Satuan Kerja : Satker NVT Pelaksanaan Jaringan Pemanfaatan Air Papua Provinsi Papua Barat

Nama Paket : Rehabilitasi Bendung D.I. Wariori Di Kab. Manokwari; Papua Barat; Kab. Manokwari; 1 Unit; 1 Unit; F; K; SYC
No. Kontrak : 01/HK.02.01/IR.1/PJPA/2023
Tanggal Kontrak : 31 Maret 2023
Penyedia Jasa : PT. MENARA GADING SAKTI
Prop / Kab : Papua Barat / Manokwari
Tahun Anggaran : 2023

JADWAL WAKTU PELAKSANAAN

MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER


No.
Mata HARGA SATUAN JUMLAH HARGA BOBOT 31/03/2023 03/04/2023 10/04/2023 17/04/2023 24/04/2023 01/05/2023 08/05/2023 15/05/2023 22/05/2023 29/05/2023 05/06/2023 12/06/2023 19/06/2023 26/06/2023 03/07/2023 10/07/2023 17/07/2023 24/07/2023 31/07/2023 07/08/2023 14/08/2023 21/08/2023 28/08/2023 04/09/2023 11/09/2023 18/09/2023 25/09/2023 02/10/2023 09/10/2023 16/10/2023 23/10/2023 30/10/2023 06/11/2023 13/11/2023 20/11/2023
URAIAN SAT KUANTITAS
Pembay ( Rp ) ( Rp ) (% ) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d KET
aran 02/04/2023 09/04/2023 16/04/2023 23/04/2023 30/04/2023 07/05/2023 14/05/2023 21/05/2023 28/05/2023 04/06/2023 11/06/2023 18/06/2023 25/06/2023 02/07/2023 09/07/2023 16/07/2023 23/07/2023 30/07/2023 06/08/2023 13/08/2023 20/08/2023 27/08/2023 03/09/2023 10/09/2023 17/09/2023 24/09/2023 01/10/2023 08/10/2023 15/10/2023 22/10/2023 29/10/2023 05/11/2023 12/11/2023 19/11/2023 25/11/2023

