Anda di halaman 1dari 4

(RAB)

RENCANA ANGGARAN BIAYA

PEMBANGUNAN
RUMAH TINGGAL 2
LANTAI

LOKASI : BODOK, KALIMANTAN BARAT


RINCIAN ANGGARAN BIAYA
KEGIATAN : PEKERJAAN RUMAH TINGGAL 2 LANTAI
PEKERJAAN : PEKERJAAN RUMAH TINGGAL 2 LANTAI
LOKASI : BODOK, KABUPATEN SANGGAU
TAHUN : 2021

TOTAL JUMLAH
NO URAIAN PEKERJAAN HARGA
(Rp)
1 2 3

I. PEKERJAAN PERSIAPAN 4,039,244.67

II. PEKERJAAN PONDASI 4,413,802.35

III. PEKERJAAN STRUKTUR 62,978,769.99

IV. PEKERJAAN ATAP 28,454,982.08

V. PEKERJAN FINISHING KERAMIK 27,222,937.50

VI. PEKERJAAN DINDING DAN PLESTERAN 47,533,908.71

VII. PEKERJAAN PLAFOND 18,226,442.20

VIII. PEKERJAAN PINTU, JENDELA DAN VENTILASI 16,897,294.14

IX. PEKERJAAN TOILET 1,587,903.00

X. PEKERJAAN PENGECATAN 16,449,484.20

JUMLAH TOTAL 227,804,768.85


PPN (10%) 22,780,476.88
JUMLAH TOTAL + PPN 250,585,245.73
DIBULATKAN 250,585,200.00
Dua Ratus Lima Puluh Juta Lima Ratus Delapan Puluh Lima Ribu
TERBILANG
Dua Ratus Rupiah
RINCIAN ANGGARAN BIAYA
NAMA KEGIATAN : PEKERJAAN RUMAH TINGGAL 2 LANTAI
PEKERJAAN : PEKERJAAN RUMAH TINGGAL 2 LANTAI
LOKASI : BODOK, KABUPATEN SANGGAU
TAHUN : 2021

KODE HARGA SATUAN


NO URAIAN PEKERJAAN SAT VOLUME JUMLAH TOTAL (Rp.)
ANALISA (Rp.)
1 2 3 4 5 6 7
I. PEKERJAAN PERSIAPAN
1 Papan Nama Proyek ls 100,000.00 1.00 100,000.00
2 Mobilisasi & Demobilisasi ls 500,000.00 1.00 500,000.00
3 Pemasangan Bowplank m' A.2.2.1.4 101,154.26 34.00 3,439,244.67

Sub Total I 4,039,244.67


II. PEKERJAAN PONDASI
Galian Tanah Pondasi M³ A.2.3.1.1 83,038.13 4.50 373,671.56
Urugan Pasir M³ A.2.3.1.11 183,965.25 0.45 82,784.36
Lantai Kerja M³ A.4.1.1.1.a 979,989.86 0.45 440,995.44
Pondasi Type 1
- Beton K-250 Kg A.4.1.1.10.a 1,184,779.21 1.15 1,364,865.65
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 83.09 1,363,172.35
- Bekisting Pondasi M² A.4.1.1.20.a 136,859.90 5.76 788,313.00

Sub Total II 4,413,802.35


III. PEKERJAAN STRUKTUR
LANTAI 1
Sloof
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 1.50 1,777,168.82
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 192.35 3,155,491.54
- Bekisting Sloof M² A.4.1.1.21.a 136,859.90 15.00 2,052,898.43
Plat Lantai 1
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 7.35 8,708,127.21
- Wiremesh Kg A.4.1.1.19 15,947.34 129.92 2,071,874.48
- Bekisting Lantai M² A.4.1.1.24.a 370,391.75 3.84 1,422,304.30
Kolom Lantai 1
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 1.97 2,332,534.07
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 125.84 2,064,419.66
- Bekisting Kolom M² A.4.1.1.22.a 322,151.75 15.75 5,073,889.98

