PROGRAM
KEGIATAN
PEKERJAAN
PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY
KEC. SAGULUNG ( 1 Paket )
3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 24-Dec
I PEKERJAAN PERSIAPAN 0.996 0.254 0.166 0.018 0.018 0.018 0.018 0.018 0.018 0.028 0.028 0.028 0.028 0.028 0.028 0.028 0.028 0.028 0.028 0.028 0.028 0.028 0.028 100%
-
II PEKERJAAN LANTAI 1 GEDUNG BLOCK A -
A PEKERJAAN PERSIAPAN 0.220 0.220
B PEKERJAAN TANAH DAN PONDASI 28.314 8.529 8.529 3.655 4.996 1.671 3.496 3.744 3.744 3.744 3.744
B PEKERJAAN PAGAR -
B.1 PEKERJAAN PAGAR BETON TYPE 1 6.279 0.897 0.897 0.897 0.897 0.897 0.897 0.897
(%)
A PEKERJAAN PERSIAPAN -
B PEKERJAAN PAGAR
0%
JUMLAH
Bobot Rencana Pekerjaan Mingguan 0.34 0.47 8.55 8.55 3.67 5.01 1.69 3.51 5.21 7.07 4.24 11.67 7.71 6.16 4.06 8.08 1.29 4.88 4.50 2.61 0.31 0.42
Bobot Rencana Pekerjaan Mingguan Komulatif 0.34 0.81 9.36 17.91 21.58 26.59 28.28 31.80 37.00 44.07 48.31 59.99 67.70 73.86 77.92 86.00 87.29 92.17 96.67 99.27 99.58 100
Bobot Realisasi Pekerjaan Mingguan -
Bobot Realisasi Pekerjaan Mingguan Komulatif -
Deviasi ( - / + ) (0.34)
JONI SATRIA PUTRA, S,Pd,M.Si Ir. LUKMANUL HAKIM Ir. LUKMANUL HAKIM
NIP. 19730191 200502 1 006 Team Leader TEAM LEADER
TIME SCHEDULE PELAKSANAAN PEKERJAAN
PROGRAM : PEMBANGUNAN, PEMELIHARAAN DAN PENGEMBANGAN INFRASTRUKTUR SARANA DAN PENYEDIA JASA : PT. SUMBER ARTHA REKSA MULIA
PRASARANA PEMUKIMAN DAN PERUMAHAN KONTRAK NO. : 11/KONTRAK/FISIK-PENATAAN/PPK/DTK/VII/2013
KEGIATAN : PENATAAN LINGKUNGAN KANTOR DINAS BERSAMA TANGGAL KONTRAK : 18 JULI 2013
PEKERJAAN : PENATAAN LINGKUNGAN KANTOR DINAS BERSAMA
LOKASI : KOTA BATAM
TA.Anggaran : 2013
I PEKERJAAN PERSIAPAN
1 Papan nama proyek 1.00 ls 0.002 0.002 100%
2 Direksi Keet 1.00 ls 0.104 0.104
3 Pelaporan dan dokumentasi 1.00 ls 0.116 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012
4 Shop drawing 1.00 ls 0.081 0.041 0.041
5 Asbuilt drawing 1.00 ls 0.081 0.041 0.041
6 Penyediaan air kerja 1.00 ls 0.070 0.070
7 Penyediaan listrik kerja 1.00 ls 0.104 0.104
8 Pembongkaran bangunan eksisting (paving, kanstin dan taman parkir) 3,762.0 m2 0.240 0.034 0.034 0.034 0.034 0.034 0.034 0.034
