KEMENTERIAN RISET, TEKNOLOGI DAN PENDIDIKAN TINGGI

POLITEKNIK NEGERI PONTIANAK


LABORATORIUM TEKNIK SIPIL

ANALISA AYAK / SIEVE ANALYSIS


SNI 02-2834-1992

Proyek : Tinjauan Rancangan Campuran Asphalt Concreat-Wearing Course


(AC-WC) Pada Proyek Pelebaran Jalan Nanga Badau-Lanjak
Lokasi : Laboratorium POLNEP
Sumber Material : Quarry Genting Lanjak
Pekerjaan : AC - Wearing Course (AC-WC)
Berat Contoh : 2000.00 gr 2000
Type : Coarse Agregat (CA)-Batu Pecah Alam 3/4"

DIAMETER Pengujian 1 Pengujian 2


Berat Persen Persen Tertahan Berat Persen
AYAKAN Tertahan Tertahan Kumulatif Lolos Tertahan Tertahan
Inch mm gram % % % gram %
1 25.40 0.00 0.00 0.00 100.00 0.00 0.00
3/4 19.10 183.48 9.17 9.17 90.83 297.34 14.89
1/2 12.70 1439.09 71.96 81.13 18.87 1357.34 67.97
3/8 9.50 309.78 15.49 96.62 3.38 297.34 14.89
No. 4 4.750 66.51 3.33 99.95 0.05 43.62 2.18
No. 8 2.360 0.00 0.00 99.95 0.05 0.00 0.00
No. 16 1.180 0.00 0.00 99.95 0.05 0.00 0.00
No. 30 0.600 0.00 0.00 99.95 0.05 0.00 0.00
No. 50 0.300 0.00 0.00 99.95 0.05 0.00 0.00
No. 100 0.150 0.00 0.00 99.95 0.05 0.00 0.00
No. 200 0.075 0.00 0.00 99.95 0.05 0.00 0.00
Pan 0.00 1.02 0.05 100.00 0.00 1.25 0.06
Jumlah 1999.88 1996.89
e

e
n

L
o

o
Persen Lolos (%)
s

%
r

)
l

60
70
80
90
30
40
50
10
20
0 0.15 0.30 0.60 1.20 Ukura

100

80

60

40

20

0
1.00 10.00
Diameter Ayak (mm)
NDIDIKAN TINGGI
TIANAK
PIL

YSIS

Tanggal Uji :

Pengujian 2
Persen Tertahan Persen Lolos
Kumulatif Lolos Rata-Rata
% % %
0.00 100.00 100.00
14.89 85.11 87.97
82.86 17.14 18.00
97.75 2.25 2.81
99.94 0.06 0.06
99.94 0.06 0.06
99.94 0.06 0.06
99.94 0.06 0.06
99.94 0.06 0.06
99.94 0.06 0.06
99.94 0.06 0.06
100.00 0.00 0.00

Ukuran Saringan
2.40 (mm)

Hasil Gradasi

100.00
KEMENTERIAN RISET, TEKNOLOGI DAN PENDIDIKAN TINGGI
POLITEKNIK NEGERI PONTIANAK
LABORATORIUM TEKNIK SIPIL

ANALISA AYAK / SIEVE ANALYSIS


SNI 02-2834-1992

Proyek : Tinjauan Rancangan Campuran Asphalt Concreat-Wearing Course


(AC-WC) Pada Proyek Pelebaran Jalan Nanga Badau-Lanjak
Lokasi : Laboratorium POLNEP
Sumber Material : Quarry Genting Lanjak
Pekerjaan : AC - Wearing Course (AC-WC)
Berat Contoh : 1500.00 gr 1500
Type : Medium Aggregate (MA)-Batu Pecah Mesin 3/8"

DIAMETER Pengujian 1 Pengujian 2


Berat Persen Persen Tertahan Berat Persen
AYAKAN Tertahan Tertahan Kumulatif Lolos Tertahan Tertahan
Inch mm gram % % % gram %
1 25.40 0.00 0.00 0.00 100.00 0.00 0.00
3/4 19.10 0.00 0.00 0.00 100.00 0.00 0.00
1/2 12.70 0.00 0.00 0.00 100.00 0.00 0.00
3/8 9.50 17.43 1.16 1.16 98.84 37.39 3.40
No. 4 4.750 761.70 50.83 51.99 48.01 367.05 33.36
No. 8 2.360 444.52 29.66 81.65 18.35 402.43 36.58
No. 16 1.180 107.77 7.19 88.84 11.16 116.70 10.61
No. 30 0.600 49.50 3.30 92.14 7.86 45.70 4.15
No. 50 0.300 35.94 2.40 94.54 5.46 44.23 4.02
No. 100 0.150 48.45 3.23 97.77 2.23 47.07 4.28
No. 200 0.075 26.97 1.80 99.57 0.43 33.41 3.04
Pan 0.00 6.39 0.43 100.00 0.00 6.25 0.57
Jumlah 1498.67 1100.23

60
70
80
90
30
40
50
10
20
0 0.15 0.30 0.60 1.20 Ukuran Saringan
2.40 (m
Persen Lolos (%)

100

80

60

40

20

0
1.00 10.00
Diameter Ayak (mm)
NDIDIKAN TINGGI
TIANAK
PIL

YSIS

Tanggal Uji :

