REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)

Kegiatan : Pembangunan Rumah Tinggal


Lokasi : Kab Gowa

NO. URAIAN PEKERJAAN JUMLAH (RP)

I PEKERJAAN PERSIAPAN 1,500,000


II PEK TANAH & PONDASI 3,743,159
III PEK. BATU & DINDING 45,001,623
IV PEKERJAAN BETON 11,054,130
V PEK. KUSEN PINTU & JENDELA 29,170,330
VI PEK. ATAP DAN PLAFOND 23,392,841
VII PEK. INSTALASI LISTRIK 1,772,280
VIII PEK. SANITASI 4,700,904
IX PEK. PENGECETAN 15,523,772
X PEK. PEMBERSIHAN 1,000,000
REAL COST 136,859,038
IMB 3,421,476
TOTAL 140,280,514
DIBULATKAN 155,180,000
Terbilang : SERATUS LIMA PULUH LIMA JUTA SERATUS DELAPAN PULUH RIBU RUPIAH
keliling 100.5 116.5
tinggi 3.5
Galaian 205.04 pintu 0.65 2.6
JENDELA 2 0.9 4.8
JENDELA 1 0.3 LUAS 17.92
batu kos 23.3 pintu jendela 1.2 1.8
urugps 5.825 luas 109 3
urus tan 106.015 luAS TER 20
batu kali 69.9 LUAS KM 11 2
LUAS PLAFOND 180 3
KUSEN PINTU 11.05 RANGKA PL 43.2 27.98
PLESTERAN 625.54 93.831
PLESTERAN TARA 22 351.75 323.77
0.0015 625.54 647.54
0.006
2.25 1.6 8
1.125 2.88 21.5
72 0.0225 0.07875
0.0225 1.62 2.62125 2.52
0.04 0.96

kl den 47 50 57.5 101.2 34.5 23


kl dinding 50 7.5 0.03
luas 75 104.5 2.25
195 1,8 0.9

jendela 1 0.0339 1.8 4 7.2 0.1356


jendela 2 0.266 0.9 7 6.3 1.862
jendela k 0.0196 0.9 1 0.9 0.0196
jendela K depan 0.0196 1.8 1 1.8 0.0196
Pintu Depan 0.0539 2.25 2 4.5 0.1078
Pintu jendela 0.2891 2.25 2 4.5 0.5782
Pintu 1 0.2695 2.25 3 6.75 0.8085
0.9516 31.95 3.5313

300 268.05
1.6 536.1
11.2 0.072
1.17 21.5
1.548
0.48375

2.5
0

0
0.0196
RENCANA ANGGARAN BIAYA ( RAB)

Kegiatan : Pembangunan Rumah Tinggal


Lokasi : Kab Gowa

HARGA JUMLAH
NO URAIAN PEKERJAAN VOL. SAT SATUAN HARGA
( RP ) ( RP )

I PEKERJAAN PERSIAPAN
1 Pengukuran / Pembersihan Lokasi 1 ls 1500000 1500000
Sub Total I 1,500,000

II PEK TANAH & PONDASI


1 Galian Tanah Pondasi 101.2 M3 18,250 1,846,900
2 Urugan Tanah 23 M3 55,300 1,271,900
3 Lapisan Pasir Bawah Lantai 7.5 M3 61,900 464,250
4 Urugan Pasir Bawah Pondasi 2.875 M3 55,690 160,109
Sub Total II 3,743,159

III PEK. BATU & DINDING


1 Pasangan Batu Kosong 11.5 M3 88,650 1,019,475
2 Pasangan Batu Gunung 1 : 4 34.5 M3 289,600 9,991,200
3 Pek. Lap. Batu Merah Bawah Lantai 1 : 2 2.25 M3 157,550 354,488
4 Pek. Tembok Transram 1 : 2 3.3 M3 195,420 644,886
5 Pek. Dinding Tembok 1 : 4 265.65 M3 71,811 19,076,571
6 Pek. Plesteran Transram 1 : 2 22 M2 12,100 266,200
7 Pek. Pelasteran Tembok 1 : 4 536.1 M2 14,386 7,712,335
8 Pek. Acian Dinding Tembok 536.1 M2 1,427 764,800
9 Pek. Lantai Keramik 40 x 40 75 M2 55,171 4,137,788
11 Pek. Lantai Keramik 20 x 20 (KM) 6 M2 53,171 319,023
12 Pek. Dinding KM / WC Keramik 20 x 20 10 M2 53,171 531,705
13 Pek. Tegel Plint Keramik 40 x 10 (Teras) 7.5 M2 24,421 183,154
Sub Total III 45,001,623

