041/MHP/PRY-WRH/SPK-BLDG/IX/2022
PEKERJAAN PEMASANGAN SEKAT CLADDING AS 23 GUDANG BLOK O1.
MARUNDA CENTER
A. PEKERJAAN PERSIAPAN
1. Alat Kerja Scafolding (tinggi = 12 m) 1.00 Ls 1.63 1.00 - 1.00 100% 0% 100% 1.63
2. Biaya Transportasi Dan Mob Demob 1.00 Ls 2.17 1.00 - 1.00 100% 0% 100% 2.17
3. Bedeng Pekerja 1.00 Ls 2.17 0.50 0.50 1.00 50% 50% 100% 2.17
4. Administrasi & Dokumentasi 1.00 Ls 0.54 - 1.00 1.00 0% 100% 100% 0.54
5. Pembersihan Akhir 1.00 Ls 0.76 - 1.00 1.00 0% 100% 100% 0.76
B. RANGKA CLADING
1. KOLOM
Wf - 250.125 3,125.76 kg 20.37 1,875.46 1,250.30 3,125.76 60% 40% 100% 20.37
Plat Besi 12 mm 56.44 kg 0.25 33.86 22.57 56.44 60% 40% 100% 0.25
Plat Besi 10 mm ( kopel sambungan ) 100.19 kg 0.44 60.11 40.07 100.19 60% 40% 100% 0.44
Plat Besi 8 mm ( kopel sambungan ) 160.82 kg 0.70 96.49 64.33 160.82 60% 40% 100% 0.70
Chamical Angkur M20 32.00 bh 5.30 19.20 12.80 32.00 60% 40% 100% 5.30
2. RANGKA CLADING
CNP 150.65.20.3,2 mm 6,765.30 kg 33.07 4,397.45 2,367.86 6,765.30 65% 35% 100% 33.07
Plat Besi 8 mm 734.99 kg 3.19 477.75 257.25 734.99 65% 35% 100% 3.19
Baut Dan Mur Hitam 12 mm 600.00 bh 1.63 390.00 210.00 600.00 65% 35% 100% 1.63
Trekstang 12 mm 270.00 bh 3.67 175.50 94.50 270.00 65% 35% 100% 3.67
3. LAIN LAIN
Pengecetan Manie Dan Finish 10,943.50 kg 23.78 9,301.97 1,641.52 10,943.50 85% 15% 100% 23.78
100.00 100.00
Page 1 of 1