WAKTU PELAKSANAAN PEKERJAAN ( S - CURVE )

PROJECT : Pembangunan Site Camp PT. EBH


TITLE : Pembangunan Pondasi Tangki 10 KL
DESIGN : PT. KARUNIA HARTA RAYA
CONSTRUCTION : Sipil

PERIODE : 29 APRIL S/D 05 MEI 2023

WAKTU PELAKSANAAN

NO URAIAN PEKERJAAN VOL SAT BOBOT MARET APRIL KET

26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pengukuran & Pas. Bowplank 35.0 m' 1.04% 0.35% 0.35% 0.35%
2 Pengadaan Listrik dan Air Kerja 1.0 Ls 1.62% 0.54% 0.54% 0.54%
3 Mobilisasi dan Demobilisasi 1.0 Ls 2.94% 0.98% 0.98% 0.98%
4 Pek. Pembersihan lahan 1.0 Ls 1.47% 0.37% 0.37% 0.37% 0.37%
5 Pembuatan Bedeng Pekerja & Direksi Kit 1.0 Ls 11.08% 2.77% 2.77% 2.77% 2.77%
6 K3 & Safety 1.0 Ls 1.47% 0.73% 0.73%
7 Surat Kesehatan & Protokol Covid 1.0 Ls 1.32% 0.66% 0.66%
SUB TOTAL I 20.93%
II. PEKERJAAN KONTRUKSI :
A PEKERJAAN TANAH & PASIR
1 Pek. Galian Tanah Pondasi foot plat L, 60 1.15 m³ 0.06% 0.02% 0.02% 0.02%
2 Pek. Urugan Kembali Bekas Galian 0.62 m³ 0.02% 0.01% 0.01% 0.01%
3 Pek. Urugan Pasir Bawah Pondasi 0.14 m³ 0.03% 0.01% 0.01%
4 Pek. Urugan Pasir Bawah Lantai 3.58 m³ 0.66% 0.22% 0.22% 0.22%
SUB TOTAL A 0.77%
B PEKERJAAN STRUKTUR BETON
1 Pek. Sloof Beton Bertulang 15/20 1.05 m³ 1.03% 0.26% 0.26% 0.26% 0.26%
2 Pek. Kolom Beton Bertulang 12/12 0.30 m³ 0.30% 0.07% 0.07% 0.07% 0.07%
3 Pek. Ring Balok Bertulang 15/20 1.38 m³ 1.43% 0.36% 0.36% 0.36% 0.36%
SUB TOTAL B 2.76%
C PEK. PASANGAN, DINDING DAN PLESTERAN
1 Pas. Pondasi Foot plat 60 x 60 0.53 m³ 0.47% 0.09% 0.09% 0.09% 0.09% 0.09%
2 Pas. Dinding hebel t= 7.5cm 86.88 m² 9.76% 2.44% 2.44% 2.44% 2.44%
3 Pas. Plesteran Dinding + Acian 173.75 m² 12.03% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00%
SUB TOTAL C 22.26%
D PEKERJAAN ATAP
Pas. Kuda² & Rangka Atap (Baja Ringan Lengkap) Kualitas Galvalum (Zinc -
1
Alumunium) Coating
132.60 m² 9.31% 2.33% 2.33% 2.33% 2.33%
2 Pas. Penutup atap genteng metalroof 132.60 m² 7.12% 2.37% 2.37% 2.37%
3 Pas. Listplank dari GRC 43.00 m' 1.04% 0.52% 0.52%
4 Pas. Bubungan metalroof 31.90 m' 1.34% 0.67% 0.67%
SUB TOTAL D 18.81%
E PEKERJAAN PINTU & JENDELA
1 Type P2 (Singel) 1.0 Unit 2.28% 0.76% 0.76% 0.76%
2 Type P2 (Double) 2.0 Unit 9.12% 3.04% 3.04% 3.04%
3 Type Lovre 4.0 Unit 1.19% 0.40% 0.40% 0.40%
SUB TOTAL E 12.59%
F PEKERJAAN LANTAI
1 Cor Lantai dan Pondasi Genset 23.30 m² 7.88% 1.97% 1.97% 1.97% 1.97%
2 Pas. Rabat beton 1.00 m² 0.23% 0.11% 0.11%
SUB TOTAL F 8.10%