II PEKERJAAN KAWASAN KANTOR DINAS
►PEKERJAAN DRAINASE
A PEKERJAAN PERSIAPAN
1 Pembersihan lahan 74.95 m2 0.012 0.012
2 Pengukuran 133.28 m' 0.097 0.097
B PEKERJAAN DRAINASE
1 Peninggian saluran sekeliling bangunan.
a Pasangan bata 109.83 m2 0.299 0.149 0.149
b Plesteran 1 : 4 175.73 m2 0.126 0.063 0.063
2 Pemasangan saluran V 60 74.95 m' 1.202 0.601 0.601
4 Pembersihan saluran / normalisasi saluran U 80 95.94 m' 1.861 0.930 0.930
► PEKERJAAN BAK PENAMPUNGAN ( 2 unit )
A PEKERJAAN PERSIAPAN
1 Pembersihan lahan 0.030 0.030
2 Pengukuran dan pemasangan bowplank 0.047 0.047
B PEKERJAAN TANAH 90%
1 Galian tanah 96.00 m2 0.270 0.270
2 Urugan kembali 32.00 m1 0.032 0.032
C PEKERJAAN BETON
1 Pondasi type P1 150x150x30 cm
- Pasir urug t = 5 cm 1.13 m3 0.006 0.006
- Lantai kerja t = 5 cm 1.13 m3 0.039 0.039
- Beton K-250 6.75 m3 0.313 0.313
- Pembesian 729.96 kg 0.446 0.446
- Bekisting 18.00 m2 0.070 0.070
2 Pondasi type P2 180x180x30 cm
- Pasir urug t = 5 cm 0.32 m3 0.002 0.002
- Lantai kerja t = 5 cm 0.32 m3 0.011 0.011
- Beton K-250 1.94 m3 0.090 0.090
- Pembesian 221.83 kg 0.136 0.136
- Bekisting 4.32 m2 0.018 0.018
3 Sloof type S1 20/20 cm
- Pasir urug t = 5 cm 0.54 m3 0.003 0.003
- Lantai kerja t = 5 cm 0.54 m3 0.019 0.019
- Beton K-250 2.16 m3 0.100 0.100
- Pembesian 416.05 kg 0.254 0.254
- Bekisting 21.60 m2 0.146 0.146
4 Kolom K1 25X25 cm
- Beton K-250 2.03 m3 0.094 0.094
- Pembesian 379.42 kg 0.232 0.232 80%
- Bekisting 32.40 m2 0.219 0.219
5 Balok B1 15/30 cm
- Beton K - 250 1.44 m3 0.067 0.067
- Pembesian 181.39 kg 0.111 0.111
- Bekisting 19.20 m2 0.153 0.153
6 Balok B2 20/30 cm
- Beton K - 250 1.32 m3 0.061 0.061
- Pembesian 169.71 kg 0.104 0.104
- Bekisting 17.60 m2 0.140 0.140
7 Plat lantai bawah tebal 20 cm
- Beton K - 250 12.00 m3 0.557 0.557
- Wiremesh - 2 lapis Ø 8 - 200 60.00 m2 0.307 0.307
8 Plat lantai atas tebal 15 cm
- Beton K-250 9.42 m3 0.437 0.437
- Pembesian 2 lapis Ø 10 - 200 780.38 kg 0.477 0.477
- Bekisting 67.74 m2 0.506 0.506
9 Dinding tebal 15 cm
- Beton K-250 12.96 m3 0.602 0.602
- Pembesian 2 lapis Ø 10 - 200 1,197.72 kg 0.733 0.733
- Bekisting 177.12 m2 1.324 0.662 0.662
D PEKERJAAN MAIN HOLE
1 Penutup baja uk. 0,65 x 0,65 m2 1.00 unit 0.209 0.209
2 Air vent 1.00 unit 0.056 0.056
E PEKERJAAN POMPA DAN RUMAH POMPA 70%
1 Pengadaan dan pemasangan pompa ( lengkap ) 2.00 bh 0.697 0.697
2 Pembuatan rumah pompa 2.00 unit 0.511 0.511
3 Instalasi listrik 2.00 titik 0.015 0.015
4 Saklar 2.00 bh 0.011 0.011
5 Perpipaan 20.00 m' 0.009 0.009
F PEKERJAAN LAIN - LAIN
1 Pembuatan tangga monyet 1.00 unit 0.163 0.163
G PEKERJAAN BAK KONTROL
1 Pembuatan bak kontrol 2.00 unit 0.016 0.016
2 Pemasangan saluran U 60 8.00 m' 0.059 0.059
H PEKERJAAN PINTU AIR
1 Pintu air ( set lengkap ) 4.00 unit 0.418 0.418
►PEKERJAAN LAHAN PARKIR DAN LANDCAPE
A PEKERJAAN PERSIAPAN
1 Pengukuran 395.00 m' 0.289 0.289
2 Pembersihan lahan 1.00 ls 0.0002 0.0002
3 Urugan bauksit untuk leveling + pemadatan 752.40 m3 3.413 0.095 0.095 0.095 0.379 0.379 0.379 0.664 0.664 0.664
