Anda di halaman 1dari 1

KEMAJUAN FISIK PEKERJAAN No. SPK : ADD.

041/MHP/PRY-WRH/SPK-BLDG/IX/2022
PEKERJAAN PEMASANGAN SEKAT CLADDING AS 23 GUDANG BLOK O1.
MARUNDA CENTER

REALISASI VOLUME PERSENTASE


NO. URAIAN PERKERJAAN QTY UOM BOBOT PROGRESS
MINGGU LALU MINGGU INI S.D MINGGU INI MINGGU LALU MINGGU INI S.D MINGGU INI
a b e d e f g h=f+g i j = g/e k=i+j l

A. PEKERJAAN PERSIAPAN
1. Alat Kerja Scafolding (tinggi = 12 m) 1.00 Ls 1.63 1.00 - 1.00 100% 0% 100% 1.63
2. Biaya Transportasi Dan Mob Demob 1.00 Ls 2.17 1.00 - 1.00 100% 0% 100% 2.17
3. Bedeng Pekerja 1.00 Ls 2.17 0.50 0.50 1.00 50% 50% 100% 2.17
4. Administrasi & Dokumentasi 1.00 Ls 0.54 - 1.00 1.00 0% 100% 100% 0.54
5. Pembersihan Akhir 1.00 Ls 0.76 - 1.00 1.00 0% 100% 100% 0.76

B. RANGKA CLADING
1. KOLOM
Wf - 250.125 3,125.76 kg 20.37 1,875.46 1,250.30 3,125.76 60% 40% 100% 20.37
Plat Besi 12 mm 56.44 kg 0.25 33.86 22.57 56.44 60% 40% 100% 0.25
Plat Besi 10 mm ( kopel sambungan ) 100.19 kg 0.44 60.11 40.07 100.19 60% 40% 100% 0.44
Plat Besi 8 mm ( kopel sambungan ) 160.82 kg 0.70 96.49 64.33 160.82 60% 40% 100% 0.70
Chamical Angkur M20 32.00 bh 5.30 19.20 12.80 32.00 60% 40% 100% 5.30

2. RANGKA CLADING
CNP 150.65.20.3,2 mm 6,765.30 kg 33.07 4,397.45 2,367.86 6,765.30 65% 35% 100% 33.07
Plat Besi 8 mm 734.99 kg 3.19 477.75 257.25 734.99 65% 35% 100% 3.19
Baut Dan Mur Hitam 12 mm 600.00 bh 1.63 390.00 210.00 600.00 65% 35% 100% 1.63
Trekstang 12 mm 270.00 bh 3.67 175.50 94.50 270.00 65% 35% 100% 3.67

3. LAIN LAIN
Pengecetan Manie Dan Finish 10,943.50 kg 23.78 9,301.97 1,641.52 10,943.50 85% 15% 100% 23.78

4. PEKERJAAN DILUAR SPK


Dynabolt M12 28.00 bh 0.33 - 28.00 28.00 0% 100% 100% 0.33

100.00 100.00

Jakarta, September 2022


Disetujui Diperiksa Dibuat oleh,
PT. MULTIKARYA HASILPRIMA PT. MULTIKARYA HASILPRIMA PENYEDIA JASA BORONGAN

MANGIHUT SAMUEL STEPHAN DANANG WIJAYANTO ANANG YANA MULYANA


PROJECT MANAGER SUPERVISOR PELAKSANA/MANDOR

Page 1 of 1