Anda di halaman 1dari 47

REKAPITULASI

PEKERJAAN : PEMBANGUNAN MENARA JAGA DI OBJEK WISATA PANTAI GEDAMBAAN


KABUPATEN : KOTABARU
PROVINSI : KALIMANTAN SELATAN
TA. : 2022

JUMLAH NILAI
HARGA BOBOT
No. URAIAN PEKERJAAN
(Rp.) %

I PEKERJAAN PERSIAPAN 1,148,000.00 0.64

II PEKERJAAN TANAH DAN PENUTUP 2,307,985.86 1.28

III PEKERJAAN ALUMINIUM - -

IV PEKERJAAN BETON/BETON BERTULANG 128,871,594.42 71.69

V PEKERJAAN PLESTERAN 9,671,375.29 5.38

VII PEKERJAAN LAIN-LAIN 37,767,623.93 21.01

JUMLAH 179,766,579.50
PPN 11 % 19,774,323.75 100.00
TOTAL 199,540,903.25
DIBULATKAN 199,540,000.00

TERBILANG : SERATUS SEMBILAN PULUH SEMBILAN JUTA LIMA RATUS EMPAT PULUH RIBU RUPIAH

Kotabaru, 31 mei 2022


Penawar
CV. MALEWA

HADASIAH
Direktur
RENCANA ANGGARAN BIAYA
KEGIATAN : PENGELOLAAN DESTINASI PARIWISATA KABUPATEN/KOTA
PEKERJAAN : PEMBANGUNAN MENARA JAGA DI OBJEK WISATA PANTAI GEDAMBAAN
KABUPATEN : KOTABARU
PROVINSI : KALIMANTAN SELATAN

SA HARGA JUMLAH
No. ITEM PEKERJAAN KODE ANALISA VOLUME TU SATUAN HARGA
AN (Rp.) (Rp.)

I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lokasi - 1.00 Ls 145,000.00 145,000.00
2 Papan Nama Pekerjaan - 1.00 Bh 245,000.00 245,000.00
3 SMKK - 1.00 Ls 758,000.00 758,000.00
JUMLAH (I) 1,148,000.00
II. PEKERJAAN TANAH DAN PENUTUP
1 Pek. Galian Tanah A.1.5.1.1. 11.40 m3 132,178.40 1,506,833.76
2 Pek. Urugan Tanah Kembali A.1.5.1. 3.80 m3 210,829.50 801,152.10
JUMLAH (II) 2,307,985.86

III PEKERJAAN BETON/BETON BERTULANG


1 Pek. Cor Rabat K-175 A.4.1.1.5. 0.58 m3 1,151,233.59 663,110.55
2 Pek. Lantai Beton Bertulang Lt. 3 K-225
a. Bekisting A.4.1.1.24. 30.52 Kg 373,620.50 11,402,897.66
b. Pembesian A.4.1.1.15 332.42 Kg 18,799.55 6,249,424.17
c. Beton Bertulang A.4.1.1.7. 2.04 m3 1,217,385.50 2,477,622.96
3 Pek. Pondasi Foot Plat K-225
a. Bekisting Pondasi Foot Plat A.4.1.1.18. 7.68 m2 87,400.50 671,235.84
b. Pembesian A.4.1.1.15 283.92 Kg 18,799.55 5,337,568.24
c. Beton Bertulang A.4.1.1.7. 2.30 m3 1,217,385.50 2,804,856.18
4 Pek. Kolom Pandestel 30/30 K-225
a. Bekisting Kolom Pandestel A.4.1.1.22. 4.80 m2 153,810.25 738,289.20
b. Pembesian A.4.1.1.15 68.21 Kg 18,799.55 1,282,253.78
c. Beton Bertulang A.4.1.1.7. 0.36 m3 1,217,385.50 438,258.78
5 Pek. Sloof 30/35 K-225 (Sloof 1)
a. Bekisting A.4.1.1.21. 12.80 m2 91,525.50 1,171,526.40
b. Pembesian A.4.1.1.15 257.20 Kg 18,799.55 4,835,298.13
c. Beton Bertulang A.4.1.1.7. 1.34 m3 1,217,385.50 1,636,166.11
6 Pek. Sloof 30/35 K-225 (Sloof 2)
a. Bekisting A.4.1.1.21. 13.64 m2 91,525.50 1,248,407.82
b. Pembesian A.4.1.1.15 19.54 Kg 18,799.55 367,275.23
c. Beton Bertulang A.4.1.1.7. 1.47 m3 1,217,385.50 1,789,556.68
7 Pek. Kolom Lt. 1 30/30 K-225
a. Bekisting A.4.1.1.22. 15.12 m2 153,810.25 2,325,610.98
b. Pembesian A.4.1.1.15 147.63 kg 18,799.55 2,775,441.18
c. Beton Bertulang A.4.1.1.7. 1.13 m3 1,217,385.50 1,380,515.15
8 Pek. Balok Lt. 1 30/35 K-225
a. Bekisting A.4.1.1.23. 13.64 m2 157,275.25 2,145,234.41
b. Pembesian A.4.1.1.15 128.60 kg 18,799.55 2,417,649.06
c. Beton Bertulang A.4.1.1.7. 1.47 m3 1,217,385.50 1,789,556.68
9 Pek. Kolom Lt.2 30/30 K-225
a. Bekisting A.4.1.1.22. 13.44 m2 153,810.25 2,067,209.76
b. Pembesian A.4.1.1.15 134.18 kg 18,799.55 2,522,611.51
c. Beton Bertulang A.4.1.1.7. 1.01 m3 1,217,385.50 1,227,124.58
10 Pek. Balok Lt. 2 30/35 K-225
a. Bekisting A.4.1.1.23. 13.64 m2 157,275.25 2,145,234.41
b. Pembesian A.4.1.1.15 128.60 kg 18,799.55 2,417,649.06
c. Beton Bertulang A.4.1.1.7. 1.47 m3 1,217,385.50 1,789,556.68
11 Pek. Kolom Lt. 3 30/30 K-225
a. Bekisting A.4.1.1.22. 12.00 m2 153,810.25 1,845,723.00
b. Pembesian A.4.1.1.15 108.07 kg 18,799.55 2,031,707.56
c. Beton Bertulang A.4.1.1.7. 0.90 m3 1,217,385.50 1,095,646.95
12 Pek. Balok Lt. 3 30/35 K-225
a. Bekisting A.4.1.1.23. 11.60 m2 157,275.25 1,824,392.90
b. Pembesian A.4.1.1.15 128.60 kg 18,799.55 2,417,649.06
c. Beton Bertulang A.4.1.1.7. 1.05 m3 1,217,385.50 1,278,254.77
13 Pek. Dak K-225
a. Bekisting A.4.1.1.24. 69.60 m2 373,620.50 26,002,529.68
b. Pembesian A.4.1.1.15 794.97 kg 18,799.55 14,945,127.64
c. Beton Bertulang A.4.1.1.7. 6.57 m3 1,217,385.50 7,992,379.26
14 Kolom Praktis 10/10 (KP2)
a. Bekisting A.4.1.1.22. 4.80 m2 153,810.25 738,289.20
b. Pembesian A.4.1.1.15 23.65 kg 18,799.55 444,605.17
c. Beton Bertulang (K-175) A.4.1.1.7. 0.12 m3 1,151,233.59 138,148.03
JUMLAH (III) 128,871,594.42
IV PEKERJAAN PLESTERAN
1 Acian A.4.5.1.5. 145.41 m2 64,102.50 9,321,375.29
2 Penamaan Pada Bangunan - 1.00 Ls 350,000.00 350,000.00
JUMLAH (IV) 9,671,375.29
V PEKERJAAN LAIN-LAIN
1 Pagar Kayu - 20.43 m' 750,000.00 15,322,500.00
2 Plat Penutup - 1.00 Ls 700,000.00 700,000.00
3 Tangga Plat - 1.00 Ls 14,000,000.00 14,000,000.00
4 Pek. Cat Tembok A. 4.7.1.10. 145.60 m2 47,356.10 6,895,123.93
5 Titik Lampu 5.00 Bh 170,000.00 850,000.00
JUMLAH (V) 37,767,623.93
JUMLAH I s/d V 179,766,579.50
BACK UP VOLUME
UNIT KERJA : DINAS PARIWISATA PEMUDA DAN OLAHRAGA
SUB KEGIATAN : PENGELOLAAN DESTINASI PARIWISATA KABUPATEN/KOTA
PEKERJAAN : PEMBANGUNAN MENARA JAGA DI OBJEK WISATA PANTAI GEDAMBAAN
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN PERHITUNGAN JUMLAH

I PEKERJAAN PERSIAPAN
1. Pengukuran dan Pembersihan Lokasi = 1.00 Ls

2. Papan Nama Pekerjaan = 1.00 Bh

3. SMKK = 1.00 Ls

II PEKERJAAN TANAH DAN PENUTUP


1. Pek. Galian Tanah PxLxTxn 1.20 x 1.20 x 1.50 x 4.00 = 8.64 m3
PxLxTxn 2.30 x 0.30 x 1.00 x 4.00 = 2.76 m3
11.40 m3

2. Pek. Urugan Tanah Kembali 1/3 dari galian tanah = 3.80 m3

III PEKERJAAN BETON/BETON BERTULANG/DINDING


1. Pek. Cor Rabat K-175 PxLxTxn 1.20 x 1.20 x 0.10 x 4.00 = 0.58 m3

2. Pek. Lantai Beton Bertulang Lt. 3 K-225


a. Beton K-225 P x L x (( T1 + T2 ) / 2) 5.60 x 0.90 x (0.15+0.3)/2 = 0.81 m3
PxLxT 3.20 x 3.20 x 0.12 = 1.23 m3
2.04 m3
b. Bekisting PxLxn 5.60 x 0.90 x 2.00 = 10.08 m2
PxLxn 3.80 x 0.90 x 2.00 = 6.84 m2
PxL 3.20 x 3.20 = 10.24 m2
PxLxn 5.60 x 0.15 x 4.00 = 3.36 m2
30.52 m3
3. Pek. Pondasi Foot Plat K-225
a. Bekisting Pondasi Foot Plat PxLxn 1.20 x 0.40 x 16.00 = 7.68 m2
b. Beton Bertulang PxLxTxn 1.20 x 1.20 x 0.40 x 4.00 = 2.30 m3

4. Pek. Kolom Pandestel 30/30 K-225


a. Bekisting Kolom Pandestel PxLxn 0.30 x 1.00 x 16.00 = 4.80 m2
b. Beton Bertulang PxLxTxn 0.30 x 0.30 x 1.00 x 4.00 = 0.36 m3

5. Pek. Sloof 30/35 K-225 (Sloof 1)


a. Bekisting Sloof
PxLxn 3.80 x 0.35 x 4.00 = 5.32 m2
PxLxn 3.20 x 0.35 x 4.00 = 4.48 m2
PxLxn 2.50 x 0.30 x 4.00 = 3.00 m2
12.80 m2
b. Beton Bertulang
PxLxTxn 3.20 x 0.30 x 0.35 x 4.00 = 1.34 m3
1.34 m2

6. Pek. Sloof 30/35 K-225 (Sloof 2)


a. Bekisting Sloof
PxLxn 3.80 x 0.35 x 4.00 = 5.32 m2
PxLxn 3.20 x 0.35 x 4.00 = 4.48 m2
PxLxn 3.20 x 0.30 x 4.00 = 3.84 m2
13.64 m2
b. Beton Bertulang
PxLxTxn 3.80 x 0.30 x 0.35 x 2.00 = 0.80 m3
PxLxTxn 3.20 x 0.30 x 0.35 x 2.00 = 0.67 m3
1.47 m2

7. Pek. Kolom Lt. 1 30/30 K-225


a. Bekisting Kolom PxLxn 0.30 x 3.15 x 16.00 = 15.12 m3
b. Beton Bertulang PxLxTxn 0.30 x 0.30 x 3.15 x 4.00 = 1.13 m3

8. Pek. Balok Lt.1 30/35 K-225


a. Bekisting Balok
PxLxn 3.80 x 0.35 x 4.00 = 5.32 m2
PxLxn 3.20 x 0.35 x 4.00 = 4.48 m2
PxLxn 3.20 x 0.30 x 4.00 = 3.84 m2
13.64 m2

Page 3 of 47 BACK UP
NO URAIAN PEKERJAAN PERHITUNGAN JUMLAH
b. Beton Bertulang
PxLxTxn 3.80 x 0.30 x 0.35 x 2.00 = 0.80 m3
PxLxTxn 3.20 x 0.30 x 0.35 x 2.00 = 0.67 m3
1.47 m3

9. Pek. Kolom Lt. 2 30/30 K-225


a. Bekisting Kolom PxLxn 0.30 x 2.80 x 16.00 = 13.44 m3
b. Beton Bertulang PxLxTxn 0.30 x 0.30 x 2.80 x 4.00 = 1.01 m3

10. Pek. Balok Lt. 2 30/35 K-225


a. Bekisting Balok
PxLxn 3.80 x 0.35 x 4.00 = 5.32 m2
PxLxn 3.20 x 0.35 x 4.00 = 4.48 m2
PxLxn 3.20 x 0.30 x 4.00 = 3.84 m2
13.64 m2
b. Beton Bertulang
PxLxTxn 3.80 x 0.30 x 0.35 x 2.00 = 0.80 m3
PxLxTxn 3.20 x 0.30 x 0.35 x 2.00 = 0.67 m3
1.47 m3

11. Pek. Kolom Lt. 3 30/30 K-225


a. Bekisting Kolom PxLxn 0.30 x 2.50 x 16.00 = 12.00 m3
b. Beton Bertulang PxLxTxn 0.30 x 0.30 x 2.50 x 4.00 = 0.90 m3

12. Pek. Balok Lt. 3 25/30 K-225


a. Bekisting Balok
PxLxn 3.80 x 0.30 x 4.00 = 4.56 m2
PxLxn 3.20 x 0.30 x 4.00 = 3.84 m2
PxLxn 3.20 x 0.25 x 4.00 = 3.20 m2
11.60 m2
b. Beton Bertulang
PxLxTxn 3.80 x 0.25 x 0.30 x 2.00 = 0.57 m3
PxLxTxn 3.20 x 0.25 x 0.30 x 2.00 = 0.48 m3
1.05 m3

13. Pek. Dak K-225


a. Bekisting Dak PxLxn 0.80 x 6.20 x 4.00 = 19.84 m2
PxLxn 0.10 x 6.08 x 4.00 = 2.43 m2
PxLxn 0.48 x 5.96 x 4.00 = 11.44 m2
PxLxn 1.12 x 5.96 x 2.00 = 13.35 m2
PxLxn 1.12 x 3.20 x 2.00 = 7.17 m2
PxLxn 0.20 x 6.00 x 4.00 = 4.80 m2
PxL 3.25 x 3.25 = 10.56 m2
69.60 m3

b. Beton Bertulang PxLxT 6.00 x 6.00 x 0.12 = 4.32 m3


PxLxTxn 0.80 x 6.10 x 0.12 x 4.00 = 2.34 m3
Pengurang PxLxT 0.90 x 0.90 x 0.12 = 0.10 m3
6.57 m3

15. Kolom Praktis 10/10 (KP2)


Bekisting PxLxn 0.10 x 1.00 x 48.00 4.80 m2
Beton K-175 PxLxTxn 0.10 x 0.10 x 1.00 x 12.00 0.12 m3