B PEKERJAAN BETON
154
147 3
H. SOEMARLAN, SE DERY FRY YANZA
NIP. 19590209 198503 1 009 Direktur Utama
RESUME
LAPORAN MINGGUAN
BOBOT KEMAJUAN PEKERJAAN
MINGGU KE : XXII (DUA PULUH DUA)
DINAS PENDIDIKAN KOTA BATAM
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015
JUMLAH 100.00
Jumlah Bobot Pekerjaan s/d Minggu Lalu 100.00
Jumlah Bobot Pekerjaan Minggu Ini -
Jumlah Bobot Pekerjaan s/d Minggu Ini 100.00
Rencana Bobot s/d Minggu Ini 97.33
### %
Kondisi Pekerjaan s/d Minggu Ini Lebih cepat 2.67
### % dari rencana
Catatan
JONI SATRIA PUTRA, S,Pd,M.Si Ir. LUKMANUL HAKIM Ir. LUKMANUL HAKIM
NIP. 19730191 200502 1 006 TEAM LEADER TEAM LEADER
Page 7 of 19
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
I PEKERJAAN PERSIAPAN
1 Direksi keet ( sewa container 20 feet ) bln 5.00 0.10 5.00 100.00 0.10 - - 5.00 100.00 0.10
2 Papan nama proyek Ls 1.00 0.04 1.00 100.00 0.04 - - 1.00 100.00 0.04
3 Dokumentasi dan pelaporan Ls 1.00 0.04 1.00 100.00 0.04 - - - 1.00 100.00 0.04
4 Shop drawing Ls 1.00 0.04 1.00 100.00 0.04 - - - 1.00 100.00 0.04
5 As built drawing Ls 1.00 0.04 1.00 100.00 0.04 - - - 1.00 100.00 0.04
6 Penyediaan air kerja bln 5.00 0.12 5.00 100.00 0.12 - - - 5.00 100.00 0.12
7 Penyediaan listrik kerja bln 5.00 0.12 5.00 100.00 0.12 - - - 5.00 100.00 0.12
8 Mobilisasi dan demobilisasi Ls 1.00 0.04 1.00 100.00 0.04 - - - 1.00 100.00 0.04
9 Pembersihan lahan ( Area gedung sekolah baru ) m2 2,597.96 0.45 2,597.96 100.00 0.45 - - - 2,597.96 100.00 0.45
-
-
II PEKERJAAN LANTAI 1 GEDUNG BLOCK A -
-
A PEKERJAAN PERSIAPAN -
1 Pengukuran dan bouwplank m' 157.00 0.22 157.00 100.00 0.22 - - 157.00 100.00 0.22
-
B PEKERJAAN TANAH DAN PONDASI -
PEKERJAAN PONDASI -
1 Pondasi Pile Cape P1 80 x 80 x 50 cm -
- Pengadaan tiang pancang uk. 30 x 30 cm m1 514.00 7.34 514.00 100.00 7.34 - - 514.00 100.00 7.34
- Pemancangan tiang pancang uk. 30 x 30 cm m1 452.50 2.77 452.50 100.00 2.77 - - 452.50 100.00 2.77
- Penyambungan tiang pancang uk. 30 x 30 cm titik - - - -
- Pemotongan tiang pancang uk. 30 x 30 cm titik 82.00 0.33 82.00 100.00 0.33 - - 82.00 100.00 0.33
- Galian tanah m3 49.20 0.13 49.20 100.00 0.13 - - 49.20 100.00 0.13
- Urugan kembali m3 4.46 0.00 4.46 100.00 0.00 - - 4.46 100.00 0.00
- Pasir urug t = 5 cm m3 4.10 0.03 4.10 100.00 0.03 - - 4.10 100.00 0.03
- Lantai kerja t = 5 cm m3 4.10 0.15 4.10 100.00 0.15 - - 4.10 100.00 0.15
- Beton K-250 m3 26.24 1.45 26.24 100.00 1.45 - - 26.24 100.00 1.45
- Pembesian + oversteck stump kg 5,777.62 2.03 5,777.62 100.00 2.03 - - 5,777.62 100.00 2.03
- Bekisting m2 131.20 0.31 131.20 100.00 0.31 - - 131.20 100.00 0.31
646629161.xls Page 8
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
646629161.xls Page 9
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
2 Lantai kerja, t = 5 cm m3 0.74 0.03 0.74 100.00 0.03 - - 0.74 100.00 0.03
3 Sloof type S2, uk.20/30 cm, beton K-250 m3 2.53 0.14 2.53 100.00 0.14 - - 2.53 100.00 0.14
4 Penulangan sloof type S2 kg 361.16 0.13 361.16 100.00 0.13 - - 361.16 100.00 0.13
