NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH HARGA (Rp) BOBOT (%)
SATUAN (Rp)
I PEKERJAAN PERSIAPAN
1 Ulit Set / Bowplank 350.2 m' 14,373 5033424.6 0.70150
2 IMB 0 ls 0 0 0.00000
3 Air Kerja 1 ls 500,000 500000 0.06968
4 Papan Nama Proyek 1 ls 250,000 250000 0.03484
JUMLAH I 5783424.6 0.80603
II PEKERJAAN TANAH URUGAN DAN BONGKARAN
1 Bongkaran / Pembersihan Lokasi 447 m2 7,000 3129000 0.43608
2 Galian Pondasi Tanah Biasa 172.14 m3 25,623 4410743.22 0.61472
3 Urugan Kembali 17.21 m3 9,108 156748.68 0.02185
4 Urugan Pasir Bawah 10.76 m3 80,762 868999.12 0.12111
5 Urugan Pasir Bawah Lantai 39.42 m3 80,762 3183638.04 0.44370
JUMLAH II 11749129.06 1.63746
III PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan Batu Bata 1ps : 4ps 647.4 m2 65,089 42138618.6 5.87279
2 Pasangan Pondasi Batu 105.48 m3 405,031 42722669.88 5.95419
3 Pasangan Batu Kosong 17.14 m3 90,508 1551307.12 0.21620
4 Sponengan 1702.8 m' 5,719 9738313.2 1.35721
5 Pekerjaan Plesteran 1ps : 3ps 1294.8 m2 19,999 25894705.2 3.60890
JUMLAH III 122045614 17.00930
IV PEKERJAAN BETON BERTULANG 1PC : 2PS : 3KR
1 Kolom 15/15 5.93 m3 2,690,001 15951705.93 2.22316
2 Kolom Praktis 12/12 0.88 m3 2,690,001 2367200.88 0.32991
3 Balok Lantai 12/12 2.01 m3 2,890,031 5808962.31 0.80959
4 Kolom Tiang Teras 15/15 2.23 m3 2,680,001 5976402.23 0.83292
5 Ring Balok 12/18 4.93 m3 2,890,031 14247852.83 1.98570
6 Sloof 12/18 5.42 m3 2,890,031 15663968.02 2.18306
JUMLAH IV 60016092.2 8.36434
V PEKERJAAN KUSEN
1 Kusen Kayu Kamper 0.81 m3 5,001,040 4050842.4 0.56456
2 Daun Pintu Panel Kayu Kamper 0.14 m3 4,206,290 588880.6 0.08207
3 Daun Jendela Kaca Dan Kayu Kamper 0.1 m3 4,206,290 420629 0.05862
4 Jalusi Kayu Kamper 0.08 m3 4,002,983 320238.64 0.04463
JUMLAH V 5380590.64 0.74988
VI PEKERJAAN RANGKA ATAP
1 Rangka Baja Ringan 935.61 m2 143,000 133792230 18.64640
2 Pasang Eternit 685.41 m2 250,262 171532077.42 23.90615
3 Lisplank Kayu Kamper 189.91 m' 63,179 11998323.89 1.67219
JUMLAH VI 317322631.31 44.22474
VII PEKERJAAN PENUTUP ATAP
1 Atap Genteng Metal 935.61 m2 77,000 72041970 10.04037
2 Genteng Nok (Kerpus) Metal 72.55 m' 64,800 4701240 0.65520
JUMLAH VII 76743210 10.69558
VIII PEKERJAAN LANTAI
1 Pasang Kramik Polos 30/30 623.9 m2 106,369 66363619.1 9.24898916616
2 Pasang Ubin Plin 24.4 m2 106,369 2595403.6 0.3617171592472
JUMLAH VIII 68959022.7 9.6107063254071
IX PEKERJAAN KACA
1 Kaca Mati 5mm 45.7 m2 73,700 3368090 0.4694052003661
JUMLAH IX 3368090 0.4694052003661
X PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Slot Pintu Putar 2x 10 ttk 66,839 668390 0.0931524222549
2 Engsel Pintu Nilon 32 ttk 19,718 630976 0.0879380942036
3 Sait Pintu 12cm 10 ttk 16,789 167890 0.0233985549939
4 Engsel Jendela 258 ttk 16,459 4246422 0.5918168961485
5 Sait Jendela 4cm 129 ttk 14,589 1881981 0.2622886171065
6 Handel 129 ttk 10,134 1307286 0.1821943139185
7 Hak Angin 258 ttk 16,404 4232232 0.5898392590327
JUMLAH X 13135177 1.8306281576587
XI PENGERJAAN PENGECETAN
1 Cat Tembok Batu 1294.8 m2 15,100 19551480 2.7248578235299
2 Cat Genteng dihilangkan m2 0 0 0
3 Cat Plafond 685.41 m2 12,625 8653301.25 1.2059964570674
4 Cat Kusen Baru 87.5 m2 28,661 2507837.5 0.3495132149595
5 Cat Lisplank 34.18 m2 28,661 979632.98 0.136529847855
JUMLAH XI 31692251.73 4.4168973434118
XII INSTALASI LISTRIK
1 Instalasi Titik Lampu Ruang 32 ttk 23,279 744928 0.1038193982638
2 Instalasi Stop Kontak 20 ttk 19,539 390780 0.0544623701264
3 Lampu Pijar 25 Watt 32 ttk 6,000 192000 0.0267587263019
JUMLAH XII 1327708 0.1850404946921
XIII PEKERJAAN HALAMAN DAN LINGKUNGAN
1 Pasangan Pavingblok dihilangkan m2 0 0 0
JUMLAH XIII 0 0
TIME SCHEDULE
PROYEK PEMBANGUNAN SEKOLAH DASAR