PELAKSANAAN PROJECT TH 2020 - 2021
NO PEKERJAAN BOBOT NOPEMBER DESEMBER-2020 JANUARI-2021 PEBRUARI MARET APRIL MEI JUNI
7-`13 14-20 21-30 1-7 8-14 15-21 22-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21
I PRELIMINARIES 0.743% 0.371% 0.371%

II PEKERJAAN TANAH & LANTAI KERJA 0.689% 0.344% 0.344%

III PEKERJAAN STRUKTUR BETON 3.733% 0.747% 0.747% 0.747% 0.747% 0.747%

IV PEKERJAAN DINDING & PLESTERAN 33.159% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658% 1.658%

2/6
PELAKSANAAN PROJECT TH 2020 - 2021
NO PEKERJAAN BOBOT NOPEMBER DESEMBER-2020 JANUARI-2021 PEBRUARI MARET APRIL MEI JUNI
7-`13 14-20 21-30 1-7 8-14 15-21 22-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21

V PEKERJAAN PLAFOND , ATAP TRANSPARANT & TANGGA 7.709% 1.101% 1.101% 1.101% 1.101% 1.101% 1.101% 1.101%

VI PEKERJAAN PENUTUP LANTAI & DINDING 18.632% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035% 1.035%

3/6
PELAKSANAAN PROJECT TH 2020 - 2021
NO PEKERJAAN BOBOT NOPEMBER DESEMBER-2020 JANUARI-2021 PEBRUARI MARET APRIL MEI JUNI
7-`13 14-20 21-30 1-7 8-14 15-21 22-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21

VII PEKERJAAN INSTALASI LISTRIK 2.832% 0.472% 0.472% 0.472% 0.472% 0.472% 0.472%

VIII PEKERJAAN INSTALASI PLUMBING & SANITAIR 7.691% 0.961% 0.961% 0.961% 0.961% 0.961% 0.961% 0.961% 0.961%

4/6
PELAKSANAAN PROJECT TH 2020 - 2021
NO PEKERJAAN BOBOT NOPEMBER DESEMBER-2020 JANUARI-2021 PEBRUARI MARET APRIL MEI JUNI
7-`13 14-20 21-30 1-7 8-14 15-21 22-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-31 1-7 8-14 15-21 22-30 1-7 8-14 15-21 22-31 1-7 8-14 15-21

IX PEKERJAAN FINISHING 7.745% 1.291% 1.291% 1.291% 1.291% 1.291% 1.291%

X PEKERJAAN LAIN - LAIN 6.987% 1.747% 1.747% 1.747% 1.747%

XI PEKERJAAN KUSEN PINTU & JENDELA 10.087% 0.841% 0.841% 0.841% 0.841% 0.841% 0.841% 0.841% 0.841% 0.841% 0.841% 0.841% 0.841%

KOMULATIF 0.371% 1.834% 4.582% 8.088% 12.629% 17.170% 21.805% 26.440% 31.075% 35.710% 39.244% 43.249% 46.783% 50.788% 54.322% 58.327% 61.861% 65.867% 68.560% 72.686% 76.812% 82.213% 84.922% 87.630% 91.629% 93.881% 96.133% 97.424% 98.715% 100%

TOTAL 100% 0.371% 1.462% 2.749% 3.506% 4.541% 4.541% 4.635% 4.635% 4.635% 4.635% 3.534% 4.006% 3.534% 4.006% 3.534% 4.006% 3.534% 4.006% 2.693% 4.126% 4.126% 5.401% 2.708% 2.708% 3.999% 2.252% 2.252% 1.291% 1.291% 1.291%

5/6
PEKERJAAN INSTALASI LISTRIK
1 Instalasi titik lampu :
a) Lt Dasar Kabel 4 besar 45.00 ttk -
b) Lt Satu Kabel 4 besar 36.00 ttk -
2 Instalasi titik AC Kabel 4 besar
a) Lt Dasar Kabel 4 besar 9.00 ttk -
b) Lt Satu Kabel 4 besar 9.00 ttk -
3 Instalasi titik Stop Kontak :
a) Lt Dasar Kabel 4 besar 28.00 ttk -
b) Lt Satu Kabel 4 besar 24.00 ttk -
4 Kontak eks Clipsal :
a) Lt Dasar Kabel 4 besar 9.00 ttk -
b) Lt Satu Kabel 4 besar 5.00 ttk -
5 Saklar Engkel eks Clipsal :
a) Lt Dasar eks Broco Gracio / putih 8.00 ttk -
b) Lt Satu eks Broco Gracio / putih 5.00 ttk -
6 Saklar Seri eks Clipsal :
a) Lt Dasar eks Broco Gracio / putih 19.00 bh -
b) Lt Satu eks Broco Gracio / putih 5.00 bh -
7 Saklar Hotel Engkel eks Broco Gracio / putih 2.00 bh -
8 Box panel + MCCB MG matrial dr besi 2.00 unit -
9 Kabel toufur NYY 4 x 25 mm Kabel 4 besar 24.00 m' -
10 Grounding BC 6 mm Kabel 4 besar 1.00 lot -

TOTAL -