Jumlah 114,637,734
Dibulatkan 114,600,000
DATA HITUNG PEKERJAAN
Pekerjaan : Rehabilitasi Mesjid Jami Assyarif Desa Jayasari
2 TPT Samping
1. Galian Pondasi 0.8 0.5 25 10 1 10
2. Pondasi 0.5 0.5 0.5 25 6.25 2 12.5
2. Pasangan Batu 0.5 0.3 2 25 20 1 20
3. Kolom 0.15 0.15 2.5 0.05625 8 0.45
4. Balok 0.15 0.15 25 0.5625 1 0.5625
5. Plesteran dan Acian 2 25 50 1 50
3 Pagar
1. Galian Pondasi 0.5 0.5 0.5 47 11.75 1 11.75
2. Pasangan Batu 0.5 0.3 0.5 47 9.4 1 9.4
3. Pasangan Bata 1.5 33 49.5 1 49.5
3. Kolom 0.15 0.25 2 0.075 17 1.275
4. Balok 0.15 0.15 47 1.0575 1 1.0575
5. Plesteran dan Acian 1.5 47 70.5 2 141
a Bahan Material
Bata Merah 70 Bh 850 59,500
Semen Portland 0.1936 zak 68,000 13,165
Pasir Pasang 0.045 M3 260,000 11,700
b Tenaga Kerja
Pekerja 0.3 Oh 60,000 18,000
Tukang Batu 0.1 Oh 80,000 8,000
Jumlah 110,365
F003 Membuat 1 M2 Plesteran 1 PC : 3 PP, tebal 15 mm
A Bahan Material
Semen Portland 0.15552 zak 68,000 10,575
Pasir Pasang 0.023 M3 260,000 5,980
B Tenaga Kerja -
Pekerja 0.3 Oh 60,000 18,000
Tukang Batu 0.15 Oh 80,000 12,000
jumlah 46,555
F021 Membuat 1 M2 Acian
A Bahan Material
Semen portland 0.065 zak 68,000 4,420
B Tenaga Kerja -
Pekerja 0.2 Oh 60,000 12,000
Tukang Batu 0.1 Oh 80,000 8,000
jumlah 24,420
D002 1 M3 Membuat Beton Site Mix, 1 Pc : 3 Ps : 5 Kr
A Bahan Material
Semen portland 6.76 Kg 68,000 459,680
Pasir Beton 0,6500 M3 260,000 #VALUE!
Koral Beton (maksimum 30 mm) 0,7500 M3 260,000 #VALUE!
B Tenaga Kerja
Pekerja 1.65 Oh 60,000 99,000
Tukang Batu 0,2500 Oh 80,000 #VALUE!
Jumlah 942,680
D028 1 M3 Membuat Balok Beton Bertulang (100 Kg Besi + Bekisting )
a Bahan Material
Kayu kelas III 0,3200 M3 1,500,000 #VALUE!
Paku 5 cm - 12 cm 3.2 Kg 18,000 57,600
Minyak Bekisting 1.6 Lt 25,000 40,000
Besi Beton polos 157.5 Kg 12,000 1,890,000
Kawat Beton 2.25 Kg 17,000 38,250
Semen Portland 6.72 zak 68,000 456,960
Pasir Beton 0,5400 M3 260,000 #VALUE!
Koral Beton 0,8100 M3 260,000 #VALUE!
Kayu kelas II balok 0.12 m3 1,500,000 180,000
Plywood 9 mm 2.8 lbr 90,000 252,000
B Tenaga Kerja -
Pekerja 5.3 Oh 60,000 318,000
Tukang Batu 0,2750 Oh 80,000 #VALUE!
Tukang Kayu 1.3 Oh 80,000 104,000
Tukang Besi 1.05 Oh 80,000 84,000
JUMLAH Rp : 4,273,810
D041 1 M³ Beton Plat Bertulang Tebal = 8 cm
A Bahan Material
Cor beton K-175 1 M3 928,360 928,360
Besi Beton pokok, Ø 10" 15 bh, cincin Ø 8" - 15 bh 93 Kg 12,000 1,116,000
Polywood 2.8 lbr 90,000 252,000
JUMLAH Rp : 2,296,360
D007 Membuat 1 M³ Beton Mutu f'c = 14,5 Mpa (K 175), Slump (12 + 2) cm, w/c = 0.66
a Bahan Material
Semen portland 6.52 zak 68,000 443,360
Pasir Beton 0.6 m3 260,000 156,000
Koral Beton (maksimum 30 mm) 0.8 m3 260,000 208,000
b Tenaga Kerja -
Pekerja 1.65 Oh 60,000 99,000
Tukang Batu 0,2750 Oh 80,000 #VALUE!
Jumlah 928,360
Harga Satuan Upah dan Bahan
Pekerja Oh 60,000
Tukang OH 80,000