Hari Ke- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
A ADMINISTRASI
1 PO LS 1
2 Kontrak LS 1
3 Kick Of Meeting LS 1
4 Construction Drawing LS 1
5 Serah Terima Lahan LS 1
B PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi LS 1 90,000,000 4 0.03 0.0075 0.01 0.01 0.01 0.01
2 Site Office untuk Kontraktor LS 1 10,000,000 1 0.00333 0.003333 0
3 Toilet sementara dilengkapi supplai air bersih untuk Personil Kontraktor LS 1 10,000,000 1 0.00333 0.003333 0
4 Supplai air bersih LS 1 1 0 0
5 Listrik kerja LS 1 1 0 0
6 Setting Out Titik Pancang (berdasarkan titik BM berikut koordinat batas lahan) LS 1 30,000,000 38 0.01 0.000263 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 Asuransi (Jamsostek) + Safety (helm, sepatu, rompi (seragam), obat-obatan) LS 1 15,000,000 4 0.005 0.00125 0 0 0 0
8 Shop & As Built Drawing (1 asli dan 2 copy, Hard copy uk.A3 & Soft copy/CD) LS 1 10,000,000 39 0.00333 8.55E-05 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
9 Asuransi Project (CAR / TPL dan termasuk resiko efek pekerjaan pemancangan) LS 1 30,000,000 1 0.01 0.01 0.01
10 Perijinan / koordinasi dengan lingkungan termasuk kuli bongkar LS 1 10,000,000 2 0.00333 0.001667 0 0
11 Pembuatan laporan dokumen dan tanda + tanda pekerjaan project LS 1 4,328,000 7 0.00144 0.000206 0 0 0 0 0 0 0
12 Rapid test untuk pekerja di lapangan LS 1 6,000,000 8 0.002 0.00025 0 0 0 0 0 0 0 0
1 Pekerjaan Pendahuluan .
a Pagar sementara tinggi 2.4 m ( material metal zink dan rangka kayu kaso ) M1 187 71,808,000 5 0.02394 0.004787 0 0 0 0 0
b Bongkar cansten dan mengumpulkan di area proyek dengan jarak max 100 m' M1 195 5,850,000 5 0.00195 0.00039 0 0 0 0 0
c Bongkar paving block, kumpulkan di area proyek dengan jarak max 100 m' M2 1,730 51,900,000 5 0.0173 0.00346 0 0 0 0 0
d Bobok beton lantai bak air (t = 20 cm), karena ada tiang pancang di titik tsb. Titik 1 180,000 5 0.00006 0.000012 ### ### ### ### ###
b Tiang Pancang Square 350mm x 350 mm x 12 m M1 2,544 549,504,000 10 0.18317 0.018317 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 `
b Tiang Pancang Square 350mm x 350 mm x 12 m M1 2,544 203,520,000 13 0.06784 0.005218 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
b Tiang Pancang Square 350mm x 350 mm x 12 m M' 2,544 25,440,000 10 0.00848 0.000848 0 0 0 0 0 0 0 0 0 0
5 PDA Test termasuk cap wap dan pemukulan tiang pancang Nos 6 27,000,000 2 0.009 0.0045 0 0
b Tiang Pancang Square 350mm x 350 mm x 12 m titik 212 12,720,000 13 0.00424 0.000326 0 0 0 0 0 0 0 0 0 0 0 0 0
RENCANA PROGRES PER-HARI 0.004 0 0.004 0.035 0.017 0.009 0.033 0.04 0 0.031 0.031 0.031 0.035 0.031 0.031 0 0.031 0.031 0.031 0.031 0.031 0.031 0 0.031 0.031 0.031 0.031 0.031 0.031 0 0.008 0.025 0.025 0.03 0.025 0.025 0 0.025 0.025 0.025 0.025 0.025 0.006 0.006 0.006 0.008 0.008
RENCANA PROGRES KUMULATIF 1 0.004 0.004 0.007 0.042 0.059 0.068 0.101 0.14 0.14 0.172 0.203 0.234 0.269 0.3 0.331 0.331 0.362 0.393 0.424 0.455 0.486 0.517 0.517 0.548 0.579 0.61 0.641 0.672 0.703 0.703 0.711 0.736 0.761 0.791 0.816 0.841 0.841 0.866 0.891 0.916 0.941 0.966 0.972 0.978 0.984 0.991 1
1.2
0.8
0.6
0.4
0.2
0
0 5 10 15 20 25 30 35 40 45 50
JADWAL PELAKSANAAN PEKERJAAN PEMANCANGAN
PROYEK COLD STORAGE TAHAP 2 - CIPENDAWA, BEKASI
A ADMINISTRASI
1 PO LS 1
2 Kontrak LS 1
3 Kick Of Meeting LS 1
4 Construction Drawing LS 1
5 Serah Terima Lahan LS 1
B PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi LS 1
2 Site Office untuk Kontraktor LS 1
3 Toilet sementara dilengkapi supplai air bersih untuk Personil Kontraktor LS 1
4 Supplai air bersih LS 1
5 Listrik kerja LS 1
6 Setting Out Titik Pancang (berdasarkan titik BM berikut koordinat batas lahan) LS 1
7 Asuransi (Jamsostek) + Safety (helm, sepatu, rompi (seragam), obat-obatan) LS 1
8 Shop & As Built Drawing (1 asli dan 2 copy, Hard copy uk.A3 & Soft copy/CD) LS 1
9 Asuransi Project (CAR / TPL dan termasuk resiko efek pekerjaan pemancangan) LS 1
10 Perijinan / koordinasi dengan lingkungan termasuk kuli bongkar LS 1
11 Pembuatan laporan dokumen dan tanda + tanda pekerjaan project LS 1
12 Rapid test untuk pekerja di lapangan LS 1
1 Pekerjaan Pendahuluan .
a Pagar sementara tinggi 2.4 m ( material metal zink dan rangka kayu kaso ) M1 187
b Bongkar cansten dan mengumpulkan di area proyek dengan jarak max 100 m' M1 195
c Bongkar paving block, kumpulkan di area proyek dengan jarak max 100 m' M2 1,730
-
d Bobok beton lantai bak air (t = 20 cm), karena ada tiang pancang di titik tsb. Titik 1
5 PDA Test termasuk cap wap dan pemukulan tiang pancang Nos 6