G PEKERJAAN PENGECATAN
1 Pek. Cat Dinding Bangunan setara Avitex 91.22 m² 1.65% 0.41% 0.41% 0.41% 0.41%
2 Pek. Cat lisplang setara Avian 43.00 m' 0.60% 0.60%
SUB TOTAL G 2.26%
H PEKERJAAN MEKANIKAL & ELEKTRIKAL
1 Pekerjaan Elektrikal 1 Ls 6.21% 2.07% 2.07% 2.07%
2 Bak Kontrol / Oil Trap (Convensional Uk 2.55 mtr x 1.15 mtr tinggi 0.0 Bh
1.25 mtr) (Gabung dengan oil trap Pondasi Tangki)
3 Grill (Besi Ø10mm, siku 40x40x4mm) 11.0 m' 1.86% 0.62% 0.62% 0.62%
4 Instalasi Oil Trap 3" (Pipa 2" dan 3" PVC AW Setara Power) 35.0 m' 1.99% 0.40% 0.40% 0.40% 0.40% 0.40%
SUB TOTAL H 10.05%
I PEKERJAAN LAIN LAIN
1 Pembersihan bekas pekerjaan + buang puing 1.00 Ls 1.47% 0.73% 0.73%
SUB TOTAL I 1.47%
GRAND TOTAL 100%
Persentase Progress Rencana 2.7% 2.7% 0.37% 0.7% 0.3% 0.3% 3.3% 3.4% 3.4% 2.9% 0.6% 0.6% 2.4% 2.3% 2.0% 4.5% 2.6% 5.0% 4.8% 2.8% 2.4% 2.8% 5.1% 3.1% 7.3% 11.6% 11.2% 8.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Persentase Komulatif Progress Rencana 2.7% 5.5% 5.9% 6.6% 6.9% 7.3% 10.6% 14.0% 17.4% 20.3% 20.9% 21.5% 23.9% 26.2% 28.3% 32.8% 35.4% 40.3% 45.2% 47.9% 50.3% 53.1% 58.2% 61.3% 68.6% 80.2% 91.4% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Persentase Progress Realisasi 0.0% 5.48% 0.73% 0.35% 0.70% 0.98% 0.56% 0.65% 0.00% 2.87% 0.67% 0.03% 0.03% 0.00% 1.23% 2.08% 1.93% 2.04% 0.00% 1.12% 1.30% 0.90% 1.03% 0.65% 0.58% 0.60% 0.62% 0.40% 0.0% 0.0% 0.0% 2.8% 2.2% 1.5% 3.4% 0.0% 2.0% 0.0% 1.0% 1.3% 0.7%
Persentase Komulatif Progress Realisasi 0.0% 5.48% 6.22% 6.57% 7.26% 8.24% 8.80% 9.45% 9.45% 12.32% 12.99% 13.02% 13.04% 13.04% 14.27% 16.35% 18.28% 20.32% 20.32% 21.44% 22.74% 23.64% 24.67% 25.32% 25.90% 26.50% 27.12% 27.52% 27.52% 27.52% 27.52% 30.32% 32.52% 34.03% 37.41% 37.41% 39.41% 39.41% 40.41% 41.70% 42.40%
Deviasi -2.7% 0.00% 0.37% 0.00% 0.35% 0.98% -1.79% -4.6% -8.0% -8.0% -7.9% -8.5% -10.9% -13.2% -14.0% -16.4% -17.1% -20.0% -24.9% -26.5% -27.6% -29.4% -33.5% -36.0% -42.7% -53.7% -64.2% -72.5% -72.5% -72.5% -72.5% -69.7% -67.5% -66.0% -62.6% -62.6% -60.6% -60.6% -59.6% -58.3% -57.6%
DOKUMENTASI PROYEK
PROJECT : Pembangunan Site Camp PT. EBH
TITLE : Pembangunan Rumah Genset
DESIGN : PT. KARUNIA HARTA RAYA
CONSTRUCTION : Sipil
PERIODE : 29 APRIL S/D 05 MEI 2023
LAPORAN HARIAN
PROJECT : Konstruksi Simpang Sebidang Jalan Nasional STA. 10+800 Jalan Hauling di Muara Lawa
di Kabupaten Kutai Barat, Provinsi Kalimantan Timur

