% 0.28% 1.15% 2.32% 4.17% 9.10% 14.80% 20.30% 25.78% 31.71% 37.62% 43.45% 49.15% 54.64% 60.75% 66.85% 72.95% 79.29% 85.38% 89.65% 94.12% 96.88% 98.90% 100.00%

Surakarta, 23 Desember 2021


SATKER KEGIATAN PENGEMBANGAN PERKERETAAPIAN
JAWA BAGIAN TENGAH AREA 1 KONSULTAN MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANA
PEJABAT PEMBUAT KOMITMEN PT. RAYAKONSULT WIKA - BKU. KSO

Dheky Martin Ir. Arvila Delitriana, MT Ir. Suwito


NIP. 19810316 200712 1 001 Ketua Tim Manajer Proyek