IV PEKERJAAN BETON
1 Pek. Kolom Beton 20/20 0.96 M3 2,176,410 2,089,354
3 Pek. Kolom Praktis 15/15 1.62 M3 1,794,750 2,907,495
4 Pek. Ringball Beton 15/15 2.25 M3 1,794,750 4,038,188
5 Pek. Sloef Beton 15/15 1.125 M3 1,794,750 2,019,094
6 Pek. Kuda-kuda Beton 0.96 M3 2,176,410 2,089,354
Sub Total IV 11,054,130
HARGA JUMLAH
NO URAIAN PEKERJAAN VOL. SAT SATUAN HARGA
( RP ) ( RP )
V PEK. KUSEN PINTU & JENDELA
1 Pek. Kosen Pintu & Jendela Kls I 3.5313 M3 5,531,500 19,533,386
2 Pek. Daun Pintu Panil Kls I 11.2 M2 377,500 4,228,000
3 Pek. Daun Jendela Kaca 17.92 M2 201950 3,618,944
4 Pek. Kunci 2 x Putar & Upah Pasang 5 BH 40000 200,000
5 Pek. Engsel Pintu (Kuningan) & Upah Kerja 15 BH 34000 510,000
6 Pek. Engsel Jendela (Kuningan) & Upah Kerja 26 BH 25000 650,000
8 Pek. Gerendel Tanam Pintu & Upah Kerja 5 BH 27500 137,500
9 Pek. Gerendel Tanam Jendela & Upah Kerja 13 BH 22500 292,500
Sub Total V 29,170,330

VI PEK. ATAP DAN PLAFOND


1 Pek. Kuda-Kuda Kls II 6/12 0.44 M3 1,754,500 771,980
2 Pek. Goording Kls II 6/121 0.63 M3 1,635,000 1,030,050
3 Pek Atap Genteng Metal 195 M2 63,775 12,436,125
4 Pek. Nok 11 M2 30,988 340,864
5 Pek Listplank Kls I 1.17 M2 75,350 88,160
6 Pek. Plafond Eternit 100 x 100 + Rangka 104.5 M2 31,325 3,273,463
7 Pek. List Plafond 116.5 M' 46,800 5,452,200
8 Pek Lantai kayu 75 M2 377,500 28,312,500
Sub Total VI 23,392,841
VII PEK. INSTALASI LISTRIK
1 Pek. Titik Cahaya & Upah 16 Titik 31,080.00 497,280
2 Pek. Stop Kontak 16 BH 2500 40000
3 Pek. Sekring Kas & Upah 2 BH 32500 65000
4 Pek. Saklar Ganda & Upah 4 BH 27500 110000
5 Pek. Saklar Tunggal & Upah 8 BH 5000 40000
6 Pek. Saklar Seri Tiga & Upah 2 BH 25000 50000
7 Pek. Lampu SL 40 Watt & Upah 9 BH 65000 585000
8 Pek. Lampu SL 18 Watt & Upah 7 BH 55000 385000
Sub Total VII 1,772,280

VIII PEK. SANITASI


1 Pek. Kloset duduk 1 BH 145,040.00 145,040
2 Pek Kran Air 3/4 " 4 BH 10,000 40,000
4 Pek. Pipa PVC Dia. 3" 50 M' 40000 2,000,000
5 Pek. Pipa PVC Dia. 3/4" 50 M' 17500 875,000
6 Pek. Septic Tank 1 BH 1,640,863.84 1,640,864
Sub Total VIII 4,700,904

IX PEK. PENGECETAN
1 Pengecatan Tembok / Plafond 536.1 M2 27,930 14,973,273
2 Pengecatan Kayu 31.95 M2 17,230 550,499
Sub Total IX 15,523,772

XI PEK. PEMBERSIHAN
1 Pek. Pembersihan 1 ls 1000000 1,000,000
Sub Total X 1,000,000
558.1

56,055,753
20000

55555
20000

25000
DAFTAR ANALISA

1. 1 M3 GALIAN TANAH PONDASI


0.75 Pekerja @ Rp. 23000 Rp. 17250
0.025 Mandor @ Rp. 40000 Rp. 1000
Rp. 18,250.00

2. 1 M3 URUGAN TANAH
1.2 Tanah @ Rp. 40000 Rp. 48000
0.3 Pekerja @ Rp. 23000 Rp. 6900
0.01 Mandor @ Rp. 40000 Rp. 400
Rp. 55,300.00

3. 1 M3 LAPISAN PASIR BAWAH LANTAI


1.2 Pasir @ Rp. 45500 Rp. 54600
0.3 Pekerja @ Rp. 23000 Rp. 6900
0.01 Mandor @ Rp. 40000 Rp. 400
Rp. 61,900.00

1 M3 URUGAN PASIR BAWAH PONDASI


1.200 Pasir @ Rp. 45500 Rp. 54600
0.030 Pekerja @ Rp. 23000 Rp. 690
0.010 Mandor @ Rp. 40000 Rp. 400
Rp. 55,690.00
4. 1 M3 PASANGAN BATU KOSONG
1.1 M3 Batu Gunung @ Rp. 75000 Rp. 82500
0.25 Pekerja @ Rp. 23000 Rp. 5750
0.01 Mandor @ Rp. 40000 Rp. 400
Rp. 88,650.00