CONSTRUCTION : Sipil
HARI / TANGGAL : Sabtu, 12 Agustus 2023
PUKUL : 08.00 - 17.00

Capaian Man Power


No Deskripsi Pekerjaan Safety Matters Jumlah
Pekerjaan Fungsi Jumlah
1 Tidak ada kegiatan Site Manager Helem
2 Safety Rompi
3 Driver Sepatu Boot
4 Tukang Batu Sarung Tangan
5 Kenek / pekerja
6 Gudang
7 Pelaksana
8 Plumbing
9 Listrik
10 Mandor
Operator Exca
0

Material yang digunakan Alat yang digunakan Jumlah Laporan Cuaca

Palu
24
Gergaji
Cangkul 12

Sekop
Conrete Mixer 21 9 15 3 Keterangan :

Artco : Hujan

concrete vibrator : Gerimis


6
bor : Cerah

Mesin Gurinda 18

Excavator pc 200

Catatan / Lain-lain

Dibuat Oleh Diketahui Oleh Disetujui Oleh


Kontraktor PT. ENERGI BATU HITAM

AWANG PANGESTU
LAPORAN HARIAN
PROJECT : Konstruksi Simpang Sebidang Jalan Nasional STA. 10+800 Jalan Hauling di Muara Lawa
di Kabupaten Kutai Barat, Provinsi Kalimantan Timur
CONSTRUCTION : Sipil
HARI / TANGGAL : Minggu, 13 Agustus 2023
PUKUL : 08.00 - 17.00

Capaian Man Power


No Deskripsi Pekerjaan Safety Matters Jumlah
Pekerjaan Fungsi Jumlah
1 Libur Site Manager Helem
2 Safety Rompi
3 Driver Sepatu Boot
4 Tukang Batu Sarung Tangan
5 Kenek / pekerja
6 Gudang
7 Pelaksana
8 Plumbing
9 Listrik
10 Operator Exca

Material yang digunakan Alat yang digunakan Jumlah Laporan Cuaca

24
12

21 9 15 3 Keterangan :

: Hujan

: Gerimis
6
: Cerah
18

Catatan / Lain-lain

Dibuat Oleh Diketahui Oleh Disetujui Oleh


Kontraktor PT. ENERGI BATU HITAM

AWANG PANGESTU
LAPORAN HARIAN
PROJECT : Konstruksi Simpang Sebidang Jalan Nasional STA. 10+800 Jalan Hauling di Muara Lawa
di Kabupaten Kutai Barat, Provinsi Kalimantan Timur
CONSTRUCTION : Sipil
HARI / TANGGAL : Senin, 14 Agustus 2021
PUKUL : 08.00 - 17.00

Capaian Man Power


No Deskripsi Pekerjaan Safety Matters Jumlah
Pekerjaan Fungsi Jumlah
1 Tidak ada kegiatan Site Manager Helem
2 Safety Rompi
3 Driver Sepatu Boot
4 Tukang Batu Sarung Tangan
5 Kenek / pekerja
6 Gudang
7 Pelaksana
8 Plumbing
9 Listrik
10 Operator Exca

Material yang digunakan Alat yang digunakan Jumlah Laporan Cuaca


24
Palu
Gergaji 12

Cangkul
gegep 21 9 15 3
pleser Keterangan :

bar cutter : Hujan

concrete vibrator 6 : Gerimis

mesin las 18 : Cerah

Mesin Gurinda
Excavator pc 200

Catatan / Lain-lain

Dibuat Oleh Diketahui Oleh Disetujui Oleh


Kontraktor PT. ENERGI BATU HITAM

AWANG PANGESTU
LAPORAN HARIAN
PROJECT : Konstruksi Simpang Sebidang Jalan Nasional STA. 10+800 Jalan Hauling di Muara Lawa
di Kabupaten Kutai Barat, Provinsi Kalimantan Timur

CONSTRUCTION : Sipil
HARI / TANGGAL : Selasa, 15 Agustus 2023
PUKUL : 08.00 - 17.00

Capaian Man Power


No Deskripsi Pekerjaan Safety Matters Jumlah
Pekerjaan Fungsi Jumlah
1 Tidak ada kegiatan Site Manager Helem
2 Safety Rompi
3 Driver Sepatu Boot
4 Tukang Batu Sarung Tangan
5 Kenek / pekerja
6 Gudang
7 Pelaksana
8 Plumbing
9 Listrik
10 Operator Exca
Operator compact
0

