SATUAN
NO ITEM PEKERJAAN VOL
A PERSIAPAN
B PEKERJAAN TANAH
1 Pekerjaan Galian Tanah 9,766.30 m3
2 Pek.Beskisting 4,275.00 m2
D PEKERJAAN DRAINASE
1 Pek.Beskisting 17,657.23 m2
2 Pek.Pengecoran 3,252.65 m3
TOTAL
HARGA (Rp.) BOBOT
SATUAN JUMLAH % 1 2 3 4 5
28,858,112,613.02 100.00
0.30264
1.258734
0.022132 0.022132
3.332026 3.332026
0.091412 0.091412
0.301459 0.301459
0.118043 0.118043
10.51082
1.3067 5.7756 12.7963 9.4421 9.4421 6.1627 6.6588 4.4954 0.9156 10.6289
12.6608 18.4364 31.2326 40.6748 50.1169 56.2796 62.9385 67.4339 68.3495 78.9784
No Item Pekerjaan
26 27
1 Pek.Galian Tanah
3 Pek.Timbunan
Jumlah Rencana Pekerjaan
Jumlah Kumulatif rencana pekerjaan
Jumlah realisasi pekerjaan
Jumlah Kumulatif realisasi pekerjaan
Selisih
10.51082 10.51082
10.5108 10.5108
89.4892 100.00
Nilai Bobot Nilai Bobot Durasi Kemajuan
1 2 3 4
(Rp) (%) (minggu) Pekerjaan (%)
436,680,571.90 86.32 4 21.58 21.58 21.58 21.58
69,230,840.00 13.68 4 3.42 3.42 3.42
505,911,411.90 100.00 8 21.58 25.00 25.00 25.00
21.58 46.58 71.58 96.58
5
3.42
3.42
100.00
Rencana Anggaran Biaya
`
KEGIATAN : PERANCANGAN GEOMETRIK JALAN,TEBAL PERKERASAN DAN RENCANA ANGGARAN BIAYA
NO. PAKET :
NAMA PAKET :
VOLUME :
Panjang : 2323.32 m
Lebar : 14 m
KABUPATEN : Gunung Kidul
NO PERKIRAAN HARGA
MATA URAIAN SAT. KUANTITAS SATUAN
PEMB. Rp
1 2 3 4 5
DIV 1. U M U M
1.2 Persiapan Ls 1.00 162,090,000.00
Jumlah harga penawaran untuk devisi 1
DIV 2. DRAINASE
2.1 (1) Pek.Beskisting M2 17,657.23 108,914.00
2.2 (2) Pek.Pengecoran M3 3,252.65 884,427.00
2.3 (3) Pek.Bongkaran Bekisting M2 17,657.23 2,988.00
2.4 (4) Pek.Plesteran + Acian M2 17,657.23 24,325.00
Jumlah harga penawaran untuk devisi 2
DIV 3. PEKERJAAN TANAH
3.1 (1) Galian tanah biasa M3 9766.3 44,713.00
3.2 (2) Timbunan biasa M3 776 89,215.00
Jumlah harga penawaran untuk devisi 3
4.1 (1) Bekisting M2 4,275.00 108,914.00
4.2 (2) Pembesian DPT Kg 2180.24 15,000.00
4.3 (3) DPT Beton M3 2,875.00 884,427.00
4.4 (4) Pek.Bongakran Bekisting M2 4,275.00 2,988.00
Jumlah harga penawaran untuk devisi 4
81.52875
NA ANGGARAN BIAYA
GALIAN 9766.3
TIMBUNAN 776
JUMLAH
HARGA
Rp
6
LUAS DRAINASE
1.4
162,090,000.00 KELILING PERMUKAAN DRAINASE
162,090,000.00 7.6
PANJANG DRAINASE
1,923,119,766.05 2323.32
2,876,729,712.70
52,759,809.22
429,512,168.40
5,282,121,456.36
436,680,571.90
69,230,840.00
505,911,411.90
465,607,350.00
32,703,600.00
2,542,727,625.00
12,773,700.00
3,053,812,275.00 STA 100 - STA 200
KELILING LUAS DPT PANJANG DPT
17.1 11.50 250
4,109,613,875.28
4,109,613,875.28
6,402,771,511.22
6,402,771,511.22
9,341,792,083.26
28,858,112,613.02
0.75
1.4
Item Pembayaran : 2.1(1)
2
Jenis Pekerjaan : Galian Tanah Biasa
Satuan Pembayaran : M3
I Asumsi
1 Menggunakan Alat Berat
2 Lokasi Pek. Sepanjang jalan
3 Kondisi Jalan sedang/baik
4 Jam kerja efektif / hari Tk 7 Jam
5 Faktor pengembangan bahan Fk 1.2 Jam
II Urutan Kerja
1 Penggalian dilakukan dengan menggunakan Excavator
2 Excavator menuankan hasil galian ke dalam truck
3 Dum Truck membuang hasil galian keluar lokasi jalan
Sejauh L 1.00 Km
4 Sekelompok pekerjan merapikan tanah hasil galian
2 Alat
2.a EXCAVATOR (E 10)
Kapasitas Bucket V 0.93 M3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
V x Fb x Fa x 60
Kap. Pro. / jam = Q1 34.74 M3/jam
Ts1 x Fk
Koefisien alat /M3 = 1 : Q1 0.0288 Jam
Tenaga
Produksi menentukan : Excavator Q1 34.74 M3/jam
Prod. Galian / hari = Tk x Q1 Qt 243.15 M3
Kebutuhan tenaga
- Pekerja P 4.00 Org
- Mandor M 1.00 Org
I Asumsi
1 Pekerjaan dilakukan secara mekanik
2 Lokasi Pek. Sepanjang jalan
3 Kondisi Jalan sedang
4 Jam kerja efektif / hari Tk 7 Jam
5 Faktor Pengembangan Bahan Fk 1.2 -
6 Tebal hamparan t 0.15 M
II Urutan Kerja
1 Whell Loader memuat ke dalam truck
2 Dump Truck mengangkut kelapangan dengan jarak L 33 Km
quary ke lapangan
2 ALAT
2.a Whell Loader (E 15)
Kapasitas Bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu sikus Ts1
- Menggali/memuat T1 0.50 Menit
- Lain-lain T2 0.50 Menit
1.00
V x Fb x Fa x 60
Kap. Pro. / jam = Q1 56.03 M3
Ts1 x Fk
Koefisien alat /M3 = 1 : Q1 0.0178 Jam
Vxnx Fa
Kap. Pro. / jam = Q5 142.29 M3
Wc
Koef alat / M3 = 1:Q5 0.0070 Jam
Tenaga
Produksi menentukan : Whell Loader Q1 56.03 M3/jam
Prodduksi Agregat / hari = Tkx Q1 Qt 392.18 M3
Kebutuhan tenaga
- Pekerja P 4.00 Org
- Mandor M 1.00 Org
I Asumsi
1 Menggunakan Alat Berat (Cara mekanik)
2 Lokasi Pek. Sepanjang jalan
3 Kondisi Jalan sedang
4 Jarak Rata-rata Base Camp ke lokasi Pekerjaan L 33 Km
5 Tebal Lapis Agregat padat t 0.3 M
6 Faktor Kembang material ( Padat-Lepas) Fk 1.2 -
7 Jam kerja efektif / hari Tk 7 Jam
8 Lebar bahu jalan Lb 1 M
9 Proporsi Campuran - Agregat kasar Ak 64 %
- Agregat halus Ah 36 %
II Urutan Kerja
1 Whell Loader memuat Agregat ke dalam dump truck di
Base Camp.
