7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 2
I PEKERJAAN PERSIAPAN
II PEKERJAAN SMKK
1 Penyelenggaraan SMK3 Ls 38,951,000.00 0.463 35.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.423
1 Lantai Kerja K-100 m3 47,701,360.00 0.567 3.00 0.19 0.19 0.19 0.567
2 Pembuatan tetrapod beton readymix K-400 unit 5,124,560,940.00 60.939 18.00 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 3.39 60.939
3 Pembesian kg 2,149,421,312.88 25.560 18.00 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 25.560
4 Pemasangan tetrapod unit 405,917,010.00 4.827 8.00 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 4.827
5 Pemasangan batu kosong m3 484,263,810.00 5.759 6.00 0.96 0.96 0.96 0.96 0.96 0.96 5.759
8,409,365,432.88 100.00
PROGRESS 0.01 0.01 0.01 0.52 0.20 1.62 4.82 5.78 5.78 5.78 5.78 5.78 5.78 4.82 4.82 4.82 4.82 4.82 4.82 4.82 5.42 5.42 5.42 4.00 0.62 0.62 0.62 0.62 0.64 0.64 0.33 0.01 0.01 0.01 0.01
KUMULATIF PROGRESS 0.01 0.03 0.04 0.56 0.76 2.39 7.20 12.98 18.76 24.54 30.32 36.10 41.87 46.69 51.51 56.33 61.15 65.97 70.79 75.61 81.03 86.45 91.87 95.87 96.49 97.11 97.72 98.34 98.98 99.62 99.95 99.96 99.97 99.99 100.00