a b c d e f g 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
BAB I PEKERJAAN PERSIAPAN
1 Mobilisasi & Demobilisasi ls 1.00 55,000,000.00 55,000,000.00 0.18 RENC 0.04 0.04 0.04 0.05 100
REAL 0.04 0.03 0.03
2 Direksi Keet, Lost Kerja dan Gudang ls 1.00 108,518,613.96 108,518,613.96 0.36 RENC 0.12 0.12 0.12
REAL 0.18
3 Sistem Manajemen Keselamatan dan Kesehatan Kerja (SMK3) ls 1.00 86,640,961.62 86,640,961.62 0.29 RENC 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
REAL 0.01 0.01 0.01
4 Papan Nama Proyek bh 1.00 1,234,640.00 1,234,640.00 0.004 RENC 0.004
REAL 0.004
5 Pekerjaan Dewatering
- Kistdam Geobag pasir\/tanah uk. 200cm x 200 x 100cm bh 2,604.00 453,259.40 1,180,287,477.60 3.90 RENC 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
REAL
- Pengoperasian per - jam pompa air diesel jam 1,680.00 17,462.56 29,337,092.40 0.10 RENC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
REAL
- Bronjong Pabrikasi 3mm (Pengaman Kitsdam Geobag) m3 3,720.00 1,501,075.40 5,584,000,488.00 18.45 RENC 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60
REAL
BAB II PEKERJAAN PERMANEN
A Pekerjaan Tanah
1 Galian Tanah Pasir Berbatu dgn Alat Berat m3 20,981.05 37,603.04 788,951,202.57 2.61 RENC 0.09 0.09 0.13 0.13 0.13 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19
REAL
2 Mengangkut Hasil Galian m3 20,981.05 51,332.95 1,077,019,289.43 3.56 RENC 0.12 0.12 0.18 0.18 0.18 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25
REAL SCHEDULE
B Pekerjaan Pasangan/Beton RENCANA
1 Pembongkaran Konstruksi lama m3 948.75 45,123.64 42,811,057.79 0.14 RENC 0.02 0.02 0.02 0.02 0.02 0.02
REAL
2 Beton Mutu fc = 31,2 MPa (K350) Selimut Spillway m3 1,365.96 1,823,938.90 2,491,427,575.51 8.23 RENC 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 50
REAL
3 Beton Mutu fc = 31,2 MPa (K350) Lantai Appron m3 1,169.18 1,823,938.90 2,132,512,879.39 7.04 RENC 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41
REAL
4 Pembesian untuk Selimut Spillway (Besi Ulir) kg 69,882.46 30,107.77 2,104,005,032.71 6.95 RENC 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41
REAL
5 Pembesian untuk Lantai Appron (Besi Ulir) kg 56,998.73 30,107.77 1,716,104,653.13 5.67 RENC 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38
REAL
6 Besi Trashtrack = 22 mm ( Besi Ulir ) kg 35,565.47 45,000.00 1,600,446,150.00 5.29 RENC 0.88 0.88 0.88 0.88 0.88 0.88
REAL
7 Besi Siku 150.150.10 ( Rangka Saringan ) kg 14,342.00 50,000.00 717,100,000.00 2.37 RENC 0.39 0.39 0.39 0.39 0.39 0.39
REAL
8 Pekerjaan Bekisting m2 1,160.07 140,910.00 163,465,463.70 0.54 RENC 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
REAL
9 Pekerjaan Pembongkaran Bekisting m2 1,160.07 7,759.40 9,001,447.16 0.03 RENC 0.01 0.01 0.01
REAL
C Pekerjaan Pengaman Mercu
1 Pembesian Untuk Beton kg 143,265.27 30,107.77 4,313,397,798.15 14.25 RENC 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89
REAL
2 Beton untuk lantai kerja (Bedding) Pondasi m3 170.13 1,428,743.80 243,072,182.69 0.80 RENC 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
REAL
3 Mutu Beton fc = 31,2 MPa (K350) m3 2,303.67 1,823,938.90 4,201,753,318.45 13.88 RENC 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87
REAL
4 Pemasangan Bekisting Untuk Beton m2 3,750.98 140,910.00 528,550,591.80 1.75 RENC 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
REAL
SCHEDULE
REALISASI
5 Pembongkaran Bekisting m2 3,750.98 7,759.40 29,105,354.21 0.10 RENC 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
REAL
6 Pasangan Batu Kosong Dia.0.50m m3 1,260.00 846,450.00 1,066,527,000.00 3.52 RENC 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0
REAL
JUMLAH HARGA 30,270,270,270.27 100.00
PROGRESS PER MINGGU 0.05 0.17 0.17 0.85 0.73 0.73 0.73 0.94 0.96 1.06 1.47 1.88 2.58 3.47 4.80 4.80 4.80 4.80 4.80 4.80 4.80 4.80 6.08 5.64 5.64 5.27 5.71 5.71 3.94 2.53 1.67 1.19 1.18 1.18 0.06
RENCANA
KUMULATIF 0.00 0.05 0.22 0.39 1.25 1.98 2.71 3.44 4.38 5.34 6.41 7.88 9.76 12.34 15.81 20.60 25.40 30.20 35.00 39.79 44.59 49.39 54.19 60.27 65.91 71.56 76.83 82.53 88.24 92.18 94.71 96.38 97.57 98.75 99.94 100.00
PROGRESS PER MINGGU 0.05 0.04 0.23
REALISASI
KUMULATIF 0.00 0.05 0.09 0.32
DEVIASI 0.00 -0.14 -0.08

Satker NVT PJPA Papua


Provinsi Papua Barat
Pejabat Penandatangan Kontrak Konsultan Supervisi, Penyedia Jasa,
Pada Kegiatan Irigasi dan Rawa I PT. MULYA SAKTI WIJAYA PT. MENARA GADING SAKTI

Steven Samel Tasidjawa, S.T. Mochamad Santoso, S.T. Edwin Valentino Irsiandi
NIP. 19840103 201412 1 001 Team Leader Direktur Cabang