IV PEKERJAAN PLESTERAN
1. Acian
Sloof PxLxn 3.80 x 0.35 x 4.00 5.32 m2
PxLxn 3.20 x 0.30 x 4.00 3.84 m2
Kolom lt. 1 PxLxn 3.15 x 0.30 x 16.00 15.12 m2
Balok lt.1 PxLxn 3.80 x 0.35 x 4.00 5.32 m2
PxLxn 3.20 x 0.35 x 4.00 4.48 m2
PxLxn 3.20 x 0.30 x 8.00 7.68 m2
Kolom lt. 2 PxLxn 2.80 x 0.30 x 16.00 13.44 m2
Lantai PxLxn 5.60 x 0.15 x 4.00 3.36 m2
PxLxn 0.90 x 5.60 x 2.00 10.08 m2
PxLxn 0.90 x 3.80 x 2.00 6.84 m2
Dinding PxLxn 2.80 x 3.15 x 8.00 0.00 m2
Kolom Lt. 3 PxLxn 2.50 x 0.30 x 16.00 12.00 m2
Balok lt. 3 PxLxn 3.80 x 0.23 x 2.00 1.75 m2
PxLxn 3.20 x 0.23 x 2.00 1.47 m2

Page 4 of 47 BACK UP
NO URAIAN PEKERJAAN PERHITUNGAN JUMLAH
PxLxn 3.20 x 0.30 x 4.00 3.84 m2
Kolom Praktis PxLxn 1.00 x 0.10 x 40.00 4.00 m2
Dak PxLxn 6.20 x 0.80 x 4.00 19.84 m2
PxLxn 6.20 x 0.12 x 8.00 5.95 m2
PxLxn 1.08 x 5.96 x 2.00 12.87 m2
PxLxn 1.08 x 3.80 x 2.00 8.21 m2
Pengurang (Kusen pada dinding) PxLxn 2.90 x 1.50 x 3.00 0.00 m2
PxLxn 0.80 x 2.00 x 1.00 0.00 m2
PxLxn 0.20 x 0.85 x 10.00 0.00 m2
145.41 m2

2. Penamaan Pada Bangunan 1.00 Ls

V PEKERJAAN LAIN-LAIN
1. Pagar GRC 20.43 m

2. Plat Penutup 1.00 Ls

3. Tangga Plat 1.00 Ls

4. Pek. Cat Tembok


Sloof PxLxn 3.80 x 0.35 x 4.00 5.32 m2
PxLxn 3.20 x 0.30 x 4.00 3.84 m2
Kolom lt. 1 PxLxn 3.15 x 0.30 x 16.00 15.12 m2
Balok lt.1 PxLxn 3.80 x 0.35 x 4.00 5.32 m2
PxLxn 3.20 x 0.35 x 4.00 4.48 m2
PxLxn 3.20 x 0.30 x 8.00 7.68 m2
Kolom lt. 2 PxLxn 2.80 x 0.30 x 16.00 13.44 m2
Lantai 3 PxLxn 5.60 x 0.15 x 4.00 3.36 m2
PxLxn 0.91 x 5.60 x 2.00 10.19 m2
PxLxn 0.91 x 3.80 x 2.00 6.92 m2
Kolom Lt. 3 PxLxn 2.50 x 0.30 x 16.00 12.00 m2
Balok lt. 3 PxLxn 3.80 x 0.23 x 2.00 1.75 m2
PxLxn 3.20 x 0.23 x 2.00 1.47 m2
PxLxn 3.20 x 0.30 x 4.00 3.84 m2
Kolom Praktis PxLxn 1.00 x 0.10 x 40.00 4.00 m2
Dak PxLxn 6.20 x 0.80 x 4.00 19.84 m2
PxLxn 6.20 x 0.12 x 8.00 5.95 m2
PxLxn 1.08 x 5.96 x 2.00 12.87 m2
PxLxn 1.08 x 3.80 x 2.00 8.21 m2
145.60 m2

5. Titik Lampu 5.00 Bh

Page 5 of 47 BACK UP
PERHITUNGAN PEMBESIAN MENARA JAGA

Dimensi
no item pekerjaan Sket/Ket Volume satuan
p n tul koef. dia². banyak

1 Pondasi Telapak Arah memanjang 2.52 8.00 0.010417 169.00 4.00 141.96 kg
Arah melintang 2.52 8.00 0.010417 169.00 4.00 141.96 kg
283.92 kg

2 Kolom Pandestel 30/30 Tulangan Pokok 1.92 4.00 0.010417 169.00 4.00 54.08 kg
Tulangan Pokok 1.92 2.00 0.006167 100.00 4.00 9.47
Sengkang 0.92 5.00 0.003950 64.00 4.00 4.65 kg
68.21 kg

3 Sloof 30/35 Tulangan Pokok 7.52 2.00 0.010417 169.00 8.00 211.81 kg
Sengkang 1.02 22.00 0.003950 64.00 8.00 45.39 kg
257.20 kg

4 Kolom Lt. 1 30/30 Tulangan Pokok 3.87 4.00 0.010417 169.00 4.00 109.01 kg
Tulangan Pokok 3.87 2.00 0.006167 100.00 4.00 19.09 kg
Sengkang 0.92 21.00 0.003950 64.00 4.00 19.54 kg
147.63 kg

5 Balok Lt. 1 30/35 Tulangan Pokok 7.52 2.00 0.010417 169.00 4.00 105.91 kg
Sengkang 1.02 22.00 0.003950 64.00 4.00 22.69 kg
128.60 kg

6 Kolom Lt. 2 30/30 Tulangan Pokok 3.52 4.00 0.010417 169.00 4.00 99.15 kg
Tulangan Pokok 3.52 2.00 0.006167 100.00 4.00 17.37 kg
Sengkang 0.92 19.00 0.003950 64.00 4.00 17.67 kg
134.18 kg

7 Balok Lt. 2 30/35 Tulangan Pokok 7.52 2.00 0.010417 169.00 4.00 105.91 kg
Sengkang 1.02 22.00 0.003950 64.00 4.00 22.69 kg
128.60 kg

8 Kolom Lt. 3 30/30 Tulangan Pokok 2.59 4.00 0.010417 169.00 4.00 72.95 kg
Tulangan Pokok 2.59 2.00 0.006167 100.00 4.00 12.78 kg
Sengkang 1.30 17.00 0.003950 64.00 4.00 22.34 kg
108.07 kg

9 Balok Lt. 3 25/30 Tulangan Pokok 7.52 2.00 0.010417 169.00 4.00 105.91 kg
Sengkang 1.02 22.00 0.003950 64.00 4.00 22.69 kg
128.60 kg

10 Dak Tulangan Pokok 0.98 41.00 0.006167 100.00 4.00 99.12 kg


7.22 41.00 0.006167 100.00 2.00 365.12 kg
6.54 41.00 0.006167 100.00 2.00 330.73 kg
794.97 kg

12 Kolom Praktis Tulangan Pokok 1.57 4.00 0.003950 64.00 12.00 19.05 kg
Sengkang 0.26 7.00 0.003950 64.00 10.00 4.60 kg
23.65 kg

13 Plat Lantai 3 Tulangan Pokok A 5.93 26.00 0.006167 100.00 1.00 95.09 kg
Tulangan Pokok B 7.92 26.00 0.006167 100.00 1.00 127.00 kg
Tulangan Pokok C 11.32 3.00 0.006167 100.00 1.00 20.94 kg
Tulangan Pokok D 10.76 3.00 0.006167 100.00 1.00 19.91 kg
Tulangan Pokok E 10.22 3.00 0.006167 100.00 1.00 18.91 kg
Tulangan Pokok F 9.66 3.00 0.006167 100.00 1.00 17.87 kg
Tulangan Pokok G 9.12 3.00 0.006167 100.00 1.00 16.87 kg
Tulangan Pokok H 8.56 3.00 0.006167 100.00 1.00 15.84 kg
332.42 kg
PERHITUNGAN PEMBESIAN MENARA AIR BAK BETON (RESERVOIR)

Dimensi
no item pekerjaan Sket/Ket Volume satuan
p n tul koef. dia². x

1 Pondasi Telapak Arah memanjang 2.00 7.00 0.01 144.00 8.00 99.43 kg
Arah melintang 2.00 7.00 0.01 144.00 8.00 99.43 kg
Arah memanjang 2.00 7.00 0.01 144.00 8.00 99.43 kg
Arah melintang 2.00 7.00 0.01 144.00 8.00 99.43 kg
397.72 kg

Kolom Utama 30/30 Tulangan Pokok 4.99 4.00 0.01 144.00 8.00 141.89 kg
Tulangan Pokok 4.99 4.00 0.01 144.00 8.00 141.89 kg
Sengkang 1.20 26.00 0.01 64.00 8.00 98.48 kg
382.27 kg

Sloof 35/35 Tulangan Pokok 4.30 8.00 0.01 144.00 4.00 122.16 kg
Sengkang 1.40 23.00 0.01 64.00 4.00 50.82 kg
172.98 kg

Balok Atas 30/30 Tulangan Pokok 4.30 4.00 0.01 144.00 4.00 61.08 kg
Tulangan Pokok 4.30 2.00 0.01 100.00 4.00 21.21 kg
Sengkang 1.30 28.67 0.01 64.00 4.00 58.82 kg
141.10 kg

Balok Anak 20/20 Tulangan Pokok 3.70 4.00 0.01 144.00 2.00 26.28 kg
Sengkang 0.90 24.67 0.01 64.00 2.00 17.52 kg
43.80 kg

Lantai Bak Arah memanjang 5.40 36.00 0.01 144.00 2.00 345.16 kg
Arah melintang 5.40 36.00 0.01 144.00 2.00 345.16 kg
690.32 kg

Dinding Bak Arah memanjang 4.10 14.00 0.01 144.00 4.00 203.83 kg
Arah melintang 2.10 27.33 0.01 144.00 4.00 203.83 kg
Arah memanjang 4.10 14.00 0.01 144.00 4.00 203.83 kg
Arah melintang 2.10 27.33 0.01 144.00 4.00 203.83 kg
815.32 kg

Tutup Bak Arah memanjang 4.40 29.33 0.01 100.00 1.00 79.57 kg
Arah melintang 4.40 29.33 0.01 100.00 1.00 79.57 kg
159.14 kg
PERINCIAN MATA PEMBAYARAN SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI

UNIT KERJA : DINAS PARIWISATA PEMUDA DAN OLAHRAGA


SUB KEGIATAN : PENGELOLAAN DESTINASI PARIWISATA KABUPATEN/KOTA
PEKERJAAN : PEMBANGUNAN MENARA JAGA OBJEK WISATA PANTAI GEDAMBAAN
TAHUN ANGGARAN : 2022

HARGA
SATUAN TOTAL HARGA
No. URAIAN PEKERJAAN KUANTITAS SATUAN KET.
UKURAN (Rp).
(Rp).
1 2 3 4 5 6=4x5 7
1. Penyiapan RKK :
Pembuatan dokumen Rencana Keselamatan
a. Konstruksi Memperhatikan jumlah dan
b. Pembuatan prosedur dan instruksi kerja Set - - - jenis pekerjaan yang
c. Penyiapan formulir dikerjakan
A. Sub Total Penyiapan RKK -

2. Sosialisasi, promosi dan pelatihan:


a. Induksi K3 (Safety Induction) Org - - -
Memperhatikan perkiraan
jumlah pekerja, tamu, dan staf

b. Pengarahan K3 (Safety Briefing) Org - - - Memperhatikan perkiraan


jumlah pekerja dan risiko k3
pekerjaan
c. Pelatihan K3: -
1 Bekerja di ketinggian Org - - - Tidak ada
2 Penggunaan bahan kimia (MSDS) Org - - - Tidak Ada
d. Simulasi K3 Org - - - Memperhatikan perkiraan
jumlah pekerja dan risiko k3
pekerjaan
e. Spanduk (Banner) Lbr - - - Memperhatikan lokasi
pekerjaan dan waktu
pekerjaan
f. Poster Lbr - - - Memperhatikan lokasi
pekerjaan dan waktu
pekerjaan
g. Papan Informasi K3 Bh - - - Memperhatikan risiko k3
pekerjaan
B. Sub Total Sosialisasi, Promosi dan Pelatihan -

3. Alat Pelindung Kerja dan Alat Pelindung Diri:


a. APK antara lain:
1 Jaring Pengaman (Safety Net) Ls - - - Tidak Perlu
2 Tali Keselamatan (Life Line) Ls - - - Tidak Perlu
3 Pagar Pengaman (Guard Railling) Ls - - - Tidak Perlu
4 Pembatas Area (Restricted Area) Ls - - - Tidak Perlu
b. APK antara lain:
1 Topi Pelindung (Safety Helmet) Bh 3 50,000.00 150,000.00
Memperhatikan perkiraan
jumlah pekerja tamu dan staf

2 Pelindung Mata (Goggles, Spectacles Psg - - - Tidak Perlu


3 Tameng Muka (Face Shield) Bh - - - Tidak Perlu
4 Pelindung Pernafasan dan Mulut (Masker) Bh - - - Tidak Perlu
5 Sarung Tangan (Safety Gloves) Psg 6 10,000.00 60,000.00 Sesuai kebutuhan
6 Sepatu Keselamatan (Safety Shoes) Psg 3 100,000.00 300,000.00
Memperhatikan perkiraan
jumlah pekerja tamu dan staf

7 Penunjang Seluruh Tubuh (Full Body Harness) Bh - - - Tidak Perlu


8 Rompi Keselamatan (Safety Vest) Bh - - - Tidak Perlu
9 Celemek (Apron/Coveralls) Bh - - - Tidak Perlu
10 Pelindung Jatuh (Fall Arrester) Bh - - - Tidak Perlu
C. Sub Total Alat Pelindung Kerja dan Alat Pelindung Diri 510,000.00
4. Asuransi dan perizinan :
a. Asuransi Ls - - -
D. Sub Total Asuransi dan perizinan -

5. Personel K3 Konstruksi : pekerjaan. Biaya dimasukkan


a. Ahli K3 Konstruksi OB - - - ke dalam biaya personel
b. Petugas K3 Konstruksi OB - - - manajerial
E. Sub Total Personel K3 -

6. Fasilitas Protokol Pencegahan Covid-19, Sarana dan Prasarana Kesehatan:


1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Ls 1 150,000.00 150,000.00 Memperhatika n perkiraan
Perban,dll) jumlah pekerja dan risiko k3
pekerjaan
2 Tempat Cuci tangan bh 1 50,000.00 50,000.00 Sesuai Kebutuhan
3 Termometer Gun bh - - - Tidak Perlu
4 Sabun Cuci Tangan bh 1 8,500.00 8,000.00 Sesuai Kebutuhan
5 Masker Kain bh 4 10,000.00 40,000.00 Sesuai Kebutuhan
6 Face Shield bh - - - Sesuai Kebutuhan
F. Sub Total Fasilitas, sarana dan prasarana kesehatan 248,000.00

7. Rambu- Rambu yang diperlukan:


a. Rambu petunjuk Bh - - - Sesuai Kebutuhan
b. Rambu larangan Bh - - - Sesuai Kebutuhan
c. Rambu peringatan Bh - - - Sesuai Kebutuhan
d. Rambu kewajiban Bh - - - Sesuai Kebutuhan
e. Rambu informasi Bh - - - Sesuai Kebutuhan
f. Jalur Evakuasi (Escape Route) Ls - - Sesuai kebutuhan
memperhatika n jenis
pekerjaan dan risiko k3
- pekerjaan
G. Sub Total Rambu-rambu yang diperlukan -