5 Bekisting sloof type S2 m2 25.29 0.07 25.29 100.00 0.07 - - 25.29 100.00 0.07
6 Beton lantai 1:3:5 tebal 5 cm m3 81.69 2.89 81.69 100.00 2.89 - - - 81.69 100.00 2.89
-
III PEKERJAAN LANTAI 1 GEDUNG BLOCK B -
A PEKERJAAN PERSIAPAN -
1 Pengukuran dan bouwplank m' 123.60 0.17 123.60 100.00 0.17 - - 123.60 100.00 0.17
-
B PEKERJAAN TANAH DAN PONDASI -
PEKERJAAN PONDASI -
1 Pondasi Pile Cape P1 80 x 80 x 50 cm -
- Pengadaan tiang pancang uk. 30 x 30 cm m1 312.00 4.45 312.00 100.00 4.45 - - 312.00 100.00 4.45
- Pemancangan tiang pancang uk. 30 x 30 cm m1 288.30 1.76 288.30 100.00 1.76 - - 288.30 100.00 1.76
- Penyambungan tiang pancang uk. 30 x 30 cm titik 2.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
- Pemotongan tiang pancang uk. 30 x 30 cm titik 35.00 0.14 35.00 100.00 0.14 - - 35.00 100.00 0.14
- Galian tanah m3 21.00 0.05 21.00 100.00 0.05 - - 21.00 100.00 0.05
- Urugan kembali m3 4.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
- Pasir urug t = 5 cm m3 0.70 0.00 0.70 100.00 0.00 - - 0.70 100.00 0.00
- Lantai kerja t = 5 cm m3 0.70 0.02 0.70 100.00 0.02 - - 0.70 100.00 0.02
- Beton K-250 m3 11.20 0.62 11.20 100.00 0.62 - - 11.20 100.00 0.62
- Pembesian + oversteck stump kg 2,466.06 0.87 2,466.06 100.00 0.87 - - 2,466.06 100.00 0.87
- Bekisting m2 56.00 0.13 56.00 100.00 0.13 - - 56.00 100.00 0.13
2 Pondasi Pile Cape P2 80 x 80 x 50 cm -
- Pengadaan tiang pancang uk. 20 x 20 cm m1 112.00 1.37 112.00 100.00 1.37 - - 112.00 100.00 1.37
- Pemancangan tiang pancang uk. 20 x 20 cm m1 109.50 0.54 109.50 100.00 0.54 - - 109.50 100.00 0.54
- Penyambungan tiang pancang uk. 20 x 20 cm titik 5.00 0.02 5.00 100.00 0.02 - - 5.00 100.00 0.02
- Pemotongan tiang pancang uk. 20 x 20 cm titik 13.00 0.04 13.00 100.00 0.04 - - 13.00 100.00 0.04
- Galian tanah m3 7.80 0.02 7.80 100.00 0.02 - - 7.80 100.00 0.02
- Urugan kembali m3 1.42 0.00 1.42 100.00 0.00 - - 1.42 100.00 0.00
- Pasir urug t = 5 cm m3 0.65 0.00 0.65 100.00 0.00 - - 0.65 100.00 0.00
646629161.xls Page 10
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
- Lantai kerja t = 5 cm m3 0.65 0.02 0.65 100.00 0.02 - - 0.65 100.00 0.02
- Beton K-250 m3 4.16 0.23 4.16 100.00 0.23 - - 4.16 100.00 0.23
- Pembesian + oversteck stump kg 537.39 0.19 537.39 100.00 0.19 - - 537.39 100.00 0.19
- Bekisting m2 20.80 0.05 20.80 100.00 0.05 - - 20.80 100.00 0.05
3 Urugan tanah (tanah dari luar) + Pemadatan m3 349.52 0.97 349.52 100.00 0.97 - - 349.52 100.00 0.97
4 Pekerjaan Beton -
Kolom K1 -
- Kolom 40/25 cm, beton K-250 m3 14.14 0.78 14.14 100.00 0.78 - - 14.14 100.00 0.78
- Penulangan kg 3,086.98 1.08 3,086.98 100.00 1.08 - - 3,086.98 100.00 1.08
- Bekisting m2 183.82 0.96 183.82 100.00 0.96 - - 183.82 100.00 0.96
Kolom K2 -
- Kolom 25/25 cm, beton K-250 m3 3.28 0.18 3.28 100.00 0.18 - - 3.28 100.00 0.18
- Penulangan kg 567.61 0.20 567.61 100.00 0.20 - - 567.61 100.00 0.20
- Bekisting m2 52.52 0.27 52.52 100.00 0.27 - - 52.52 100.00 0.27
-
C PEKERJAAN BETON LANTAI I -
Sloof type S1, uk.20/40 cm -