2 Dump Truck mengangkut agregaat ke lokasi
3 Hamparan agregat dibasaahi dengan water tangker
sebelum dipadatkan dengan tandem roller
4 Selama pemadatan sekelompok pekerja akan merapikan
tepi hamparan dan level permukaan dengan alat bantu
2 ALAT
2.a Whell Loader (E 15)
Kapasitas Bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Vxnx Fa
Kap. Pro. / jam = Q5 59.29 M3
Wc
Koef alat / M3 = 1:Q5 0.0169 Jam
Tenaga
Produksi menentukan : Whell Loader Q1 56.03 M3/jam
Prodduksi Agregat / hari = Tkx Q1 Qt 392.18 M3
Kebutuhan tenaga
- Pekerja P 7.00 Org
- Mandor M 1.00 Org
I Asumsi
1 Menggunakan Alat Berat (Cara mekanik)
2 Lokasi Pek. Sepanjang jalan
3 Kondisi Jalan sedang
4 Jarak Rata-rata Base Camp ke lokasi Pekerjaan L 33 Km
5 Tebal Lapis Agregat padat t 0.14 M
6 Faktor Kembang material ( Padat-Lepas) Fk 1.2 -
7 Jam kerja efektif / hari Tk 7 Jam
8 Lebar bahu jalan Lb 1 M
9 Proporsi Campuran - Agregat kasar Ak 59 %
- Agregat halus Ah 41 %
II Urutan Kerja
1 Whell Loader memuat Agregat ke dalam dump truck di
Base Camp.
2 Dump Truck mengangkut agregaat ke lokasi
3 Hamparan agregat dibasaahi dengan water tangker
sebelum dipadatkan dengan tandem roller
4 Selama pemadatan sekelompok pekerja akan merapikan
tepi hamparan dan level permukaan dengan alat bantu
2 ALAT
2.a Whell Loader (E 15)
Kapasitas Bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu sikus
- Menggali/memuat T1 0.50 Menit
- Lain-lain T2 0.50 Menit
Ts1 1.00
V x Fb x Fa x 60
Kap. Pro. / jam = Q1 56.03 M3
Ts1 x Fk
Koefisien alat /M3 = 1 : Q1 0.0178 Jam
Vxnx Fa
Kap. Pro. / jam = Q5 59.29 M3
Wc
Koef alat / M3 = 1:Q5 0.0169 Jam
Tenaga
Produksi menentukan : Whell Loader Q1 56.03 M3/jam
Prodduksi Agregat / hari = Tkx Q1 Qt 392.18 M3
Kebutuhan tenaga
I Asumsi
1 Menggunakan Alat Berat (Cara mekanik)
2 Lokasi Pek. Sepanjang jalan
3 Jarak Rata-rata Base Camp ke lokasi Pekerjaan L 33 Km
4 Jam kerja efektif / hari Tk 7 Jam
5 Faktor Kehilangan bahan Fh 1.1 -
6 Komposisi Campuran
- Aspal AC-10 atau Ac-20 AS 56 %
- Minyak Flux/Pencair K 44 %
7 Berat Jenis baha
- Aspal AC-10 atau Ac-20 D1 1.05 Kg/ltr
- Minyak Flux/Pencair D2 0.8 Kg/ltr
8 Bahan dasar (Aspal dan Minyak pencair) Semuanya
diterima dilokasi pekerjaan
II Urutan Kerja
1 Aspal dan minyak flux dicampur dan dipanaskan seingga
menjadi campuran aspal panas
2 Permukaan yang akan dilapisi dibersihkan dari debu
dan kotoran dengan air compresor
3 Capuran aspal cir disemprotkan dengan aspahlt spreyer
ke permukaan yang akan di lapis
Angkutan Aspa dan minyak flux mengunakan dump truck
V x F3
Kap. Pro. / jam = Q1 332.00 Ltr
Ts
Koefisien alat /M3 = 1 : Q1 (E 03) 0.0030 Jam
3 Tenaga
Produksi menentukan : Asphal sprayer Q4 332.00 Ltr
Produksi Lapis Resap Pengikat/hari = Tk x Q4 Qt 2,324.00 Ltr
Kebutuhan tenaga
- Pekerja P 10.00 Org
- Mandor M 2.00 Org
Koefisien Tenaga/ liter
- Pekerja = (Tk x P ) : Qt (L01) 0.0301 Jam
- Mandor = ( Tk x M ) : Qt (L03) 0.0060 Jam
I Asumsi
1 Menggunakan Alat Berat (Cara mekanik)
2 Lokasi Pek. Sepanjang jalan
3 Jarak Rata-rata Base Camp ke lokasi Pekerjaan L 33 Km
4 Jam kerja efektif / hari Tk 7 Jam
5 Faktor Kehilangan bahan Fh 1.1 -
6 Komposisi Campuran
- Aspal AC-10 atau Ac-20 AS 77 %
- Minyak Flux/Pencair K 23 %
7 Berat Jenis baha
- Aspal AC-10 atau Ac-20 D1 1.05 Kg/ltr
- Minyak Flux/Pencair D2 0.8 Kg/ltr
8 Bahan dasar (Aspal dan Minyak pencair) Semuanya
diterima dilokasi pekerjaan
II Urutan Kerja
1 Aspal dan minyak flux dicampur dan dipanaskan seingga
