JADWAL PELAKSANAAN PEKERJAAN PEMANCANGAN

PROYEK COLD STORAGE TAHAP 2 - CIPENDAWA, BEKASI

Duras Bobo Bobot NOPEMBER 2020 DESEMBER 2020


No URAIAN PEKERJAAN Unit Qty Biaya i t (%) /hari
(%) 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Hari Ke- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

A ADMINISTRASI
1 PO LS 1
2 Kontrak LS 1
3 Kick Of Meeting LS 1
4 Construction Drawing LS 1
5 Serah Terima Lahan LS 1

B PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi LS 1 90,000,000 4 0.03 0.0075 0.01 0.01 0.01 0.01
2 Site Office untuk Kontraktor LS 1 10,000,000 1 0.00333 0.003333 0
3 Toilet sementara dilengkapi supplai air bersih untuk Personil Kontraktor LS 1 10,000,000 1 0.00333 0.003333 0
4 Supplai air bersih LS 1 1 0 0
5 Listrik kerja LS 1 1 0 0
6 Setting Out Titik Pancang (berdasarkan titik BM berikut koordinat batas lahan) LS 1 30,000,000 38 0.01 0.000263 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 Asuransi (Jamsostek) + Safety (helm, sepatu, rompi (seragam), obat-obatan) LS 1 15,000,000 4 0.005 0.00125 0 0 0 0
8 Shop & As Built Drawing (1 asli dan 2 copy, Hard copy uk.A3 & Soft copy/CD) LS 1 10,000,000 39 0.00333 8.55E-05 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
9 Asuransi Project (CAR / TPL dan termasuk resiko efek pekerjaan pemancangan) LS 1 30,000,000 1 0.01 0.01 0.01
10 Perijinan / koordinasi dengan lingkungan termasuk kuli bongkar LS 1 10,000,000 2 0.00333 0.001667 0 0
11 Pembuatan laporan dokumen dan tanda + tanda pekerjaan project LS 1 4,328,000 7 0.00144 0.000206 0 0 0 0 0 0 0
12 Rapid test untuk pekerja di lapangan LS 1 6,000,000 8 0.002 0.00025 0 0 0 0 0 0 0 0

C PEKERJAAN TIANG PANCANG

1 Pekerjaan Pendahuluan .
a Pagar sementara tinggi 2.4 m ( material metal zink dan rangka kayu kaso ) M1 187 71,808,000 5 0.02394 0.004787 0 0 0 0 0

b Bongkar cansten dan mengumpulkan di area proyek dengan jarak max 100 m' M1 195 5,850,000 5 0.00195 0.00039 0 0 0 0 0

c Bongkar paving block, kumpulkan di area proyek dengan jarak max 100 m' M2 1,730 51,900,000 5 0.0173 0.00346 0 0 0 0 0

d Bobok beton lantai bak air (t = 20 cm), karena ada tiang pancang di titik tsb. Titik 1 180,000 5 0.00006 0.000012 ### ### ### ### ###

2 Pekerjaan Pengadaan Tiang Pancang


a Tiang Pancang Square 400mm x 400 mm x 12 m M1 4,500 1,345,500,000 20 0.4485 0.022425 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02

b Tiang Pancang Square 350mm x 350 mm x 12 m M1 2,544 549,504,000 10 0.18317 0.018317 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 `

3 Pemancangan HSPD240, Berdasarkan Panjang Tiang Tertanam


a Tiang Pancang Square 400mm x 400 mm x 12 m M1 4,500 405,000,000 20 0.135 0.00675 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01

b Tiang Pancang Square 350mm x 350 mm x 12 m M1 2,544 203,520,000 13 0.06784 0.005218 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01

4 Handling Tiang Pancang di lokasi


a Tiang Pancang Square 400mm x 400 mm x 12 m M' 4,500 56,250,000 20 0.01875 0.000938 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

b Tiang Pancang Square 350mm x 350 mm x 12 m M' 2,544 25,440,000 10 0.00848 0.000848 0 0 0 0 0 0 0 0 0 0

5 PDA Test termasuk cap wap dan pemukulan tiang pancang Nos 6 27,000,000 2 0.009 0.0045 0 0

6 Pemotongan tiang pancang


a Tiang Pancang Square 400mm x 400 mm x 12 m titik 375 30,000,000 20 0.01 0.0005 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

b Tiang Pancang Square 350mm x 350 mm x 12 m titik 212 12,720,000 13 0.00424 0.000326 0 0 0 0 0 0 0 0 0 0 0 0 0