1 Urugan pasir, t = 5 cm m3 7.99 0.05 7.99 100.00 0.05 - - 7.99 100.00 0.05
2 Lantai kerja, t = 5 cm m3 7.99 0.28 7.99 100.00 0.28 - - 7.99 100.00 0.28
3 Sloof type S1, uk.20/40 cm, beton K-250 m3 28.40 1.57 28.40 100.00 1.57 - - 28.40 100.00 1.57
4 Penulangan sloof type S1 kg 4,433.22 1.56 4,433.22 100.00 1.56 - - 4,433.22 100.00 1.56
5 Bekisting sloof type S1 m2 268.80 0.72 268.80 100.00 0.72 - - 268.80 100.00 0.72
Sloof type S2, uk.20/30 cm -
1 Urugan pasir, t = 5 cm m3 0.60 0.00 0.60 100.00 0.00 - - 0.60 100.00 0.00
2 Lantai kerja, t = 5 cm m3 0.60 0.02 0.60 100.00 0.02 - - 0.60 100.00 0.02
3 Sloof type S2, uk.20/30 cm, beton K-250 m3 2.05 0.11 2.05 100.00 0.11 - - 2.05 100.00 0.11
4 Penulangan sloof type S2 kg 292.26 0.10 292.26 100.00 0.10 - - 292.26 100.00 0.10
5 Bekisting sloof type S2 m2 20.46 0.06 20.46 100.00 0.06 - - 20.46 100.00 0.06
6 Beton lantai 1:3:5 tebal 5 cm m3 27.65 0.98 27.65 100.00 0.98 - - 27.65 100.00 0.98
-
IV PEKERJAAN LUAR BANGUNAN -
-
646629161.xls Page 11
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
A PEKERJAAN SALURAN -
2 Pekerjaan saluran U-80, Beton K-250 -
- Pembongkaran batu miring existing ls 1.00 0.23 1.00 100.00 0.23 - - 1.00 100.00 0.23
- Pembongkaran ramp jalan existing ls 1.00 0.04 1.00 100.00 0.04 - - 1.00 100.00 0.04
- Galian tanah m3 212.89 0.54 212.89 100.00 0.54 - - 212.89 100.00 0.54
- Lantai kerja, t = 5 cm m3 10.32 0.37 10.32 100.00 0.37 - - 10.32 100.00 0.37
- Urugan pasir, t = 5 cm m3 10.32 0.06 10.32 100.00 0.06 - - 10.32 100.00 0.06
- Urugan tanah kembali m3 63.87 0.07 63.87 100.00 0.07 - - 63.87 100.00 0.07
- Pipa sub drain pvc 2" m' 43.01 0.07 43.01 100.00 0.07 - - 43.01 100.00 0.07
- Beton K-250 m3 53.33 2.96 53.33 100.00 2.96 - - 53.33 100.00 2.96
- Besi Wiewmesh dia.8 kg 2,429.31 1.55 2,429.31 100.00 1.55 - - 2,429.31 100.00 1.55
- Bekisting m2 688.13 3.59 688.13 100.00 3.59 - - 688.13 100.00 3.59
3 Perbaikan batu miring exsting -
Pondasi -
- Galian tanah m3 51.95 0.13 51.95 100.00 0.13 - - 51.95 100.00 0.13
- Lantai kerja, t = 5 cm m3 3.25 0.12 3.25 100.00 0.12 - - 3.25 100.00 0.12
- Urugan tanah kembali m3 17.32 0.02 17.32 100.00 0.02 - - 17.32 100.00 0.02
- Beton K-250 m3 14.43 0.80 14.43 100.00 0.80 - - 14.43 100.00 0.80
- Penulangan kg 1,002.43 0.35 1,002.43 100.00 0.35 - - 1,002.43 100.00 0.35
- Bekisting m2 36.08 0.08 36.08 100.00 0.08 - - 36.08 100.00 0.08
Kolom -
- Beton K-250 m3 1.74 0.10 1.74 100.00 0.10 - - 1.74 100.00 0.10
- Penulangan kg 225.01 0.08 225.01 100.00 0.08 - - 225.01 100.00 0.08
- Bekisting m2 29.08 0.15 29.08 100.00 0.15 - - 29.08 100.00 0.15
Balok 15 x 20 cm -
- Beton K-250 m3 4.33 0.24 4.33 100.00 0.24 - - - 4.33 100.00 0.24
- Penulangan kg 370.59 0.13 370.59 100.00 0.13 - - - 370.59 100.00 0.13
- Bekisting m2 43.29 0.27 43.29 100.00 0.27 - - - 43.29 100.00 0.27
Pasangan batu belah m3 28.08 0.86 28.08 100.00 0.86 - - - 28.08 100.00 0.86
Pipa sub drain pvc 2" m' 86.58 0.14 86.58 100.00 0.14 - - - 86.58 100.00 0.14
4 Perbaikan ramp jalan existing -