menjadi campuran aspal panas
2 Permukaan yang akan dilapisi dibersihkan dari debu
dan kotoran dengan air compresor
3 Capuran aspal cir disemprotkan dengan aspahlt spreyer
ke permukaan yang akan di lapis
Angkutan Aspa dan minyak flux mengunakan dump truck
V x F3
Kap. Pro. / jam = Q1 332.00 Ltr
Ts
Koefisien alat /M3 = 1 : Q1 (E 03) 0.0030 Jam
3 Tenaga
Produksi menentukan : Asphal sprayer Q4 332.00 Ltr
Produksi Lapis Resap Pengikat/hari = Tk x Q4 Qt 2,324.00 Ltr
Kebutuhan tenaga
- Pekerja P 10.00 Org
- Mandor M 2.00 Org
Koefisien Tenaga/ liter
- Pekerja = (Tk x P ) : Qt (L01) 0.0301 Jam
- Mandor = ( Tk x M ) : Qt (L03) 0.0060 Jam
Item Pembayaran : 5.3 (4)
Jenis Pekerjaan : LASTON (AC) 11
Satuan Pembayaran : M'
I Asumsi
1 Menggunakan alat berat (cara mekanik)
2 Lokasi Pek. Sepanjang jalan
3 Kondisi exiting jalan : sedang
4 Jarak Rata-rata Base Camp ke lokasi Pekerjaan L 33 KM
5 Tebal lapis (AC) padat t 0.325 M
6 Jam kerja per-hari Tk 7 Jam
7 faktor kehilangan material : -agregat Fh1 1.1 -
-aspal Fh2 1.05 -
8 Komposisi campuran AC (spesifikasi)
-Coarse agregat 30 - 50% CA 50 %
- fine agregat 39 - 59% FA 35 %
- fraksi filler 4.5 - 7.5% FF 7.5 %
- asphalt minimum 6.7% As 7.5 %
9 Berat jenis bahan
- AC D1 2.25 ton/M3
- Coarse Agregat & Fine Agregat D2 1.8 ton/M3
- Fraksi Filler D3 2 ton/M3
- Asphalt D4 1.030 ton/M3
2 ALAT
2.a WHEEL LOADER (E15)
kapasitas bucket V 1.50 M3
faktor bucket Fb 0.90 M3
faktor elisiensi alat Fa 0.83 -
waktu siklus Ts1 1.50 -
- muat T1 0.50 menit
- lain lain T2 2.000 menit
D2 x V x Fb x Fa x 60
kap. Prod / jam = D1 x 1 x Ts1 Q1 35.86 M3
koefisien alat/m2 = 1 : Q1 (E15) 0.0279
Kap.Prod / jam = V x Fa
D1 x 1 Q2 18.44 M2
koefisien Alat/M2 = 1 : Q2 (E01) 0.05 Jam
kap.prod / jam = V x Fa x 60
D1 x Ts2 x 1 Q4 0.79 M2
3 TENAGA
produksi menentukan : ASPHALT MIXING PLANT (AMP) Q2 18.44 M2/Jam
Produksi AC / hari = Tk x Q2 Qt 129.11 M2
kebutuhan tenaga :
- pekerja P 10.00 orang
- mandor M 1.00 orang
koefisien tenaga/M2
- pekerja = (Tk x P) / Qt (L01) 0.5422 Jam
- mandor = (Tk x M) / Qt (L03) 0.0542 Jam
I Asumsi
1 Menggunakan Alat Berat (Cara mekanik)
2 Lokasi Pek. Sepanjang jalan
3 Kondisi Jalan sedang
4 Jarak Rata-rata Base Camp ke lokasi Pekerjaan L 33 Km
5 Tebal Lapis Agregat padat t 0.2 M
6 Faktor Kembang material ( Padat-Lepas) Fk 1.2 -
7 Jam kerja efektif / hari Tk 7 Jam
8 Lebar bahu jalan Lb 1 M
9 Proporsi Campuran - Agregat kasar Ak 64 %
- Agregat halus Ah 36 %
II Urutan Kerja
1 Whell Loader memuat Agregat ke dalam dump truck di
Base Camp.
2 Dump Truck mengangkut agregaat ke lokasi
3 Hamparan agregat dibasaahi dengan water tangker
sebelum dipadatkan dengan tandem roller
4 Selama pemadatan sekelompok pekerja akan merapikan
tepi hamparan dan level permukaan dengan alat bantu
Vxnx Fa
Kap. Pro. / jam = Q5 59.29 M3
Wc
Koef alat / M3 = 1:Q5 0.0169 Jam
Tenaga
Produksi menentukan : Whell Loader Q1 56.03 M3/jam
Prodduksi Agregat / hari = Tkx Q1 Qt 392.18 M3
Kebutuhan tenaga
- Pekerja P 7.00 Org
- Mandor M 1.00 Org
I Asumsi
1 Menggunakan Alat Berat (Cara mekanik)
2 Lokasi Pek. Sepanjang jalan
3 Kondisi Jalan sedang
4 Jarak Rata-rata Base Camp ke lokasi Pekerjaan L 33 Km
5 Tebal Lapis Agregat padat t 0.02 M
6 Faktor Kembang material ( Padat-Lepas) Fk 1.2 -
7 Jam kerja efektif / hari Tk 7 Jam
8 Lebar bahu jalan Lb 1 M
9 Proporsi Campuran - Agregat kasar Ak 59 %
- Agregat halus Ah 41 %
II Urutan Kerja
1 Whell Loader memuat Agregat ke dalam dump truck di
Base Camp.