Material yang digunakan Alat yang digunakan Jumlah Laporan Cuaca

Palu
24
Gergaji
12
Cangkul
gegep
pleser 21 9 15 3 Keterangan :

bar cutter : Hujan

concrete vibrator : Gerimis

mesin las 6 : Cerah

Vibrator roller 18
Excavator pc 200

Catatan / Lain-lain

Dibuat Oleh Diketahui Oleh Disetujui Oleh


Kontraktor PT. ENERGI BATU HITAM

AWANG PANGESTU
LAPORAN HARIAN
PROJECT : Konstruksi Simpang Sebidang Jalan Nasional STA. 10+800 Jalan Hauling di Muara Lawa
di Kabupaten Kutai Barat, Provinsi Kalimantan Timur

CONSTRUCTION : Sipil
HARI / TANGGAL : Rabu, 16 Agustus 2023
PUKUL : 08.00 - 17.00

Capaian Man Power


No Deskripsi Pekerjaan Safety Matters Jumlah
Pekerjaan Fungsi Jumlah
1 Tidak ada kegiatan Site Manager Helem
2 Safety Rompi
3 Driver Sepatu Boot
4 Tukang Batu Sarung Tangan
5 Kenek / pekerja
6 Gudang
7 Pelaksana
8 Plumbing
9 Listrik
10 Operator Exca

Material yang digunakan Alat yang digunakan Jumlah Laporan Cuaca


24
Palu
Gergaji 12

Cangkul
gegep 21 9 15 3
pleser Keterangan :

bar cutter : Hujan


6
concrete vibrator : Gerimis

tandon air 18 : Cerah

alkon
Excavator pc 200

Catatan / Lain-lain

Dibuat Oleh Diketahui Oleh Disetujui Oleh


Kontraktor PT. ENERGI BATU HITAM

AWANG PANGESTU
LAPORAN HARIAN
PROJECT : Konstruksi Simpang Sebidang Jalan Nasional STA. 10+800 Jalan Hauling di Muara Lawa
di Kabupaten Kutai Barat, Provinsi Kalimantan Timur
CONSTRUCTION : Sipil
HARI / TANGGAL : Kamis, 17 Agustus 2023
PUKUL : 08.00 - 17.00

Capaian Man Power


No Deskripsi Pekerjaan Safety Matters Jumlah
Pekerjaan Fungsi Jumlah
1 Tidak ada kegiatan Site Manager Helem
2 Safety Rompi
3 Driver Sepatu Boot
4 Tukang Batu Sarung Tangan
5 Kenek / pekerja
6 Gudang
7 Pelaksana
8 Plumbing
9 Listrik
10 Operator Exca

Material yang digunakan Alat yang digunakan Jumlah Laporan Cuaca


24
Palu
Gergaji 12

Cangkul
gegep 21 9 15 3
pleser Keterangan :

bar cutter : Hujan


6
concrete vibrator : Gerimis

mesin las 18 : Cerah

Total station
Excavator pc 200

Catatan / Lain-lain

Dibuat Oleh Diketahui Oleh Disetujui Oleh


Kontraktor PT. ENERGI BATU HITAM

AWANG PANGESTU
LAPORAN HARIAN
PROJECT : Konstruksi Simpang Sebidang Jalan Nasional STA. 10+800 Jalan Hauling di Muara Lawa
di Kabupaten Kutai Barat, Provinsi Kalimantan Timur
CONSTRUCTION : Sipil
HARI / TANGGAL : Jumat, 18 Agustus 2023
PUKUL : 08.00 - 17.00

Capaian Man Power


No Deskripsi Pekerjaan Safety Matters Jumlah
Pekerjaan Fungsi Jumlah
1 Tidak ada kegiatan Site Manager Helem
2 Safety Rompi
3 Driver Sepatu Boot
4 Tukang Batu Sarung Tangan
5 Kenek / pekerja
6 Gudang
7 Pelaksana
8 Plumbing
9 Listrik
10 Operator Exca