8. Konsultasi dengan Ahli terkait Keselamatan Konstruksi:


a. Ahli K3 Konstruksi OJ - - - Sesuai kebutuhan
memperhatika n jenis
pekerjaan dan waktu
pelaksanaan pekerjaan
H. Sub Total Konsultansi dengan Ahli terkait Keselamatan Konstruksi -

9. Lain- Lain Terkait Pengendalian Risiko Keselamatan Konstruksi:


a. Alat Pemadam Api Ringan (APAR) Bh - - -
Sesuai kebutuhan
memperhatikan jenis
pekerjaan dan risiko k3
pekerjaan
b. Bendera K3 Bh - - - Sesuai kebutuhan
memperhatikan jenis
pekerjaan dan risiko k3
pekerjaan
c. Program Inspeksi Ls - - - Memperhatikan perkiraan
jumlah pekerja
d. Pelaporan dan Penyelidikan Insiden Ls - - - Sesuai kebutuhan
memperhatikan waktu
pelaksanaan pekerjaan
e. Pembuatan Kartu Identitas Pekerja (KIP) Lbr - - - Sesuai kebutuhan
memperhatikan jenis dan
waktu pekerjaan
I. Lain- Lain Terkait Pengendalian Risiko Keselamatan Konstruksi : -
Total Mata Pembayaran Penyelenggaraan SMKK Rp758,000.00
DAFTAR ANALISA HARGA SATUAN
UNIT KERJA : DINAS PARIWISATA PEMUDA DAN OLAHRAGA
SUB KEGIATAN : PENGELOLAAN DESTINASI PARIWISATA KABUPATEN/KOTA
PEKERJAAN : PEMBANGUNAN MENARA JAGA DI OBJEK WISATA PANTAI GEDAMBAAN
TAHUN ANGGARAN : 2022

A.1.5.1.1.
Penggalian 1 m3 tanah biasa sedalam 1 m'
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.7500 109,500.00 82,125.00
Mandor L.04 OH 0.0250 125,000.00 3,125.00
Jumlah Harga Tenaga Kerja 85,250.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah ( A+B+C ) 85,250.00
E Overhead + Profit 10% x D 8,525.00
F Harga Satuan Pekerjaan (D+E) 93,775.00

A.1.5.1.
Pengurugan kembali 1 m3 galian tanah
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.5000 109,500.00 54,750.00
Mandor L.04 OH 0.0500 125,000.00 6,250.00
Jumlah Harga Tenaga Kerja 61,000.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 61,000.00
E Overhead + Profit 10% x D 6,100.00
F Harga Satuan Pekerjaan (D+E) 67,100.00

A.4.1.1.5.
Membuat 1 M3 Beton Mutu F'c = 14,5 MPa (K 175), Slump (12 ± 2) cm, w/c = 0,66
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 1.6500 109,500.00 180,675.00
Tukang Batu L.02 OH 0.2750 109,500.00 30,112.50
Kepala Tukang L.03 OH 0.0280 125,000.00 3,500.00
Mandor L.04 OH 0.0830 125,000.00 10,375.00
Jumlah Harga Tenaga Kerja 224,662.50
B Bahan
Semen Portland Kg 326.0000 1,400.00 456,400.00
Pasir Beton M3 0.5429 170,000.00 92,285.71
Kerikil (Maks 30 mm) M3 0.7622 350,000.00 266,777.78
Air Liter 215.0000 30.00 6,450.00
Jumlah Harga Bahan 821,913.49
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 1,046,575.99
E Overhead + Profit 10% x D 104,657.60
F Harga Satuan Pekerjaan (D+E) 1,151,233.59
A.4.1.1.7.
Membuat 1 M3 Beton Mutu F'c = 19,3 MPa (K 225), Slump (12 ± 2) cm, w/c = 0,58
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 1.6500 109,500.00 180,675.00
Tukang Batu L.02 OH 0.2750 109,500.00 30,112.50
Kepala Tukang L.03 OH 0.0280 125,000.00 3,500.00
Mandor L.04 OH 0.0830 125,000.00 10,375.00
Jumlah Harga Tenaga Kerja 224,662.50
B Bahan
Semen Portland Kg 371.0000 1,400.00 519,400.00
Pasir Beton M3 0.4986 170,000.00 84,757.14
Kerikil (Maks 30 mm) M3 0.7756 350,000.00 271,444.44
Air Liter 215.0000 30.00 6,450.00
Jumlah Harga Bahan 882,051.59
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 1,106,714.09
E Overhead + Profit 10% x D 110,671.41
F Harga Satuan Pekerjaan (D+E) 1,217,385.50

A.4.1.1.15
Pembesian 10 Kg dengan Besi Polos / Besi Ulir
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.0700 109,500.00 7,665.00
Tukang Besi L.02 OH 0.0700 109,500.00 7,665.00
Kepala Tukang L.03 OH 0.0070 125,000.00 875.00
Mandor L.04 OH 0.0040 125,000.00 500.00
Jumlah Harga Tenaga Kerja 16,705.00
B Bahan
Besi Beton Kg 10.5000 14,400.00 151,200.00
Kawat Beton Kg 0.1500 20,000.00 3,000.00
Jumlah Harga Bahan 154,200.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 170,905.00
E Overhead + Profit 10% x D 17,090.50
F Harga Satuan Pekerjaan (D+E) 10 Kg 187,995.50
G Harga Satuan Pekerjaan (F/10) 1 Kg 18,799.55

A.4.1.1.18.
Pemasangan 1 M2 Bekisting Untuk Pondasi Telapak
Kode Satuan Harga satuan Jumlah
No Uraian Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.520 109,500.00 56,940.00
Tukang Kayu L.02 OH 0.260 109,500.00 28,470.00
Kepala Tukang L.03 OH 0.026 125,000.00 3,250.00
Mandor L.04 OH 0.026 125,000.00 3,250.00
Jumlah Harga Tenaga Kerja 91,910.00
B Bahan
Kayu kelas III M3 0.040 1,500,000.00 60,000.00
Paku 5 cm - 10 cm Kg 0.300 20,000.00 6,000.00
Minyak Bekisting Liter 0.100 10,000.00 1,000.00
Jumlah Harga Bahan 67,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 158,910.00
E Overhead + Profit 10% x D 15,891.00
F Harga Satuan Pekerjaan (D+E) 174,801.00
G Dipakai 2X 87,400.50
A.4.1.1.21.
Pemasangan 1 M2 Bekisting Untuk Sloof
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.520 109,500.00 56,940.00
Tukang Kayu L.02 OH 0.260 109,500.00 28,470.00
Kepala Tukang L.03 OH 0.026 125,000.00 3,250.00
Mandor L.04 OH 0.026 125,000.00 3,250.00
Jumlah Harga Tenaga Kerja 91,910.00
B Bahan
Kayu kelas III M3 0.045 1,500,000.00 67,500.00
Paku 5 cm - 10 cm Kg 0.300 20,000.00 6,000.00
Minyak Bekisting Liter 0.100 10,000.00 1,000.00
Jumlah Harga Bahan 74,500.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 166,410.00
E Overhead + Profit 10% x D 16,641.00
F Harga Satuan Pekerjaan (D+E) 183,051.00
G 2x Pakai 91,525.50

A.4.1.1.22.
Pemasangan 1 M2 Bekisting Untuk Kolom
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.660 109,500.00 72,270.00
Tukang Kayu L.02 OH 0.330 109,500.00 36,135.00
Kepala Tukang L.03 OH 0.033 125,000.00 4,125.00
Mandor L.04 OH 0.033 125,000.00 4,125.00
Jumlah Harga Tenaga Kerja 116,655.00
B Bahan
Kayu kelas III M3 0.040 1,500,000.00 60,000.00
Paku 5 cm - 10 cm Kg 0.400 20,000.00 8,000.00
Minyak Bekisting Liter 0.200 10,000.00 2,000.00
Balok Kayu Kelas II M3 0.015 2,100,000.00 31,500.00
Plywood Tebal 9 mm Lembar 0.350 90,000.00 31,500.00
Dolken Kayu Ø 8 - 10 cm, P = 4 m Batang 2.000 15,000.00 30,000.00
Jumlah Harga Bahan 163,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 279,655.00
E Overhead + Profit 10% x D 27,965.50
F Harga Satuan Pekerjaan (D+E) 307,620.50
G 2x Pakai 153,810.25
A.4.1.1.23.
Pemasangan 1 M2 Bekisting Untuk Balok
Kode Satuan Koefisien Harga satuan Jumlah
No Uraian
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.660 109,500.00 72,270.00
Tukang Kayu L.02 OH 0.330 109,500.00 36,135.00
Kepala Tukang L.03 OH 0.033 125,000.00 4,125.00
Mandor L.04 OH 0.033 125,000.00 4,125.00
Jumlah Harga Tenaga Kerja 116,655.00
B Bahan
Kayu kelas III M3 0.040 1,500,000.00 60,000.00
Paku 5 cm - 10 cm Kg 0.400 20,000.00 8,000.00
Minyak Bekisting Liter 0.200 10,000.00 2,000.00
Balok Kayu Kelas II M3 0.018 2,100,000.00 37,800.00
Plywood Tebal 9 mm Lembar 0.350 90,000.00 31,500.00
Dolken Kayu Ø 8 - 10 cm, P = 4 m Batang 2.000 15,000.00 30,000.00
Jumlah Harga Bahan 169,300.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 285,955.00
E Overhead + Profit 10% x D 28,595.50
F Harga Satuan Pekerjaan (D+E) 314,550.50
G 2x Pakai 157,275.25

A.4.1.1.24.
Pemasangan 1 M2 Bekisting Untuk Lantai Dak
No Harga satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.660 109,500.00 72,270.00
Tukang Kayu L.02 OH 0.330 109,500.00 36,135.00
Kepala Tukang L.03 OH 0.033 125,000.00 4,125.00
Mandor L.04 OH 0.033 125,000.00 4,125.00
Jumlah Harga Tenaga Kerja 116,655.00
B Bahan
Kayu kelas III M3 0.040 1,500,000.00 60,000.00
Paku 5 cm - 10 cm Kg 0.400 20,000.00 8,000.00
Minyak Bekisting Liter 0.200 10,000.00 2,000.00
Balok Kayu Kelas II M3 0.015 2,100,000.00 31,500.00
Plywood Tebal 9 mm Lembar 0.350 90,000.00 31,500.00
Dolken Kayu Ø 8 - 10 cm, P = 4 m Batang 6.000 15,000.00 90,000.00
Jumlah Harga Bahan 223,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 339,655.00
E Overhead + Profit 10% x D 33,965.50
F Harga Satuan Pekerjaan (D+E) 373,620.50
A. 4.4.1.26.
Pemasangan 1 m2 Dinding Bata Ringan Tebal 7,5cm
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.670 109,500.00 73,365.00
Tukang Batu L.02 OH 0.130 109,500.00 14,235.00
Kepala Tukang L.03 OH 0.013 125,000.00 1,625.00
Mandor L.04 OH 0.003 125,000.00 375.00
Jumlah Harga Tenaga Kerja 89,600.00
B Bahan
Bata Ringan tebal 7,5cm Bh 8.400 10,000.00 84,000.00
Mortar Kg 0.473 2,000.00 946.00
Jumlah Harga Bahan 84,946.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 174,546.00
E Overhead + Profit 10% x D 17,454.60
F Harga Satuan Pekerjaan (D+E) 192,000.60

A. 4.4.2.4.
Pemasangan 1 M2 Plesteran 1 SP : 4 PP Tebal 15mm
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.300 109,500.00 32,850.00
Tukang Batu L.02 OH 0.150 109,500.00 16,425.00
Kepala Tukang L.03 OH 0.015 125,000.00 1,875.00
Mandor L.04 OH 0.015 125,000.00 1,875.00
Jumlah Harga Tenaga Kerja 53,025.00
B Bahan
Semen portland Kg 6.240 1,400.00 8,736.00
Pasir beton M3 0.024 170,000.00 4,080.00
Jumlah Harga Bahan 12,816.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 65,841.00
E Overhead + Profit 10% x D 6,584.10
F Harga Satuan Pekerjaan (D+E) 72,425.10

A.4.5.1.5.
Pemasangan 1 m2 Langit-Langit Kayu Lapis Tebal 3mm
Uraian Kode Harga satuan Jumlah
No Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.100 109,500.00 10,950.00
Tukang Kayu L.02 OH 0.100 109,500.00 10,950.00
Kepala Tukang L.03 OH 0.010 125,000.00 1,250.00
Mandor L.04 OH 0.005 125,000.00 625.00
Jumlah Harga Tenaga Kerja 23,775.00
B Bahan
Kayu Lapis Lembar 0.375 90,000.00 33,750.00
Paku Tripleks Kg 0.030 25,000.00 750.00
Jumlah Harga Bahan 34,500.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 58,275.00
E Overhead + Profit 10% x D 5,827.50
F Harga Satuan Pekerjaan (D+E) 64,102.50
A. 4.4.2.27.
Pemasangan 1 M2 Acian
Uraian Kode Harga satuan Jumlah
No Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.020 0.00 -
Tukang Cat L.02 OH 0.100 109,500.00 10,950.00
Kepala Tukang L.03 OH 0.010 109,500.00 1,095.00
Mandor L.04 OH 0.010 125,000.00 1,250.00
Jumlah Harga Tenaga Kerja 13,295.00
B Bahan
Semen Portland Kg 3.250 125,000.00 406,250.00
Jumlah Harga Bahan 406,250.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 419,545.00
E Overhead + Profit 10% x D 41,954.50
F Harga Satuan Pekerjaan (D+E) 461,499.50

A. 4.7.1.10.
Pengecatan 1 M2 Bidang Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Harga satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga
Pekerja L.01 OH 0.020 109,500.00 2,190.00
Tukang Cat L.02 OH 0.063 109,500.00 6,898.50
Kepala Tukang L.03 OH 0.006 125,000.00 787.50
Mandor L.04 OH 0.003 125,000.00 375.00
Jumlah Harga Tenaga Kerja 10,251.00
B Bahan
Plamir kg 0.100 22,000.00 2,200.00
Cat Dasar kg 0.100 20,000.00 2,000.00
Cat Penutup kg 0.260 110,000.00 28,600.00
Jumlah Harga Bahan 32,800.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah ( A+B+C ) 43,051.00
E Overhead + Profit 10% x D 4,305.10
F Harga Satuan Pekerjaan (D+E) 47,356.10
DAFTAR UPAH DAN BAHAN
###
NO. URAIAN SATUAN HARGA KET.