2 Dump Truck mengangkut agregaat ke lokasi
3 Hamparan agregat dibasaahi dengan water tangker
sebelum dipadatkan dengan tandem roller
4 Selama pemadatan sekelompok pekerja akan merapikan
tepi hamparan dan level permukaan dengan alat bantu
2 ALAT
2.a Whell Loader (E 15)
Kapasitas Bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Vxnx Fa
Kap. Pro. / jam = Q5 47.43 M3
Wc
Koef alat / M3 = 1:Q5 0.0211 Jam
Tenaga
Produksi menentukan : Whell Loader Q1 56.03 M3/jam
Prodduksi Agregat / hari = Tkx Q1 Qt 392.18 M3
Kebutuhan tenaga
I Asumsi
1 Menggunakan Alat Berat (Cara mekanik)
2 Lokasi Pek. Sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak Rata-rata Base Camp ke lokasi Pekerjaan L 33 Km
5 Jam kerja efektif / hari Tk 7 Jam
9 Perbandingan Pasir & Semen : - Volume Semen Sm 25 %
: - Volume Pasir Ps 75 %
Perbandingan Batu & Mortar :
- Batu Bt 65 %
- Mortar (campuran semen & pasir) Mr 35 %
Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.4 ton/M3
- Batu D2 1.6 ton/M3
- Adukan (mortar) D3 1.8 ton/M3
- Pasir D4 1.3 ton/M3
- Semen Portland D5 1.44 ton/M3
II Urutan Kerja
1 Semen, pasir dan air dicampur dan diaduk menjadi
mortar dengan menggunakan Concrete Mixer
2 Batu dibersihkan dan dibasahi seluruh permukaannya
sebelum dipasang
3 Penyelesaian dan perapihan setelah pemasangan
1 BAHAN
1.a. Batu -----> {(Bt x D1 x 1 M3) : D2} x 1.20 (M02) 1.17 M3
1.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x 1.05 (M12) 0.1225 M3
x {D5 x (1000)} (M12) 176 Kg
1.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x 1.05 (M01) 0.5088 M3
2 ALAT
2.a CONCRETE MIXER (E06)
Kapasitas Alat V 500.00 liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 8.00 Menit
- Mengaduk T2 4.00 Menit
- Menuang T3 3.00 Menit
- Tunggu, dll. T4 2.00 Menit
17.00 Menit
Jumlah 2,360,000.00
B Peralatan (lihat Lampiran) A.
Jumlah
C Fasilitas Kontraktor
1 Base Camp M2 50.000 118,000.00 5,900,000.00
2 Kantor M2 40.000 11,800.00 472,000.00 B.
3 Barak M2 - - -
4 Bengkel M2 - - -
5 Gudang dll M2 - - -
6,372,000.00 C.
D Fasilitas Direksi 1
1 Kantor M2 - 236,000.00 - 2
2 Akomodasi utk wakil Direksi M2 - 88,500.00 - 3
3 Bang Laboratorium M2 - 106,200.00 - 4
4 Peralatan Laboratorium Set - 5,900,000.00 - 5
Jumlah -
E Mobilisasi Lainnya D. FASILITAS DIREKSI TE
E.I Pekerjaan Darurat 1
1 Pemeliharaan Jalan Kerja Ls 1.00 - -
2 Pemindahan tiang Telpon Bh 18.00 4,130,000.00 74,340,000.00
3 Pemindahan tiang LPJU Bh 4.00 8,260,000.00 33,040,000.00
4 Pemotongan pohon Batang 23.00 236,000.00 5,428,000.00
5 Pemindahan pipa PDAM M' 0.00 1,770,000.00 -
6 Pemindahan trafic light Bh 2.00 3,540,000.00 7,080,000.00
7 Manajemen + keselamatan lalu litas Ls 1.00 4,720,000.00 4,720,000.00 2
E. II Lain-Lain 3
1 Asbuild Drawing Set 5.000 4,750,000.00 23,750,000.00 4
2 Dokumentasi Ls 1.000 5,000,000.00 5,000,000.00 5 ..................
Jumlah 153,358,000.00 6 ..................
F Demobilisasi Ls - - -
Jumlah Peralatan 162,090,000.00
E.
E.I.
1
2
3
4 Pemindahan Tiang Tel
5 Pemindahan Tiang LP
6 Penebangan Pohon
7 Pemindahan pipa PDA
8 Pemindahan Trafic Li
9 Manajemen + Keselamatan
E.II.
1
2
3
4
5
F.
Catatan :
4720000
: 1.2
: MOBILISASI
BASE CAMP
Sewa tanah untuk Base Camp M2 20.00 100,000.00 2,000,000.00
PERALATAN
Periksa lembar ke-2 0.00
FASILITAS KONTRAKTOR
Base Camp M2 50.00 100,000.00 5,000,000.00
Kantor M2 40.00 100,000.00 4,000,000.00
Barak M2 0.00
Bengkel M2 0.00
Gudang dan lain-lain M2 0.00
MOBILISASI LAINNYA
PEKERJAAN DARURAT
Jembatan Darurat LS 0.00 0.00
Perkuatan Jembatan Lama LS 0.00 0.00
Pemeliharaan Jalan Kerja / Samping LS 0.00 0.00
Pemindahan Tiang Telpon Bh 18.00 3,500,000.00 63,000,000.00
Pemindahan Tiang LPJU Bh 4.00 7,000,000.00 28,000,000.00
Penebangan Pohon Batang 23.00 200,000.00 4,600,000.00
Pemindahan pipa PDAM m' 1,500,000.00 0.00
Pemindahan Trafic Light Bh 2.00 3,000,000.00 6,000,000.00
Manajemen + Keselamatan Lalulintas LS 1.00 4,000,000.00 4,000,000.00
LAIN-LAIN
Rekayasa Lapangan LS 0.00 500,000.00 0.00
Radio Komunikasi (HT) LS 0.00 0.00
Radio Komunikasi (SSB) LS 0.00 0.00
...................... ....
...................... ....
: Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
4 Harga Satuan Pekerja
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
A TENAGA
1 Pekerja Jam 0.1152 9,285.71 1,069.31
2 Mandor Jam 0.0288 13,857.14 398.93
B MATERIAL
C PERALATAN
1 Excavator Jam 0.0288 515,541.04 14,841.91
2 Dump truck Jam 0.0955 287,000.00 27,403.31
3 Alat bantu Ls 1.0000 1,000.00 1,000.00
Catatan :
### SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran berat untuk
bahan-bahan.
### Kuantitas satuan adalah kuantitas Perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran. Harga satuan yang disampaikan Peserta lelang tidak dapat diubah, kecuali persyaratan Ayat 13.4 dari Instruksi
Kepada Peserta Lelang
### Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
### Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang dibayar dari kontrak) dan biaya-biaya lainnya.