5. 1 M3 PAS. BATU GUNUNG 1 : 4


1 M3 Batu Gunung @ Rp. 75000 Rp. 75,000
2.25 Sak Semen PC @ Rp. 27000 Rp. 60,750
0.45 M3 Pasir pasangan @ Rp. 40000 Rp. 18,000
1 Tukang Batu @ Rp. 30000 Rp. 30,000
0.95 Kepala Tukang Batu @ Rp. 45000 Rp. 42,750
2.5 Pekerja @ Rp. 23000 Rp. 57,500
0.14 Mandor @ Rp. 40000 Rp. 5,600
Rp. 289,600.00
1 M3 PEK. LAPISAN BATU MERAH BAWAH LANTAI 1 : 2
90.000 BIJI Batu Bata @ Rp. 300 Rp. 27000
0.0210 Zak Semen PC @ Rp. 27000 Rp. 567
0.0387 M3 Pasir Pasangan @ Rp. 40000 Rp. 1548
0.0400 Tukang Batu @ Rp. 30000 Rp. 1200
0.0500 Kep.Tukang Batu @ Rp. 45000 Rp. 2250
0.7200 Pekerja @ Rp. 23000 Rp. 16560
0.0650 Mandor @ Rp. 40000 Rp. 2600
Rp. 51,725.00
6. 1 M3 PEK. TEMBOK TRANSRAM 1 : 2 ..
450.00 Bj Batu bata @ Rp. 300 Rp. 135000
1.50 Sak Semen @ Rp. 27000 Rp. 40500
0.33 M3 Pasir pasangan @ Rp. 40000 Rp. 13200
0.05 Tukang Batu @ Rp. 30000 Rp. 1500
0.01 Kepala Tukang Batu @ Rp. 45000 Rp. 450
0.15 Pekerja @ Rp. 23000 Rp. 3450
0.03 Mandor @ Rp. 40000 Rp. 1320
Rp. 195,420.00

7. 1 M2 PEK. DINDING TEMBOK 1 : 4


65 Bj Batu bata @ Rp. 300 Rp. 19500
1.5 Sak Semen @ Rp. 27000 Rp. 40500
0.25 M3 Pasir pasangan @ Rp. 40000 Rp. 10000
1.5 Tukang Batu @ Rp. 30000 Rp. 45000
0.15 Kepala Tukang Batu @ Rp. 45000 Rp. 6750
4.2 Pekerja @ Rp. 23000 Rp. 96600
0.23 Mandor @ Rp. 40000 Rp. 9200
Rp. 227,550.00
22,755.00
8. 1 M2 PEK. PLESTERAN TRASRAM 1 : 4
0.1000 Sak Semen @ Rp. 27000 Rp. 2700
0.0200 M3 Pasir Pasangan @ Rp. 40000 Rp. 800
0.0150 Tukang Batu @ Rp. 30000 Rp. 450
0.0100 Kepala Tukang Batu @ Rp. 45000 Rp. 450
0.3000 Pekerja @ Rp. 23000 Rp. 6900
0.0200 Mandor @ Rp. 40000 Rp. 800
Rp. 12,100.00

9. 1 M2 PEK. PLESTERAN TEMBOK 1 : 5


0.1080 Sak Semen @ Rp. 27000 Rp. 2916
0.0130 M3 Pasir Pasangan @ Rp. 40000 Rp. 520
0.1000 Tukang Batu @ Rp. 30000 Rp. 3000
0.0100 Kepala Tukang Batu @ Rp. 45000 Rp. 450
0.3000 Pekerja @ Rp. 23000 Rp. 6900
0.0150 Mandor @ Rp. 40000 Rp. 600
Rp. 14,386.00
10 M2 PEK. ACIAN DINDING TEMBOK
0.1080 Sak Semen @ Rp. 27000 Rp. 2916
0.0100 Kg Kapur Pasangan @ Rp. 40000 Rp. 400
0.1000 Tukang Batu @ Rp. 30000 Rp. 3000
0.0100 Kepala Tukang Batu @ Rp. 45000 Rp. 450
0.3000 Pekerja @ Rp. 23000 Rp. 6900
0.0150 Mandor @ Rp. 40000 Rp. 600
Rp. 14,266.00
10 M 1,426.60

10. 1 M3 BETON RABAT 1 : 3 : 5


0.9 M3 Kerikil @ Rp. 120000 Rp. 108000
4.54 Sak Semen @ Rp. 27000 Rp. 122580
0.54 M3 Pasir Beton @ Rp. 40000 Rp. 21600
0.5 Tukang Batu @ Rp. 30000 Rp. 15000
0.05 Kepala Tukang Batu @ Rp. 45000 Rp. 2250
5 Pekerja @ Rp. 23000 Rp. 115000
0.3 Mandor @ Rp. 40000 Rp. 12000
Rp. 396,430.00
G.69 1 M2 PEREKAT
0.020 Sak Semen @ Rp. 27,000.00 Rp. 540.00
0.032 M3 Pasir pasangan @ Rp. 40,000.00 Rp. 1,280.00
Rp. 1,820.00

1 M2 PASANGAN TEGEL KERAMIK, PORSELIN


A. Perekat + Upah
0.025 M3 Perekat G.69 @ Rp. 1,820.00 Rp. 45.50
0.500 hr Pekerja @ Rp. 27,000.00 Rp. 13,500.00
0.025 hr Mandor @ Rp. 40,000.00 Rp. 1,000.00
0.250 hr Tukang Batu @ Rp. 30,000.00 Rp. 7,500.00
0.025 hr Kepala Tukang @ Rp. 45,000.00 Rp. 1,125.00
Rp. 23,170.50
Bahan 0.00
a. 1.000 dos Tegel Keramik 40/40 @ Rp. 32,000 Rp. 32,000.00
1M2 Pas. Keramik Lantai Rp. 55,170.50
b. 1.000 dos Tegel Keramik 20/20 @ Rp. 30,000 Rp. 30,000.00
1M2 Pas. Keramik Lantai A+ b Rp. 53,170.50
1.000 Bh Tegel Plint Keramik 40/10 @ Rp. 1,250 Rp. 1,250.00
Rp. 24,420.50
1 M3 BETON BERTULANG