Pengujian 2
Persen Tertahan Persen Lolos
Kumulatif Lolos Rata-Rata
% % %
0.00 100.00 100.00
0.00 100.00 100.00
0.00 100.00 100.00
3.40 96.60 97.72
36.76 63.24 55.63
73.34 26.66 22.51
83.94 16.06 13.61
88.10 11.90 9.88
92.12 7.88 6.67
96.40 3.60 2.92
99.43 0.57 0.50
100.00 0.00 0.00

Ukuran Saringan
2.40 (mm)

Hasil Gradasi

100.00
KEMENTERIAN RISET, TEKNOLOGI DAN PENDIDIKAN TINGGI
POLITEKNIK NEGERI PONTIANAK
LABORATORIUM TEKNIK SIPIL

ANALISA AYAK / SIEVE ANALYSIS


SNI 02-2834-1992

Proyek : Tinjauan Rancangan Campuran Asphalt Concreat-Wearing Course


(AC-WC) Pada Proyek Pelebaran Jalan Nanga Badau-Lanjak
Lokasi : Laboratorium POLNEP
Sumber Material : Quarry Genting Lanjak
Pekerjaan : AC - Wearing Course (AC - WC)
Berat Contoh : 500.00 gr 500
Type : Fine Aggregate (FA)-Abu Batu

DIAMETER Pengujian 1 Pengujian 2


Berat Persen Persen Tertahan Berat Persen
AYAKAN Tertahan Tertahan Kumulatif Lolos Tertahan Tertahan
Inch mm gram % % % gram %
1 25.40 0.00 0.00 0.00 100.00 0.00 0.00
3/4 19.10 0.00 0.00 0.00 100.00 0.00 0.00
1/2 12.70 0.00 0.00 0.00 100.00 0.00 0.00
3/8 9.50 0.00 0.00 0.00 100.00 0.00 0.00
No. 4 4.750 0.22 0.04 0.04 99.96 0.00 0.00
No. 8 2.360 24.32 4.91 4.95 95.05 26.19 5.24
No. 16 1.180 94.70 19.11 24.06 75.94 100.05 20.03
No. 30 0.600 81.77 16.50 40.56 59.44 84.33 16.88
No. 50 0.300 75.94 15.33 55.89 44.11 83.21 16.66
No. 100 0.150 125.34 25.29 81.18 18.82 77.64 15.54
No. 200 0.075 81.00 16.35 97.53 2.47 95.20 19.06
Pan 0.00 12.24 2.47 100.00 0.00 32.94 6.59
Jumlah 495.53 499.56
%
e

e
n

L
o

o
s

s
r

)
Persen Lolos (%)
l

60
70
80
90
30
40
50
10
20
0 0.15 0.30 0.60 1.20 Ukuran Saringan
2.40 (m

100

80

60

40 Hasil Gradasi

20

0
1.00 10.00
Diameter Ayak (mm)
NDIDIKAN TINGGI
TIANAK
PIL

YSIS

Tanggal Uji : 24-Jul-16

Pengujian 2
Persen Tertahan Persen Lolos
Kumulatif Lolos Rata-Rata
% % %
0.00 100.00 100.00
0.00 100.00 100.00
0.00 100.00 100.00
0.00 100.00 100.00
0.00 100.00 99.98
5.24 94.76 94.90
25.27 74.73 75.33
42.15 57.85 58.64
58.81 41.19 42.65
74.35 25.65 22.23
93.41 6.59 4.53
100.00 0.00 0.00

Ukuran Saringan
2.40 (mm)

Hasil Gradasi

100.00
KEMENTERIAN RISET, TEKNOLOGI DAN PENDIDIKAN TINGGI
POLITEKNIK NEGERI PONTIANAK
LABORATORIUM TEKNIK SIPIL

ANALISA AYAK / SIEVE ANALYSIS


SNI 02-2834-1992

Proyek : Tinjauan Rancangan Campuran Asphalt Concreat-Wearing Course


(AC-WC) Pada Proyek Pelebaran Jalan Nanga Badau-Lanjak
Lokasi : Laboratorium Polnep
Sumber Material : Quarry Genting Lanjak
Pekerjaan : AC - Wearing Course (AC-WC)
Berat Contoh : 500.00 gr 500 gr
Type : Pasir (Sand)

DIAMETER Pengujian 1 Pengujian 2


Berat Persen Persen Tertahan Berat Persen Persen Tertahan
AYAKAN Tertahan Tertahan Kumulatif Lolos Tertahan Tertahan Kumulatif
Inch mm gram % % % gram % %
1 25.40 0.00 0.00 0.00 100.00 0.00 0.00 0.00
3/4 19.10 0.00 0.00 0.00 100.00 0.00 0.00 0.00
1/2 12.70 0.00 0.00 0.00 100.00 0.00 0.00 0.00
3/8 9.50 0.00 0.00 0.00 100.00 0.00 0.00 0.00
No. 4 4.750 4.95 0.99 0.99 99.01 4.81 0.97 0.97
No. 8 2.360 24.86 4.98 5.97 94.03 34.02 6.83 7.79
No. 16 1.180 77.08 15.44 21.42 78.58 96.54 19.37 27.16
No. 30 0.600 127.65 25.58 46.99 53.01 136.80 27.45 54.61
No. 50 0.300 141.91 28.43 75.42 24.58 124.52 24.98 79.59
No. 100 0.150 96.62 19.36 94.78 5.22 83.79 16.81 96.40
No. 200 0.075 21.98 4.40 99.19 0.81 15.29 3.07 99.47
Pan 0.00 4.06 0.81 100.00 0.00 2.66 0.53 100.00
Jumlah 499.11 498.43
%
P
e

e
n

L
o
Persen Lolos (% )o
s

s
r

)
l

60
70
80
90
30
40
50
10
20
0 0.15 0.30 0.60 1.20 Ukuran Saringan
2.40 (mm)