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
A TENAGA
1 Pekerja Jam 0.1249 9,285.71 1,160.20
2 Mandor Jam 0.0178 13,857.14 247.34
B MATERIAL
1 Agregat Kasar M3 0.7680 420,475.17 322,924.93
2 Agregat Halus M3 0.4320 405,176.29 175,036.16
C PERALATAN
1 Wheel Loader Jam 0.0178 515,113.70 9,194.35
2 Dump Truck Jam 0.4819 287,000.00 138,313.25
3 Motor Grader Jam 0.0059 671,266.80 3,931.45
4 Water Tanker Jam 0.0169 199,929.73 3,372.31
5 Tandem Roller Jam 0.0134 515,114 6,895.77
5 Alat Bantu Ls 1.0000 30,000 30,000.00
Jumlah
D Harga Pekerja, Material dan Peralatan 661,075.76
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
A TENAGA
1 Pekerja Jam 0.1249 9,285.71 1,160.20
2 Mandor Jam 0.0178 13,857.14 247.34
B MATERIAL
1 Agregat Kasar M3 0.7080 420,475.17 297,696.42
2 Agregat Halus M3 0.4920 405,176.29 199,346.74
C PERALATAN
1 Wheel Loader Jam 0.0178 515,113.70 9,194.35
2 Dump Truck Jam 0.4819 287,000.00 138,313.25
3 Motor Grader Jam 0.0879 671,266.80 58,971.73
4 Water Tanker Jam 0.0211 199,929.73 4,215.39
5 Tandem Roller Jam 0.1339 221,848 29,698.57
6 Alat Bantu Ls 1.0000 30,000.00 30,000.00
Jumlah
D Harga Pekerja, Material dan Peralatan 709,145.42
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
A TENAGA
1 Pekerja Jam 0.1249 9,285.71 1,160.20
2 Mandor Jam 0.0178 13,857.14 247.34
B MATERIAL
1 Agregat Kasar M3 0.7680 420,475.17 322,924.93
2 Agregat Halus M3 0.4320 405,176.29 175,036.16
C PERALATAN
1 Wheel Loader Jam 0.0178 515,113.70 9,194.35
2 Dump Truck Jam 0.4819 287,000.00 138,313.25
3 Motor Grader Jam 0.0059 671,266.80 3,931.45
4 Water Tanker Jam 0.0169 199,929.73 3,372.31
5 Alat Bantu Ls 1.0000 30,000 30,000.00
6 Three wheel Roller Jam 0.0089 221,848.33 1,979.90
Jumlah
D Harga Pekerja, Material dan Peralatan 656,159.90
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
A TENAGA
1 Pekerja Jam 0.1249 9,285.71 1,160.20
2 Mandor Jam 0.0178 13,857.14 247.34
B MATERIAL
1 Agregat Kasar M3 0.7080 420,475.17 297,696.42
2 Agregat Halus M3 0.4920 405,176.29 199,346.74
C PERALATAN
1 Wheel Loader Jam 0.0178 515,113.70 9,194.35
2 Dump Truck Jam 0.4819 287,000.00 138,313.25
3 Motor Grader Jam 0.0126 671,266.80 8,424.53
4 Water Tanker Jam 0.0169 199,929.73 3,372.31
5 Alat Bantu Ls 1.0000 30,000 30,000.00
6 Three wheel Roller Jam 0.0191 221,848.33 4,242.65
Jumlah
D Harga Pekerja, Material dan Peralatan 661,997.80
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
A TENAGA
1 Pekerja Jam 0.0301 9,285.71 279.69
2 Mandor Jam 0.0060 13,857.14 83.48
B BAHAN
1 Aspal Kg 0.6468 10,000.00 6,468.00
2 Kerosene Lt 0.4840 10,000.00 4,840.00
C PERALATAN
1 Asphalt Sprayer Jam 0.0030 120,439.88 362.77
2 Compresor Jam 0.0031 152,105.73 475.33
3 Dump truck Jam 0.0030 287,000.00 864.46
Jumlah
D Harga Pekerja, Material dan Peralatan 13,373.73
A TENAGA
1 Pekerja Jam 0.0301 9,285.71 279.69
2 Mandor Jam 0.0060 13,857.14 83.48
B BAHAN
1 Aspal Kg 0.8894 10,000.00 8,893.50
2 Kerosene Lt 0.2530 10,000.00 2,530.00
C PERALATAN
1 Asphalt Sprayer Jam 0.0030 120,439.88 362.77
2 Compresor Jam 0.0063 152,105.73 950.66
3 Dump truck Jam 0.0030 287,000.00 864.46
Jumlah
D Harga Pekerja, Material dan Peralatan 13,964.56
A TENAGA
1 Pekerja Jam 0.5422 9,285.71 5,034.42
2 Mandor Jam 0.0542 13,857.14 751.29
B BAHAN
1 Agregat Kasar M3 0.2234 420,475.17 93,949.92
2 Agregat Halus M3 0.1564 405,176.29 63,372.10
3 Filler Kg 0.0603 1,300.00 78.43
4 Aspalt Kg 0.0576 10,000.00 575.86
C PERALATAN
1 Whell Loader 1.0-1.6M3 Jam 0.0279 515,113.70 14,366.18
2 AMP Jam 0.0542 4,140,001.10 224,457.89
3 Genset Jam 0.0542 265,153.86 14,375.81
4 Dump Truck 3-4 M3 Jam 1.2662 287,000.00 363,396.46
5 Asphalt Finisher Jam 0.0678 950,564.17 64,420.76
6 P. Tyre Roller Jam 0.0030 221,848.33 670.74
7 Tandem Roller Jam 0.0016 221,848.33 356.38
8 Alat bantu Ls 1.0000 15,000.00 15,000.00
Jumlah
D Harga Pekerja, Material dan Peralatan 860,806.26
KEGIATAN : 0
NO. PAKET :
NAMA PAKET :
KABUPATEN : 0
NO. MATA PEMBAYARAN : 5.3 (4) PERKIRAAN KUANTITAS :
URAIAN : LASTON (AC - BC) JUMLAH HARGA :
SATUAN : M2 % THD HARGA PEK :
A TENAGA
1 Pekerja Jam 0.5422 9,285.71 5,034.42
2 Mandor Jam 0.0542 13,857.14 751.29
-
B BAHAN -
1 Agregat Kasar M3 0.2234 420,475.17 93,949.92
2 Agregat Halus M3 0.1564 405,176.29 63,372.10
3 Filler Kg 0.0603 1,300.00 78.43
4 Aspalt Kg 0.0576 10,000.00 575.86
-
C PERALATAN -
1 Whell Loader 1.0-1.6M3 Jam 0.0279 515,113.70 14,366.18
2 AMP Jam 0.0542 4,140,001.10 224,457.89
3 Genset Jam 0.0542 265,153.86 14,375.81
4 Dump Truck 3-4 M3 Jam 1.2662 287,000.00 363,396.46
5 Asphalt Finisher Jam 0.0678 950,564.17 64,420.76
6 P. Tyre Roller Jam 0.0030 221,848.33 670.74
7 Tandem Roller Jam 0.0016 221,848.33 356.38
8 Alat bantu Ls 1.0000 15,000.00 15,000.00
Jumlah
D Harga Pekerja, Material dan Peralatan 860,806.26
A TENAGA
1 Pekerja Oh 1.500 65,000.00 97,500.00
2 Tukang Batu Oh 0.750 81,000.00 60,750.00
3 Kepala Tukang Oh 0.075 81,000.00 6,075.00
4 Mandor Oh 0.075 97,000.00 7,275.00
B MATERIAL
1 Batu Kali m3 1.2000 325,881.00 391,057.20
2 Semen Portland kg 1.3600 1,500.00 2,040.00
3 Pasir Pasang m3 0.5440 406,375.20 221,068.11
KEGIATAN : 0
NO. PAKET :
NAMA PAKET :
KABUPATEN : 0
