DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 25,030,000.00 25,030,000.00
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air Ls 131.00 29,912.35 3,918,517.85
DIVISI 3. PEKERJAAN TANAH
3.1.(3) Galian Struktur dengan kedalaman 0 - 2 meter M3 12.00 28,426.63 341,119.56
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 162.75 174,687.18 28,430,338.55
3.3.(1) Penyiapan Badan Jalan M2 3,200.00 1,763.03 5,641,696.00
DIVISI 5. PERKERASAN BERBUTIR
5.1.(1) Lapis Pondasi Agregat Kelas A M3 420.00 612,090.02 257,077,808.40
5.1.(2) Lapis Pondasi Agregat Kelas B M3 608.00 572,342.13 347,984,015.04
DIVISI 6. PERKERASAN ASPAL
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 1,920.00 13,058.98 25,073,241.60
6.3(6a) Laston Lapis Antara (AC-BC) Ton 334.00 1,409,733.35 470,850,938.90
DIVISI 7. STRUKTUR
7.1 (7) a Beton mutu sedang fc’20 Mpa (K-250) M3 8.00 1,538,625.49 12,309,003.92
7.1 (8) Beton mutu rendah fc’15 MPa (K-175) M3 48.00 1,166,137.31 55,974,590.88
7.3 (1) Baja Tulangan U 24 Polos Kg 2,895.00 15,294.17 44,276,622.15
A JUMLAH 1,276,907,892.85
B PPn 10% 127,690,789.28
C JUMLAH (A + B) 1,404,598,682.13
D DIBULATKAN 1,404,598,000.00
No. Mata Uraian Pekerjaan Satuan Perkiraan Nilai Bobot AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER Masa
Pembayaran Kuantitas Pekerjaan Minggu ke- Minggu ke- Minggu ke- Minggu ke- Minggu ke- Pemeliharaan KETERANGAN
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 180 (HK)
28-Jul 31-Jul 7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct 23-Oct 30-Oct 6-Nov 13-Nov 20-Nov 27-Nov 4-Dec 11-Dec 18-Dec
30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec 20-Dec
100
DIVISI 1. UMUM
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air Ls 131.00 0.31 0.31
5.1.(2) Lapis Pondasi Agregat Kelas B M3 608.00 27.25 5.45 5.45 5.45 5.45 5.45
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 1,920.00 1.96 0.65 0.65 0.65
6.3(6a) Laston Lapis Antara (AC-BC) Ton 334.00 36.87 12.29 12.29 12.29
DIVISI 7. STRUKTUR
7.1 (7) a Beton mutu sedang fc’20 Mpa (K-250) M3 8.00 0.96 0.48 0.48
7.1 (8) Beton mutu rendah fc’15 MPa (K-175) M3 48.00 4.38 1.10 1.10 1.10 1.10
7.3 (1) Baja Tulangan U 24 Polos Kg 2,895.00 3.47 0.58 0.58 0.58 0.58 0.58 0.58 0
Rencana Kemajuan Pekerjaan Mingguan (%) 0.65 0.65 0.25 1.59 1.06 1.67 1.67 1.67 1.67 5.45 5.45 5.45 5.45 10.48 5.03 5.03 5.03 12.95 12.95 12.95 2.23 0.65
Rencana Kemajuan Pekerjaan Kumulatif (%) 0.65 1.31 1.55 3.14 4.20 5.88 7.55 9.22 10.90 16.35 21.80 27.25 32.70 43.18 48.22 53.25 58.28 71.23 84.17 97.12 99.35 100.00
DEVIASI (%)
MATA HARGA SATUAN VOLUME HARGA KONTRAK VOLUME HARGA CCO.1 DEVIASI
DIVISI 1. UMUM
1.2 Mobilisasi Ls 25,030,000.00 1.00 25,030,000.00 1.00 25,030,000.00 - - Tetap
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air Ls 29,912.35 131.00 3,918,517.85 174.61 5,222,995.43 1,304,477.58 Tambah
DIVISI 3. PEKERJAAN TANAH
3.1.(3) Galian Struktur dengan kedalaman 0 - 2 meter M3 28,426.63 12.00 341,119.56 5.98 169,991.25 171,128.31 Kurang
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 174,687.18 162.75 28,430,338.55 - - 28,430,338.55 Hilang
3.3.(1) Penyiapan Badan Jalan M2 1,763.03 3,200.00 5,641,696.00 1,665.00 2,935,444.95 2,706,251.05 Kurang
DIVISI 5. PERKERASAN BERBUTIR