100

80

60

Hasil Gradasi
40

20

0
1.00 10.00 10
Diameter Ayak (mm)
DIDIKAN TINGGI
IANAK
L

SIS

Tanggal Uji :

Pengujian 2
Persen Tertahan Persen Lolos
Lolos Rata-Rata
% %
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
99.03 99.02
92.21 93.12
72.84 75.71
45.39 49.20
20.41 22.49
3.60 4.41
0.53 0.67
0.00 0.00

Ukuran Saringan
2.40 (mm)

100.00
KEMENTERIAN RISET, TEKNOLOGI DAN PENDIDIKAN TINGGI
POLITEKNIK NEGERI PONTIANAK
LABORATORIUM TEKNIK SIPIL

ANALISA AYAK / SIEVE ANALYSIS


SNI 02-2834-1992

Proyek : Tinjauan Rancangan Campuran Asphalt Concreat-Wearing Course

Lokasi : Laboratorium POLNEP


Sumber Material : Quarry Lanjak
Pekerjaan : AC - Wearing Course (AC-WC)
Berat Contoh : -
Type : Agregat Gabungan

DIAMETER Campuran
% Lolos
AYAKAN 14.00% 49.00% 20.50% 12.50% 4.00%
Inch mm CA 1 - 2 MA 0.5 FA pasir PC CA 1 - 2 MA 0.5 FA pasir PC
1 25.40 100.00 100.00 100.00 100.00 100.00 14.00 50.00 20.50 12.50 4.00
3/4 19.10 87.97 100.00 100.00 100.00 100.00 12.32 49.00 20.50 12.50 4.00
1/2 12.70 18.00 100.00 100.00 100.00 100.00 2.52 49.00 20.50 12.50 4.00
3/8 9.50 2.81 97.72 100.00 100.00 100.00 0.39 47.88 20.50 12.50 4.00
No. 4 4.750 0.06 55.63 99.98 99.02 100.00 0.01 27.26 20.50 12.38 4.00
No. 8 2.360 0.06 22.51 94.90 93.12 100.00 0.01 11.03 19.46 11.64 4.00
No. 16 1.180 0.06 13.61 75.33 75.71 100.00 0.01 6.67 15.44 9.46 4.00
No. 30 0.600 0.06 9.88 58.64 49.20 80.97 0.01 4.84 12.02 6.15 3.24
No. 50 0.300 0.06 6.67 42.65 22.49 59.53 0.01 3.27 8.74 2.81 2.38
No. 100 0.150 0.06 2.92 22.23 4.41 19.01 0.01 1.43 4.56 0.55 0.76
No. 200 0.075 0.06 0.50 4.53 0.67 5.92 0.01 0.24 0.93 0.08 0.24
Pan 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00
Jumlah
sen Lolos (%)
s

%
P
e

e
n

L
o

o
r

)
l

60
70
80
90
30
40
50
10
20
0 0.15 0.30 1.20 9
100 .
6
0
KEMENTERIAN RISET, TEKNOLOGI DAN PENDIDIKAN TINGGI
POLITEKNIK NEGERI PONTIANAK
LABORATORIUM TEKNIK SIPIL

ANALISA AYAK / SIEVE ANALYSIS


SNI 02-2834-1992

Proyek : Tinjauan Rancangan Campuran Asphalt Concreat-Wearing Course

Lokasi : Laboratorium POLNEP


Sumber Material : Quarry Lanjak
Pekerjaan : AC - Wearing Course (AC-WC)
Berat Contoh : -
Type : Agregat Gabungan
Persen Lolos (%)
s

%
P
e

e
n

L
o

o
r

)
l

60
70
80
90
30
40
50
10
20
0 0.15 0.30 1.20 9
100 .
6
0
Batas Atas Spesifikasi
80
Hasil
60
Campu
40 ran
Gradasi
20
Batas Bawah Spesifikasi

0
0.01 0.10 1.00 10.00
Diameter Ayak (mm)
100.00% Spesifikasi
Campuran
101.00 100
98.32 100
88.52 90 - 100
85.28 77 - 90
64.14 53 - 69
46.13 33.0 - 53
35.58 21.0 - 40
26.26 14.0 - 30
17.21 9.0 - 22
7.31 6 - 15
1.50 4 - 9
0.00

9 19.0
.
6
0
9 19.0
.
6
0

Hasil
Campu
ran
Gradasi
Spesifikasi

10.00 100.00
KEMENTERIAN RISET, TEKNOLOGI DAN PENDIDIKAN TINGGI
POLITEKNIK NEGERI PONTIANAK
LABORATORIUM TEKNIK SIPIL

ANALISA AYAK / SIEVE ANALYSIS


SNI 02-2834-1992

Proyek : Tinjauan Rancangan Campuran Asphalt Concreat-Wearing Course


(AC-WC) Pada Proyek Pelebaran Jalan Nanga Badau-Lanjak
Lokasi : Lab Teknik Sipil Pontianak
Sumber Material : Quarry Genting Lanjak
Pekerjaan : AC - Wearing Course (AC-WC)
Berat Contoh 500 gr 500 gr
Type : Portland Cement (PC)