A. BAHAN BETON (G.14)


0.820 M3 Batu Pecah 2 - 3 @ Rp. 120,000.00 Rp. 98,400.00
0.540 M3 Pasir Beton @ Rp. 40,000.00 Rp. 21,600.00
6.800 Zak Semen PC @ Rp. 27,000.00 Rp. 183,600.00
Upah
6.000 hr Pekerja @ Rp. 23,000.00 Rp. 138,000.00
0.300 hr Mandor @ Rp. 40,000.00 Rp. 12,000.00
1.000 hr Tukang Batu @ Rp. 30,000.00 Rp. 30,000.00
0.100 hr Kepala Tukang Batu @ Rp. 45,000.00 Rp. 4,500.00
A..................... Rp. 488,100.00

B. 100 Kg BAHAN PEMBESIAN


Bahan :
100.000 Kg. Besi Beton @ Rp. 8,500.00 Rp. 850,000.00
2.000 Kg. Kawat Beton @ Rp. 8,000.00 Rp. 16,000.00
Upah
2.250 hr Kepala Tukang @ Rp. 45,000.00 Rp. 101,250.00
6.750 hr Tukang Besi @ Rp. 30,000.00 Rp. 202,500.00
6.750 hr Pekerja @ Rp. 23,000.00 Rp. 155,250.00
B............................. Rp. 1,325,000.00
Untuk 1 Kg Rp. 13,250.00
0.50
C. 10 M2 PEMBUATAN CETAKAN
Bahan :
4.000 Kg. Paku Campuran @ Rp. 7,500.00 Rp. 30,000.00
0.400 M3 Balok / Papan Kls III @ Rp. 1,300,000.00 Rp. 520,000.00
Upah
0.500 hr Kepala Tukang @ Rp. 45,000.00 Rp. 22,500.00
5.000 hr Tukang @ Rp. 30,000.00 Rp. 150,000.00
0.100 hr Mandor @ Rp. 40,000.00 Rp. 4,000.00
2.000 hr Pekerja @ Rp. 23,000.00 Rp. 46,000.00
4.000 hr Bongkaran / Siram @ Rp. 23,000.00 Rp. 92,000.00
c............................. Rp. 314,500.00
Untuk 1 m2 Rp. 31,450.00
1 M3 Kolom Beton 25/40

1.100 M3 Adukan Beton 1:2:3 @ Rp. 488,100.00 Rp. 536,910.00


100.000 Kg Pek. Besi @ Rp. 13,250.00 Rp. 1,325,000.00
10.000 M2 Cetakan Beton,Bongkar Siram @ Rp. 31,450.00 Rp. 314,500.00
Rp. 2,176,410.00

1 M3 Beton Bertulang Praktis ( Besi 100 KG/M3 )

1.000 M3 Adukan Beton 1:2:3 @ Rp. 155,250.00 Rp. 155,250.00


100.000 Kg Pek. Besi @ Rp. 13,250.00 Rp. 1,325,000.00
10.000 M2 Cetakan Beton,Bongkar Siram @ Rp. 31,450.00 Rp. 314,500.00
Rp. 1,794,750.00

1 M2 PELESTERAN PLAT T = 12 cm
0.364 zak Semen @ Rp. 27,000.00 Rp. 9,828.00
0.044 Pasir @ Rp. 40,000.00 Rp. 1,760.00
0.014 Kep. Tukang @ Rp. 45,000.00 Rp. 607.50
0.720 Pekerja @ Rp. 23,000.00 Rp. 16,560.00
0.036 Mandor @ Rp. 40,000.00 Rp. 1,440.00
Rp. 30,195.50
Rp.

1 M3 Beton Bertulang Pelat Lantai ( Besi 110 KG/M3 )

1.000 M3 Adukan Beton 1:2:3 @ Rp. 155,250.00 Rp. 155,250.00


110.000 Kg Pek. Besi @ Rp. 13,250.00 Rp. 1,457,500.00
10.000 M2 Cetakan Beton,Bongkar Siram @ Rp. 31,450.00 Rp. 314,500.00

Rp. 1,927,250.00

1 M3 Beton Bertulang Poer ( Besi 125 KG/M3 )


1.000 M3 Adukan Beton 1:2:3 @ Rp. 155,250.00 Rp. 155,250.00
125.000 Kg Pek. Besi @ Rp. 13,250.00 Rp. 1,656,250.00
10.000 M2 Cetakan Beton,Bongkar Siram @ Rp. 155,250.00 Rp. 1,552,500.00
Rp. 3,364,000.00

