JANGKA WAKTU PELAKSANAAN 240 (dua ratus empat puluh) HARI KALENDER
JUMLAHHARGA BOBOT
NO. URAIAN PEKERJAAN BULAN I BULAN II BULAN III BULAN IV BULAN V BULAN VI BULAN VII BULAN VIII KETERANGAN
(Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A. PEKERJAAN PERSIAPAN
100
1 Mobilisasi/demobilisasi personil dan alat berat 50,656,000.00 2.38 0.594 0.594 0.594 0.594
2 Pekerjaan Dewattering 51,999,472.26 2.44 0.610 0.610 0.610 0.610
80
B.2.3 PENGETESAN PIPA
1 Pipa GI Ø 10" 33,425,159.97 1.57 0.522 0.522 0.522
50
D PEKERJAAN REHABILITASI PIPA DI KALI 9 (PEMBUATAN
PENYANGGA PIPA)
0
JUMLAH 2,132,797,444.81 100.00
RENCANA PROGRES FISIK 0.59 1.33 3.40 2.75 3.17 0.95 1.28 1.71 1.31 0.49 1.43 1.26 1.26 3.53 3.58 3.58 6.45 6.45 5.68 5.68 5.68 5.68 5.68 5.68 5.68 2.58 2.58 2.58 2.58 3.11 1.12 1.12
KOMULATIF RENCANA PROGRES FISIK 0.59 1.92 5.32 8.07 11.24 12.19 13.47 15.18 16.50 16.99 18.42 19.68 20.94 24.47 28.05 31.63 38.09 44.54 50.22 55.91 61.59 67.28 72.96 78.64 84.33 86.91 89.50 92.08 94.66 97.77 98.88 100.00
2,132,797,444.81
0.00