I. UPAH KERJA
1 Pembantu Tukang Hari 110,000.00 ###
2 Pekerja Hari 109,500.00 ###
3 Tukang Kayu, Batu, Besi, Cat dan Pipa Hari 109,500.00 Mandor
4 Kepala Tukang Hari 125,000.00 Pekerja
5 Mandor Hari 125,000.00 Operator
6 Operator Terlatih Hari 240,000.00
7 Pembantu Operator Hari 110,000.00

II. BAHAN
1 Tanah Urug M3 125,000.00 Tukang Besi
2 Tanah Laterit M3 125,000.00 Kepala Tukang
3 Pasir Urug M3 170,000.00
4 Pasir Pasang M3 170,000.00 Material dari Sungup
5 Pasir Beton M3 170,000.00 Material dari Sungup
6 Pasir Batu M3 129,400.00
7 Semen PC Kg 1,400.00 Tiga Roda
8 Batu Gunung M3 175,000.00
9 Batu split 1/2 M3 350,000.00
10 Besi Beton Kg 12,000.00 Top
12 Besi Ulir Kg 14,400.00
13 Besi Kawat Bendrat Kg 20,000.00
14 Paku biasa Kg 20,000.00
15 Paku Triplek Kg 25,000.00
### 16 Air Bersih Ltr 30.00
17 Plywood Lembar 90,000.00 Sampai Lokasi
18 Kayu Bekisting m3 1,560,000.00 Sampai Lokasi
19 Kayu Klas II m3 2,100,000.00 Sampai Lokasi
20 Kayu Bekisting Klas III m3 1,500,000.00
21 Kayu perancah / andang btg 15,000.00
22 Plameer Kg 22,000.00
23 Minyak Cat Liter 11,000.00
24 Minyak Bekisting Liter 10,000.00
25 Cat Jotun Kg 200,000.00 Jotun
26 Aluminium 4 inc m 160,000.00
27 Skrup Fixer bh 1,500.00
28 Sealant Tube 20,000.00
29 Kaca Tebal 5 mm m2 125,000.00
30 Silicone sealant 300 ml Tube 45,000.00
30 Bata Ringan Tebal 7,5 cm Bh 10,000.00
31 Cat Dasar Kg 20,000.00
32 Cat Penutup Kg 110,000.00 Jotun
JADWAL WAKTU PELAKSANAAN

KEGIATAN : PENGELOLAAN DESTINASI PARIWISATA KABUPATEN/KOTA


PEKERJAAN : PEMBANGUNAN MENARA JAGA DI OBJEK WISATA PANTAI GEDAMBAAN
TAHUN : 2022

BULAN
NO URAIAN Jumlah Harga BOBOT 1 2 3 KET.
(%) 1 2 3 4 1 2 3 4 1 2 3 4
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lokasi 150,000 0.083 0.042 0.042
2 Papan Nama Pekerjaan 250,000 0.139 0.139
3 SMKK 761,000 0.423 0.141 0.141 0.141

II. PEKERJAAN TANAH DAN PENUTUP


1 Pek. Galian Tanah 1,506,834 0.837 0.419 0.419
2 Pek. Urugan Tanah Kembali 801,152 0.445 0.445

III PEKERJAAN BETON/BETON BERTULANG


1 Pek. Cor Rabat K-175 663,720 0.369 0.184 0.184
2 Pek. Lantai Beton Bertulang Lt. 3 K-225
a. Bekisting 11,419,516 6.347 2.116 2.116 2.116
b. Pembesian 6,251,984 3.475 1.158 1.158 1.158
c. Beton Bertulang 2,479,778 1.378 1.378
3 Pek. Pondasi Foot Plat K-225
a. Bekisting Pondasi Foot Plat 672,883 0.374 0.187 0.187
b. Pembesian 5,339,754 2.968 1.484 1.484
c. Beton Bertulang 2,807,296 1.560 1.560
4 Pek. Kolom Pandestel 30/30 K-225
a. Bekisting Kolom Pandestel 739,596 0.411 0.206 0.206
b. Pembesian 1,282,779 0.713 0.356 0.356
c. Beton Bertulang 438,640 0.244 0.244
5 Pek. Sloof 30/35 K-225 (Sloof 1)
a. Bekisting 1,174,272 0.653 0.326 0.326
b. Pembesian 4,837,279 2.688 1.344 1.344
c. Beton Bertulang 1,637,589 0.910 0.910
6 Pek. Sloof 30/35 K-225 (Sloof 2)
a. Bekisting 1,251,334 0.695 0.348 0.348
b. Pembesian 367,426 0.204 0.102 0.102
c. Beton Bertulang 1,791,113 0.995 0.995
7 Pek. Kolom Lt. 1 30/30 K-225
a. Bekisting 2,329,727 1.295 0.647 0.647
b. Pembesian 2,776,578 1.543 0.772 0.772
c. Beton Bertulang 1,381,716 0.768 0.768
8 Pek. Balok Lt. 1 30/35 K-225
a. Bekisting 2,148,948 1.194 0.597 0.597
b. Pembesian 2,418,639 1.344 0.672 0.672
c. Beton Bertulang 1,791,113 0.995 0.995 90 ( Sembilan
9 Pek. Kolom Lt.2 30/30 K-225 puluh) hari
kalender
a. Bekisting 2,070,869 1.151 0.575 0.575
b. Pembesian 2,523,645 1.403 0.701 0.701
c. Beton Bertulang 1,228,192 0.683 0.683
10 Pek. Balok Lt. 2 30/35 K-225
a. Bekisting 2,148,948 1.194 0.597 0.597
b. Pembesian 2,418,639 1.344 0.672 0.672
c. Beton Bertulang 1,791,113 0.995 0.995
11 Pek. Kolom Lt. 3 30/30 K-225
a. Bekisting 1,848,990 1.028 0.514 0.514
b. Pembesian 2,032,540 1.130 0.565 0.565
c. Beton Bertulang 1,096,600 0.609 0.609
12 Pek. Balok Lt. 3 30/35 K-225
a. Bekisting 1,827,551 1.016 0.508 0.508
b. Pembesian 2,418,639 1.344 0.672 0.672
c. Beton Bertulang 1,279,366 0.711 0.711
13 Pek. Dak K-225
a. Bekisting 26,040,425 14.472 7.236 7.236
b. Pembesian 14,951,249 8.309 4.155 4.155
c. Beton Bertulang 7,999,330 4.446 4.446

14 Kolom Praktis 10/10 (KP2)


a. Bekisting 739,596 0.411 0.206 0.206
b. Pembesian 444,787 0.247 0.124 0.124
c. Beton Bertulang (K-175) 138,275 0.077 0.077

IV PEKERJAAN PLESTERAN
1 Acian 9,337,371 5.189 1.730 1.730 1.730
2 Penamaan Pada Bangunan 350,000 0.195 0.195

V PEKERJAAN LAIN-LAIN
1 Pagar Kayu 15,322,500 8.516 2.839 2.839 2.839
2 Plat Penutup 700,000 0.389 0.389
3 Tangga Plat 14,000,000 7.781 3.890 3.890
4 Pek. Cat Tembok 6,901,771 3.836 1.279 1.279 1.279
5 Titik Lampu 850,000 0.472 0.472
179,931,061 100.000 0.740 1.048 1.855 5.913 10.499 6.998 7.032 6.142 18.756 22.173 10.321 8.522
0.740 1.789 3.644 9.557 20.057 27.054 34.087 40.229 58.984 81.157 91.478 100.000

Kotabaru, 31 mei 2022


Penawar
CV. MALEWA

HADASIAH
Direktur
DAFTAR ANALISA SNI

HARGA SATUAN
NO. URAIAN KOEFISIEN SATUAN JUMLAH (Rp)
(Rp)
1 2 3 4 5 6
3 PEKERJAAN BETON

3.2 Membuat 1 M³ Beton Mutu f'c = 14,5 Mpa (K 175), Slump (12 + 2) cm, w/c = 0.66
A Bahan Material
Semen portland 326.0000 Kg 1,400.00 456,400.00
Pasir Beton 0.5429 m3 170,000.00 92,285.71
Koral Beton (maksimum 30 mm) 0.7622 m3 350,000.00 266,777.78
Air 215.0000 ltr 30.00 6,450.00
Jumlah A 821,913.49
B Tenaga Kerja
Pekerja 1.6500 Oh 109,500.00 180,675.00
Tukang Batu 0.2750 Oh 109,500.00 30,112.50
Kepala Tukang 0.0280 Oh 125,000.00 3,500.00
Mandor 0.0830 Oh 125,000.00 10,375.00
Jumlah B 224,662.50
C Jumlah Total (A+B) 1,046,575.99
D Overhead & profit (Contoh 15% x C) 156,986.40
E Harga Satuan Pekerjaan (C+D) 1,203,562.39

3.2.a Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
A Bahan Material
Semen portland 371.0000 kg 1,400.00 519,400.00
Pasir Beton 0.4986 m3 170,000.00 84,757.14
Koral Beton (maksimum 30 mm) 0.7756 m3 350,000.00 271,444.44
Air 215.0000 ltr 30.00 6,450.00
Jumlah A 882,051.59
B Tenaga Kerja
Pekerja 1.6500 Oh 109,500.00 180,675.00
Tukang Batu 0.2750 Oh 109,500.00 30,112.50
Kepala Tukang 0.0280 Oh 125,000.00 3,500.00
Mandor 0.1650 Oh 125,000.00 20,625.00
Jumlah B 234,912.50
C Jumlah Total (A+B) 1,116,964.09
D Overhead & profit (Contoh 15% x C) 167,544.61
E Harga Satuan Pekerjaan (C+D) 1,284,508.70
3.3 Pembesian 10 Kg dengan besi polos atau besi ulir
Bahan Material
Besi Beton ( polos/ulir ) 10.5000 Kg 12,000.00 126,000.00
Kawat Beton 0.1500 Kg 20,000.00 3,000.00
Jumlah A 129,000.00
Tenaga Kerja
Pekerja 0.0700 Oh 109,500.00 7,665.00
Tukang Batu 0.0700 Oh 109,500.00 7,665.00
Kepala Tukang 0.0070 Oh 125,000.00 875.00
Mandor 0.0040 Oh 125,000.00 500.00
Jumlah B 16,705.00
C Jumlah Total (A+B) 145,705.00
D Overhead & profit (Contoh 15% x C) 21,855.75
E Harga Satuan Pekerjaan (C+D) 167,560.75

1 Kg Pembesian dengan besi polos 16,756.08

3.4 Memasang 1 M² bekisting untuk pondasi


A Bahan Material
Kayu kelas III 0.0400 m³ 1,500,000.00 60,000.00
Paku 5 cm - 10 cm 0.3000 Kg 20,000.00 6,000.00
Minyak Bekisting 0.1000 liter 10,000.00 1,000.00
Jumlah A 67,000.00
B Tenaga Kerja
Pekerja 0.5200 Oh 109,500.00 56,940.00
Tukang Batu 0.2600 Oh 109,500.00 28,470.00
Kepala Tukang 0.0260 Oh 125,000.00 3,250.00
Mandor 0.0260 Oh 125,000.00 3,250.00
Jumlah B 91,910.00
C Jumlah Total (A+B) 158,910.00
D Overhead & profit (Contoh 15% x C) 23,836.50
E Harga Satuan Pekerjaan (C+D) 182,746.50

3.5 Memasang 1 M² bekisting untuk sloof


A Bahan Material
Kayu kelas III 0.0450 m³ 1,500,000.00 67,500.00
Paku 5 cm - 10 cm 0.3000 Kg 20,000.00 6,000.00
Minyak Bekisting 0.1000 liter 10,000.00 1,000.00
Jumlah A 74,500.00
B Tenaga Kerja
Pekerja 0.5200 Oh 109,500.00 56,940.00
Tukang Batu 0.2600 Oh 109,500.00 28,470.00
Kepala Tukang 0.0260 Oh 125,000.00 3,250.00
Mandor 0.0260 Oh 125,000.00 3,250.00
Jumlah B 91,910.00
C Jumlah Total (A+B) 166,410.00
D Overhead & profit (Contoh 15% x C) 24,961.50
E Harga Satuan Pekerjaan (C+D) 191,371.50

3.6 Memasang 1 M² bekisting untuk kolom


A Bahan Material
Kayu kelas III 0.0400 m³ 1,500,000.00 60,000.00
Paku 5 cm - 12 cm 0.4000 Kg 20,000.00 8,000.00
Minyak Bekisting 0.2000 liter 10,000.00 2,000.00
Balok Kayu kelas II 0.0150 m³ 2,100,000.00 31,500.00
Plywood tebal 9 mm 0.3500 lmbr 90,000.00 31,500.00
Dolken kayu galam Ø (8-10) cm panjang 4 m 2.0000 btng 15,000.00 30,000.00
Jumlah A 163,000.00
B Tenaga Kerja -
Pekerja 0.6600 Oh 109,500.00 72,270.00
Tukang Batu 0.3300 Oh 109,500.00 36,135.00
Kepala Tukang 0.0330 Oh 125,000.00 4,125.00
Mandor 0.0330 Oh 125,000.00 4,125.00
Jumlah B 116,655.00
C Jumlah Total (A+B) 279,655.00
D Overhead & profit (Contoh 15% x C) 41,948.25
E Harga Satuan Pekerjaan (C+D) 321,603.25

3.7 Memasang 1 M² bekisting untuk balok


A Bahan Material
Kayu kelas III 0.0400 m³ 1,500,000.00 60,000.00
Paku 5 cm - 12 cm 0.4000 Kg 20,000.00 8,000.00
Minyak Bekisting 0.2000 liter 10,000.00 2,000.00
Balok Kayu kelas II 0.0180 m³ 2,100,000.00 37,800.00
Plywood tebal 9 mm 0.3500 lmbr 90,000.00 31,500.00
Dolken kayu galam Ø (8-10) cm panjang 4 m 2.0000 btng 15,000.00 30,000.00
Jumlah A 169,300.00
B Tenaga Kerja
Pekerja 0.6600 Oh 109,500.00 72,270.00
Tukang Batu 0.3300 Oh 109,500.00 36,135.00
Kepala Tukang 0.0330 Oh 125,000.00 4,125.00
Mandor 0.0330 Oh 125,000.00 4,125.00
Jumlah B 116,655.00
C Jumlah Total (A+B) 285,955.00
D Overhead & profit (Contoh 15% x C) 42,893.25
E Harga Satuan Pekerjaan (C+D) 328,848.25

3.8 Memasang 1 M² bekisting untuk lantai dak


A Bahan Material
Kayu kelas III 0.0400 m³ 1,500,000.00 60,000.00
Paku 5 cm - 12 cm 0.4000 Kg 20,000.00 8,000.00
Minyak Bekisting 0.2000 Liter 10,000.00 2,000.00
Balok Kayu kelas II 0.0150 m³ 2,100,000.00 31,500.00
Plywood tebal 9 mm 0.3500 lmbr 90,000.00 31,500.00
Dolken kayu galam Ø (8-10) 6.0000 Btng 15,000.00 90,000.00
Jumlah A 223,000.00
B Tenaga Kerja
Pekerja 0.6600 Oh 109,500.00 72,270.00
Tukang Batu 0.3300 Oh 109,500.00 36,135.00
Kepala Tukang 0.0330 Oh 125,000.00 4,125.00
Mandor 0.0330 Oh 125,000.00 4,125.00
Jumlah B 116,655.00
C Jumlah Total (A+B) 339,655.00
D Overhead & profit (Contoh 15% x C) 50,948.25
E Harga Satuan Pekerjaan (C+D) 390,603.25