1 M3 Beton Bertulang Sloef ( Besi 110 KG/M3 )


1.000 M3 Adukan Beton 1:2:3 @ Rp. 155,250.00 Rp. 155,250.00
100.000 Kg Pek. Besi @ Rp. 13,250.00 Rp. 1,325,000.00
10.000 M2 Cetakan Beton,Bongkar Siram @ Rp. 155,250.00 Rp. 1,552,500.00
Rp. 3,032,750.00

1 M3 BETON RABAT 1 : 3 : 5
0.82 M3 Batu split @ Rp. 120,000.00 Rp. 98,400.00
0.52 M3 Pasir beton @ Rp. 40,000.00 Rp. 20,800.00
3.50 Sak Semen PC @ Rp. 27,000.00 Rp. 94,500.00
1.00 Tukang @ Rp. 30,000.00 Rp. 30,000.00
0.10 Kepala Tukang @ Rp. 45,000.00 Rp. 4,500.00
2.50 Pekerja @ Rp. 23,000.00 Rp. 57,500.00
0.25 Mandor @ Rp. 40,000.00 Rp. 10,000.00
Rp. 102,000.00
19. 1 M3 PEK. KOSEN PINTU & JENDELA
1.1 M3 Kayu kls I @ Rp. 4000000 Rp. 4400000
27 Tukang Kayu @ Rp. 30000 Rp. 810000
2.7 Kepala Tukang Kayu @ Rp. 45000 Rp. 121500
8 Pekerja @ Rp. 23000 Rp. 184000
0.4 Mandor @ Rp. 40000 Rp. 16000
Rp. 5,531,500.00

20. 1 M2 PEK. DAUN PINTU PANIL KLS I


0.035 M3 Papan kls I @ Rp. 4500000 Rp. 157500
5 Tukang Kayu @ Rp. 30000 Rp. 150000
0.5 Kepala Tukang Kayu @ Rp. 45000 Rp. 22500
1.9 Pekerja @ Rp. 23000 Rp. 43700
0.095 Mandor @ Rp. 40000 Rp. 3800
Rp. 377,500.00

21. 1 M2 PEK. DAUN JENDELA KACA


0.032 M3 Kayu Kelas I @ Rp. 4000000 Rp. 128000
0.3 Tukang Kayu @ Rp. 30000 Rp. 9000
0.25 Kepala Tukang Kayu @ Rp. 45000 Rp. 11250
1.9 Pekerja @ Rp. 23000 Rp. 43700
0.25 Mandor @ Rp. 40000 Rp. 10000
Rp. 201,950.00

1 M2 PEK. PAS. KACA MATI 5 mm


1.0000 M2 Kaca Polos 5 mm @ Rp. 65000 Rp. 65000
0.0016 M' List Kayu @ Rp. 10000 Rp. 16
0.5000 Tukang Kayu 45000 Rp. 22500
0.0500 Kep.Tukang Kayu 23000 Rp. 1150
0.1000 Pekerja 40000 Rp. 4000
Rp. 92,666.00
22. 1 M3 PEK. KAYU KUDA-KUDA 8/16

Bahan :
1.05 M3 Kayu kls II @ Rp. 1300000 Rp. 1,365,000
8 Tukang Kayu @ Rp. 30000 Rp. 240,000
1.1 Kepala Tukang Kayu @ Rp. 45000 Rp. 49,500
4 Pekerja @ Rp. 23000 Rp. 92,000
0.2 Mandor @ Rp. 40000 Rp. 8,000
Rp. 1,754,500

23. 1 M3 PEK. GORDING KAYU KLS II 8/12

Bahan :
1 M3 Kayu kls II @ Rp. 1300000 Rp. 1,300,000
8 Tukang Kayu @ Rp. 30000 Rp. 240,000
1 Kepala Tukang Kayu @ Rp. 45000 Rp. 45,000
2 Pekerja @ Rp. 23000 Rp. 46,000
0.1 Mandor @ Rp. 40000 Rp. 4,000
Rp. 1,635,000

1 M2 PEK. KASO + RENG KAYU KLS II


0.01 M3 Kayu kls II @ Rp. 1300000 Rp. 13000
0.15 Paku Kaso @ Rp. 7500 Rp. 1125
0.1 Paku Reng @ Rp. 7500 Rp. 750
0.1 Tukang Kayu @ Rp. 30000 Rp. 3000
0.01 Kepala Tukang Kayu @ Rp. 45000 Rp. 450
0.1 Pekerja @ Rp. 23000 Rp. 2300
0.005 Mandor @ Rp. 40000 Rp. 200
Total Rp. 20,825

1 M2 PEK. ATAP GENTENG


20 Psg Genteng @ Rp. 2500 Rp. 50000
0.15 Tukang Batu @ Rp. 30000 Rp. 4500
0.015 Kepala Tukang Batu @ Rp. 45000 Rp. 675
0.2 Pekerja @ Rp. 23000 Rp. 4600
0.1 Mandor @ Rp. 40000 Rp. 4000
Total Rp. 63,775

1m3 Perekat
0.36 m3 Semen @ Rp. 27000 Rp. 9720
1.08 m3 Pasir @ Rp. 40000 Rp. 43200
Rp. 52,920