Material yang digunakan Alat yang digunakan Jumlah Laporan Cuaca


24
Palu
Gergaji 12

Cangkul
gegep 21 9 15 3
pleser Keterangan :

bar cutter : Hujan


6
concrete vibrator : Gerimis

mesin las 18 : Cerah

Mesin Gurinda
Excavator pc 200

Catatan / Lain-lain

Dibuat Oleh Diketahui Oleh Disetujui Oleh


Kontraktor PT. ENERGI BATU HITAM

AWANG PANGESTU
PROGRESS PEKERJAAN
: Konstruksi Simpang Sebidang Jalan Nasional STA. 10+800 Jalan Hauling di Muara Lawa di Kabupaten Kutai Barat,
PROJECT
Provinsi Kalimantan Timur

CONSTRUCTION : Sipil

PERIODE : 12 AGUSTUS S/D 18 AGUSTUS 2023

S/D MINGGU LALU MINGGU INI S/D MINGGU INI


NO URAIAN PEKERJAAN VOL SAT BOBOT
PROGRESS BOBOT (%) PROGRESS BOBOT (%) PROGRESS BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Mobilisasi
Mobilisasi 1.0 Ls 6.84 1.0 6.84000000027067 0 0 1 6.84000000027067
Excavator Mini

SUB TOTAL I 6.84 6.84000000027067 0 6.84000000027067


A PEKERJAAN GALIAN
1 Galian Biasa 768.00 M3 2.538 672 2.22070231823188 0 0 672 2.22070231823188
2 Galian Perkerasan Beraspal dengan Cold Milling Machine 8.40 M3 0.189 - 0 0 0 0 0
3 Galian Perkerasan berbutir 33.60 M3 0.036 - 0 0 0 0 0
4 Penyiapan Badan Jalan 1200.00 M2 1.034 258.00 0.22227068572308 0 258 0.22227068572308

SUB TOTAL A 3.797526327 2.44297300395496 0 2.44297300395496


B PEKERJAAN BETON
BAHU JALAN
Lapis Pondasi 60.00 M3 0.461 30.98 0.23821552307228 - 0 30.98 0.23821552307228
Perkerasan Beton 80.00 M3 6.350 - 0 0 0 0 0
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 40.00 M3 2.695 30.98 2.08759916736992 - 0 30.98 2.08759916736992
Bekisting 40.00 M2 0.322 14.66 0.1180043464161 0 14.66 0.1180043464161
Bowhplank 200.00 m1 0.526 180.00 0.4733377714473 0 0 180 0.4733377714473
SUB TOTAL B 10.35498659 2.91715680830561 0 2.91715680830561
C BADAN JALAN
Lapis Pondasi 37.50 M3 0.288 48.00 0.36908796344318 0 48 0.36908796344318
Perkerasan Beton ( 12m x 100m x 0.3m ) 360.00 M3 31.203 - 0 0 0 0 0
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 120.00 M3 9.525 - 0 0 0 0 0
Bekisting 30.00 M2 0.241 30.00 0.24148229143813 0 0 30 0.24148229143813
Bowhplank 200.00 m1 0.526 0.21 0.00055320653303 0 0.21037234286547 0.00055320653303
DRAINASE
Perkerasan Beton 168.00 M3 13.336 45 3.57204603524135 0 0 45 3.57204603524135
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 24.00 M3 1.617 15.66 1.0552550988061 0 0 15.66 1.0552550988061
Bekisting 960.00 M2 7.727 718.16 5.78076408064018 0 0 718.16 5.78076408064018
Besi Beton 11413.33 Kg 9.033 7943.67768 6.287178034394 0.00 0 7943.67768 6.287178034394
Pipa Drainase 37.50 m1 0.069 5.00 0.00924132857179 0 0 5 0.00924132857179
Geotekstil 10.00 M2 0.041 2.50 0.01026000000041 0 0 2.5 0.01026000000041
Bowhplank 300.00 m1 0.789 225.00 0.59167221430913 0 0 225 0.59167221430913
SUB TOTAL C 74.39716478 17.9175402533773 0 17.9175402533773
D POS PANTAU DAN POS SCURITY

Pos Pantau (Permanen ) 4.00 m² 0.521 4 0.52114285716348 0.00 0 4 0.52114285716348