NO. MATA PEMBAYARAN : 7.9 PERKIRAAN KUANTITAS :
URAIAN : Siar Pasangan Batu kali JUMLAH HARGA :
SATUAN : m2 % THD HARGA PEK :
A TENAGA
1 Pekerja Oh 0.300 65,000.00 19,500.00
2 Tukang Batu Oh 0.150 81,000.00 12,150.00
3 Kepala Tukang Oh 0.015 81,000.00 1,215.00
4 Mandor Oh 0.015 97,000.00 1,455.00
B MATERIAL
1 Semen Portland kg 6.3400 1,500.00 9,510.00
2 Pasir Pasang m3 0.0120 406,375.20 4,876.50
KEGIATAN : 0
NO. PAKET :
NAMA PAKET :
KABUPATEN : 0
NO. MATA PEMBAYARAN : 7.9 PERKIRAAN KUANTITAS :
URAIAN : 1 m3 Beton Mutu f'c 25 Mpa (K 300), JUMLAH HARGA :
SATUAN : m2 % THD HARGA PEK :
A TENAGA
1 Pekerja Oh 1.650 65,000.00 107,250.00
2 Mandor Oh 0.165 97,000.00 16,005.00
3 Tukang Batu Oh 0.0280 81,000.00 2,268.00
4 Kepala Tukang Batu Oh 0.2750 81,000.00 22,275.00
B MATERIAL
1 Semen Portland kg 0.4130 1,500.00 619.50
2 Pasir Beton m3 0.6810 15,000.00 10,215.00
3 Batu Split2 - 3 cm m3 1.0210 395,000.00 403,295.00
4 Air LTR 215.0000 1,500.00 322,500.00
KEGIATAN : 0
NO. PAKET :
NAMA PAKET :
KABUPATEN : 0
NO. MATA PEMBAYARAN : 7.9 PERKIRAAN KUANTITAS :
URAIAN : 1 m3 Bekisting JUMLAH HARGA :
SATUAN : m2 % THD HARGA PEK :
A TENAGA
1 Pekerja Oh 0.520 65,000.00 33,800.00
2 Mandor Oh 0.026 97,000.00 2,522.00
3 Tukang kayu Oh 0.0260 81,000.00 2,106.00
4 Kepala Tukang Batu Oh 0.0260 81,000.00 2,106.00
B MATERIAL
1 Kayu Kelas III kg 0.0400 1,500,000.00 60,000.00
2 Paku m3 0.3000 24,600.00 7,380.00
3 Minyak Bekisting m3 0.1000 10,000.00 1,000.00
KEGIATAN : 0
NO. PAKET :
NAMA PAKET :
KABUPATEN : 0
NO. MATA PEMBAYARAN : 7.9 PERKIRAAN KUANTITAS :
URAIAN : plesteran Acian JUMLAH HARGA :
SATUAN : m2 % THD HARGA PEK :
A TENAGA
1 Pekerja Oh 0.100 65,000.00 6,500.00
2 Mandor Oh 0.050 97,000.00 4,850.00
3 Tukang kayu Oh 0.0500 81,000.00 4,050.00
4 Kepala Tukang Batu Oh 0.0500 81,000.00 4,050.00
B MATERIAL
1 Semen Portland kg 3.2500 1,500.00 4,875.00
2 m3 - -
3 m3 - -
KEGIATAN : 0
NO. PAKET :
NAMA PAKET :
KABUPATEN : 0
NO. MATA PEMBAYARAN : 7.9 PERKIRAAN KUANTITAS :
URAIAN : 1 m3 Pembongkaran Bekisting JUMLAH HARGA :
SATUAN : m2 % THD HARGA PEK :
A TENAGA
1 Pekerja Oh 0.040 65,000.00 2,600.00
2 Mandor Oh 0.004 97,000.00 388.00
Oh -
Oh -
B MATERIAL
1 kg -
2 m3 - -
3 m3 - -
II METHODE PELAKSANAAN
1 Whell loader mengangkut gravel dari tumpukan dan
menuangkannya ke alat pemecah batu
Batu /gravel dipecah dengan alat pemecah batu shgg
menghasilkan agregat batu pecah
III PERITUNGAN
III.1 HARGA SATUAN AGREGAT PRODUKSI STONE CRUS
1.a Kerja stone crusher memecah batu/gravel
- waktu kerja stone crusher TSt 1.00 Jam
- Produksi Stone crusher 1 jam = (Fa1xCp1):D3 Qb 19.44 M3/Jam Batu Pecah
- Kebutuhan batu/gravel 1 jam = (Fa1xCp1):D1 Qg 19.44 M3/Jam
Harga
No Uraian Kode Satuan Satuan Keterangan
(Rp)
I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L 20.00 Km
Harga satuan pasir di quary Rp M01 1.00 M3 320,000.00
Harga satuan dasar excavator Rp E10 1.00 Jam 515,541.04
Harga satuan dasar Dump truck Rp E08 1.00 Jam 287,000.00
II Urutan kerja
Pasir digali dengan excavator
Excavator memuat pasir ke dalam truck
Dump Truck mengangkut pasir ke proyek
III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
waktu siklus Ts1
-Menggali memuat T1 0.50 Menit
-Lain-lain T2 0.50 Menit
TS1 1.00
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 41.68 M3/Jam
TS1
Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 Rp1 12,368.26 M3/Jam
DUMP TRUCK (E08)
Kapasitas bak V 4.00 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan Rata-rata bermuatan V1 25.00 Km/Jam
Kecepatan Rata-rata kosong V2 30.00 Km/Jam
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 48.00 Menit
- waktu tempuh kosong=(L/V2)x 60 T2 40.00 Menit
-muat = (V/Q1)x60 T3 5.76 Menit
-Lain-lain T4 1.00 Menit
Ts2 94.76 Menit
Kapasitas produksi / perjam =
V*Fax60
Ts2 Q2 2.10 M3/jam
I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L 20.00 Km
Harga satuan pasir di quary Rp M01 1.00 M3 240,000.00
Harga satuan dasar excavator Rp E10 1.00 Jam 515,541.04
Harga satuan dasar Dump truck Rp E08 1.00 Jam 234,480.76
II Urutan kerja
Batu kali digali dengan excavator
Excavator memuat Batu kali ke dalam truck
Dump Truck mengangkut Batu kali ke proyek
III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.75 -
Faktor efisiensi alat Fa 0.83 -
waktu siklus Ts1
-Menggali memuat T1 0.75 Menit
-Lain-lain T2 0.50 Menit
TS1 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 27.79 M3/Jam
TS1
Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 Rp1 18,552.38 M3/Jam
I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L 25.00 Km
Harga satuan Batu belah di quary Rp M06 1.00 M3 245,000.00
Harga satuan dasar excavator Rp E10 1.00 Jam 515,541.04
Harga satuan dasar Dump truck Rp E06 1.00 Jam 234,480.76
Harga satuan dasar Whell Loader Rp E15 1.00 Jam 515,113.70
Harga satuan Upah Pekerja Rp L01 1.00 Jam 9,285.71
II Urutan kerja
1 Batu Kali digali dengan excavator
2 Batu Kali di belah oleh pekerja
3 whell Loader memuat batu belah ke dalam truck
4 Dump Truck mengangkut Batu belah ke proyek
III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.75 -
Faktor efisiensi alat Fa 0.83 -
waktu siklus Ts1
-Menggali memuat T1 0.75 Menit