1 M2 PEK. NOK MULTIROOF


5 Bh Bumbungan Atap @ Rp. 2500 Rp. 12500
0.03 m3 perekat @ Rp. 52,920 Rp. 1587.6
0.2 Tukang Kayu @ Rp. 30000 Rp. 6000
0.02 Kepala Tukang Kayu @ Rp. 45000 Rp. 900
0.4 Pekerja @ Rp. 23000 Rp. 9200
0.02 Mandor @ Rp. 40000 Rp. 800
Total Rp. 30,988
24. 1 M2 PEK. LIS PLANK KAYU KLS I

Bahan :
0.02 M3 Papan kelas II @ Rp. 2000000 Rp. 40000
0.1 Kg Paku @ Rp. 7500 Rp. 750
0.8 Tukang Kayu @ Rp. 30000 Rp. 24000
0.08 Kepala Tukang Kayu @ Rp. 45000 Rp. 3600
0.28 Pekerja @ Rp. 23000 Rp. 6440
0.014 Mandor @ Rp. 40000 Rp. 560
Rp. 75,350

26. 1 M3 PEK. RANGKA PLAFOND


0.01 M3 Kayu kls II @ Rp. 1,300,000.00 Rp. 7,800.00
0.25 Kg Paku biasa @ Rp. 7,500.00 Rp. 1,875.00
0.15 Tukang kayu @ Rp. 30,000.00 Rp. 4,500.00
0.02 Kepala Tukang @ Rp. 45,000.00 Rp. 900.00
0.15 Pekerja @ Rp. 23,000.00 Rp. 3,450.00
0.01 Mandor @ Rp. 40,000.00 Rp. 400.00
Rp. 18,925

25. 1 M2 PEK. PLAFON ETERNIT 100 x 100 + RANGKA

Bahan :
1 lbr Eternit 100 x 100 @ Rp. 8000 Rp. 8000
1.1 kg Paku Tripleks @ Rp. 4000 Rp. 4400
0.15 Tukang Kayu @ Rp. 30000 Rp. 4500
0.02 Kepala Tukang Kayu @ Rp. 45,000.00 Rp. 900
0.15 Pekerja @ Rp. 23,000.00 Rp. 3450
0.01 Mandor @ Rp. 40,000.00 Rp. 400
Rp. 12,400
Plafon + Rangka Rp. 31,325
1 M' PEK. LISTPLAN PLAFONT
1 M' List plant @ Rp. 10000 Rp. 10000
0.55 Kg Paku @ Rp. 4000 Rp. 2200
0.8 Tukang Kayu @ Rp. 30000 Rp. 24000
0.08 Kepala Tukang Kayu @ Rp. 45000 Rp. 3600
0.28 Pekerja @ Rp. 23000 Rp. 6440
0.014 Mandor @ Rp. 40000 Rp. 560
Rp. 46,800

26. 1 M3 PEK. PLAFON PLAYWOOD

Bahan :
0.38 Lbr Playwood 1,2 x 2,4 m @ Rp. 0 Rp. 0
10 M' Lest Plafon @ Rp. 0 Rp. 0
0.02 kg Paku List @ Rp. 4000 Rp. 80
0.2 Tukang Kayu @ Rp. 30000 Rp. 6000
0.02 Kepala Tukang Kayu @ Rp. 45000 Rp. 900
Pekerja @ Rp. 23000 Rp. 0
0.025 Mandor @ Rp. 40000 Rp. 1000
Rp. 7980
27. 1 M2 PEK. PASANGAN ATAP ASBES

Bahan :
0.8 Lbr Asbes Gelombang 1 m @ Rp. 0 Rp. 0
4 Bh Paku Atap @ Rp. 0 Rp. 0
0.2 Tukang Kayu @ Rp. 30000 Rp. 6000
0.02 Kepala Tukang Kayu @ Rp. 45000 Rp. 900
0.1 Pekerja @ Rp. 23000 Rp. 2300
0.005 Mandor @ Rp. 40000 Rp. 200
Rp. 9400

28. 1 M2 PEK. PASANGAN BUBUNGAN ASBES

Bahan :
1 M' Asbes Bubungan @ Rp. 0 Rp. 0
2 Bh Paku Asbes @ Rp. 0 Rp. 0
0.025 Tukang Kayu @ Rp. 30000 Rp. 750
0.0025 Kepala Tukang Kayu @ Rp. 45000 Rp. 112.5
0.025 Mandor @ Rp. 40000 Rp. 1000
Rp. 1862.5

29. 10 M2 PEK. ACIAN TEMBOKBES

Bahan :
0.055 Sak Semen PC @ Rp. 27000 Rp. 1485
0.003 M3 Kapur Ayakan @ Rp. 40000 Rp. 120
1 Tukang Batu @ Rp. 30000 Rp. 30000
0.1 Kepala Tukang Batu @ Rp. 45000 Rp. 4500
0.1 Pekerja @ Rp. 23000 Rp. 2300
0.1 Mandor @ Rp. 40000 Rp. 4000
10 M2 Rp. 42405
1 M2 Rp. 4240.5

30. 10 M2 PEK. PENGECATAN TEMBOK/PLAFONT

Bahan :
4.2 Kg. Cat Tembok @ Rp. 25000 Rp. 105000
1.2 lbr Kertas Gosok @ Rp. 1500 Rp. 1800
1 Tukang Cat @ Rp. 30000 Rp. 30000
0.1 Kepala Tukang Cat @ Rp. 45000 Rp. 4500
6 Pekerja @ Rp. 23000 Rp. 138000
10 M2 Rp. 279,300
1 M2 Rp. 27,930

