Kepada
Yth. Kontraktor CV. TRITUNGGAL JAYA PERDANA
di –
Tempat
Dalam Rangka Pelaksanaan Pekerjaan Peningkatan Kapasitas Struktur Jalan (Khusus Kabupaten)
Ruas Bagalbui - Eibiki, tahun anggaran 2022
Laporan kemajuan pekerjaan Minggu Ke-12 Tanggal 20 Agustus 2022 yang di laksanakan Oleh
Kontraktor pelaksana CV. TRITUNGGAL JAYA PERDANA, Yaitu:
Demikian surat ini kami buat, atas kerja samanya kami ucapkan terima kasih.
IRVAN SAPUTRA
Kepala Perwakilan
Tembusan :
I DIVISI I. UMUM
1 Mobilisasi Ls 1.00 29,640,000.00 29,640,000.00 0.63% 0.50 - 0.50 14,820,000.00 - 14,820,000.00 0.31% 0.00% 0.31%
2 Manajemen Keselamatan Lalu Lintas Ls 1.00 5,710,000.00 5,710,000.00 0.12% - - - - - 0.00% 0.00% 0.00%
3 Keselamatan dan Kesehatan Kerja Ls 1.00 3,450,000.00 3,450,000.00 0.07% - - - - - 0.00% 0.00% 0.00%
SUB JUMLAH DIVISI I. UMUM 38,800,000.00 0.82% 14,820,000.00 - 14,820,000.00 0.31% 0.00% 0.31%
SUB JUMLAH DIVISI 2. PEKERJAAN DRAINASE 258,101,459.96 5.46% - - - 0.00% 0.00% 0.00%
SUB JUMLAH DIVISI 5. PERKERASAN BERBUTIR 504,831,769.14 10.67% - - - 0.00% 0.00% 0.00%
VI DIVISI 7. STRUKTUR
1 Beton Stuktur, fc' 20 Mpa M³ 1,636.98 2,055,242.80 3,364,396,678.81 71.13% - - - - 0.00% 0.00% 0.00%
2 Beton , fc' 15 Mpa M³ - - - - - - -
3 Baja Tulangan Polos BJTP 280 M³ - - - - - - -
4 Pasangan Batu M³ - - - - - - -
SUB JUMLAH DIVISI 7. STRUKTUR 3,364,396,678.81 71.13% - - - 0.00% 0.00% 0.00%
TOTAL KESELURUHAN 4,729,730,357.43 100% 91,296,922.53 35,235,813.60 126,532,736.13 1.93% 0.74% 2.68%
PPN ( 11 / 100 x A ) 520,270,339.32 10,042,661.48 3,875,939.50 13,918,600.97
TOTAL ( A + B ) 5,250,000,696.75 101,339,584.01 39,111,753.10 140,451,337.10
DIBULATKAN 5,250,000,600.00 101,339,500.00 39,111,700.00 140,451,300.00
JUMLAH MINGGU KE
BOBOT I II III IV V VI VII KET.
HARGA
NO URAIAN PEKERJAAN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
(Rp) %
I DIVISI I. UMUM
1 Mobilisasi 29,640,000.00 0.63% 0.44% 0.19%
2 Pasangan Batu dengan Mortar 116,119,970.21 2.46% 0.49% 0.49% 0.49% 0.49% 0.49%
II DIVISI 7. STRUKTUR
1 Beton Stuktur, fc' 20 Mpa 3,364,396,678.81 71.13% 5.47% 5.47% 5.47% 5.47% 5.47% 5.47% 5.47% 5.47% 5.47% 5.47% 5.47% 5.47% 5.47%
2 Beton , fc' 15 Mpa - 0.00%
3 Baja Tulangan Polos BJTP 280 0.00%
4 Pasangan Batu 0.00%
0.00% 0.00% 0.44% 0.38% 0.51% 1.69% 1.69% 0.38% 0.38% 0.38% 0.38% 0.98% 7.14% 6.76% 7.25% 7.25% 6.65% 7.99% 7.99% 7.50% 6.81% 6.81% 6.81% 6.81% 6.81% 0.19%
Komulatif 0 0.00% 0.00% 0.44% 0.83% 1.33% 3.02% 4.71% 5.10% 5.48% 5.87% 6.25% 7.24% 14.38% 21.14% 28.39% 35.65% 42.30% 50.29% 58.27% 65.77% 72.58% 79.39% 86.20% 93.01% 99.82% 100.00%
Realisasi 0.00% 0.00% 0.00% 0.00% 0.31% 0.48% 0.16% 0.09% 0.09% 0.06% 0.74%
Komulatif 0.0% 0.0% 0.0% 0.00% 0.31% 0.79% 0.95% 1.04% 1.12% 1.19% 1.93%
Deviasi 0.00% 0.00% -0.44% -0.83% -1.0% -2.23% -3.76% -4.06% -4.36% -4.68% -4.32%
Diketahui Oleh:
Pejabat Pembuat Komitmen Bidang Bina Marga Diperiksa Oleh Dibuat Oleh:
Dinas Pekerjaan Umum dan Penataan Ruang Konsultan Supervisi Kontraktor Pelaksana
Kabupaten Alor PT. KONINDO PANORAMA KONSULTAN