NO. NAMA PEKERJAAN / KEGIATAN VOLUME SATUAN BOBOT SKALA
1 2 3 4 5 6 7 8 9 10 11 12

A Pekerjaan Persiapan
100
1 Pengukuran dan Bowplank 147.5 m2 0.3823 0.3823
2 Desain Perencanaan 176 m2 1.1360 1.1360
3 Sumur Bor 1 Titik 1.0757 1.0757
4 Laporan dan Dokumentasi 1 ls 0.2151 0.0717 0.0717 0.0717

B Pekerjaan Tanah
1 Galian Tanah Pondasi 42.126 m3 0.6566 0.6566
2 Urugan Pasir Pondasi 3.009 m3 0.2178 0.2178
3 Pasangan Batu Kosong 12.036 m3 1.8609 1.8609
4 Pasangan Batu Pecah Pondasi 27.081 m3 4.2217 4.2217
5 Urugan Sirtu Leveling 88 m3 3.1849 3.1849

C Pekerjaan Struktur
1 Sloof
- Bekisting 40.12 m2 0.2637 0.2637
- Pembesian 251.99372 kg 0.8860 0.4430 0.4430
- Beton K.175 3.009 m3 0.5831 0.2916 0.2916
2 Kolom
- Bekisting 96 m2 1.2882 1.2882
- Pembesian 401.984 kg 1.4134 0.7067 0.7067
- Beton K.175 3.6 m3 0.6977 0.3488 0.3488
3 Ring Balok
- Bekisting 30.09 m2 0.4166 0.4166
- Pembesian 251.99372 kg 0.8860 0.4430 0.4430
- Beton K.175 2.25675 m3 0.4374 75 0.2187 0.2187
4 Kanopi Beton
- Bekisting 30.3 m2 0.6308 0.6308
- Pembesian 315 kg 1.1075 0.5538 0.5538
- Beton K.225 4.545 m3 0.9351 0.4676 0.4676

D Pekerjaan Dinding
1 Pasangan Bata Merah 349.05 m2 7.0199 2.3400 2.3400 2.3400
2 Plesteran 698.1 m2 5.5034 5.5034
3 Acian 698.1 m2 3.3023 3.3023
4 Roster Dinding 4.5 m2 0.1640 0.1640
5 Keramik Dinding WC 38.25 m2 1.4947 1.4947
6 Keramik Dinding Dapur 5 m2 0.1954 0.1954
7 Batu Alam Dinding Fasad 19.2 m2 0.6400 0.6400
8 Pengecatan 698.1 m2 3.1329 1.5665 1.5665
JADWAL RENCANA PEKERJAAN
RUMAH SATU LANTAI
J HOUSE (Mr. Jajang)

MINGGU KE :
NO. NAMA PEKERJAAN / KEGIATAN VOLUME SATUAN BOBOT SKALA
1 2 3 4 5 6 7 8 9 10 11 12

E Pekerjaan Pintu dan Jendela


1 Jendela Double Uk.160x150cm 6 set 1.5491 1.5491
2 Jendela Single Uk.80x150cm 1 set 0.1291 0.1291
3 Jendela WC 3 set 0.1614 0.1614
4 Jendela Atas 1 set 0.0861 0.0861
5 Jendela Sudut 1 set 0.5379 0.5379
6 Pintu Kamar 5 set 1.6136 1.6136
7 Pintu WC 3 set 0.3873 0.3873
8 Pintu Utama 1 set 0.4303 50 0.4303
9 Pintu Geser 1 set 0.5594 0.5594

F Pekerjaan Atap
1 Rangka Atap Baja Ringan 286 m2 9.8451 4.9225 4.9225
2 Penutup Atap Genteng Metal 286 m2 8.1132 4.0566 4.0566
3 Listplank 54 m' 0.6867 0.6867
4 Rangka Plafond 259.25 m2 3.8162 1.9081 1.9081
5 Plafond Gypsum 259.25 m2 3.3466 3.3466
6 List Gypsum 180.54 m2 1.1696 1.1696
7 Pengecatan 259.25 m2 1.1635 1.1635

G Pekerjaan Instalasi
1 Instalasi Listrik
- Pasang Sambungan (MCB) 1 set 0.6454 0.6454
- Sikring Listrik 1 set 0.0645 0.0645
- Lampu 20 Watt 15 set 0.4841 0.4841
- Lampu 10 Watt 3 set 0.0775 0.0775
- Lampu Utama 2 set 0.2582 0.2582
- Lampu Down Light 4 set 0.1033 0.1033
- Lampu Fasad 2 set 0.1291 0.1291
- Lampu LED Teras 30 m' 0.3873 0.3873
- Stop Kontak 14 set 0.1205 0.1205
- Saklar Single 7 set 0.0753 0.0753
- Saklar Double 7 set 0.0904 25 0.0904
- Exhause Fan WC 1 set 0.1506 0.1506
2 Instalasi Air
- Instalasi Air Kotor 3" 1 ls 0.3227 0.3227
- Instalasi Air Bekas 2" 1 ls 0.2151 0.2151
- Instalasi Air Bersih 3/4" 1 ls 0.4303 0.4303
- Washtafel 1 set 0.1291 0.1291
- Sink 1 set 0.1076 0.1076
- Closet Duduk 2 set 0.8606 0.8606
- Floordrain 4 set 0.0430 0.0430
- Bak Terazo 2 bh 0.3227 0.3227
- Shower 2 set 0.1721 0.1721
- Jet Pump 1 set 0.4303 0.4303
JADWAL RENCANA PEKERJAAN
RUMAH SATU LANTAI
J HOUSE (Mr. Jajang)

MINGGU KE :
NO. NAMA PEKERJAAN / KEGIATAN VOLUME SATUAN BOBOT SKALA
1 2 3 4 5 6 7 8 9 10 11 12

H Pekerjaan Lantai
1 Urugan Pasir Lantai 8.8 m2 0.6369 0.6369
2 Pasangan Granit Tile 60x60cm 173.3 m2 7.8598 2.6199 2.6199 2.6199
3 Pasangan Keramik WC 20x20cm 7.2 m2 0.2814 0.2814

I Pekerjaan Lain-lain
1 Kanopi Garasi Baja Ringan 17.5 m2 1.1295 1.1295
2 Gerbang 5.25 m2 1.3554 1.3554
3 Pagar 1 ls 3.3042 3.3042
4 Septictank dan Bak Kontrol 1 ls' 0.4303 0.2151 0.2151
5 Paving / Grass Block 67.5 m2 1.8390 0.9195 0.9195
0

BOBOT RENCANA MINGGUAN 3.5733 7.2221 8.8998 3.9739 9.6998 12.6966 14.9477 16.0564 6.9328 6.4243 2.0829 7.4903
BOBOT KOMULATIF RENCANA MINGGUAN 0 3.5733 10.7954 19.6952 23.6692 33.3690 46.0656 61.0133 77.0697 84.0025 90.4268 92.5097 100.00
BOBOT REALISASI MINGGUAN
BOBO KOMULATIF REALISASI MINGGUAN

Kuningan, 10 Juli 2023

Disetujui Oleh : Dibuat Oleh :


Pemilik Pekerjaan Marantica Team

Jajang Abdul Azis Lutfi Marantica, ST., MT.


Owner J House Ketua Tim

Anda mungkin juga menyukai