4 PEKERJAAN PLESTERAN
4.1 1 M2 Plesteran 1 Pc : 4 Ps, tebal 15 mm
A Bahan
Semen Portland 6.2400 Kg 1,560.00 9,734.40
Pasir pasang 0.0240 M3 196,000.00 4,704.00
Jumlah A 14,438.40
B Tenaga
Pekerja 0.3000 Oh 111,000.00 33,300.00
Tukang batu 0.1500 Oh 111,000.00 16,650.00
Kepala tukang 0.0150 Oh 123,000.00 1,845.00
Mandor 0.0150 Oh 123,000.00 1,845.00
Jumlah B 53,640.00
C Jumlah Total (A+B) 68,078.40
D Overhead & profit (Contoh 15% x C) 10,211.76
E Harga Satuan Pekerjaan (C+D) 78,290.16

4.2 1 M2 Acian
A Bahan
Semen Portland 3.2500 Kg 1,560.00 5,070.00
Jumlah A 5,070.00
B Tenaga
Pekerja 0.2000 Oh 111,000.00 22,200.00
Tukang batu 0.1000 Oh 111,000.00 11,100.00
Kepala tukang 0.0100 Oh 123,000.00 1,230.00
Mandor 0.0100 Oh 123,000.00 1,230.00
Jumlah B 35,760.00
C Jumlah Total (A+B) 40,830.00
D Overhead & profit (Contoh 15% x C) 6,124.50
E Harga Satuan Pekerjaan (C+D) 46,954.50

6 PEKERJAAN CAT-CATAN
6.1 1 M2 Pengecatan Bidang Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A Bahan
Plamir 0.1000 Kg 22,000.00 2,200.00
Cat Dasar 0.1000 Kg 20,000.00 2,000.00
Cat Penutup 2 Kali 0.2600 Kg 52,000.00 13,520.00
Jumlah A 17,720.00
B Tenaga
Pekerja 0.0200 Oh 111,000.00 2,220.00
Tukang Cat 0.0630 Oh 111,000.00 6,993.00
Kepala tukang 0.0063 Oh 123,000.00 774.90
Mandor 0.0025 Oh 123,000.00 307.50
Jumlah B 10,295.40
C Jumlah Total (A+B) 28,015.40
D Overhead & profit (Contoh 15% x C) 4,202.31
E Harga Satuan Pekerjaan (C+D) 32,217.71

6.2 1 M2 Pengecatan Bidang Kayu (Besi), 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A Bahan
Minyak cat 0.2000 Ltr 11,000.00 2,200.00
Cat Dasar 0.1700 Kg 20,000.00 3,400.00
Cat Penutup 2 Kali 0.2600 Kg 52,000.00 13,520.00
Jumlah A 19,120.00
B Tenaga
Pekerja 0.0700 Oh 111,000.00 7,770.00
Tukang Cat 0.0060 Oh 111,000.00 666.00
Kepala tukang 0.0900 Oh 123,000.00 11,070.00
Mandor 0.0025 Oh 123,000.00 307.50
Jumlah B 19,813.50
C Jumlah Total (A+B) 38,933.50
D Overhead & profit (Contoh 15% x C) 5,840.03
E Harga Satuan Pekerjaan (C+D) 44,773.53

5.13 1 M Crossing Pipa Galvanis 6 M Jalan Beton


A Bahan
Pipa Galvanis 3" 6.0000 m 184,000.00 1,104,000.00
Pembongkaran Perkerasan 1.4000 m2 50,000.00 70,000.00
Jumlah A 1,174,000.00
B Tenaga
Pemasangan Pipa dan Alat Bantu 6.0000 m' 50,000.00 300,000.00
Cor Beton 0.7000 m3 288,348.33 201,843.83

Jumlah B 501,843.83
C Jumlah Total (A+B) 1,675,843.83
D Overhead & profit (Contoh 15% x C) 251,376.58
E Harga Satuan Pekerjaan (C+D) 1,927,220.41
per 1 meter 321,203.40
DAFTAR ANALISA SNI

HARGA SATUAN
NO. URAIAN KOEFISIEN SATUAN JUMLAH (Rp)
(Rp)
1 2 3 4 5 6
1 PEKERJAAN TANAH
1.1 1M3 Galian tanah Keras sedalam 1 meter
A Bahan -
Jumlah A -

B Tenaga
Pekerja 1.0000 Oh 112,000.00 112,000.00
Mandor 0.0320 Oh 125,000.00 4,000.00
Jumlah B 116,000.00
C Jumlah Total (A+B) 116,000.00
D Overhead & profit (Contoh 15% x C) 17,400.00
E Harga Satuan Pekerjaan (C+D) 133,400.00

1.2 1M3 Galian tanah cadas sedalam 1 meter


A Bahan -
Jumlah A -

B Tenaga
Pekerja 1.5000 Oh 112,000.00 168,000.00
Mandor 0.0600 Oh 125,000.00 7,500.00
Jumlah B 175,500.00

C Jumlah Total (A+B) 175,500.00

D Overhead & profit (Contoh 15% x C) 26,325.00


E Harga Satuan Pekerjaan (C+D) 201,825.00

1.3 1 M3 Urugan kembali


A Bahan -
Pasir urug -
Jumlah A
B Tenaga
Pekerja 0.5000 Oh 112,000.00 56,000.00
Mandor 0.0500 Oh 125,000.00 6,250.00
Jumlah B 62,250.00
C Jumlah Total (A+B) 62,250.00
D Overhead & profit (Contoh 15% x C) 9,337.50
E Harga Satuan Pekerjaan (C+D) 71,587.50

1.4 1 M3 Urugan pasir


A Bahan
Pasir urug 1.2000 M3 164,000.00 196,800.00
Jumlah A 196,800.00
B Tenaga
Pekerja 0.3000 Oh 112,000.00 33,600.00
Mandor 0.0100 Oh 125,000.00 1,250.00
Jumlah B 34,850.00
C Jumlah Total (A+B) 231,650.00
D Overhead & profit (Contoh 15% x C) 34,747.50
E Harga Satuan Pekerjaan (C+D) 266,397.50

1.5 1 M3 Urugan tanah


A Bahan
Tanah urug 1.2000 M3 125,000.00 150,000.00
Jumlah A 150,000.00
B Tenaga
Pekerja 0.3000 Oh 112,000.00 33,600.00
Mandor 0.0100 Oh 125,000.00 1,250.00
Jumlah B 34,850.00
C Jumlah Total (A+B) 184,850.00
D Overhead & profit (Contoh 15% x C) 27,727.50
E Harga Satuan Pekerjaan (C+D) 212,577.50
2 PEKERJAAN PONDASI
2.1 1M3 Pas. Pondasi Batu Kali 1 Pc : 4 Ps
A. Bahan
Batu Gunung 1.1000 M3 204,000.00 224,400.00
Semen Portland 163.0000 Kg 1,600.00 260,800.00
Pasir pasang 0.5200 M3 197,000.00 102,440.00
Jumlah A 587,640.00
B. Tenaga
Pekerja 1.5000 Oh 112,000.00 168,000.00
Tukang batu 0.6000 Oh 112,000.00 67,200.00
Kepala tukang 0.0600 Oh 125,000.00 7,500.00
Mandor 0.0750 Oh 125,000.00 9,375.00
Jumlah B 252,075.00
C Jumlah Total (A+B) 839,715.00
D Overhead & profit (Contoh 15% x C) 125,957.25
E Harga Satuan Pekerjaan (C+D) 965,672.25

3 PEKERJAAN BETON
3.1 1M3 Membuat Beton Tumbuk, 1 Pc : 5 Ps : 7 Kr
A Bahan
Semen Portland 218.0000 Kg 1,600.00 348,800.00
Pasir beton 0.5200 M3 197,000.00 102,440.00
Koral Beton (maksimum 30 mm) 0.8700 M3 230,000.00 200,100.00
Jumlah A 651,340.00
B Tenaga
Pekerja 1.6500 Oh 112,000.00 184,800.00
Tukang batu 0.2500 Oh 112,000.00 28,000.00
Kepala tukang 0.0250 Oh 125,000.00 3,125.00
Mandor 0.0800 Oh 125,000.00 10,000.00
Jumlah B 225,925.00
C Jumlah Total (A+B) 877,265.00
D Overhead & profit (Contoh 15% x C) 131,589.75
E Harga Satuan Pekerjaan (C+D) 1,008,854.75

3.2 Membuat 1 M³ Beton Mutu f'c = 14,5 Mpa (K 175), Slump (12 + 2) cm, w/c = 0.66
A Bahan Material
Semen portland 326.0000 Kg 1,600.00 521,600.00
Pasir Beton 0.5429 m3 197,000.00 106,942.86
Koral Beton (maksimum 30 mm) 0.7622 m3 230,000.00 175,311.11
Air 215.0000 ltr 30.00 6,450.00
Jumlah A 810,303.97
B Tenaga Kerja
Pekerja 1.6500 Oh 112,000.00 184,800.00
Tukang Batu 0.2750 Oh 112,000.00 30,800.00
Kepala Tukang 0.0280 Oh 125,000.00 3,500.00
Mandor 0.0830 Oh 125,000.00 10,375.00
Jumlah B 229,475.00
C Jumlah Total (A+B) 1,039,778.97
D Overhead & profit (Contoh 15% x C) 155,966.85
E Harga Satuan Pekerjaan (C+D) 1,195,745.81

3.2 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
A Bahan Material
Semen portland 371.0000 kg 1,600.00 593,600.00
Pasir Beton 0.4986 m3 197,000.00 98,218.57
Koral Beton (maksimum 30 mm) 0.7756 m3 230,000.00 178,377.78
Air 215.0000 ltr 30.00 6,450.00
Jumlah A 876,646.35
B Tenaga Kerja
Pekerja 1.6500 Oh 112,000.00 184,800.00
Tukang Batu 0.2750 Oh 112,000.00 30,800.00
Kepala Tukang 0.0830 Oh 125,000.00 10,375.00
Mandor 0.0830 Oh 125,000.00 10,375.00
Jumlah B 236,350.00
C Jumlah Total (A+B) 1,112,996.35
D Overhead & profit (Contoh 15% x C) 166,949.45
E Harga Satuan Pekerjaan (C+D) 1,279,945.80
3.3 Pembesian 10 Kg dengan besi polos atau besi ulir
Bahan Material
Besi Beton ( polos/ulir ) 10.5000 Kg 10,000.00 105,000.00
Kawat Beton 0.1500 Kg 20,000.00 3,000.00
Jumlah A 108,000.00
Tenaga Kerja
Pekerja 0.0700 Oh 112,000.00 7,840.00
Tukang Batu 0.0700 Oh 112,000.00 7,840.00
Kepala Tukang 0.0070 Oh 125,000.00 875.00
Mandor 0.0040 Oh 125,000.00 500.00
Jumlah B 17,055.00
C Jumlah Total (A+B) 125,055.00
D Overhead & profit (Contoh 15% x C) 18,758.25
E Harga Satuan Pekerjaan (C+D) 143,813.25

1 Kg Pembesian dengan besi polos 14,381.33

3.4 Memasang 1 M² bekisting untuk pondasi


A Bahan Material
Kayu kelas III 0.0400 m³ 1,500,000.00 60,000.00
Paku 5 cm - 10 cm 0.3000 Kg 20,000.00 6,000.00
Minyak Bekisting 0.1000 liter 10,000.00 1,000.00
Jumlah A 67,000.00
B Tenaga Kerja
Pekerja 0.5200 Oh 112,000.00 58,240.00
Tukang Batu 0.2600 Oh 112,000.00 29,120.00
Kepala Tukang 0.0260 Oh 125,000.00 3,250.00
Mandor 0.0260 Oh 125,000.00 3,250.00
Jumlah B 93,860.00
C Jumlah Total (A+B) 160,860.00
D Overhead & profit (Contoh 15% x C) 24,129.00
E Harga Satuan Pekerjaan (C+D) 184,989.00

3.5 Memasang 1 M² bekisting untuk sloof


A Bahan Material
Kayu kelas III 0.0450 m³ 1,500,000.00 67,500.00
Paku 5 cm - 10 cm 0.3000 Kg 20,000.00 6,000.00
Minyak Bekisting 0.1000 liter 10,000.00 1,000.00
Jumlah A 74,500.00
B Tenaga Kerja
Pekerja 0.5200 Oh 112,000.00 58,240.00
Tukang Batu 0.2600 Oh 112,000.00 29,120.00
Kepala Tukang 0.0260 Oh 125,000.00 3,250.00
Mandor 0.0260 Oh 125,000.00 3,250.00
Jumlah B 93,860.00
C Jumlah Total (A+B) 168,360.00
D Overhead & profit (Contoh 15% x C) 25,254.00
E Harga Satuan Pekerjaan (C+D) 193,614.00

3.6 Memasang 1 M² bekisting untuk kolom


A Bahan Material
Kayu kelas III 0.0400 m³ 1,500,000.00 60,000.00
Paku 5 cm - 12 cm 0.4000 Kg 20,000.00 8,000.00
Minyak Bekisting 0.2000 liter 10,000.00 2,000.00
Balok Kayu kelas II 0.0150 m³ 2,200,000.00 33,000.00
Plywood tebal 9 mm 0.3500 lmbr 155,000.00 54,250.00
Dolken kayu galam Ø (8-10) cm panjang 4 m 2.0000 btng 15,000.00 30,000.00
Jumlah A 187,250.00
B Tenaga Kerja -
Pekerja 0.6600 Oh 112,000.00 73,920.00
Tukang Batu 0.3300 Oh 112,000.00 36,960.00
Kepala Tukang 0.0330 Oh 125,000.00 4,125.00
Mandor 0.0330 Oh 125,000.00 4,125.00
Jumlah B 119,130.00
C Jumlah Total (A+B) 306,380.00
D Overhead & profit (Contoh 15% x C) 45,957.00
E Harga Satuan Pekerjaan (C+D) 352,337.00
3.7 Memasang 1 M² bekisting untuk balok
A Bahan Material
Kayu kelas III 0.0400 m³ 1,500,000.00 60,000.00
Paku 5 cm - 12 cm 0.4000 Kg 20,000.00 8,000.00
Minyak Bekisting 0.2000 liter 15,000.00 3,000.00
Balok Kayu kelas II 0.0180 m³ 2,200,000.00 39,600.00
Plywood tebal 9 mm 0.3500 lmbr 155,000.00 54,250.00
Dolken kayu galam Ø (8-10) cm panjang 4 m 2.0000 btng 15,000.00 30,000.00
Jumlah A 194,850.00
B Tenaga Kerja
Pekerja 0.6600 Oh 112,000.00 73,920.00
Tukang Batu 0.3300 Oh 112,000.00 36,960.00
Kepala Tukang 0.0330 Oh 125,000.00 4,125.00
Mandor 0.0330 Oh 125,000.00 4,125.00
Jumlah B 119,130.00
C Jumlah Total (A+B) 313,980.00
D Overhead & profit (Contoh 15% x C) 47,097.00
E Harga Satuan Pekerjaan (C+D) 361,077.00

3.8 Memasang 1 M² bekisting untuk lantai dak


A Bahan Material
Kayu kelas III 0.0400 m³ 1,500,000.00 60,000.00
Paku 5 cm - 12 cm 0.4000 Kg 20,000.00 8,000.00
Minyak Bekisting 0.2000 Liter 15,000.00 3,000.00
Balok Kayu kelas II 0.0150 m³ 2,200,000.00 33,000.00
Plywood tebal 9 mm 0.3500 lmbr 155,000.00 54,250.00
Dolken kayu galam Ø (8-10) 6.0000 Btng 15,000.00 90,000.00
Jumlah A 248,250.00
B Tenaga Kerja
Pekerja 0.6600 Oh 112,000.00 73,920.00
Tukang Batu 0.3300 Oh 112,000.00 36,960.00
Kepala Tukang 0.0330 Oh 125,000.00 4,125.00
Mandor 0.0330 Oh 125,000.00 4,125.00
Jumlah B 119,130.00
C Jumlah Total (A+B) 367,380.00
D Overhead & profit (Contoh 15% x C) 55,107.00
E Harga Satuan Pekerjaan (C+D) 422,487.00