31. 10 M2 PEK. PENGECATAN KAYU

Bahan :
1 Kg. Cat Kayu @ Rp. 24000 Rp. 24000
0.8 Kg. Dempul @ Rp. 15000 Rp. 12000
2 lbr Kertas Gosok @ Rp. 1500 Rp. 3000
0.57 Kg. Minyak Cat @ Rp. 15000 Rp. 8550
3.4 Tukang Cat @ Rp. 30000 Rp. 102000
0.34 Kepala Tukang Cat @ Rp. 45000 Rp. 15300
0.15 Pekerja @ Rp. 23000 Rp. 3450
0.1 Mandor @ Rp. 40000 Rp. 4000
10 M2 Rp. 172,300
1 M2 Rp. 17,230
60. 1 BH. PAS. SEPTIKTANK
9.49 M3 Galian Tanah @ Rp. 55,300.00 Rp. 524,797.00
1.45 M3 Urugan Kembali @ Rp. 61,900.00 Rp. 89,755.00
0.10 M3 Urugan Pasir @ Rp. 55,690.00 Rp. 5,569.00
1.00 KG Ijuk @ Rp. Rp. 0.00
1.00 M' Pipa PVC @ 4 @ Rp. 90,000.00 Rp. 90,000.00
1.49 M3 Pas. Batu Bata @ Rp. 195,420.00 Rp. 291,175.80
10.64 M2 Pas. Plesteran @ Rp. 14,386.00 Rp. 153,067.04
1.00 M' Pipa Besi @ 2 " @ Rp. 230,000.00 Rp. 230,000.00
2.85 M' Pipa PVC @ 4 @ Rp. 90,000.00 Rp. 256,500.00
Rp. 1,640,863.84

56. 1 BH PAS. CLOSET JONGKOK


1.00 Bh Closet Jongkok @ Rp. 135,000.00 Rp.
0.12 Kg Semen @ Rp. 27,000.00 Rp. 3,240.00
0.20 Tukang @ Rp. 30,000.00 Rp. 6,000.00
0.02 Mandor @ Rp. 40,000.00 Rp. 800.00
Rp. 10,040.00

1 M3 PEREKAT
0.508 m3 pasir @ Rp. 40000 Rp. 20,320.00
0.508 m3 semen @ Rp. 27000 Rp. 13,716.00
Rp. 34,036.00

M' SALURAN KELILING BANGUNAN


115 Buah Bata @ Rp. 300 34,500.00
0.076 semen @ Rp. 27000 2,052.00
0.076 pasir @ Rp. 40000 3,040.00
1.1 Tukang @ Rp. 30000 33,000.00
0.12 kep. Tukang @ Rp. 45000 5,400.00
2.1 pekerja @ Rp. 23000 48,300.00
0.12 mandor @ Rp. 40000 4,800.00
Rp. 91,500.00
Rp. 160,036.00

MEMASANG STOP KONTAK + INSTALASI UNTUK 1 TITIK


Bahan
0.200 Roll Kabel Listrik NYK @ Rp. 102,000.00 Rp. 20,400.00
Bahan Lainnya @ Rp. 30,000.00 Rp. 30,000.00
Rp. 50,400.00
Upah
0.200 Roll Kabel Listrik NYK @ Rp. 50,400.00 Rp. 10,080.00
1.000 hr Upah Pekerja @ Rp. 21,000.00 Rp. 21,000.00
Rp. 31,080.00

PEKERJAAN KONSOL ( TALANG)


0.01 M3 Adukan Beton @ Rp. 488,100.00 Rp. 4,881.00
50.00 Pek. Besi @ Rp. 13,250.00 Rp. 662,500.00
1.10 M2 Cetakan Beton,Bongkar Siram @ Rp. 155,250.00 Rp. 170,775.00
Rp. 838,156.00
10 M2 PEK. PENGECATAN PAGAR/TROTOAR

Bahan :
4.2 Kg. Cat @ Rp. 25000 Rp. 105000
1 Tukang Cat @ Rp. 30000 Rp. 30000
0.1 Kepala Tukang Cat @ Rp. 45000 Rp. 4500
4 Pekerja @ Rp. 23000 Rp. 92000
10 M2 Rp. 231,500
1 M2 Rp. 23,150

1 M2 PENGADAAN DAN PEMASANGAN PAVING BLOCK


Bahan
0.050 M3 Pasir Urug @ Rp. 40,000.00 Rp. 2,000.00
50.000 Bh Paving Block @ Rp. 1,250.00 Rp. 62,500.00
Upah
0.200 hr Pekerja @ Rp. 23,000.00 Rp. 4,600.00
0.015 hr Mandor @ Rp. 40,000.00 Rp. 600.00
0.100 hr Tukang Batu @ Rp. 30,000.00 Rp. 3,000.00
0.010 hr Kepala Tukang @ Rp. 45,000.00 Rp. 450.00
Rp. 73,150.00
DAFTAR HARGA SATUAN BAHAN DAN UPAH