-Lain-lain T2 0.50 Menit
TS1 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 27.79 M3/Jam
TS1
3.d PEKERJA
Produksi menentukan : Excavator Q1 27.79 M3/jam
Hasil galian batu / hari = Q1 x 7 jam Qt 194.52 M3/ 7 jam
Kebutuhan pekerja P 15 Org
Biaya pekerja ./ M3 =
((7 jam x P):Qt) x RpL01 Rp4 5,012.37 Rupiah
I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L 25.00 Km
Harga satuan Gravel di quary Rp M7 1.00 M3 265,000.00
Harga satuan dasar excavator Rp E10 1.00 Jam 515,541.04
Harga satuan dasar Dump truck Rp E08 1.00 Jam 234,480.76
II Urutan kerja
Gravel digali dengan excavator
Excavator memuat Gravel ke dalam truck
Dump Truck mengangkut Gravel ke proyek
III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.75 -
Faktor efisiensi alat Fa 0.83 -
waktu siklus Ts1
-Menggali memuat T1 0.75 Menit
-Lain-lain T2 0.50 Menit
TS1 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
TS1 Q1 27.79 M3/Jam
I Asumsi
1 Menggunakan alat berat (Mekanik)
2 Kondisi jalan sedang / baik
3 Jarak Quary ke loksasi proyek L 20.00 Km
4 Harga satuan Sirtu di quary Rp M16 1.00 M3 175,000.00
5 Harga satuan dasar excavator Rp E10 1.00 Jam 515,541.04
6 Harga satuan dasar Dump truck Rp E08 1.00 Jam 234,480.76
II Urutan kerja
Sirtu digali dengan excavator
Excavator memuat Sirtu ke dalam truck
Dump Truck mengangkut Sirtu ke proyek
III Perhitungan
3a EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
waktu siklus Ts1
-Menggali memuat T1 0.50 Menit
-Lain-lain T2 0.50 Menit
TS1 1.00
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 41.68 M3/Jam
TS1
I Asumsi
1 Menggunakan alat berat (Mekanik)
2 Kondisi jalan sedang / baik
3 Jarak Quary ke loksasi proyek L 15.00 Km
4 Harga satuan Pasir urug di quary Rp M16 1.00 M3 150,000.00
5 Harga satuan dasar excavator Rp E10 1.00 Jam 515,541.04
6 Harga satuan dasar Dump truck Rp E08 1.00 Jam 234,480.76
II Urutan kerja
1 Pasir urug digali dengan excavator
2 Excavator memuat Pasir urug ke dalam truck
3 Dump Truck mengangkut Pasir urug ke proyek
III Perhitungan
3a EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
waktu siklus Ts1
-Menggali memuat T1 0.50 Menit
-Lain-lain T2 0.50 Menit
TS1 1.00
Kap. Prod/jam =
V x Fb x Fa x 60
TS1
Q1 41.68 M3/Jam
(12,5%) x B'
3 Perawatan dan perbaikan = K 307,546.894 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan ASPAL FINISHER E02
Tenaga Pw 72.40 Hp
Kapasitas Cp 10.00 Ton
Alat baru : A. Umur Eknomi A 6.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 4,094,937,525.00 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 6.00 Tahun
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam
C. Harga alat (*) B' 4,094,937,525.00 Rupiah
B Biaya pasti perjam kerja
1 Nilai sisa alat = 10% x B C 409,493,752.50 Rupiah
2 i x (1+i)^ A'
Faktor angsuran modal = D 0.301 -
(1+i )^A'-1
3 Biaya pasti perjam kerja
( B-C)x D
a. Biaya pengembalian modal = E 554,117.06 Rupiah
W'
0,002 x B
b. Asuransi dll F 4,094.94 Rupiah
W'
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 255,933.60 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan ASPAL SPRAYER E02
Tenaga Pw 4.00 Hp
Kapasitas Cp - Liter
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 307,520,090.00 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 307,520,090.00 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 19,220.01 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan BULLDOZER 100-150 HP E04
Tenaga Pw 150.00 Hp
Kapasitas Cp - -
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 2,464,072,325.00 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 2,464,072,325.00 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 154,004.52 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan COMPRESOR 4000-6500 L\M E05
Tenaga Pw 60.00 Hp
Kapasitas Cp - -
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 142,601,587.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 142,601,587.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 8,912.60 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan CONCRETE MIXER 03-06 M3 E06
Tenaga Pw 20.00 Hp
Kapasitas Cp 500.00 Liter
Alat baru : A. Umur Eknomi A 4.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 57,670,087.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 4.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 57,670,087.50 Rupiah Alat baru
B Biaya pasti perjam kerja
1 Nilai sisa alat = 10% x B C 5,767,008.75 Rupiah
2 i x (1+i)^ A' 1.72800
Faktor angsuran modal = D 0.386 -
(1+i )^A'-1
3 Biaya pasti perjam kerja
( B-C)x D
a. Biaya pengembalian modal = E 10,024.80 Rupiah
W'
0,002 x B
b. Asuransi dll F 57.67 Rupiah
W'
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 3,604.38 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan CRANE 10-15 TON E07
Tenaga Pw 138.00 Hp
Kapasitas Cp 15.00 Liter
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 358,601.37 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 358,601.37 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 22.41 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan DUMP TRUCK 3-4 M3 E07
Tenaga Pw 100.00 Hp
Kapasitas Cp 4.00 Ton