- Beton K-250 m3 7.80 0.43 7.80 100.00 0.43 - - 7.80 100.00 0.43
646629161.xls Page 12
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
- Besi Wiewmesh dia.8 kg 205.40 0.13 205.40 100.00 0.13 - - 205.40 100.00 0.13
- Bekisting m2 4.35 0.01 4.35 100.00 0.01 - - 4.35 100.00 0.01
- Plastik cor m2 52.00 0.01 52.00 100.00 0.01 - - 52.00 100.00 0.01
5 Pebuatan ramp baru ( jalan masuk ) -
- Galian tanah ( badan jalan ) m3 33.80 0.09 33.80 100.00 0.09 - - 33.80 100.00 0.09
- Beton K-250 m3 7.80 0.43 7.80 100.00 0.43 - - 7.80 100.00 0.43
- Besi Wiewmesh dia.8 kg 205.40 0.13 205.40 100.00 0.13 - - 205.40 100.00 0.13
- Bekisting m2 4.35 0.01 4.35 100.00 0.01 - - 4.35 100.00 0.01
- Plastik cor m2 52.00 0.01 52.00 100.00 0.01 - - 52.00 100.00 0.01
6 Pekerjaan saluran precast U-40 -
- Galian tanah m3 202.85 0.52 202.85 100.00 0.52 - - 202.85 100.00 0.52
- Lantai kerja, t = 5 cm m3 9.84 0.35 9.84 100.00 0.35 - - 9.84 100.00 0.35
- Urugan tanah kembali m3 67.62 0.07 67.62 100.00 0.07 - - 67.62 100.00 0.07
- Saluran Beton precast U-40 m' 204.90 2.01 204.90 100.00 2.01 - - 204.90 100.00 2.01
8 Pekerjaan gorong-gorong dia.40 cm -
- Galian tanah m3 2.16 0.01 2.16 100.00 0.01 - - 2.16 100.00 0.01
- Urugan tanah kembali m3 0.54 0.00 0.54 100.00 0.00 - - 0.54 100.00 0.00
- Urugan pasir, t = 5 cm m3 0.06 0.00 0.06 100.00 0.00 - - 0.06 100.00 0.00
- Lantai kerja, t = 5 cm m3 0.06 0.00 0.06 100.00 0.00 - - 0.06 100.00 0.00
- Gorong-gorong dia. 40 cm m' 6.00 0.08 6.00 100.00 0.08 - - 6.00 100.00 0.08
10 Bak kontrol uk. 96 x 96 x 120 cm -
- Galian tanah m3 7.20 0.02 7.20 100.00 0.02 - - 7.20 100.00 0.02
- Urugan tanah kembali m3 2.16 0.00 2.16 100.00 0.00 - - 2.16 100.00 0.00
- Urugan pasir, t = 5 cm m3 0.30 0.00 0.30 100.00 0.00 - - 0.30 100.00 0.00
- Lantai kerja tebal 5 cm, beton 1 : 3 : 5 m3 0.30 0.01 0.30 100.00 0.01 - - 0.30 100.00 0.01
- Pasangan bata 1Pc : 4Ps m2 21.12 0.11 21.12 100.00 0.11 - - 21.12 100.00 0.11
- Plesteran 1Pc : 4Ps tebal 15 mm + acian halus m2 42.24 0.07 42.24 100.00 0.07 - - 42.24 100.00 0.07
- Beton 1 : 2 : 3 m3 1.73 0.06 1.73 100.00 0.06 - - 1.73 100.00 0.06
- Penulangan kg 56.88 0.02 56.88 100.00 0.02 - - - 56.88 100.00 0.02
- Bekisting m2 6.00 0.03 6.00 100.00 0.03 - - - 6.00 100.00 0.03
11 Bak kontrol uk. 70 x 70 x 80 cm -
- Galian tanah m3 3.58 0.01 3.58 100.00 0.01 - - 3.58 100.00 0.01
646629161.xls Page 13
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
- Urugan tanah kembali m3 1.08 0.00 1.08 100.00 0.00 - - 1.08 100.00 0.00
- Urugan pasir, t = 5 cm m3 0.17 0.00 0.17 100.00 0.00 - - 0.17 100.00 0.00
- Lantai kerja tebal 5 cm, beton 1 : 3 : 5 m3 0.17 0.01 0.17 100.00 0.01 - - 0.17 100.00 0.01
- Pasangan bata 1Pc : 4Ps m2 10.20 0.05 10.20 100.00 0.05 - - 10.20 100.00 0.05
- Plesteran 1Pc : 4Ps tebal 15 mm + acian halus m2 20.41 0.03 20.41 100.00 0.03 - - 20.41 100.00 0.03
- Beton 1 : 2 : 3 m3 0.34 0.01 0.34 100.00 0.01 - - 0.34 100.00 0.01
- Penulangan kg 17.42 0.01 17.42 100.00 0.01 - - 17.42 100.00 0.01