DIAMETER Pengujian 1 Pengujian 2


Berat Persen Persen Tertahan Berat Persen Persen Tertahan
AYAKAN Tertahan Tertahan Kumulatif Lolos Tertahan Tertahan Kumulatif
Inch mm gram % % % gram % %
1 25.40 0.00 0.00 0.00 100.00 0.00 0.00 0.00
3/4 19.10 0.00 0.00 0.00 100.00 0.00 0.00 0.00
1/2 12.70 0.00 0.00 0.00 100.00 0.00 0.00 0.00
3/8 9.50 0.00 0.00 0.00 100.00 0.00 0.00 0.00
No. 4 4.750 0.00 0.00 0.00 100.00 0.00 0.00 0.00
No. 8 2.360 0.00 0.00 0.00 100.00 0.00 0.00 0.00
No. 16 1.180 0.00 0.00 0.00 100.00 0.00 0.00 0.00
No. 30 0.600 78.51 15.74 15.74 84.26 111.35 22.32 22.32
No. 50 0.300 126.43 25.34 41.08 58.92 87.44 17.54 39.86
No. 100 0.150 256.86 51.49 92.57 7.43 147.32 29.55 69.41
No. 200 0.075 34.91 7.00 99.57 0.43 95.66 19.19 88.60
Pan 0.00 2.16 0.43 100.00 0.00 56.79 11.39 99.99
Jumlah 498.87 498.56
Persen Lolos (%)

60
70
80
90
30
40
50
10
20
0 0.15 0.30 0.60 1.20 Ukuran Sa

100

80
Hasil Gradasi
60

40

20

0
0.010 0.100 1.000
Diameter Ayak (mm)
TINGGI
K

gujian 2
Persen Tertahan Persen Lolos
Lolos Rata-Rata
% %
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
77.68 80.97
60.14 59.53
30.59 19.01
11.40 5.92
0.01 0.01

Ukuran Saringan
2.40 (mm)

Hasil Gradasi

1.000
PEMERIKSAAN I II PEM
No. Cawan FA1 FA2 No. Cawan
Berat Cawan (W1) Gram 124 124 Berat Cawan
Berat Cawan + Benda Uji (W2) Gram 1293 1362 Berat Cawan + Benda Uji
Berat benda uji (W3=W2-W1)Gram 1169 1238 Berat benda uji
Berat cawan + benda uji kering oven (W4) Gram 1262 1355 Berat cawan + benda uji ke
Berat benda uji kering oven (W5=W4=W1)Gram 1138 1231 Berat benda uji kering oven
PEMERIKSAAN I II Rata-rata PEMERIK

Kadar Air Agregat = 2.72% 0.57% 1.65% Kadar Air Agregat =

PEMERIKSAAN I II PEM
No. Cawan CA1 CA2 No. Cawan
Berat Cawan (W1) Gram 270 294 Berat Cawan
Berat Cawan + Benda Uji (W2) Gram 3627 3693 Berat Cawan + Benda Uji
Berat benda uji (W3=W2-W1)Gram 3357 3399 Berat benda uji
Berat cawan + benda uji kering oven (W4) Gram 3626 3671 Berat cawan + benda uji ke
Berat benda uji kering oven (W5=W4=W1)Gram 3356 3377 Berat benda uji kering oven
PEMERIKSAAN I II Rata-rata PEMERIK

Kadar Air Agregat = 0.03% 0.65% 0.34% Kadar Air Agregat =


PEMERIKSAAN I II
No. Cawan PS1 PS2
Berat Cawan (W1) Gram 124 158
Berat Cawan + Benda Uji (W2) Gram 2112 2296
Berat benda uji (W3=W2-W1)Gram 1988 2138
Berat cawan + benda uji kering oven (W4) Gram 2107 2285
Berat benda uji kering oven (W5=W4=W1)Gram 1983 2127
PEMERIKSAAN I II Rata-rata

Kadar Air Agregat = 0.25% 0.52% 0.38%

PEMERIKSAAN I II
No. Cawan MA1 MA2
Berat Cawan (W1) Gram 273 150
Berat Cawan + Benda Uji (W2) Gram 3101 2001
Berat benda uji (W3=W2-W1)Gram 2828 1851
Berat cawan + benda uji kering oven (W4) Gram 3090 1999
Berat benda uji kering oven (W5=W4=W1)Gram 2817 1849
PEMERIKSAAN I II Rata-rata

Kadar Air Agregat = 0.39% 0.11% 0.25%


Padat Lepas
PEMRIKSAAN (CA)
I II I II
Berat Mould (W1) Gram 3019 3019 3019 3019
Berat Mould + benda uji (W2) Gram 7484 7460 7270 7210
Berat benda uji (W3 = W2 - W1) Gram 4465 4441 4251 4191
Berat Mould + Air (W4) Gram 6021 6021 6021 6021
Berat Air / Isi Mould (V = W4 - W1) Gram 3002 3002 3002 3002

PEMERIKSAAN I II III IV

Berat Isi (kg/dm3) 1.49 1.48 1.42 1.40


Rata - rata 1.48 1.41
Rata - rata 1.44

Padat Lepas
PEMRIKSAAN (FA)
I II I II
Berat Mould (W1) Gram 3019 3019 3019 3019
Berat Mould + benda uji (W2) Gram 8489 8474 7749 7960
Berat benda uji (W3 = W2 - W1) Gram 5470 5455 4730 4941
Berat Mould + Air (W4) Gram 6021 6021 6021 6021
Berat Air / Isi Mould (V = W4 - W1) Gram 3002 3002 3002 3002