Pos Security (Semi Permanen) 12.00 m² 1.563 11.89 1.54920881638985 0.000 0 11.891 1.54920881638985
SUB TOTAL D 2.084571429 2.07035167355333 0 2.07035167355333
E SAFETY EQUIPMENT
Rotary 2.0 Set 0.110 - 0 0 0 0 0
Lampu Sorot 2.0 Unit 0.666 - 0 0 0 0 0
Instalasi Listrik 1.0 Ls 0.489 - 0 0 0 0 0
Instalasi Air / Penyiraman 1.0 Ls 0.651 - 0 0 0 0 0
Marka Jalan 1.0 Ls 0.395 - 0 0 0 0 0
Rambu Rambu 12.0 Set 0.216 0 0 0 0 0

SUB TOTAL E 2.525750875 0 0 0


GRAND TOTAL 100 32.1880217394619 0 10,236.72 32.1880217394619
JADWAL PELAKSANAAN PEKERJAAN ( KURVA " S " )

Kegiatan
Tahun Anggaran

W A K T U P E L A K S A N AAN
BOBOT
NO. URAIAN PEKERJAAN JUMLAH HARGA (BERDASARKAN HARI dari 17 MEI - 17 JULI) KET.
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

I PEKERJAAN PERSIAPAN
1 Mobilisasi
2 Mobilisasi 6.84 1.71 1.71 1.71 1.71
3 Excavator Mini

A PEKERJAAN GALIAN
1 Galian Biasa 2.54 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
2 Galian Perkerasan Beraspal dengan Cold Milling Machine 0.19 0.05 0.05 0.05 0.05
3 Galian Perkerasan berbutir 0.04 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
4 Penyiapan Badan Jalan 1.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03

B PEKERJAAN BETON
BAHU JALAN
Lapis Pondasi 0.46 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Perkerasan Beton 6.35 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 2.70 0.67 0.67 0.67 0.67
Bekisting 0.32 0.06 0.06 0.06 0.06 0.06
Bowhplank 0.53 0.18 0.18 0.18

C BADAN JALAN
Lapis Pondasi 0.29 0.07 0.07 0.07 0.07
Perkerasan Beton ( 12m x 100m x 0.3m ) 31.20 7.80 7.80 7.80 7.80
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 9.53 2.38 2.38 2.38 2.38
Bekisting 0.24 0.06 0.06 0.06 0.06
Bowhplank 0.53 0.13 0.13 0.13 0.13
DRAINASE
Perkerasan Beton 13.34 3.33 3.33 3.33 3.33
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 1.62 0.40 0.40 0.40 0.40
Bekisting 7.73 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86
Besi Beton 9.03 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Pipa Drainase 0.07 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Geotekstil 0.04 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Bowhplank 0.79 0.39 0.39

D POS PANTAU DAN POS SCURITY


Pos Pantau (Permanen ) 0.52 0.17 0.17 0.17
Pos Security (Semi Permanen) 1.56 0.26 0.26 0.26 0.26 0.26 0.26

E SAFETY EQUIPMENT
Rotary 0.11 0.05 0.05
Lampu Sorot 0.67 0.33 0.33
Instalasi Listrik 0.49 0.24 0.24
Instalasi Air / Penyiraman 0.65 0.33 0.33
Marka Jalan 0.39 0.20 0.20
Rambu Rambu 0.22 0.11 0.11

100.00
RENCANA KEMAJUAN PEKERJAAN 1.71 1.71 1.71 0.00 0.00 0.00 1.34 2.34 1.08 1.11 1.63 1.87 1.34 0.79 9.81 14.29 4.26 0.59 2.06 4.16 1.84 0.93 2.46 4.43 2.09 8.70 12.55 6.63 1.67
KUMULATIF RENCANA KEMAJUAN PEKERJAAN 1.71 3.42 5.13 5.13 5.13 5.13 6.47 8.81 9.89 11.00 12.63 14.50 15.84 16.62 26.43 40.73 44.99 45.58 47.63 51.79 53.63 54.56 57.02 61.45 63.54 72.24 84.79 91.41 93.08

19

84.79

72.24

63.54

61.45

57.02

54.56
53.63

51.79

47.63

45.58
44.99

40.73

26.43

16.62
15.84
14.50

12.63

11.00
9.89
8.81

6.47
5.13 5.13 5.13 5.13

3.42

1.71

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
JADWAL PELAKSANAAN PEKERJAAN ( KURVA " S " )