- Bekisting m2 3.43 0.02 3.43 100.00 0.02 - - 3.43 100.00 0.02
15 Pekerjaan Boxculvert uk. 80 x 80 x 100 cm, t=12 cm -
- Galian tanah m3 33.80 0.09 33.80 100.00 0.09 - - 33.80 100.00 0.09
- Urugan tanah kembali m3 10.14 0.01 10.14 100.00 0.01 - - 10.14 100.00 0.01
- Urugan pasir, t = 5 cm m3 1.00 0.01 1.00 100.00 0.01 - - 1.00 100.00 0.01
- Lantai kerja, t = 5 cm m3 1.00 0.04 1.00 100.00 0.04 - - 1.00 100.00 0.04
- Beton K-250 m3 9.24 0.51 9.24 100.00 0.51 - - 9.24 100.00 0.51
- Penulangan Besi kg 1,191.40 0.42 1,191.40 100.00 0.42 - - 1,191.40 100.00 0.42
- Bekisting m2 84.00 0.23 84.00 100.00 0.23 - - 84.00 100.00 0.23
- Pasangan bata 1Pc : 4Ps pagar m2 4.32 0.02 4.32 100.00 0.02 - - - 4.32 100.00 0.02
- Plesteran 1Pc : 4Ps tebal 15 mm + acian halus m2 8.64 0.01 8.64 100.00 0.01 - - 8.64 100.00 0.01
-
-
B PEKERJAAN PAGAR -
B.1 PEKERJAAN PAGAR BETON TYPE 1 -
Pekerjaan persiapan -
1 Pengukuran dan bouwplank m' 85.06 0.12 85.06 100.00 0.12 - - 85.06 100.00 0.12
2 Pekerjaan Tanah dan Pondasi -
- Galian tanah m3 3.82 0.01 3.82 100.00 0.01 - - 3.82 100.00 0.01
- Urugan tanah kembali m3 1.27 0.00 1.27 100.00 0.00 - - 1.27 100.00 0.00
- Urugan pasir tebal 5 cm m3 0.23 0.00 0.23 100.00 0.00 - - 0.23 100.00 0.00
- Lantai kerja tebal 5 cm, beton 1 : 3 : 5 m3 0.23 0.01 0.23 100.00 0.01 - - 0.23 100.00 0.01
- Pondasi foot plat, beton 1 : 2 : 3 m3 0.74 0.03 0.74 100.00 0.03 - - 0.74 100.00 0.03
- Penulangan kg 122.33 0.04 122.33 100.00 0.04 - - 122.33 100.00 0.04
- Bekisting m2 7.54 0.02 7.54 100.00 0.02 - - 7.54 100.00 0.02
646629161.xls Page 14
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
2 Pekerjaan Beton -
Sloof 15/20 cm -
- Galian tanah m3 4.65 0.01 4.65 100.00 0.01 - - 4.65 100.00 0.01
- Urugan tanah kembali m3 1.55 0.00 1.55 100.00 0.00 - - 1.55 100.00 0.00
- Urugan pasir tebal 5 cm m3 0.29 0.00 0.29 100.00 0.00 - - 0.29 100.00 0.00
- Lantai kerja tebal 5 cm, beton 1 : 3 : 5 m3 0.29 0.01 0.29 100.00 0.01 - - 0.29 100.00 0.01
- Sloof 15/20 cm, beton 1 : 2 : 3 m3 1.16 0.04 1.16 100.00 0.04 - - 1.16 100.00 0.04
- Penulangan kg 158.98 0.06 158.98 100.00 0.06 - - 158.98 100.00 0.06
- Bekisting m2 15.48 0.04 15.48 100.00 0.04 - - 15.48 100.00 0.04
3 Kolom 15/15 cm -
- Kolom 15/15 cm, beton 1 : 2 : 3 m3 1.18 0.04 1.18 100.00 0.04 - - 1.18 100.00 0.04
- Penulangan kg 237.64 0.08 237.64 100.00 0.08 - - 237.64 100.00 0.08
- Bekisting m2 31.50 0.16 31.50 100.00 0.16 - - 31.50 100.00 0.16
4 Ringbalk 15/20 cm -
- Ringbalk 15/20 cm, beton 1 : 2 : 3 m3 2.55 0.09 2.55 100.00 0.09 - - 2.55 100.00 0.09
- Penulangan kg 349.05 0.12 349.05 100.00 0.12 - - 349.05 100.00 0.12
- Bekisting m2 34.02 0.09 34.02 100.00 0.09 - - 34.02 100.00 0.09
5 Pekerjaan Pasangan dan Plesteran -
- Pasangan bata 1Pc : 4Ps m2 114.92 0.59 114.92 100.00 0.59 - - 114.92 100.00 0.59
- Pasangan bata penebalan kolom m2 99.75 0.51 99.75 100.00 0.51 - - 99.75 100.00 0.51
- Plesteran 1Pc : 4Ps tebal 15 mm + acian halus m2 379.86 0.64 379.86 100.00 0.64 - - 379.86 100.00 0.64
- List beton m' 693.86 2.83 693.86 100.00 2.83 - - 693.86 100.00 2.83