3.9 Memasang 1 M² bekisting untuk dinding


A Bahan Material
Kayu kelas III 0.0300 m³ 1,500,000.00 45,000.00
Paku 5 cm - 12 cm 0.4000 Kg 20,000.00 8,000.00
Minyak Bekisting 0.2000 liter 15,000.00 3,000.00
Balok Kayu kelas II 0.0200 m³ 2,200,000.00 44,000.00
Plywood tebal 9 mm 0.3500 lmbr 155,000.00 54,250.00
Dolken kayu galam Ø (8-10) cm panjang 4 m 3.0000 btng 15,000.00 45,000.00
Formite/penjaga jarak bekisting/spacer 4.0000 buah 13,000.00 52,000.00
Jumlah A 251,250.00
B Tenaga Kerja
Pekerja 0.6600 Oh 112,000.00 73,920.00
Tukang Batu 0.3300 Oh 112,000.00 36,960.00
Kepala Tukang 0.0330 Oh 125,000.00 4,125.00
Mandor 0.0330 Oh 125,000.00 4,125.00
Jumlah B 119,130.00
C Jumlah Total (A+B) 370,380.00
D Overhead & profit (Contoh 15% x C) 55,557.00
E Harga Satuan Pekerjaan (C+D) 425,937.00
3.10 1 M' Membuat Kolom Praktis
A Bahan
Kayu bekisting 0.0020 M3 1,500,000.00 3,000.00
Paku 0.0100 Kg 20,000.00 200.00
Besi beton polos 3.0000 Kg 10,000.00 30,000.00
Kawat beton 0.0450 Kg 20,000.00 900.00
Semen Portland 4.0000 Kg 1,600.00 6,400.00
Pasir beton 0.0060 M3 197,000.00 1,182.00
Kerikil Cor 0.0090 M3 230,000.00 2,070.00
Jumlah A 43,752.00
B Tenaga
Pekerja 0.1800 Oh 112,000.00 20,160.00
Tukang batu 0.0200 Oh 112,000.00 2,240.00
Tukang Kayu 0.0200 Oh 112,000.00 2,240.00
Tukang besi 0.0200 Oh 112,000.00 2,240.00
Kepala tukang 0.0060 Oh 125,000.00 750.00
Mandor 0.0090 Oh 125,000.00 1,125.00
Jumlah B 28,755.00
C Jumlah Total (A+B) 72,507.00
D Overhead & profit (Contoh 15% x C) 10,876.05
E Harga Satuan Pekerjaan (C+D) 83,383.05

4 PEKERJAAN PLESTERAN
4.1 1 M2 Plesteran 1 Pc : 4 Ps, tebal 15 mm
A Bahan
Semen Portland 6.2400 Kg 1,600.00 9,984.00
Pasir pasang 0.0240 M3 197,000.00 4,728.00
Jumlah A 14,712.00
B Tenaga
Pekerja 0.3000 Oh 112,000.00 33,600.00
Tukang batu 0.1500 Oh 112,000.00 16,800.00
Kepala tukang 0.0150 Oh 125,000.00 1,875.00
Mandor 0.0150 Oh 125,000.00 1,875.00
Jumlah B 54,150.00
C Jumlah Total (A+B) 68,862.00
D Overhead & profit (Contoh 15% x C) 10,329.30
E Harga Satuan Pekerjaan (C+D) 79,191.30

4.2 1 M2 Acian
A Bahan
Semen Portland 3.2500 Kg 1,600.00 5,200.00
Jumlah A 5,200.00
B Tenaga
Pekerja 0.2000 Oh 112,000.00 22,400.00
Tukang batu 0.1000 Oh 112,000.00 11,200.00
Kepala tukang 0.0100 Oh 125,000.00 1,250.00
Mandor 0.0100 Oh 125,000.00 1,250.00
Jumlah B 36,100.00
C Jumlah Total (A+B) 41,300.00
D Overhead & profit (Contoh 15% x C) 6,195.00
E Harga Satuan Pekerjaan (C+D) 47,495.00
5 PEKERJAAN PIPA
5.1 1 M Pasang pipa Galvanis 2"
A Bahan
Pipa galvanis 1.2000 m 116,666.67 140,000.00
Perlengkapan 35.0000 % 40,833.33 40,833.33
Jumlah A 180,833.33
B Tenaga
Pekerja 0.0540 Oh 112,000.00 6,048.00
Tukang batu/pipa 0.0900 Oh 112,000.00 10,080.00
Kepala Tukang 0.0090 Oh 125,000.00 1,125.00
Mandor 0.0270 Oh 125,000.00 3,375.00
Jumlah B 20,628.00
C Jumlah Total (A+B) 201,461.33
D Overhead & profit (Contoh 15% x C) 30,219.20
E Harga Satuan Pekerjaan (C+D) 231,680.53

5.2 1 M Pasang pipa Galvanis 3"


A Bahan
Pipa galvanis 1.2000 m 150,000.00 180,000.00
Perlengkapan 35.0000 % 52,500.00 52,500.00
Jumlah A 232,500.00
B Tenaga
Pekerja 0.1350 Oh 112,000.00 15,120.00
Tukang batu/pipa 0.2250 Oh 112,000.00 25,200.00
Kepala Tukang 0.0230 Oh 125,000.00 2,875.00
Mandor 0.0700 Oh 125,000.00 8,750.00
Jumlah B 51,945.00
C Jumlah Total (A+B) 284,445.00
D Overhead & profit (Contoh 15% x C) 42,666.75
E Harga Satuan Pekerjaan (C+D) 327,111.75

5.3 1 M Pasang pipa Galvanis 4"


A Bahan
Pipa galvanis 1.2000 m 200,000.00 240,000.00
Perlengkapan 35.0000 % 70,000.00 70,000.00
Jumlah A 310,000.00
B Tenaga
Pekerja 0.1350 Oh 112,000.00 15,120.00
Tukang batu/pipa 0.2250 Oh 112,000.00 25,200.00
Kepala Tukang 0.0230 Oh 125,000.00 2,875.00
Mandor 0.0700 Oh 125,000.00 8,750.00
Jumlah B 51,945.00
C Jumlah Total (A+B) 361,945.00
D Overhead & profit (Contoh 15% x C) 54,291.75
E Harga Satuan Pekerjaan (C+D) 416,236.75

5.4 1 M Pasang pipa Galvanis 6"


A Bahan
Pipa galvanis 1.2000 m 250,000.00 300,000.00
Perlengkapan 35.0000 % 87,500.00 87,500.00
Jumlah A 387,500.00
B Tenaga
Pekerja 0.1350 Oh 112,000.00 15,120.00
Tukang batu/pipa 0.2250 Oh 112,000.00 25,200.00
Kepala Tukang 0.0230 Oh 125,000.00 2,875.00
Mandor 0.0700 Oh 125,000.00 8,750.00
Jumlah B 51,945.00
C Jumlah Total (A+B) 439,445.00
D Overhead & profit (Contoh 15% x C) 65,916.75
E Harga Satuan Pekerjaan (C+D) 505,361.75
5.5 1 M Pasang pipa pvc 1/2"
A Bahan
Pipa pvc 1.2000 m 3,250.00 3,900.00
Perlengkapan 0.3500 % 1,137.50 398.13
Jumlah A 4,298.13
B Tenaga
Pekerja 0.0360 Oh 112,000.00 4,032.00
Tukang batu/pipa 0.0600 Oh 112,000.00 6,720.00
Kepala Tukang 0.0060 Oh 125,000.00 750.00
Mandor 0.0018 Oh 125,000.00 225.00
Jumlah B 11,727.00
C Jumlah Total (A+B) 16,025.13
D Overhead & profit (Contoh 15% x C) 2,403.77
E Harga Satuan Pekerjaan (C+D) 18,428.89

5.6 1 M Pasang pipa pvc SNI 1,5" (50 mm)


A Bahan
Pipa PVC S-12,5 1.0000 m 17,000.00 17,000.00
Jumlah A 17,000.00
B Tenaga
Pekerja 0.0810 Oh 112,000.00 9,072.00
Tukang batu/pipa 0.0410 Oh 112,000.00 4,592.00
Mandor 0.0080 Oh 125,000.00 1,000.00
Jumlah B 14,664.00
C Jumlah Total (A+B) 31,664.00

D Overhead & profit (Contoh 15% x C) 4,749.60


E Harga Satuan Pekerjaan (C+D) 36,413.60

5.7 1 M Pasang pipa pvc SNI 2" (63mm)


A Bahan
Pipa PVC S-12,5 1.0000 m 30,000.00 30,000.00
Jumlah A 30,000.00
B Tenaga
Pekerja 0.0810 Oh 112,000.00 9,072.00
Tukang batu/pipa 0.0410 Oh 112,000.00 4,592.00
Mandor 0.0080 Oh 125,000.00 1,000.00
Jumlah B 14,664.00
C Jumlah Total (A+B) 44,664.00
D Overhead & profit (Contoh 15% x C) 6,699.60
E Harga Satuan Pekerjaan (C+D) 51,363.60

5.8 1 M Pasang pipa pvc SNI 3" (90mm)


A Bahan
Pipa PVC S-12,5 SCJ (Lem) 1.0000 m 172,500.00 172,500.00

B Tenaga
Pekerja 0.0940 Oh 112,000.00 10,528.00
Tukang batu/pipa 0.0470 Oh 112,000.00 5,264.00
Mandor 0.0090 Oh 125,000.00 1,125.00
Jumlah B 16,917.00
C Jumlah Total (A+B) 189,417.00
D Overhead & profit (Contoh 15% x C) 28,412.55
E Harga Satuan Pekerjaan (C+D) 217,829.55

5.9 1 M Pasang pipa pvc SNI 4" (110mm)


A Bahan
Pipa PVC S-10 (SCJ) 1.0000 m 75,000.00 75,000.00
Jumlah A 75,000.00
B Tenaga
Pekerja 0.1050 Oh 112,000.00 11,760.00
Tukang batu/pipa 0.0530 Oh 112,000.00 5,936.00
Mandor 0.0110 Oh 125,000.00 1,375.00
Jumlah B 19,071.00
C Jumlah Total (A+B) 94,071.00
D Overhead & profit (Contoh 15% x C) 14,110.65
E Harga Satuan Pekerjaan (C+D) 108,181.65
5.10 1 M Pasang pipa HDPE 63 mm (3")
A Bahan
Pipa HDPE 3" 1.0000 m 94,163.00 94,163.00
Jumlah A 94,163.00
B Tenaga
Pekerja 0.0350 Oh 112,000.00 3,920.00
Tukang batu/pipa 0.0170 Oh 112,000.00 1,904.00
Mandor 0.0030 Oh 125,000.00 375.00
Jumlah B 6,199.00

C Peralatan
Mesin sambung pipa Butt Fussion/Elektro Fussion 0.5823 Jam 130,000.00 75,699.00
Genset 0.4052 Jam 85,000.00 34,442.00
Scrapper 0.0163 Jam 20,000.00 326.00
Pick Up 0.0052 Jam 210,000.00 1,092.00
Jumlah C 111,559.00

D Jumlah Total (A+B+C) 211,921.00


E Overhead & profit (Contoh 15% x D) 31,788.15
F Harga Satuan Pekerjaan (D+E) 243,709.15

5.11 1 M Pasang pipa HDPE 100 mm (4")


A Bahan
Pipa pvc 1.0000 m 141,750.00 141,750.00
Jumlah A 141,750.00
B Tenaga
Pekerja 0.0350 Oh 112,000.00 3,920.00
Tukang batu/pipa 0.0170 Oh 112,000.00 1,904.00
Mandor 0.0030 Oh 125,000.00 375.00
Jumlah B 6,199.00
C Peralatan
Mesin sambung pipa Butt Fussion/Elektro Fussion 0.5823 Jam 130,000.00 75,699.00
Genset 0.4052 Jam 85,000.00 34,442.00
Scrapper 0.0163 Jam 20,000.00 326.00
Pick Up 0.0052 Jam 210,000.00 1,092.00
Jumlah C 111,559.00

D Jumlah Total (A+B+C) 259,508.00


E Overhead & profit (Contoh 15% x D) 38,926.20
F Harga Satuan Pekerjaan (D+E) 298,434.20

5.12 1 M Pasang pipa HDPE 160 mm (6")


A Bahan
Pipa pvc 1.0000 m 297,675.00 297,675.00
Jumlah A 297,675.00
B Tenaga
Pekerja 0.0350 Oh 112,000.00 3,920.00
Tukang batu/pipa 0.0170 Oh 112,000.00 1,904.00
Mandor 0.0030 Oh 125,000.00 375.00
Jumlah B 6,199.00
C Peralatan
Mesin sambung pipa Butt Fussion/Elektro Fussion 0.5823 Jam 130,000.00 75,699.00
Genset 0.4052 Jam 85,000.00 34,442.00
Scrapper 0.0163 Jam 20,000.00 326.00
Pick Up 0.0052 Jam 210,000.00 1,092.00
Jumlah C 111,559.00

D Jumlah Total (A+B+C) 415,433.00


E Overhead & profit (Contoh 15% x D) 62,314.95
F Harga Satuan Pekerjaan (D+E) 477,747.95
6 PEKERJAAN CAT-CATAN
6.1 1 M2 Pengecatan Bidang Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A Bahan
Plamir 0.1000 Kg 22,000.00 2,200.00
Cat Dasar 0.1000 Kg 20,000.00 2,000.00
Cat Penutup 2 Kali 0.2600 Kg 52,000.00 13,520.00
Jumlah A 17,720.00
B Tenaga
Pekerja 0.0200 Oh 112,000.00 2,240.00
Tukang Cat 0.0630 Oh 112,000.00 7,056.00
Kepala tukang 0.0063 Oh 125,000.00 787.50
Mandor 0.0025 Oh 125,000.00 312.50
Jumlah B 10,396.00
C Jumlah Total (A+B) 28,116.00
D Overhead & profit (Contoh 15% x C) 4,217.40
E Harga Satuan Pekerjaan (C+D) 32,333.40

6.2 1 M2 Pengecatan Bidang Kayu (Besi), 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A Bahan
Minyak cat 0.2000 Ltr 11,000.00 2,200.00
Cat Dasar 0.1700 Kg 20,000.00 3,400.00
Cat Penutup 2 Kali 0.2600 Kg 52,000.00 13,520.00
Jumlah A 19,120.00
B Tenaga
Pekerja 0.0700 Oh 112,000.00 7,840.00
Tukang Cat 0.0060 Oh 112,000.00 672.00
Kepala tukang 0.0900 Oh 125,000.00 11,250.00
Mandor 0.0025 Oh 125,000.00 312.50
Jumlah B 20,074.50
C Jumlah Total (A+B) 39,194.50
D Overhead & profit (Contoh 15% x C) 5,879.18
E Harga Satuan Pekerjaan (C+D) 45,073.68
DAFTAR UPAH DAN BAHAN
###
NO. URAIAN SATUAN HARGA KET.