RENCANA PROGRES PER-HARI 0.004 0 0.004 0.035 0.017 0.009 0.033 0.04 0 0.031 0.031 0.031 0.035 0.031 0.031 0 0.031 0.031 0.031 0.031 0.031 0.031 0 0.031 0.031 0.031 0.031 0.031 0.031 0 0.008 0.025 0.025 0.03 0.025 0.025 0 0.025 0.025 0.025 0.025 0.025 0.006 0.006 0.006 0.008 0.008

RENCANA PROGRES KUMULATIF 1 0.004 0.004 0.007 0.042 0.059 0.068 0.101 0.14 0.14 0.172 0.203 0.234 0.269 0.3 0.331 0.331 0.362 0.393 0.424 0.455 0.486 0.517 0.517 0.548 0.579 0.61 0.641 0.672 0.703 0.703 0.711 0.736 0.761 0.791 0.816 0.841 0.841 0.866 0.891 0.916 0.941 0.966 0.972 0.978 0.984 0.991 1

REALISASI PROGRES PER-HARI


REALISASI PROGRES KUMULATIF
total harga 3,000,000,000
Disetujui Oleh, Diketahui Oleh, Dibuat Oleh,
PT. MULIA BOSCO UTAMA PT. INTISWISS CONSULINDO PT. MASTERPANCANG PONDASI

Ir. Danny Kurniawan


Construction Manager
KET.

1.2

0.8

0.6

0.4

0.2

0
0 5 10 15 20 25 30 35 40 45 50
JADWAL PELAKSANAAN PEKERJAAN PEMANCANGAN
PROYEK COLD STORAGE TAHAP 2 - CIPENDAWA, BEKASI

Bobot NOPEMBER 2020 DESEMBER 2020


No URAIAN PEKERJAAN Unit Qty (%) 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 KET.
Hari Ke- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45

A ADMINISTRASI
1 PO LS 1
2 Kontrak LS 1
3 Kick Of Meeting LS 1
4 Construction Drawing LS 1
5 Serah Terima Lahan LS 1

B PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi LS 1
2 Site Office untuk Kontraktor LS 1
3 Toilet sementara dilengkapi supplai air bersih untuk Personil Kontraktor LS 1
4 Supplai air bersih LS 1
5 Listrik kerja LS 1
6 Setting Out Titik Pancang (berdasarkan titik BM berikut koordinat batas lahan) LS 1
7 Asuransi (Jamsostek) + Safety (helm, sepatu, rompi (seragam), obat-obatan) LS 1
8 Shop & As Built Drawing (1 asli dan 2 copy, Hard copy uk.A3 & Soft copy/CD) LS 1
9 Asuransi Project (CAR / TPL dan termasuk resiko efek pekerjaan pemancangan) LS 1
10 Perijinan / koordinasi dengan lingkungan termasuk kuli bongkar LS 1
11 Pembuatan laporan dokumen dan tanda + tanda pekerjaan project LS 1
12 Rapid test untuk pekerja di lapangan LS 1

C PEKERJAAN TIANG PANCANG

1 Pekerjaan Pendahuluan .
a Pagar sementara tinggi 2.4 m ( material metal zink dan rangka kayu kaso ) M1 187
b Bongkar cansten dan mengumpulkan di area proyek dengan jarak max 100 m' M1 195
c Bongkar paving block, kumpulkan di area proyek dengan jarak max 100 m' M2 1,730
-
d Bobok beton lantai bak air (t = 20 cm), karena ada tiang pancang di titik tsb. Titik 1

2 Pekerjaan Pengadaan Tiang Pancang


a Tiang Pancang Square 400mm x 400 mm x 12 m M1 4,500
`
b Tiang Pancang Square 350mm x 350 mm x 12 m M1 2,544

3 Pemancangan HSPD240, Berdasarkan Panjang Tiang Tertanam


a Tiang Pancang Square 400mm x 400 mm x 12 m M1 4,500
b Tiang Pancang Square 350mm x 350 mm x 12 m M1 2,544

4 Handling Tiang Pancang di lokasi


a Tiang Pancang Square 400mm x 400 mm x 12 m M' 4,500
b Tiang Pancang Square 350mm x 350 mm x 12 m M' 2,544

5 PDA Test termasuk cap wap dan pemukulan tiang pancang Nos 6

6 Pemotongan tiang pancang


a Tiang Pancang Square 400mm x 400 mm x 12 m titik 375
b Tiang Pancang Square 350mm x 350 mm x 12 m titik 212

RENCANA PROGRES PER-HARI


RENCANA PROGRES KUMULATIF
REALISASI PROGRES PER-HARI
REALISASI PROGRES KUMULATIF

Disetujui Oleh, Diketahui Oleh, Dibuat Oleh,


PT. MULIA BOSCO UTAMA PT. INTISWISS CONSULINDO PT. MASTERPANCANG PONDASI

Ir. Danny Kurniawan


Construction Manager