- Plesteran Ciprat tebal 10 mm, 1 Pc : 5 Ps m2 13.80 0.02 13.80 100.00 0.02 - - 13.80 100.00 0.02
6 Pekerjaan pengecatan -
- Pengecatan dinding baru m2 393.66 0.69 393.66 100.00 0.69 - - - 393.66 100.00 0.69
-
B.2 PEKERJAAN PAGAR TYPE 2 -
PEKERJAAN PAGAR PANEL PRECAST TINGGI 2.8 m -
Pekerjaan Tanah dan Pondasi -
- Galian tanah m3 16.76 0.04 16.76 100.00 0.04 - - 16.76 100.00 0.04
- Urugan tanah kembali m3 4.19 0.00 4.19 100.00 0.00 - - - 4.19 100.00 0.00
- Urugan pasir tebal 5 cm m3 0.68 0.00 0.68 100.00 0.00 - - 0.68 100.00 0.00
646629161.xls Page 15
RINCIAN LAPORAN KEMAJUAN PELAKSANAAN PEKERJAAN MINGGUAN
MINGGU KE : XXII (DUA PULUH DUA) NO. ADD-1 KONTRAK : ADD I/634/423.9/PROG/KONTRAK/PEMB.SMAN 19 BATAM/IX/2015
PERIODE TANGGAL : 22 DESEMBER S/D 24 DESEMBER 2015 TANGGAL ADD-1 KONT : 25 SEPTEMBER 2015
PEKERJAAN : PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY WAKTU PELAKSANAAN : 150 HARI KALENDER
KEC. SAGULUNG ( 1 Paket ) NILAI KONTRAK : RP. 2.451.547.000,-
LOKASI : KOTA BATAM KONTRAKTOR : PT. SEMANGAT KARYA SENTOSA
INSTANSI/DINAS : DINAS PENDIDIKAN KOTA BATAM KONSULTAN PENGAWA : PT. ASTAKONA CITRA GRAFINDO
Kemajuan s/d Minggu Lalu Kemajuan Minggu Ini Kemajuan s/d Minggu Ini
Thd. Item Thd. Total Thd. Item Thd. Total Thd. Item Thd. Total
Bobot
No Uraian Pekerjaan Satuan Volume
(%) Volume
Volume Pekerjaan Pekerjaan Pekerjaan Pekerjaan Volume Pekerjaan Pekerjaan
(%) (%) (%) (%) (%) (%)
- Lantai kerja tebal 5 cm, beton 1 : 3 : 5 m3 0.68 0.02 0.68 100.00 0.02 - - 0.68 100.00 0.02
- Pondasi foot plat, beton 1 : 2 : 3 m3 7.08 0.26 7.08 100.00 0.26 - - - 7.08 100.00 0.26
- Penulangan kg 510.84 0.18 510.84 100.00 0.18 - - - 510.84 100.00 0.18
- Bekisting m2 69.92 0.16 69.92 100.00 0.16 - - - 69.92 100.00 0.16
Pekerjaan Beton -
Sloof 20/25 cm -
- Galian tanah m3 4.75 0.01 4.75 100.00 0.01 - - 4.75 100.00 0.01
- Urugan tanah kembali m3 1.19 0.00 1.19 100.00 0.00 - - - 1.19 100.00 0.00
- Urugan pasir tebal 5 cm m3 0.95 0.01 0.95 100.00 0.01 - - - 0.95 100.00 0.01
- Lantai kerja tebal 5 cm, beton 1 : 3 : 5 m3 0.95 0.03 0.95 100.00 0.03 - - - 0.95 100.00 0.03
- Sloof 20/25 cm, beton 1 : 2 : 3 m3 4.75 0.17 4.75 100.00 0.17 - - - 4.75 100.00 0.17
- Penulangan kg 417.23 0.15 417.23 100.00 0.15 - - - 417.23 100.00 0.15
- Bekisting m2 47.45 0.13 47.45 100.00 0.13 - - - 47.45 100.00 0.13
Tiang pagar Precast 360 x 16 x 16 cm + pemasangan tiang 38.00 0.76 38.00 100.00 0.76 - - - 38.00 100.00 0.76
Panel beton precast 240 x 40 x 5 cm + pemasangan m2 255.09 2.33 255.09 100.00 2.33 - - - 255.09 100.00 2.33
-
C PEKERJAAN LAHAN PARKIR -
1 Penyiapan badan jalan m2 3,520.53 0.90 3,520.53 100.00 0.90 - - - 3,520.53 100.00 0.90
2 Urugan tanah bauksit tebal 15 cm + pemadatan m3 633.69 7.02 633.69 100.00 7.02 - - - 633.69 100.00 7.02
JONI SATRIA PUTRA, S,Pd,M.Si Ir. LUKMANUL HAKIM Ir. LUKMANUL HAKIM
NIP. 19730191 200502 1 006 TEAM LEADER TEAM LEADER
646629161.xls Page 16
DOKUMENTASI PROYEK
PEMBANGUNAN SMAN 19 BATAM TUNAS REGENCY
KEC. SAGULUNG ( 1 Paket )