Kegiatan
Tahun Anggaran

W A K T U P E L A K S A N AAN
BOBOT
NO. URAIAN PEKERJAAN JUMLAH HARGA (BERDASARKAN HARI) KET.
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

I PEKERJAAN PERSIAPAN
1 Mobilisasi
2 Mobilisasi 6.84 3.42 3.42
3 Excavator Mini

A PEKERJAAN GALIAN
1 Galian Biasa 2.54 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
2 Galian Perkerasan Beraspal dengan Cold Milling Machine 0.19 0.05 0.05 0.05 0.05
3 Galian Perkerasan berbutir 0.04 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002
4 Penyiapan Badan Jalan 1.03 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06

B PEKERJAAN BETON
BAHU JALAN
Lapis Pondasi 0.46 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
Perkerasan Beton 6.35 1.59 1.59 1.59 1.59
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 2.70 0.67 0.67 0.67 0.67
Bekisting 0.32 0.06 0.06 0.06 0.06 0.06
Bowhplank 0.53 0.18 0.18 0.18

C BADAN JALAN
Lapis Pondasi 0.29 0.07 0.07 0.07 0.07
Perkerasan Beton ( 12m x 100m x 0.3m ) 31.20 7.80 7.80 7.80 7.80
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 9.53 2.38 2.38 2.38 2.38
Bekisting 0.24 0.06 0.06 0.06 0.06
Bowhplank 0.53 0.13 0.13 0.13 0.13
DRAINASE
Perkerasan Beton 13.34 3.33 3.33 3.33 3.33
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 1.62 0.40 0.40 0.40 0.40
Bekisting 7.73 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86
Besi Beton 9.03 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Pipa Drainase 0.07 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Geotekstil 0.04 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Bowhplank 0.79 0.39 0.39

D POS PANTAU DAN POS SCURITY


Pos Pantau (Permanen ) 0.52 0.17 0.17 0.17
Pos Security (Semi Permanen) 1.56 0.26 0.26 0.26 0.26 0.26 0.26

E SAFETY EQUIPMENT
Rotary 0.11 0.05 0.05
Lampu Sorot 0.67 0.33 0.33
Instalasi Listrik 0.49 0.24 0.24
Instalasi Air / Penyiraman 0.65 0.33 0.33
Marka Jalan 0.39 0.20 0.20
Rambu Rambu 0.22 0.11 0.11

100.00
RENCANA KEMAJUAN PEKERJAAN 3.42 3.42 0.00 0.00 0.00 0.00 1.41 2.42 1.16 1.21 1.74 1.97 1.44 0.92 9.94 14.40 5.16 0.72 2.19 4.26 2.73 1.06 2.60 4.46 2.91 8.75 12.61 6.63 2.46
KUMULATIF RENCANA KEMAJUAN PEKERJAAN 3.42 6.84 6.84 6.84 6.84 6.84 8.25 10.67 11.83 13.04 14.78 16.75 18.19 19.11 29.05 43.45 48.61 49.33 51.52 55.79 58.52 59.58 62.18 66.64 69.55 78.31 90.91 97.54 100.00

100.00
JADWAL PELAKSANAAN PEKERJAAN ( KURVA " S " )

Kegiatan
Tahun Anggaran

W A K T U P E L A K S A N AAN
BOBOT
(BERDASARKAN HARI dari 17 MEI - 15 JULI)
NO. URAIAN PEKERJAAN MEI JUNI JULI KET.
18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 99.74 60 100.00
98.81
97.88
96.96
96.03

I PEKERJAAN PERSIAPAN
1 Mobilisasi 91.66

2 Mobilisasi 6.84 1.71 1.71 1.71 1.71


3 Excavator Mini 86.91

A PEKERJAAN GALIAN 82.33


1 Galian Biasa 2.54 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 80.77
79.55
2 Galian Perkerasan Beraspal dengan Cold Milling Machine 0.19 0.05 0.05 0.05 0.05 79.39 79.52

3 Galian Perkerasan berbutir 0.04 0.007 0.007 0.007 0.007 0.007 76.79

4 Penyiapan Badan Jalan 1.03 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 74.19

B PEKERJAAN BETON 70.92

BAHU JALAN 69.06

67.18
Lapis Pondasi 0.46 0.12 0.12 0.12 0.12 66.48

Perkerasan Beton 6.35 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79
64.73

Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 2.70 0.45 0.45 0.45 0.45 0.45 0.45 61.85

Bekisting 0.32 0.08 0.08 0.08 0.08


Bowhplank 0.53 0.18 0.18 0.18
56.55

C BADAN JALAN
52.84
Lapis Pondasi 0.29 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Perkerasan Beton ( 12m x 100m x 0.3m ) 31.20 2.60 2.60 2.60 49.34 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60
48.50
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 9.53 1.19 1.19 1.19 1.19
47.67 1.19 1.19 1.19 1.19
Bekisting 0.24 0.03 0.03 0.03 45.650.03 0.03 0.03 0.03 0.03
Bowhplank 0.53 0.13 42.96 0.13 43.35 0.13 0.13
DRAINASE
Perkerasan Beton 13.34 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 39.79
0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67
Lapis Pondasi bawah Beton Kurus (Concrete Vibrator) 1.62 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20
36.26
Bekisting 7.73 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64
Besi Beton 9.03 1.13 1.13 1.13 1.13 32.72 1.13 1.13 1.13 1.13
Pipa Drainase 0.07 0.02 0.02 30.85 0.02 0.02
Geotekstil 0.04 0.01 0.01 27.96 28.20
28.68
29.16
0.01 0.01
27.84
Bowhplank 0.79 0.20 0.20 26.21
27.02
0.20 0.20
25.50
24.62

D POS PANTAU DAN POS SCURITY 22.94

Pos Pantau (Permanen ) 0.52 20.79


0.17 0.17 0.17
18.99
Pos Security (Semi Permanen) 1.56 18.12
18.79 18.79
0.26 0.26 0.26 0.26 0.26 0.26
17.45
16.79
16.12
20.75
E SAFETY EQUIPMENT 13.35 19.75 20.00 20.25
19.25 19.50
Rotary 0.11 0.05 0.05 18.55
19.00
11.12 18.11
Lampu Sorot 0.67 0.33
16.76
17.21
17.66
0.33
16.32
Instalasi Listrik 0.49 7.09 7.35
7.8015.87 0.24 0.24
6.84 15.25
Instalasi Air / Penyiraman 0.65 5.13 14.02
14.64
0.33 0.33
Marka Jalan 0.39 3.42 12.79
13.41
0.20 0.20
12.18
Rambu Rambu 0.2211.56
1.71 0.11 0.11

100.00
RENCANA KEMAJUAN PEKERJAAN 1.71 1.71 1.71 1.71 0.25 0.25 0.45 3.32 2.23 2.78 0.67 0.67 0.67 0.67 0.00 0.20 1.80 2.15 1.69 0.88 0.70 0.82 0.82 0.12 0.25 0.48 0.48 1.69 1.87 3.53 3.53 3.17 0.39 2.30 2.02 0.83 0.84 3.50 3.70 5.31 2.88 1.75 0.70 1.89 1.86 3.27 2.60 2.60 0.13 0.03 1.22 1.56 4.57 4.75 4.37 0.93 0.93 0.93 0.93 0.26
KUMULATIF RENCANA KEMAJUAN PEKERJAAN 1.71 3.42 5.13 6.84 7.09 7.35 7.80 11.12 13.35 16.12 16.79 17.45 18.12 18.79 18.79 18.99 20.79 22.94 24.62 25.50 26.21 27.02 27.84 27.96 28.20 28.68 29.16 30.85 32.72 36.26 39.79 42.96 43.35 45.65 47.67 48.50 49.34 52.84 56.55 61.85 64.73 66.48 67.18 69.06 70.92 74.19 76.79 79.39 79.52 79.55 80.77 82.33 86.91 91.66 96.03 96.96 97.88 98.81 99.74 100.00
REALISASI KEMAJUAN PEKERJAAN 9.50 10.50 11.56 12.18 12.79 13.41 14.02 14.64 15.25 15.87 16.32 16.76 17.21 17.66 18.11 18.55 19.00 19.25 19.50 19.75 20.00 20.25 20.75
DEVIASI 6.43 -0.25 -1.79 -7.09
4.31 0.62 3.13 0.45