I. UPAH KERJA
1 Pembantu Tukang Hari 112,000.00 ###
2 Pekerja Hari 112,000.00 ###
3 Tukang Kayu, Batu, Besi, Cat dan Pipa Hari 112,000.00 ###
4 Kepala Tukang Hari 125,000.00 ###
5 Mandor Hari 125,000.00 ###
6 Operator Terlatih Hari 250,000.00
7 Pembantu Operator Hari 112,000.00

II. BAHAN
1 Tanah Urug M3 125,000.00
2 Tanah Laterit M3 125,000.00
3 Pasir Urug M3 164,000.00
4 Pasir Pasang M3 197,000.00
5 Pasir Beton M3 197,000.00
6 Pasir Batu M3 129,400.00
7 Semen PC Kg 1,600.00
8 Batu Gunung M3 204,000.00
9 Batu split 2/3 M3 230,000.00
10 Besi Beton Kg 10,000.00
11 Besi Kawat Bendrat Kg 20,000.00
12 Paku biasa Kg 20,000.00
13 Air Bersih Ltr 30.00
14 Plywood Lembar 155,000.00
15 Kayu Bekisting Kayu Kelas III m3 1,500,000.00
Kayu Balok Kelas II m3 2,200,000.00
Kayu perancah / andang btg 15,000.00
Plameer 22,000.00
Cat Dasar 20,000.00
Cat penutup 52,000.00
16 Oli Mesin liter 35,000.00
17 Baut dia. 16 mm Bh 1,000.00
18 Baut & Muur Bj 2,300.00
19 Pipa Besi Galvanis 1/2" (sudah dg drat muka-belakang) M' 29,900.00
20 Pipa Besi Galvanis 2" (Med. A, 6m) M' 115,000.00
21 Pipa Besi Galvanis 3" (Med. A, 6m) M' 172,500.00
22 Pipa HDPE (PN 12,5) 1/2" M' 80,500.00
23 Pipa HDPE (PN 10) 1,5" M' 8,050.00
24 ###Pompa Submersible setara Grunfosh, Kap. 5 m3/jam + Kabel Unit 16,157,500.00
25 ###Pemasangan Listrik PLN 3500 Watt, 1 Phase Unit 6,000,000.00
25 Lem PVC 400 gram merk TruGlue Klg 51,750.00
26 PVC 1,5" AW btg 69,000.00
26 Pipa PVC SNI f 1,5" (50mm), S-12.5, 6 m, setara Maspion M' 17,000.00
27 Pipa PVC SNI f 2" (63mm), S-12.5, 6 m, setara Maspion M' 30,000.00
28 Pipa PVC SNI f 3" (90mm), S-12.5, 6 m, setara Maspion M' 55,000.00
29 Tee 90 x 90 (3") SNI Bh 115,000.00
30 Tee 63 x 63 (2") SNI Bh 57,500.00
31 Tee 50 x 50 (1,5") Bh 18,400.00
32 Knee 90 (3") SNI Bh 46,000.00
33 Knee 63 (2") SNI Bh 23,000.00
34 Knee 50 (1,5") SNI Bh 11,500.00
35 Water Meter Merk Barindo (Plastik) Bh 287,500.00
36 Water Meter Merk Onda Bh 402,500.00
37 Stop Kran AW (2") Tangkai Plastik Bh 86,250.00
38 Stop Kran AW (3") Tangkai Plastik Bh 373,750.00
39 Clamp Sadle 90 ke 1/2 Bh 59,800.00
40 Clamp Sadle 63 ke 1/2 Bh 46,000.00
41 Clamp Sadle 50 ke 1/2 Bh 34,500.00
42 Reducer 90 ke 63 (SNI) Bh 69,000.00
43 Reducer 90 ke 50 (SNI) Bh 60,375.00
44 Reducer 63 ke 50 (SNI) Bh 23,920.00
45 Dop (End Cap) 2" SNI bh 17,940.00
46 Dop (End Cap) 1,5" SNI bh 10,350.00

III. ALAT
1 Butt Fussion jam 165,000.00
2 Genset jam 185,000.00
3 Genset Hari 1,480,000.00
4 potong pipa T2/mekanik Hari 85,000.00
5 Mobil Pick Up jam 90,000.00
6 Scrapper jam 30,000.00
7 Pompa Hari 75,000.00
DAFTAR ANALISA
HARGA SATUAN JUMLAH
NO. URAIAN KOEFISIEN SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
I PEKERJAAN TANAH
I.1 1M3 Galian tanah Keras sedalam 1 meter
A Bahan -
Jumlah A -

B Tenaga
Pekerja 1.000 Oh 112,000.00 112,000.00
Mandor 0.032 Oh 125,000.00 4,000.00
Jumlah B 116,000.00
C Jumlah Total (A+B) 116,000.00
D Overhead & profit (Contoh 15% x C) 17,400.00
E Harga Satuan Pekerjaan (C+D) 133,400.00

I.2 1 M3 Urugan kembali


A Bahan -
Pasir urug Jumlah A -

B Tenaga
Pekerja 0.500 Oh 112,000.00 56,000.00
Mandor 0.050 Oh 125,000.00 6,250.00
Jumlah B 62,250.00
C Jumlah Total (A+B) 62,250.00
D Overhead & profit (Contoh 15% x C) 9,337.50
E Harga Satuan Pekerjaan (C+D) 71,587.50

I.3 1 M3 Urugan pasir


A Bahan
Pasir urug 1.200 M3 164,000.00 196,800.00
Jumlah A 196,800.00
B Tenaga
Pekerja 0.300 Oh 112,000.00 33,600.00
Mandor 0.010 Oh 125,000.00 1,250.00
Jumlah B 34,850.00
C Jumlah Total (A+B) 231,650.00
D Overhead & profit (Contoh 15% x C) 34,747.50
E Harga Satuan Pekerjaan (C+D) 266,397.50

I.4 1 M3 Urugan tanah


A Bahan
Tanah urug 1.200 M3 125,000.00 150,000.00
Jumlah A 150,000.00
B Tenaga
Pekerja 0.300 Oh 112,000.00 33,600.00
Mandor 0.010 Oh 125,000.00 1,250.00
Jumlah B 34,850.00
C Jumlah Total (A+B) 184,850.00
D Overhead & profit (Contoh 15% x C) 27,727.50
E Harga Satuan Pekerjaan (C+D) 212,577.50

II PEKERJAAN PONDASI
II.1 1M3 Pas. Pondasi Batu Kali 1 Pc : 4 Ps
A. Bahan
Batu Gunung 1.100 M3 204,000.00 224,400.00
Semen Portland 163.000 Kg 1,600.00 260,800.00
Pasir pasang 0.520 M3 197,000.00 102,440.00
Jumlah A 587,640.00
B. Tenaga
Pekerja 1.500 Oh 112,000.00 168,000.00
Tukang batu 0.600 Oh 112,000.00 67,200.00
Kepala tukang 0.060 Oh 125,000.00 7,500.00
Mandor 0.075 Oh 125,000.00 9,375.00
Jumlah B 252,075.00
C Jumlah Total (A+B) 839,715.00
D Overhead & profit (Contoh 15% x C) 125,957.25
E Harga Satuan Pekerjaan (C+D) 965,672.25

III PEKERJAAN BETON


III.1 1M3 Membuat lantai kerja beton, 1 Pc : 3 Ps : 5 Kr
A Bahan
Semen Portland 230.000 Kg 1,600.00 368,000.00
Pasir beton 0.520 M3 197,000.00 102,440.00
Kerikil cor 0.870 M3 230,000.00 200,100.00
Jumlah A 670,540.00
B Tenaga
Pekerja 1.200 Oh 112,000.00 134,400.00
Tukang batu 0.200 Oh 112,000.00 22,400.00
Kepala tukang 0.020 Oh 125,000.00 2,500.00
Mandor 0.060 Oh 125,000.00 7,500.00
Jumlah B 166,800.00
C Jumlah Total (A+B) 837,340.00
D Overhead & profit (Contoh 15% x C) 125,601.00
E Harga Satuan Pekerjaan (C+D) 962,941.00

III.2 1 M3 Membuat pondasi beton bertulang ( 150 Kg Besi + Bekisting )


Bahan
Kayu bekisting 0.200 M3 1,500,000.00 300,000.00
Paku 1.500 Kg 20,000.00 30,000.00
Minyak bekisting 0.400 Ltr 10,000.00 4,000.00
Besi beton polos 157.500 Kg 10,000.00 1,575,000.00
Kawat beton 2.250 Kg 20,000.00 45,000.00
Semen Portland 336.000 Kg 1,600.00 537,600.00
Pasir beton 0.540 M3 197,000.00 106,380.00
Kerikil Cor 0.810 M3 230,000.00 186,300.00
Jumlah A 2,784,280.00
Tenaga
Pekerja 5.300 Oh 112,000.00 593,600.00
Tukang batu 0.275 Oh 112,000.00 30,800.00
Tukang Kayu 1.300 Oh 112,000.00 145,600.00
Tukang besi 1.050 Oh 112,000.00 117,600.00
Kepala tukang 0.262 Oh 125,000.00 32,750.00
Mandor 0.265 Oh 125,000.00 33,125.00
Jumlah B 953,475.00
C Jumlah Total (A+B) 3,737,755.00
D Overhead & profit (Contoh 15% x C) 560,663.25
E Harga Satuan Pekerjaan (C+D) 4,298,418.25

III.3 1 M3 Membuat sloof beton bertulang ( 200 Kg Besi + Bekisting )


A Bahan
Kayu bekisting 0.270 M3 1,500,000.00 405,000.00
Paku 2.000 Kg 20,000.00 40,000.00
Minyak bekisting 0.600 Ltr 10,000.00 6,000.00
Besi beton polos 210.000 Kg 10,000.00 2,100,000.00
Kawat beton 3.000 Kg 20,000.00 60,000.00
Semen Portland 336.000 Kg 1,600.00 537,600.00
Pasir beton 0.540 M3 197,000.00 106,380.00
Kerikil Cor 0.810 M3 230,000.00 186,300.00
Jumlah A 3,441,280.00
B Tenaga
Pekerja 5.650 Oh 112,000.00 632,800.00
Tukang batu 0.275 Oh 112,000.00 30,800.00
Tukang Kayu 1.560 Oh 112,000.00 174,720.00
Tukang besi 1.400 Oh 112,000.00 156,800.00
Kepala tukang 0.323 Oh 125,000.00 40,375.00
Mandor 0.283 Oh 125,000.00 35,375.00
Jumlah B 1,070,870.00
C Jumlah Total (A+B) 4,512,150.00
D Overhead & profit (Contoh 15% x C) 676,822.50
E Harga Satuan Pekerjaan (C+D) 5,188,972.50

III.4 1 M3 Membuat kolom beton bertulang ( 150 Kg Besi + Bekisting )


A Bahan
Kayu bekisting 0.320 M3 1,500,000.00 480,000.00
Paku 3.200 Kg 20,000.00 64,000.00
Minyak bekisting 1.600 Ltr 10,000.00 16,000.00
Besi beton polos 157.500 Kg 10,000.00 1,575,000.00
Kawat beton 2.250 Kg 20,000.00 45,000.00
Semen Portland 336.000 Kg 1,600.00 537,600.00
Pasir beton 0.540 M3 197,000.00 106,380.00
Kerikil Cor 0.810 M3 230,000.00 186,300.00
Kayu Kelas II balok 0.120 M3 1,500,000.00 180,000.00
Plywood 9mm 2.800 Lbr 155,000.00 434,000.00
Galam 32.000 Btg 11,000.00 352,000.00
Jumlah A 3,976,280.00
B Tenaga
Pekerja 5.300 Oh 112,000.00 593,600.00
Tukang batu 0.275 Oh 112,000.00 30,800.00
Tukang Kayu 1.300 Oh 112,000.00 145,600.00
Tukang besi 1.050 Oh 112,000.00 117,600.00
Kepala tukang 0.265 Oh 125,000.00 33,125.00
Mandor 0.265 Oh 125,000.00 33,125.00
Jumlah B 953,850.00
C Jumlah Total (A+B) 4,930,130.00
D Overhead & profit (Contoh 15% x C) 739,519.50
E Harga Satuan Pekerjaan (C+D) 5,669,649.50

III.5 1 M3 Membuat Plat beton bertulang ( 150 Kg Besi + Bekisting )


A Bahan
Kayu bekisting 0.32 M3 1,500,000.00 480,000.00
Paku 3.2 Kg 20,000.00 64,000.00
Minyak bekisting 1.6 Ltr 10,000.00 16,000.00
Besi beton polos 157.5 Kg 10,000.00 1,575,000.00
Kawat beton 2.25 Kg 20,000.00 45,000.00
Semen Portland 336 Kg 1,600.00 537,600.00
Pasir beton 0.54 M3 197,000.00 106,380.00
Kerikil Cor 0.81 M3 230,000.00 186,300.00
Kayu Kelas II balok 0.12 M3 1,500,000.00 180,000.00
Plywood 9mm 2.8 Lbr 155,000.00 434,000.00
Galam 32 Btg 11,000.00 352,000.00
Jumlah A 3,976,280.00
B Tenaga
Pekerja 5.3 Oh 112,000.00 593,600.00
Tukang batu 0.275 Oh 112,000.00 30,800.00
Tukang Kayu 1.3 Oh 112,000.00 145,600.00
Tukang besi 1.05 Oh 112,000.00 117,600.00
Kepala tukang 0.265 Oh 125,000.00 33,125.00
Mandor 0.265 Oh 125,000.00 33,125.00
Jumlah B 953,850.00
C Jumlah Total (A+B) 4,930,130.00
D Overhead & profit (Contoh 15% x C) 739,519.50
E Harga Satuan Pekerjaan (C+D) 5,669,649.50

III.6 1 M' Membuat Kolom Praktis


A Bahan
Kayu bekisting 0.002 M3 1,500,000.00 3,000.00
Paku 0.010 Kg 20,000.00 200.00
Besi beton polos 3.000 Kg 10,000.00 30,000.00
Kawat beton 0.045 Kg 20,000.00 900.00
Semen Portland 4.000 Kg 1,600.00 6,400.00
Pasir beton 0.006 M3 197,000.00 1,182.00
Kerikil Cor 0.009 M3 230,000.00 2,070.00
Jumlah A 43,752.00
B Tenaga
Pekerja 0.180 Oh 112,000.00 20,160.00
Tukang batu 0.020 Oh 112,000.00 2,240.00
Tukang Kayu 0.020 Oh 112,000.00 2,240.00
Tukang besi 0.020 Oh 112,000.00 2,240.00
Kepala tukang 0.006 Oh 125,000.00 750.00
Mandor 0.009 Oh 125,000.00 1,125.00
Jumlah B 28,755.00
C Jumlah Total (A+B) 72,507.00
D Overhead & profit (Contoh 15% x C) 10,876.05
E Harga Satuan Pekerjaan (C+D) 83,383.05

