LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN

PENINGKATAN JALAN RUAS LASSANG


DANA ALOKASI UMUM (DAU)
TAHUN ANGGARAN 2022
KONSULTAN PENGAWAS LAPORAN BULANAN (BULAN KE-1)

CV. AULIFAH PERIODE TANGGAL :20 DESEMBER 2022 s/d 01 DESEMBER 2022
KONTRAK AWAL REALISASI

Harga Satuan Jumlah Harga BOBOT VOLUME


No Uraian Pekerjaan VOLUME Sat JUMLAH HARGA PROGRES BOBOT (%)
( Rp ) ( Rp ) ( %) MINGGU LALU MINGGU INI S/D MINGGU INI
1 2 4 5 6 7
A. DIVISI 1. UMUM
1.2 MOBILISASI 1.00 Ls 25,000,000.00 25,000,000.00 2.83% 1.00 1.00 25,000,000.00 100.00 0.03

25,000,000.00 2.83% 25,000,000.00 0.03


B. DEVISI 2. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)
2.1 Penyiapan Dokumen Penerapan SMKK 1.00 Ls 150,000.00 150,000.00 0.02% 1.00 1.00 150,000.00 100.00 0.00
2.2 Papan Informasi Keselamatan Konstruksi 1.00 Ls 150,000.00 150,000.00 0.02% 1.00 1.00 150,000.00 100.00 0.00
Topi Pelindung (safety Helmet) 5.00 Ls 50,000.00 250,000.00 0.03% 5.00 5.00 250,000.00 100.00 0.00
Pelindung Pernafasan dan Mulut (Masker, Masker Respirator) 5.00 Ls 10,000.00 50,000.00 0.01% 5.00 5.00 50,000.00 100.00 0.00
Sarung Tangan (Safety Glovers) 5.00 Ls 7,000.00 35,000.00 0.00% 5.00 5.00 35,000.00 100.00 0.00
2.3 Sepatu Keselamatan (Safety Shoes, Rubber Safety and Toe Cap) 5.00 Ls 250,000.00 1,250,000.00 0.14% 5.00 5.00 1,250,000.00 100.00 0.00
Rompi Keselamtan (Safety Vest) 5.00 Ls 85,000.00 425,000.00 0.05% 5.00 5.00 425,000.00 100.00 0.00
Rambu Peringatan 2.00 Ls 150,000.00 300,000.00 0.03% 2.00 2.00 300,000.00 100.00 0.00
Rampu / Alat Pemberi Isyarat Lalu Lintas Sementara 2.00 Ls 150,000.00 300,000.00 0.03% 2.00 2.00 300,000.00 100.00 0.00

2,910,000.00 0.33% 2,910,000.00 0.00


C DEVISI 6. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
6.3 Perkerasan Beton Semen (PC) 375.00 M3 1,886,817.80 707,556,673.46 80.03% 375.00 375.00 707,556,673.46 100.00 0.80
6.3 lapis Pondasi Bawah Beton kurus (Concrete Vibrator) 131.25 M3 1,132,346.74 148,620,509.30 16.81% 131.25 131.25 148,620,509.30 100.00 0.17

856,177,182.76 96.84% 856,177,182.76 0.97


TOTAL JUMLAH 884,087,182.76 100% JUMLAH KEMAJUAN PEKERJAAN 884,087,182.76 1.00

PPN 11 % 97,249,590.10 JUMLAH BOBOT BULAN INI 884,087,182.76 1.00

JUMLAH TOTAL HARGA PEKERJAAN 981,336,772.87 JUMLAH BOBOT BULAN LALU

DI BULATKAN 981,337,000.00 JUMLAH BOBOT S/D BULAN INI 884,087,182.76 1.00

PEJABAT PEMBUAT KOMITMEN Dibuat Oleh :


Dinas PUPRPKP Kab. Takalar Konsultan Supervisi
CV. AULIFAH

ABDUL WAHAB, ST AGUS.RK, ST


Nip. 19760525 200901 1 010 Supervision Engineer