5.1.(1) Lapis Pondasi Agregat Kelas A M3 612,090.02 420.00 257,077,808.40 223.46 136,777,635.87 120,300,172.53 Kurang
5.1.(2) Lapis Pondasi Agregat Kelas B M3 572,342.13 608.00 347,984,015.04 294.39 168,491,799.65 179,492,215.39 Kurang
DIVISI 6. PERKERASAN ASPAL
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 13,058.98 1,920.00 25,073,241.60 1,091.96 14,259,883.80 10,813,357.80 Kurang
6.1 (2)(a) Lapis Perekat - Aspal Cair Liter 13,500.00 716.78 9,676,530.00 9,676,530.00 Item Baru
6.3(5a) Laston Lapis Aus (AC-WC) Ton 1,403,797.67 125.58 176,288,911.40 176,288,911.40 Item Baru
6.3(6a) Laston Lapis Antara (AC-BC) Ton 1,409,733.35 334.00 470,850,938.90 367.88 518,612,704.80 47,761,765.90 Tambah
6.3(6c) Laston Lapis Antara Perata (AC-BC(L) Ton 1,323,267.41 - 26.10 34,537,279.40 34,537,279.40 Item Baru
DIVISI 7. STRUKTUR
7.1 (7) a Beton mutu sedang fc’20 Mpa (K-250) M3 1,538,625.49 8.00 12,309,003.92 2.25 3,461,907.35 8,847,096.57 Kurang
7.1 (8) Beton mutu rendah fc’15 MPa (K-175) M3 1,166,137.31 48.00 55,974,590.88 109.16 127,295,548.76 71,320,957.88 Tambah
7.3 (1) Baja Tulangan U 24 Polos Kg 15,294.17 2,895.00 44,276,622.15 3,540.38 54,147,173.58 9,870,551.43 Tambah
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 1.00
Sesuai Kontrak 1.00
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air Ls 131.00 174.61
Galian Drainase 296.00 0.72 0.72 153.45
Cuci Parit 35.00 0.84 0.72 21.17
DIVISI 3. PEKERJAAN TANAH
3.1.(3) Galian Struktur dengan kedalaman 0 - 2 meter M3 12.00 5.98
Galian Box 5.98
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 162.75 -
DIVISI 1. UMUM
1.2 Mobilisasi LS 42,750,000.00 1.00 42,750,000.00 2.44 1.00 42,750,000.00 2.44 Tetap
DIVISI 3. PEKERJAAN TANAH
3.1.(1a) Galian Biasa M3 32,396.47 306.80 9,939,237.00 0.57 306.80 9,939,237.00 0.57 Tetap
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 164,645.75 95.30 15,690,739.98 0.89 95.30 15,690,739.98 0.89 Tetap
DIVISI 5. PERKERASAN BERBUTIR
5.1.(1) Lapis Pondasi Agregat Kelas A M3 468,940.64 334.00 156,626,173.76 8.93 334.00 156,626,173.76 8.93 Tetap
DIVISI 6. PERKERASAN ASPAL Tetap
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 12,864.71 1,234.50 15,881,484.50 0.91 1,234.50 15,881,484.50 0.91
6.1 (2)(a) Lapis Perekat - Aspal Cair Liter 14,809.94 2,238.23 33,148,052.01 1.89 2,238.23 33,148,052.01 1.89 Tetap
6.3(5a) Laston Lapis Aus (AC-WC) Ton 1,387,414.90 722.00 1,001,713,557.80 57.12 722.00 1,001,713,557.80 57.12
6.3(6a) Laston Lapis Antara (AC-BC) Ton 1,374,886.44 209.13 287,530,001.20 16.39 209.13 287,530,001.20 16.39 Tetap
6.3(6c) Laston Lapis Antara Perata (AC-BC(L) Ton 1,320,306.92 24.15 31,885,412.12 1.82 24.15 31,885,412.12 1.82 Tetap
DIVISI 7. STRUKTUR Tetap
7.1 (8) Beton mutu rendah fc’15 MPa (K-175) M3 925,979.47 129.89 120,275,473.36 6.86 129.89 120,275,473.36 6.86
7.3 (1) Baja Tulangan U 24 Polos Kg 14,802.69 2,590.63 38,348,292.79 2.19 2,590.63 38,348,292.79 2.19 Tetap
-
Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :
PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS BINA MARGA DAN PENGAIRAN PT. RAISSA GEMILANG CV. MITRA ROHUL
PROGRAM :
PENINGKATAN JALAN DAK
KEGIATAN :
PENINGKATAN JALAN SIMPANG SUPRA - RSUD ROKAN HULU
FINAL QUANTITY
KONTRAKTOR PELAKSANA
CV. MITRA ROHUL
KONSULTAN PENGAWAS
PT. RAISSA GEMILANG
TAHUN ANGGARAN 2016