REKAP BACK UP QUANTITY

KEGIATAN : PENINGKATAN JALAN POROS KE DESA HIMBA LESTARI (LAPEN KE AC-BC) (DAK)
PAKET : PENINGKATAN JALAN POROS KE DESA HIMBA LESTARI (LAPEN KE AC-BC) (DAK) NOMOR : MC 02
NOMOR KONTRAK : 600.620/149/HL.DAK/BM/DPU-KT/III/2020 BULAN : MEI
TANGGAL : 27 Maret 2020 TANGGAL : 26 APRIL - 25 MEI 2020
KONTRAKTOR : CV. BERKAH BERSAMA JAYA SUMBER DANA : DAK
NILAI KONTRAK : Rp 7.559.706.000,00 TAHUN ANGGARAN : 2020

KONTRAK VOLUME SERTIFIKAT BULANAN (MC) VOLUME BACK UP


SISA VOLUME
No. Mata
Uraian Satuan S/D BULAN S/D BULAN S/D BULAN S/D BULAN YANG BELUM KETERANGAN
Pembayaran Volume Harga Satuan (Rp.) Total harga (Rp.) Bobot (%) BULAN INI BOBOT (%) BULAN INI
LALU INI LALU INI DITAGIHKAN

DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 134,500,000.00 134,500,000.00 1.96 0.20 - 0.20 0.39 0.20 - 0.20 -
1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00 51,600,000.00 51,600,000.00 0.75 - 0.10 0.10 0.08 - 0.10 0.10 -
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 23,125,000.00 23,125,000.00 0.34 - 1.00 1.00 0.34 - 1.00 1.00 -
SUBTOTAL DIVISI 1 209,225,000.00 3.04 0.80

DIVISI 3. PEKERJAAN TANAH


3.2.(1)a Timbunan Biasa dari Sumber Galian M3 334.47 87,385.74 29,227,908.46 0.43 - - - - - - - -
3.3.1 Penyiapan Badan Jalan M2 10,800.00 4,870.82 52,604,856.00 0.77 - - - - - - - -
SUBTOTAL DIVISI 3 81,832,764.46 1.19 -

DIVISI 5. PERKERASAN BERBUTIR


5.1.1 Lapis Pondasi Agregat Kelas A M3 1,188.00 1,639,822.83 1,948,109,522.04 28.35 - - - - - - - -
5.1.2 Lapis Pondasi Agregat Kelas B M3 1,204.28 1,632,226.50 1,965,657,729.420 28.60 - - - - - - - -
SUBTOTAL DIVISI 5 3,913,767,251.460 56.949 -

DIVISI 6. PERKERASAN ASPAL


6.1 (1a) Lapis Resap Pengikat - Aspal Cair Liter 7,920.00 20,343.58 161,121,153.60 2.34 - - - - - - - -
6.3 (6a) Laston Lapis Antara (AC-BC) Ton 1,102.46 2,252,671.06 2,483,479,736.81 36.14 - - - - - - - -
SUBTOTAL DIVISI 6 2,644,600,890.41 38.48 -

DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.4(1) Marka Jalan Termoplastik M2 89.17 258,321.28 23,034,508.54 0.34 - - - - - - - -
SUBTOTAL DIVISI 8 23,034,508.54 0.34 -

TOTAL 6,872,460,414.86 100.00


PPn 10% 687,246,041.49
TOTAL KONTRAK + PPn 10% 7,559,706,456.35
DIBULATKAN 7,559,706,000.00

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


DPU Bina Marga Konsultan Supervisi Kontraktor Pelaksana
Pejabat Pembuat Komitmen CV. Executive 04 Consultant CV. Berkah Bersama Jaya

Fahmi Ramdani, ST.MM Hadi Wiyono, ST Riza Setyawan, ST


NIP 197908072006041014 Site Engineer Site Manager