IV PEKERJAAN PASANGAN DINDING


IV.1 1 M2 Pasangan batako
A Bahan
Batako 12.500 buah 2,500.00 31,250.00
Semen Portland 12.130 Kg 1,600.00 19,408.00
Pasir pasang 0.032 M3 197,000.00 6,304.00
Jumlah A 56,962.00
B Tenaga
Pekerja 0.300 Oh 112,000.00 33,600.00
Tukang batu 0.150 Oh 112,000.00 16,800.00
Kepala tukang 0.015 Oh 125,000.00 1,875.00
Mandor 0.015 Oh 125,000.00 1,875.00
Jumlah B 54,150.00
C Jumlah Total (A+B) 111,112.00
D Overhead & profit (Contoh 15% x C) 16,666.80
E Harga Satuan Pekerjaan (C+D) 127,778.80

V PEKERJAAN PLESTERAN
V.1 1 M2 Plesteran 1 Pc : 4 Ps, tebal 15 mm
A Bahan
Semen Portland 6.240 Kg 1,600.00 9,984.00
Pasir pasang 0.024 M3 197,000.00 4,728.00
Jumlah A 14,712.00
B Tenaga
Pekerja 0.300 Oh 112,000.00 33,600.00
Tukang batu 0.150 Oh 112,000.00 16,800.00
Kepala tukang 0.015 Oh 125,000.00 1,875.00
Mandor 0.015 Oh 125,000.00 1,875.00
Jumlah B 54,150.00
C Jumlah Total (A+B) 68,862.00
D Overhead & profit (Contoh 15% x C) 10,329.30
E Harga Satuan Pekerjaan (C+D) 79,191.30

V.2 1 M2 Ondrongan
A Bahan
Semen Portland 3.250 Kg 1,600.00 5,200.00
Jumlah A 5,200.00
B Tenaga
Pekerja 0.200 Oh 112,000.00 22,400.00
Tukang batu 0.100 Oh 112,000.00 11,200.00
Kepala tukang 0.010 Oh 125,000.00 1,250.00
Mandor 0.010 Oh 125,000.00 1,250.00
Jumlah B 36,100.00
C Jumlah Total (A+B) 41,300.00
D Overhead & profit (Contoh 15% x C) 6,195.00
E Harga Satuan Pekerjaan (C+D) 47,495.00

VI PEKERJAAN PIPA INLET - OUTLET


VI.1 1 M Pasang pipa Galvanis 2"
A Bahan
Pipa galvanis 1.000 m 115,000.00 115,000.00
Jumlah A 115,000.00
B Tenaga
Pekerja 0.345 Oh 112,000.00 38,640.00
Tukang batu/pipa 0.172 Oh 112,000.00 19,264.00
Mandor 0.034 Oh 125,000.00 4,250.00
Jumlah B 62,154.00
C Jumlah Total (A+B) 177,154.00
D Overhead & profit (Contoh 15% x C) 26,573.10
E Harga Satuan Pekerjaan (C+D) 203,727.10

VI.2 1 M Pasang pipa Galvanis 3"


A Bahan
Pipa galvanis 1.000 m 115,000.00 115,000.00
Jumlah A 115,000.00
B Tenaga
Pekerja 0.400 Oh 112,000.00 44,800.00
Tukang batu/pipa 0.200 Oh 112,000.00 22,400.00
Mandor 0.040 Oh 125,000.00 5,000.00
Jumlah B 72,200.00
C Jumlah Total (A+B) 187,200.00
D Overhead & profit (Contoh 15% x C) 28,080.00
E Harga Satuan Pekerjaan (C+D) 215,280.00

VI.2.2 1 M Pasang pipa pvc 1/2"


A Bahan
Pipa pvc 1.200 m 3,250.00 3,900.00
Perlengkapan 0.350 % 1,137.50 398.13
Jumlah A 4,298.13
B Tenaga
Pekerja 0.036 Oh 112,000.00 4,032.00
Tukang batu/pipa 0.060 Oh 112,000.00 6,720.00
Kepala Tukang 0.006 Oh 125,000.00 750.00
Mandor 0.002 Oh 125,000.00 225.00
Jumlah B 11,727.00
C Jumlah Total (A+B) 16,025.13
D Overhead & profit (Contoh 15% x C) 2,403.77
E Harga Satuan Pekerjaan (C+D) 18,428.89

VI.2.3 1 M Pasang pipa pvc SNI 1,5" (50 mm)


A Bahan
Pipa pvc 1.000 m 17,000.00 17,000.00
Jumlah A 17,000.00
B Tenaga
Pekerja 0.0810 Oh 112,000.00 9,072.00
Tukang batu/pipa 0.0410 Oh 112,000.00 4,592.00
Mandor 0.0080 Oh 125,000.00 1,000.00
Jumlah B 14,664.00
C Jumlah Total (A+B) 31,664.00
D Overhead & profit (Contoh 15% x C) 4,749.60
E Harga Satuan Pekerjaan (C+D) 36,413.60

VI.2.4 1 M Pasang pipa pvc SNI 2" (63mm)


A Bahan
Pipa pvc 1.000 m 17,000.00 17,000.00
Jumlah A 17,000.00
B Tenaga
Pekerja 0.0810 Oh 112,000.00 9,072.00
Tukang batu/pipa 0.0410 Oh 112,000.00 4,592.00
Mandor 0.0080 Oh 125,000.00 1,000.00
Jumlah B 14,664.00
C Jumlah Total (A+B) 31,664.00
D Overhead & profit (Contoh 15% x C) 4,749.60
E Harga Satuan Pekerjaan (C+D) 36,413.60

VI.2.5 1 M Pasang pipa pvc SNI 3" (90mm)


A Bahan
Pipa pvc 1.000 m 30,000.00 30,000.00
Jumlah A 30,000.00
B Tenaga
Pekerja 0.0940 Oh 112,000.00 10,528.00
Tukang batu/pipa 0.0470 Oh 112,000.00 5,264.00
Mandor 0.0090 Oh 125,000.00 1,125.00
Jumlah B 16,917.00
C Jumlah Total (A+B) 46,917.00
D Overhead & profit (Contoh 15% x C) 7,037.55
E Harga Satuan Pekerjaan (C+D) 53,954.55

VI.3 1 bh Pasang kran 3/4"


A Bahan
Kran air 1.000 bh 35,000.00 35,000.00
Seal tape 0.025 bh 5,000.00 125.00
Jumlah A 35,125.00
B Tenaga
Pekerja 0.010 Oh 70,000.00 700.00
Tukang batu/pipa 0.100 Oh 77,000.00 7,700.00
Kepala Tukang 0.010 Oh 105,000.00 1,050.00
Mandor 0.005 Oh 87,000.00 435.00
Jumlah B 9,885.00
C Jumlah Total (A+B) 45,010.00
D Overhead & profit (Contoh 15% x C) 6,751.50
E Harga Satuan Pekerjaan (C+D) 51,761.50

VII PEKERJAAN CAT-CATAN


VII.1 1 M2 Pengecatan Bidang Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A Bahan
Plamir 0.100 Kg 20,000.00 2,000.00
Cat Dasar 0.100 Kg 17,500.00 1,750.00
Cat Penutup 2 Kali 0.260 Kg 25,000.00 6,500.00
Jumlah A 10,250.00
B Tenaga
Pekerja 0.020 Oh 112,000.00 2,240.00
Tukang Cat 0.063 Oh 112,000.00 7,056.00
Kepala tukang 0.006 Oh 125,000.00 787.50
Mandor 0.003 Oh 125,000.00 312.50
Jumlah B 10,396.00
C Jumlah Total (A+B) 20,646.00
D Overhead & profit (Contoh 15% x C) 3,096.90
E Harga Satuan Pekerjaan (C+D) 23,742.90

VII.2 1 M2 Pengecatan Bidang Kayu (Besi), 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A Bahan
Minyak cat 0.200 Ltr 8,000.00 1,600.00
Cat Dasar 0.170 Kg 22,000.00 3,740.00
Cat Penutup 2 Kali 0.260 Kg 62,000.00 16,120.00
Jumlah A 21,460.00
B Tenaga
Pekerja 0.070 Oh 112,000.00 7,840.00
Tukang Cat 0.006 Oh 112,000.00 672.00
Kepala tukang 0.090 Oh 125,000.00 11,250.00
Mandor 0.003 Oh 125,000.00 312.50
Jumlah B 20,074.50
C Jumlah Total (A+B) 41,534.50
D Overhead & profit (Contoh 15% x C) 6,230.18
E Harga Satuan Pekerjaan (C+D) 47,764.68
PERHITUNGAN PEMBESIAN BRONCAPTERING

Dimensi
no item pekerjaan Sket/Ket Volume satuan
p n tul koef. dia². x

Dinding Vol 1 Arah memanjang 1.60 12.00 0.006165 64.00 2.00 15.15 kg
Arah melintang 1.70 11.00 0.006165 64.00 2.00 14.76 kg
Arah memanjang 1.60 12.00 0.006165 64.00 2.00 15.15 kg
Arah melintang 1.70 11.00 0.006165 64.00 2.00 14.76 kg

Dinding Vol 2 Arah memanjang 1.10 8.00 0.006165 64.00 2.00 6.94 kg
Arah melintang 1.20 8.00 0.006165 64.00 2.00 7.58 kg
Arah memanjang 1.10 8.00 0.006165 64.00 2.00 6.94 kg
Arah melintang 1.20 8.00 0.006165 64.00 2.00 7.58 kg

Dinding Vol 3 Arah memanjang 0.90 4.67 0.006165 64.00 2.00 3.31 kg
Arah melintang 0.70 6.00 0.006165 64.00 2.00 3.31 kg
Arah memanjang 0.90 4.67 0.006165 64.00 2.00 3.31 kg
Arah melintang 0.70 6.00 0.006165 64.00 2.00 3.31 kg
102.11 kg

Dinding Vol 4 Arah memanjang 1.70 14.00 0.006165 64.00 1.00 9.39 kg
Arah melintang 2.10 11.33 0.006165 64.00 1.00 9.39 kg
Arah memanjang 1.70 14.00 0.006165 64.00 1.00 9.39 kg
Arah melintang 2.10 11.33 0.006165 64.00 1.00 9.39 kg

Dinding Vol 5 Arah memanjang 0.70 14.00 0.006165 64.00 2.00 7.73 kg
Arah melintang 2.10 4.67 0.006165 64.00 2.00 7.73 kg
Arah memanjang 0.70 14.00 0.006165 64.00 2.00 7.73 kg
Arah melintang 2.10 4.67 0.006165 64.00 2.00 7.73 kg

Dinding Vol 6 Arah memanjang 0.70 6.00 0.006165 64.00 1.00 1.66 kg
Arah melintang 0.90 4.67 0.006165 64.00 1.00 1.66 kg
71.81 kg

Tutup Vol 1 Arah memanjang 2.60 14.00 0.006165 64.00 1.00 14.36 kg
Arah melintang 2.10 17.33 0.006165 64.00 1.00 14.36 kg

Tutup Vol 2 Arah memanjang 0.90 6.00 0.006165 64.00 1.00 2.13 kg
Arah melintang 0.90 6.00 0.006165 64.00 1.00 2.13 kg

Lantai Vol 1 Arah memanjang 2.60 14.00 0.006165 64.00 1.00 14.36 kg
Arah melintang 2.10 17.33 0.006165 64.00 1.00 14.36 kg

Lantai Vol 2 Arah memanjang 0.90 6.00 0.006165 64.00 1.00 2.13 kg
Arah melintang 0.90 6.00 0.006165 64.00 1.00 2.13 kg
65.97 kg
Angkur Panjang Total Reservoir 0.70 30.00 0.006165 144.00 2.00 37.29 kg
Panjang Total bak kontrol 0.70 8.00 0.006165 144.00 2.00 9.94 kg
47.23 kg
REKAPITULASI
PEKERJAAN : PEMBANGUNAN SPAMS JARINGAN PERPIPAAN DESA BERANGAS KECAMATAN PULAU LAUT TIMUR
LOKASI : DESA BERANGAS KECAMATAN PULAU LAUT TIMUR
KABUPATEN : KOTABARU
PROVINSI : KALIMANTAN SELATAN
TA. : 2020

HARGA
NO URAIAN PEKERJAAN
( Rp )
1 2 3

I PEKERJAN PEMBUATAN MENARA AIR BAK BETON (RESERVOIR) #NAME?

II PEKERJAAN PEMBUATAN BRONCAPTERING #REF!

III PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI DAN AKSESORIES #REF!

IV PENGADAAN DAN PEMASANGAN PAKET SAMBUNGAN RUMAH (SR) : 209 Unit #REF!

V SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI #REF!


JUMLAH #REF!
PPN 10% #REF!
JUMLAH TOTAL #REF!
PEMBULATAN #REF!
Terbilang : LIMA RATUS LIMA PULUH DELAPAN JUTA RUPIAH

Kotabaru, 2020

DISETUJUI OLEH: DIBUAT OLEH :


PEJABAT PEMBUAT KOMITMEN (PPK) KONSULTAN PERENCANA
BIDANG PENYELENGGARAAN SISTEM PENYEDIAAN AIR MINUM CV. QUANTUM TEKNIK
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KAB. KOTABARU

FATHURRAHMAN FADIL,ST,M.IP MUHAMMAD SANUSI


NIP. 19730706 200312 1 009 DIREKTUR
BACK UP VOLUME BESI TULANGAN

PROVINSI : KALIMANTAN SELATAN


KABUPATEN : KOTABARU
KECAMATAN : SAMPANAHAN
LOKASI : DESA BERANGAS

Dimensi
No. Item Pekerjaan Volume Satuan
Panjang n tul Berat/m dia. Jumlah

I.
C pembesian

1 Tulangan lantai Reservoir lebar 2.5*2m


memanjang 2.50 14.00 0.395 Ø8 1.00 13.83 kg
melebar 2.00 17.00 0.395 Ø8 1.00 13.43 kg
Dinding tinggi 1.6m full
Vertikal 1.60 14.00 0.395 Ø8 6.00 53.09 kg
Horizontal 2.00 11.00 0.395 Ø8 6.00 52.14 kg
Plat penutup
memanjang 2.00 10.00 0.395 Ø8 1.00 7.90 kg
melebar 1.50 14.00 0.395 Ø8 1.00 8.30 kg

Dinding 50cm
Vertikal 0.60 14.00 0.395 Ø8 2.00 6.64 kg
Horizontal 2.00 4.00 0.395 Ø8 2.00 6.32 kg
Plat penutup
memanjang 2.00 7.00 0.395 Ø8 1.00 5.53 kg
melebar 1.00 14.00 0.395 Ø8 1.00 5.53 kg
Dinding tinggi 1.10 m full
Vertikal 1.10 14.00 0.395 Ø8 6.00 36.50 kg
Horizontal 2.00 4.00 0.395 Ø8 6.00 18.96 kg
Dinding bak kontrol 60 cm
Vertikal 0.60 6.00 0.395 Ø8 2.00 2.84 kg
Horizontal 0.80 4.00 0.395 Ø8 4.00 5.06 kg
lantai bak kontrol
memanjang 0.80 6.00 0.395 Ø 10 1.00 1.90 kg
melebar 0.80 6.00 0.395 Ø 10 1.00 1.90 kg
Plat penutup
memanjang 0.80 6.00 0.395 Ø8 1.00 1.90 kg
melebar 0.80 6.00 0.395 Ø8 1.00 1.90 kg

Angkur
memanjang 11.4m 0.50 76.00 0.888 Ø 12 1.00 33.74 kg

277.38 kg #REF!

Page 47 of 47 BOQ BESI BAK