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 304,077,012.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 304,077,012.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 19,004.81 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan EXCAVATOR 80-140 HP E07
Tenaga Pw 133.00 Hp
Kapasitas Cp 0.93 m3
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 1,433,228,287.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 1,433,228,287.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 89,576.77 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan GENERATOR SET E07
Tenaga Pw 180.00 Hp
Kapasitas Cp 395.00 Liter
Alat baru : A. Umur Eknomi A 5.00 KVA
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 414,612.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 414,612.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 25.91 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan MOTOR GRADER > 100 HP E07
Tenaga Pw 135.00 Hp
Kapasitas Cp 800.00 -
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 2,149,842,482.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 2,149,842,482.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 134,365.16 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan Track Loader E14
Tenaga Pw 70.00 Hp
Kapasitas Cp 0.80 M3
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 132,629,875.00 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 132,629,875.00 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 8,289.37 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan Wheel Loader 1,0 - 1,6 M3 E14
Tenaga Pw 96.00 Hp
Kapasitas Cp 1.50 M3
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 1,637,975,112.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 1,637,975,112.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 102,373.44 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan Three Whell Roller 6-8 T M3 E16
Tenaga Pw 55.00 Hp
Kapasitas Cp 8.00 Ton
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 496,484,375.00 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 496,484,375.00 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 31,030.27 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan STONE CRUSHER E21
Tenaga Pw 220.00 Hp
Kapasitas Cp 50.00 Ton/jam
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 1,466,122,587.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 1,466,122,587.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 91,632.66 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan Vibro Roller 5-8 T E19
Tenaga Pw 82.00 Hp
Kapasitas Cp 7.05 M3
Alat baru : A. Umur Eknomi A 4.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 1,637,975,112.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 4.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 1,637,975,112.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 102,373.44 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
A URAIAN PERALATAN
Jenis peralatan Water Tanker 3000-4500 L E23
Tenaga Pw 100.00 Hp
Kapasitas Cp 5,000.00 Liter
Alat baru : A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 142,601,587.50 Rupiah
Alat yang dipakai : A. Umur Eknomi A' 5.00 Tahun Alat baru
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam Alat baru
C. Harga alat (*) B' 142,601,587.50 Rupiah Alat baru
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 8,912.60 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
(12,5%-17,5%) x B'
3 Perawatan dan perbaikan = K 655.36 Rupiah
W'
4 Operator = ( 1 Org/Jam) x U1 L 13,857.14 Rupiah
5 Pembantu Operator = ( 3 Org/Jam) x U1 M 36,000.00 Rupiah
E Lain-lain
1 Tingkat suku bunga i 20.00 % /Thn
2 Upah operator / sopir U1 13,857.14 Rp/Jam
3 Upah Pembantu operator / sopir U2 12,000.00 Rp/Jam
4 Bahan bakar bensin Mb 7,400.00 Ltr
5 Bahan bakar solar Ms 6,900.00 Ltr
6 Minyak pelumas Mp 33,310.00 Ltr
JARAK RATA-RATA
DARI SUMBER BAHAN
Harga Jarak
No Uraian Kode Satuan Satuan Quary Keterangan
(Rp) (Km)
Harga Harga
No Uraian Kode Satuan Satuan Satuan
(Rp) (Rp)
80,000.00 72,000.00
93,000.00 83,700.00
106,000.00 95,400.00
106,000.00 95,400.00
Jam kerja perhari 7 Jam 100,000.00 90,000.00
100,000.00 90,000.00
87,000.00 78,300.00
106,000.00 95,400.00
93,000.00 83,700.00
Beton DPT
STA Keliling Luas Panjang DPT Bekisting Beton DPT
8+950 17.1 4 50 855 200
8+975 17.1 4 50 855 200
8+992 17.1 4 50 855 200
9+648 17.1 4 50 855 200
9+808 17.1 4 50 855 200
Beton Drainase
Tinggi Drainase Keliling Luas Panjang DPT Bekisting Beton DPT
1 12.1 12 50 605 600
Pembesian
STA 8+950 Kiri
Jenis Diameter Panjang (m) Jumlah Total Panjang Jumlah tul/batang (12 m)
wall stem check (front) 16 5.5 10 55 5
wall stem check (back) 16 6 10 60 5
wall hell check 19 3 5 15 2
wall jum check 36 3 5 15 2
Spread footing 0 0
Berat Per batang (kg) Total Besi (kg) STA 9+808 Kanan
19 57 Jenis Diameter Panjang (m)
19 95 wall stem check (front) 16 5.5
26.8 53.6 wall stem check (back) 16 6
75.72 151.44 wall hell check 16 3
0 wall jum check 36 3
Spread footing
2180.24
Jumlah Total PanjangJumlah tul/batang (12
Berat
m) Per batang (kg)Total Besi (kg)
5 27.5 3 19 57
5 30 3 19 57
5 15 2 26.8 53.6
5 15 2 75.72 151.44
0 0 0