PEMERIKSAAN I II III IV

Berat Isi (kg/dm3) 1.82 1.82 1.58 1.65


Rata - rata 1.82 1.61
Rata - rata 1.72
Padat Lepas
PEMRIKSAAN (MA)
I II I II
Berat Mould (W1) Gram 3019 3019 3019 3019
Berat Mould + benda (W2)
u Gram 7848 7917 7370 7343
Berat benda uji (W3 = W2 - W1) Gram 4829 4898 4351 4324
Berat Mould + Air (W4) Gram 6021 6021 6021 6021
Berat Air / Isi Mould (V = W4 - W1) Gram 3002 3002 3002 3002

PEMERIKSAAN I II III IV

Berat Isi (kg/dm3) 1.61 1.63 1.45 1.44


Rata - rata 1.62 1.44
Rata - rata 1.53

Padat Lepas
PEMRIKSAAN (PS)
I II I II
Berat Mould (W1) Gram 3019 3019 3019 3019
Berat Mould + benda (W2)
u Gram 8289 8305 7951 7943
Berat benda uji (W3 = W2 - W1) Gram 5270 5286 4932 4924
Berat Mould + Air (W4) Gram 6021 6021 6021 6021
Berat Air / Isi Mould (V = W4 - W1) Gram 3002 3002 3002 3002

PEMERIKSAAN I II III IV

Berat Isi (kg/dm3) 1.76 1.76 1.64 1.64


Rata - rata 1.76 1.64
Rata - rata 1.70
PEMERIKSAAN (CA) I II PEMERIK
Berat benda uji jenuh permukaan kering (Bj) (gram) 449.43 502.06 Berat benda uji jenuh permuka
Berat benda uji kering oven (B2) (gram) 446.78 499.75 Berat benda uji kering oven
Berat bejana berisi air (B3) (gram) 1282.95 1283.67 Berat bejana berisi air
Berat Bejana + benda uji air (B1) (gram) 1563.21 1602.59 Berat Bejana + benda uji air

PEMERIKSAAN I II Rata-rata PEMERIKSA

Berat jenis bulk/ov. 2.64 2.73 2.68 Berat jenis bulk/ov.

Berat jenis SSD 2.66 2.74 2.70 Berat jenis SSD

Berat jenis app. 2.68 2.76 2.72 Berat jenis app.

Penyerapan 0.59% 0.46% 0.53% Penyerapan


PEMERIKSAAN (MA) I II PEMERIKSAAN (FA
Berat benda uji jenuh permukaan kering (Bj) (gram) 500 500 Berat benda uji jenuh permukaan kering
Berat benda uji kering oven (B2) (gram) 493.59 493.28 Berat benda uji kering oven
Berat bejana berisi air (B3) (gram) 1285.07 1276.37 Berat bejana berisi air
Berat Bejana + benda uji air (B1) (gram) 1585.24 1574.65 Berat Bejana + benda uji air

PEMERIKSAAN I II Rata-rata PEMERIKSAAN

Berat jenis bulk/ov. 2.47 2.45 2.46 Berat jenis bulk/ov.

Berat jenis SSD 2.50 2.48 2.49 Berat jenis SSD

Berat jenis app. 2.55 2.53 2.54 Berat jenis app.

Penyerapan 1.30% 1.36% 1.33% Penyerapan


PEMERIKSAAN (FA) I II PEMERIKSAAN (PS)
nda uji jenuh permukaan kering (Bj) (gram) 500.01 331.33 Berat benda uji jenuh permukaan kering
nda uji kering oven (B2) (gram) 488.87 323.84 Berat benda uji kering oven
ana berisi air (B3) (gram) 1270.04 1269.73 Berat bejana berisi air
ana + benda uji air (B1) (gram) 1580.81 1468.08 Berat Bejana + benda uji air

PEMERIKSAAN I II Rata-rata PEMERIKSAAN

s bulk/ov. 2.58 2.44 2.51 Berat jenis bulk/ov.

s SSD 2.64 2.49 2.57 Berat jenis SSD

s app. 2.74 2.58 2.66 Berat jenis app.

an 2.28% 2.31% 2.30% Penyerapan


PEMERIKSAAN (PS) I II
h permukaan kering (Bj) (gram) 500.01 500
ng oven (B2) (gram) 496.09 495.93
air (B3) (gram) 1499.65 1499.1
da uji air (B1) (gram) 1801.67 1805.88

EMERIKSAAN I II Rata-rata

2.51 2.57 2.54

2.53 2.59 2.56

2.56 2.62 2.59

0.79% 0.82% 0.81%


pengujian penetrasi
No Waktu
I II
1 5 61.00 65.00
2 5 61.00 65.00
3 5 64.50 68.00
4 5 61.00 70.00
5 5 69.00 69.00
rata-rata penetrasi per benda uji 63.30 67.40
rata-rata penetrasi 65.35
Perobaan
Pemeriksaan
I II
Berat piknometer + penutup (A) 29.06 29.20
Berat piknometer + air + penutup (B) 77.08 80.06
Berat piknometer + aspal + penutup ( C) 47.64 41.11
Berat piknometer + aspal + air + penutup (D) 77.74 80.46
Berat Jenis 1.04 1.03

