PEMBANGUNAN
RUMAH TINGGAL 2
LANTAI
TOTAL JUMLAH
NO URAIAN PEKERJAAN HARGA
(Rp)
1 2 3
LANTAI II
Balok
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 1.50 1,777,168.82
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 192.35 3,155,491.54
- Bekisting Balok M² A.4.1.1.23.a 332,267.07 10.00 3,322,670.70
Plat Lantai 2
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 6.72 7,961,716.31
- Wiremesh Kg A.4.1.1.19 15,947.34 113.83 1,815,240.43
- Bekisting Lantai M² A.4.1.1.24.a 370,391.75 3.78 1,400,080.80
Kolom Lantai 2
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 1.97 2,332,534.07
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 125.84 2,064,419.66
- Bekisting Kolom M² A.4.1.1.22.a 322,151.75 15.75 5,073,889.98
LANTAI ATAP
Ring Balok
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 0.45 533,150.65
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 115.41 1,893,294.92
- Bekisting Balok M² A.4.1.1.23.a 332,267.07 9.00 2,990,403.63