NO JENIS BAHAN SATUAN HARGA

I BAHAN JENIS LOKAL

1 Batu Bata/Merah 1 Biji Rp. 300


2 Batu Gunung 1 M3 Rp. 75000
Kapur Ayakan 1 M3 Rp. 40000
4 Kayu Kls I 1 M3 Rp. 4000000
5 Kayu Kls II 1 M3 Rp. 1300000
Papan Kls III 1 M3 1400000
Balok Kls III 1300000
Papan Kls II 2000000
Semen PC 50 Kg 1 Sak Rp. 27000
Semen Putih 1 Sak Rp. 65000
6 Kerikil / Cipping 1 M3 Rp. 120000
7 Papan Klas I 1 M3 Rp. 4500000
8 Pasir Beton 1 M3 Rp. 40000
9 Pasir Pasangan 1 M3 Rp. 40000
10 Tanah Timbunan 1 M3 Rp. 40000
Bambu 1 Btg Rp. 8000
Paving Blok 1 Btg Rp. 1250
Pasir Timbunan 1 M3 Rp. 45500
II. BAHAN JENIS PABRIKAN

1 Plin Tegel Lantai 10 x 40 1 Dos Rp. 1250


2 Tegel Kramik 20 x 20 Cm 1 Dos Rp. 30000
3 Tegel Kramik 20 x 25 Cm 1 Dos Rp. 30000
4 Tegel Kramik 40 x 40 Cm 1 Dos Rp. 32000
III. BAHAN JENIS INDUSTRI

9 Asbes Gelombang 1 m 1 LBR Rp. 16000


1 Besi Beton 1 btg Rp. 8500
2 Bubungan Asbes 1 m 1 M Rp. 14375
Bak Kit 1 BH Rp. 350000
Bak Fiber Lapis Kramik Kap. 110 ltr 1 BH Rp. 150000
Bak Air 2 M3 1 BH Rp. 1400000
3 Cat Dasar Mini 1 KG Rp. 5000
4 Cat Kayu 1 KG Rp. 24000
5 Cat Tembok dan semacamnya 1 KG Rp. 25000
6 Closet Duduk Merk KIA 1 SET Rp. 1050000
Demoul Kayu 1 KG Rp. 15000
7 Engsel Jendela 1 PSG Rp. 6000
8 Engsel Pintu 1 PSG Rp. 10250
Exhaus 1 BH Rp. 150000
Gantungan Handuk 1 BH Rp. 75000
10 Grendel Jendela 1 BH Rp. 8750
11 Grendel Pintu 1 BH Rp. 10000
12 Hak Angin 1 PSG Rp. 7500
13 Kaca Bening 5 MM 1 M2 Rp. 65000
15 Kawat Ikat Beton 1 KG Rp. 8000
16 Kertas Gosok 1 LBR Rp. 1500
17 Kran Air Biasa 1 BH Rp. 7500
18 Kran Air Doble 1 BH Rp. 125000
19 Kunci Ex. RRT 1 BH Rp. 34500
Kabel NYK 1 roll Rp. 102000
20 List Profil Kayu 1 M' Rp. 10000
21 Minyak Cat ( Tenner ) 1 KG Rp. 15000
22 Mur,Baut, Angker 1 BH Rp. 3500
23 Paku Asbes 1 BH Rp. 350
24 Paku Biasa 1 KG Rp. 7500
25 Pipa PVC 1 " 1 M' Rp. 6000
26 Pipa PVC 3 " 1 M' Rp. 20000
27 Pipa PVC 3/4 " 1 M' Rp. 3000
28 Pipa PVC 4 " 1 M' Rp. 30000
Pipa Besi 1 " 1 M' Rp. 30000
Genteng Biasa 2500
Pipa Besi 3/4 " 1 M' Rp. 25000
Pompa Air 1 BH Rp. 750000
29 Ploor Drain 1 BH Rp. 7500
Plamur Tembok 1 KG Rp. 5000
30 Semen 1 ZAK Rp. 20000
31 Semen Putih 1 ZAK Rp. 40000
Stop Kran 1 BH Rp. 15000
34 Tempat Sabun Merk Kia 1 BH Rp. 10000
35 Tripleks Playwood 4 mm 1 LBR Rp. 40000
36 Wastaafel 1 BH Rp. 200000
Water Haiter Kap. 100 ltr 1 BH Rp. 1750000
Paku Seng Rp. 13000
Paku Tripleks 4000
Etenit 100 x 100 1 Lbr Rp. 8000
List Profil Kayu 4 x 5 10000
Multiroof 1 BH Rp. 55000
IV JENIS PEKERJA

1 Pekerja 1 Hari Rp. 23000


2 Tukang Batu 1 Hari Rp. 30000
Tukang Besi 1 Hari Rp. 30000
Tukang Cat 1 Hari Rp. 30000
Tukang Kayu 1 Hari Rp. 30000
3 Kepala Tukang Batu 1 Hari Rp. 45000
Kepala Tukang Besi 1 Hari Rp. 45000
Kepala Tukang Cat 1 Hari Rp. 45000
Kepala Tukang Kayu 1 Hari Rp. 45000
Kepala Listrik 1 Hari Rp. 45000
4 Mandor 1 Hari Rp 40000