Berat jenis rata - rata 1.036


Benda Uji
No
Waktu Suhu Titik Lembek
I II I II
0 0 0 5 5
1 1 1 10 8
2 2 2 9 11
3 3 3 14 14
4 4 4 19 17
5 5 5 23 19.5
6 6 6 26 22.5
7 7 7 29.5 25.5
8 8 8 33 28
9 9 9 37 30.5
10 10 10 40.5 33
11 11 11 43.5 35.5
12 12 12 47.5 38
13 13 13 49.5 43
14 14 45
15 15 46.75
27.61 23.61
Rata-rata Titik Lembek (°C) 25.61
NOMOR Tinggi (mm) Diameter (mm)
volume
CONTOH I II III IV Rata-rata I II Rata - rata
1 69.50 70.32 69.44 69.64 69.73 10.18 10.17 10.17 566.44
2 69.50 69.52 69.12 69.62 69.44 10.14 10.15 10.15 561.14
3 68.66 68.64 68.00 67.04 68.09 10.20 10.18 10.19 555.08
Rata - rata 69.22 69.49 68.85 68.77 69.08 10.17 10.17 10.17 560.89
1 69.10 69.10 68.74 68.84 68.95 10.17 10.20 10.19 561.43
2 69.22 69.62 69.52 69.82 69.55 10.17 10.16 10.17 564.09
3 67.80 67.86 67.86 68.30 67.96 10.15 10.17 10.16 550.55
Rata - rata 68.71 68.86 68.71 68.99 68.82 10.16 10.17 10.17 558.69
1 66.58 66.90 67.16 67.28 66.98 10.22 10.16 10.19 545.96
2 68.48 68.90 68.64 68.12 68.54 10.19 10.15 10.17 556.23
3 69.22 69.12 68.94 68.96 69.06 10.17 10.21 10.19 562.92
Rata - rata 68.09 68.31 68.25 68.12 68.19 10.19 10.17 10.18 555.04
1 67.80 67.60 67.52 67.92 67.71 10.16 10.16 10.16 548.88
2 68.00 66.94 66.82 67.60 67.34 10.15 10.14 10.15 544.27
3 68.74 68.80 69.28 68.92 68.94 10.16 10.15 10.15 557.94
Rata - rata 68.18 67.78 67.87 68.15 68.00 10.16 10.15 10.15 550.36
1 66.78 67.00 67.00 66.88 66.92 10.16 10.20 10.18 544.26
2 67.46 68.00 67.88 67.02 67.59 11.30 11.60 11.45 695.61
3 65.84 65.60 65.84 66.08 65.84 11.48 11.54 11.51 684.72
Rata - rata 66.69 66.87 66.91 66.66 66.78 10.98 11.11 11.05 641.53

Bj Aspal 1.04
Kalibrasi Prov. Ring 29.893 lbt/div
Bj app 2.60
Bj Bulk Bj Eff
a b c d e f g h
total Agregat Agregat
4.0 3.85 1222.64 1242.39 696.69 545.70 2.24 2.43 2.63 2.49
4.0 3.85 1220.48 1236.10 695.39 540.71 2.26 2.43 2.63 2.49
4.0 3.85 1228.05 1242.36 704.09 538.27 2.28 2.43 2.63 2.49
4.0 3.85 1223.72 1240.28 698.72 541.56 2.26 2.43 2.63 2.49
4.5 4.31 1231.19 1245.94 700.96 544.98 2.26 2.43 2.63 2.47
4.5 4.31 1224.58 1240.64 696.14 544.50 2.25 2.43 2.63 2.47
4.5 4.31 1232.38 1248.03 716.02 532.01 2.32 2.43 2.63 2.47
4.5 4.31 1229.38 1244.87 704.37 540.50 2.27 2.43 2.63 2.47
5.0 4.76 1225.10 1236.69 717.32 519.37 2.36 2.43 2.63 2.45
5.0 4.76 1238.12 1249.95 711.37 538.58 2.30 2.43 2.63 2.45
5.0 4.76 1228.09 1246.51 714.23 532.28 2.31 2.43 2.63 2.45
5.0 4.76 1230.44 1244.38 714.31 530.08 2.32 2.43 2.63 2.45
5.5 5.21 1240.27 1252.56 727.76 524.80 2.36 2.43 2.63 2.44
5.5 5.21 1235.22 1247.35 723.83 523.52 2.36 2.43 2.63 2.44
5.5 5.21 1238.85 1250.13 712.16 537.97 2.30 2.43 2.63 2.44
5.5 5.21 1238.11 1250.01 721.25 528.76 2.34 2.43 2.63 2.44
6.0 5.66 1243.57 1254.16 730.83 523.33 2.38 2.43 2.63 2.42
6.0 5.66 1245.68 1257.97 731.68 526.29 2.37 2.43 2.63 2.42
6.0 5.66 1236.68 1245.13 729.10 516.03 2.40 2.43 2.63 2.42
6.0 5.66 1241.98 1252.42 730.54 521.88 2.38 2.43 2.63 2.42