LANTAI II
Balok
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 1.50 1,777,168.82
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 192.35 3,155,491.54
- Bekisting Balok M² A.4.1.1.23.a 332,267.07 10.00 3,322,670.70
Plat Lantai 2
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 6.72 7,961,716.31
- Wiremesh Kg A.4.1.1.19 15,947.34 113.83 1,815,240.43
- Bekisting Lantai M² A.4.1.1.24.a 370,391.75 3.78 1,400,080.80
Kolom Lantai 2
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 1.97 2,332,534.07
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 125.84 2,064,419.66
- Bekisting Kolom M² A.4.1.1.22.a 322,151.75 15.75 5,073,889.98

LANTAI ATAP
Ring Balok
- Beton K-250 M³ A.4.1.1.8.a 1,184,779.21 0.45 533,150.65
- Tulangan U32 Kg A.4.1.1.17.a 16,405.12 115.41 1,893,294.92
- Bekisting Balok M² A.4.1.1.23.a 332,267.07 9.00 2,990,403.63

Sub Total III 62,978,769.99


IV. PEKERJAAN ATAP
Rangka Baja Ringan Zincalume (truss/polos) M² A.4.2.1.22 429,137.01 45.00 19,311,165.45
Atap Steel Sheet 0,35 M² A.4.5.2.41.a 203,195.93 45.00 9,143,816.63
Perabung M' 7.00 -
Talang Air M' - -

Sub Total IV 28,454,982.08


V. PEKERJAN FINISHING KERAMIK
LANTAI 1
Lantai Keramik 40 x 40 cm Polished M² A.4.4.3.35.b 272,229.38 55.00 14,972,615.63
LANTAI 2
Lantai Keramik 40 x 40 cm Polished M² A.4.4.3.35.b 272,229.38 45.00 12,250,321.88

Sub Total V 27,222,937.50


KODE HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH TOTAL (Rp.)
ANALISA (Rp.)
1 2 3 4 5 6 7

VI. PEKERJAAN DINDING DAN PLESTERAN


LANTAI 1
Dinding Batako Uk. 20x40x7 M² A.4.4.1.17.b 104,359.20 150.15 15,669,533.88
Plesteran Dinding Batako M² A.4.4.2.6 66,104.88 150.15 9,925,647.73
LANTAI 2
Dinding Batako Uk. 20x40x7 M² A.4.4.1.17.b 104,359.20 128.70 13,431,029.04
Plesteran Dinding Batako M² A.4.4.2.6 66,104.88 128.70 8,507,698.06

Sub Total VI 47,533,908.71


VII. PEKERJAAN PLAFOND
LANTAI 1
Rangka Plafond Metalfuring M² A.4.2.1.21 130,000.00 55.00 7,150,000.00
Plafond Gypsum Board 9 mm M² A.4.5.1.7 52,264.42 55.00 2,874,543.21
LANTAI 2
Rangka Plafond Metalfuring M² A.4.2.1.21 130,000.00 45.00 5,850,000.00
Plafond Gypsum Board 9 mm M² A.4.5.1.7 52,264.42 45.00 2,351,898.99

Sub Total VII 18,226,442.20


VIII. PEKERJAAN PINTU, JENDELA DAN VENTILASI
Pintu Unit A.4.6.1.6.a 633,351.00 16.00 10,133,616.00
Jendela Unit A.4.6.1.6.a 633,351.00 4.00 2,533,404.00
Ventilasi Unit A.4.6.1.6.a 633,351.00 1.20 760,021.20
Kusen Kayu M³ A.4.6.1.1 21,474,337.50 0.16 3,470,252.94

Sub Total VIII 16,897,294.14


IX. PEKERJAAN TOILET
Kloset Unit A.5.1.1 2. 552,046.50 2.00 1,104,093.00
Kran Air Stainless Bh A.5.1.1.19. 90,952.50 4.00 363,810.00
Tempat Sabun Bh 60,000.00 2.00 120,000.00

Sub Total IX 1,587,903.00


X. PEKERJAAN PENGECATAN
Cat Tembok Interior M² A.4.7.1.10. 43,419.52 61.85 2,685,497.16
Cat Tembok Weathershield M² A.4.7.1.10. 43,419.52 217.00 9,422,035.30
Cat Plafond Interior M² A.4.7.1.10. 43,419.52 100.00 4,341,951.75

Sub Total X 16,449,484.20


JUMLAH TOTAL 227,804,768.85
PPN (10%) 22,780,476.88
JUMLAH TOTAL + PPN 250,585,245.73