65.1 0.96
65.84 0.946125
66.7 0.93
angka
i j k l m n o p q
koreksi
11.30 9.92 12.15 67 2002.83 0.874 1750.47 2.630 665.58 3.21
10.64 9.25 13.00 94 2809.94 0.885 2486.80 2.090 1189.86 3.21
9.67 8.28 14.45 120 3587.16 0.902 3235.62 2.490 1299.45 3.21
10.54 9.15 13.20 93.67 2799.98 0.89 2490.96 2.403 1051.63 3.21
10.99 8.57 22.00 120 3587.16 0.885 3174.64 2.390 1328.30 3.19
11.39 8.98 21.13 80 2391.44 0.879 2102.08 2.220 946.88 3.19
8.73 6.25 28.39 92 2750.16 0.916 2519.14 2.300 1095.28 3.19
10.37 7.93 23.84 97.33 2909.59 0.89 2598.62 2.303 1123.49 3.19
7.50 3.91 47.88 112 3348.02 0.930 3113.65 2.060 1511.48 3.18
9.85 6.35 35.52 105 3138.77 0.899 2821.75 2.950 956.53 3.18
9.52 6.01 36.88 80 2391.44 0.882 2109.25 2.100 1004.40 3.18
8.96 5.42 40.09 99.00 2959.41 0.90 2681.55 2.370 1157.47 3.18
7.76 3.11 59.99 102 3049.09 0.921 2808.21 2.240 1253.66 3.16
7.91 3.26 58.75 115 3437.70 0.935 3214.24 2.380 1350.52 3.16
10.13 5.59 44.83 105 3138.77 0.893 2802.92 2.130 1315.92 3.16
8.60 3.99 54.53 107.33 3208.52 0.92 2941.79 2.250 1306.70 3.16
7.70 1.96 74.57 93 2780.05 0.935 2599.35 3.890 668.21 3.15
8.06 2.34 70.93 88 2630.58 0.914 2404.35 2.060 1167.16 3.15
6.91 1.12 83.78 114 3407.80 0.946 3223.78 2.300 1401.64 3.15
7.56 1.81 76.42 98.33 2939.48 0.93 2742.49 2.750 1079.01 3.15
r
0.76
0.76
0.76
0.76
1.25
1.25
1.25
1.25
1.73
1.73
1.73
1.73
2.21
2.21
2.21
2.21
2.69
2.69
2.69
2.69
Berat Jenis Komposis
Agregat
Bulk SSD Efektif i Agregat
a b c=(a+b)/2 d
CA 2.69 2.70 2.70 14.00
MA 2.46 2.49 2.48 49.00
FA 2.51 2.57 2.54 20.50
Pasir 2.54 2.56 2.55 12.50
Filler 1.35 - - 4.00
100

Berat Jenis Aspal 1.036

Perhitungan Berat Jenis Bulk Agregat 2.43

Perhitungan Berat Jenis Efektif Agregat 2.63


Berat %
Berat Jenis % Rongga Di
Rongga
Nomor Diameter Kadar Aspal Kadar Aspal Isi Contoh Berat Isi maximum Antara
Tinggi (mm) Dalam Terhadap
Contoh (mm) (% Campuran) (% Batuan) Kering SSD (d-e) (c/f) campuran Agregat
Air Campura
(teoritis) (VMA)
n (ViM)
Rata-Rata Rata-Rata % % (gram) (gram) (gram) (gram) % %
a b c d e f g h i j
1 69.73 10.17 4.0 3.85 1222.64 1242.39 696.69 545.70 2.24 2.49 11.30 9.92
2 69.44 10.15 4.0 3.85 1220.48 1236.10 695.39 540.71 2.26 2.49 10.64 9.25
3 68.09 10.19 4.0 3.85 1228.05 1242.36 704.09 538.27 2.28 2.49 9.67 8.28
Rata - rata 69.08 10.17 4.00 3.85 1223.72 1240.28 698.72 541.56 2.26 2.49 10.54 9.15
1 68.95 10.19 4.5 4.31 1231.19 1245.94 700.96 544.98 2.26 2.47 10.99 8.57
2 69.55 10.17 4.5 4.31 1224.58 1240.64 696.14 544.50 2.25 2.47 11.39 8.98
3 67.96 10.16 4.5 4.31 1232.38 1248.03 716.02 532.01 2.32 2.47 8.73 6.25
Rata - rata 68.82 10.17 4.50 4.31 1229.38 1244.87 704.37 540.50 2.27 2.47 10.37 7.93
1 66.98 10.19 5.0 4.76 1225.10 1236.69 717.32 519.37 2.36 2.45 7.50 3.91
2 68.54 10.17 5.0 4.76 1238.12 1249.95 711.37 538.58 2.30 2.45 9.85 6.35
3 69.06 10.19 5.0 4.76 1228.09 1246.51 714.23 532.28 2.31 2.45 9.52 6.01
Rata - rata 68.19 10.18 5.00 4.76 1230.44 1244.38 714.31 530.08 2.32 2.45 8.96 5.42
1 67.71 10.16 5.5 5.21 1240.27 1252.56 727.76 524.80 2.36 2.44 7.76 3.11
2 67.34 10.15 5.5 5.21 1235.22 1247.35 723.83 523.52 2.36 2.44 7.91 3.26
3 68.94 10.15 5.5 5.21 1238.85 1250.13 712.16 537.97 2.30 2.44 10.13 5.59
Rata - rata 68.00 10.15 5.50 5.21 1238.11 1250.01 721.25 528.76 2.34 2.44 8.60 3.99
1 66.92 10.18 6.0 5.66 1243.57 1254.16 730.83 523.33 2.38 2.42 7.70 1.96
2 67.59 11.45 6.0 5.66 1245.68 1257.97 731.68 526.29 2.37 2.42 8.06 2.34
3 65.84 11.51 6.0 5.66 1236.68 1245.13 729.10 516.03 2.40 2.42 6.91 1.12
Rata - rata 66.78 11.05 6.00 5.66 1241.98 1252.42 730.54 521.88 2.38 2.42 7.56 1.81

Bj Aspal 1.04
Kalibrasi Prov.Ring 29.893 lbt/div

KADAR STABILI
DENSITY VMA ViM VFB FLOW MQ
ASPAL TAS
KADAR STABILI
DENSITY VMA ViM VFB FLOW MQ
ASPAL TAS
% Gram/Cm3 % % % KG MM KG/MM
1 2 3 4 5 6 7 8
4.00 2.26 10.54 9.15 13.20 2490.96 2.40 1051.63
4.50 2.27 10.37 7.93 23.84 2598.62 2.30 1123.49
5.00 2.32 8.96 5.42 40.09 2681.55 2.37 1157.47
5.50 2.34 8.60 3.99 54.53 2941.79 2.25 1306.70
6.00 2.38 7.56 1.81 76.42 2742.49 2.75 1079.01
D e n s it y (g r/c m 3 )

VMA (%)
16.00 10.00

ViM (%)
2.400
14.00 8.00

2.350
12.00 6.00 Max. 5
Min. 14
2.300
10.00 4.00
8.00 Min. 3,5
2.250 2.00

2.200
6.00 0.00
4.00 4.50 5.00 5.50 6.00 4.00 4.50 5.00 5.50 6.00 4.00 4.50 5.00 5.50 6.00
Kadar Aspal (%) Kadar Aspal (%) Kadar Aspal (%)
Stabilitas (Kg)

Flow (mm)

MQ (kg/mm)
4.00

3500.00 Min. 3
3.00 1200.00
3000.00

2500.00 2.00 800.00


2000.00
1.00
1500.00 400.00 Min. 250
Min. 800
1000.00
0.00
500.00 4.00 4.50 5.00 5.50 6.00 0.00
3500.00 Min. 3

Stab

F
1200.00

MQ
3.00
3000.00

2500.00 2.00 800.00


2000.00
1.00
1500.00 400.00 Min. 250
Min. 800
1000.00
0.00
500.00 4.00 4.50 5.00 5.50 6.00 0.00
4.00 4.50 5.00 5.50 6.00
Kadar Aspal (%) 4.00 4.50 5.00 5.50 6.00
Kadar Aspal (%)
Kadar Aspal (%)

VMA

VIM

VFB

STABILITAS

FLOW

MQ

4 4.5 5 5.5 6

KADAR ASPAL (%)

Kesimpulan : Jadi, dari grafik di dapat Kadar Aspal Minimum


Kadar Aspal Optimum
Kadar Aspal Maksimum
%
Rongga Pembacaan Stabilitas Stabilitas Hasil Bagi Kadar
Angka Penyerap
Terisi Arloji (l x (m x Kelelehan Marshall Aspal
Aspal Stabilitas Kalibrasi) Koreksi Koreksi) (MQ)
an Aspal
Efektif
(VFB)
% (div.) (kg) (kg) (mm) (kg/mm)
k l m n o p q r
12.15 67 2002.83 0.874 1750.47 2.63 665.58 3.21 0.76
13.00 94 2809.94 0.885 2486.80 2.09 1189.86 3.21 0.76
14.45 120 3587.16 0.902 3235.62 2.49 1299.45 3.21 0.76
13.20 93.67 2799.98 0.89 2490.96 2.40 1051.63 3.21 0.76
22.00 120 3587.16 0.885 3174.64 2.39 1328.30 3.19 1.25
21.13 80 2391.44 0.879 2102.08 2.22 946.88 3.19 1.25
28.39 92 2750.16 0.916 2519.14 2.30 1095.28 3.19 1.25
23.84 97.33 2909.59 0.89 2598.62 2.30 1123.49 3.19 1.25
47.88 112 3348.02 0.930 3113.65 2.06 1511.48 3.18 1.73
35.52 105 3138.77 0.899 2821.75 2.95 956.53 3.18 1.73
36.88 80 2391.44 0.882 2109.25 2.10 1004.40 3.18 1.73
40.09 99.00 2959.41 0.90 2681.55 2.37 1157.47 3.18 1.73
59.99 102 3049.09 0.921 2808.21 2.24 1253.66 3.16 2.21
58.75 115 3437.70 0.935 3214.24 2.38 1350.52 3.16 2.21
44.83 105 3138.77 0.893 2802.92 2.13 1315.92 3.16 2.21
54.53 107.33 3208.52 0.92 2941.79 2.25 1306.70 3.16 2.21
74.57 93 2780.05 0.935 2599.35 3.89 668.21 3.15 2.69
70.93 88 2630.58 0.914 2404.35 2.06 1167.16 3.15 2.69
83.78 114 3407.80 0.946 3223.78 2.30 1401.64 3.15 2.69
76.42 98.33 2939.48 0.93 2742.49 2.75 1079.01 3.15 2.69
VFB (%)

80.00
Min. 63
60.00

40.00

20.00

0.00
00 5.50 6.00
4.00 4.50 5.00 5.50 6.00
pal (%)
Kadar Aspal (%)

0
0

5.00 5.50 6.00

ar Aspal (%)
SPESIFIKASI
Kdr Aspal VMA Vim VFB Stab. Flow MQ
5 14 3.5 5 63 800 3 250
5.5 14 3.5 5 63 800 3 250
5.57 14 3.5 5 63 800 3 250
6 14 3.5 5 63 800 3 250
6.5 14 3.5 5 63 800 3 250
7 14 3.5 5 63 800 3 250

VMA ViM VFB Stabilitas


4.5 7 3.5 5.5 5.8 7 4.5 7
5.77

Min Max
VMA 4.5 7 1 1
ViM 3.5 5.5 2 2
VFB 5.8 7 3 3
Stabilitas 4.5 7 4 4
Flow 5.9 7 5 5
MQ 4.5 7 6 6
Flow MQ
5.9 7 4.5 7