Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

I. PEKERJAAN PERSIAPAN
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN VOLUME JUMLAH HARGA (Rp)
(Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
A Pekerjaan Pembersihan Lapangan m2 512,00 8.200,00 4.198.400,00

TOTAL 4.198.400,00

II. RUANG BELAJAR


HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN VOLUME JUMLAH HARGA (Rp)
(Rp)
1 2 3 4 5 6
A PEKERJAAN PENDAHULUAN
1 Pek. Pemasangan Bowplank m' 96,00 55.320,00 5.310.720,00
SUB TOTAL 5.310.720,00
B PEKERJAAN PONDASI
1 Galian m3 50,27 61.500,00 3.091.605,00
2 Timbunan m3 -
3 Pondasi Sumuran Ø 100 cm, Dalam = 2,00 m Titik 32,00 2.174.752,70 69.592.086,40
4 Pondasi Tapak
a. Bekisting m2 86,40 118.060,00 10.200.384,00
b. Tulangan kg 2.594,13 10.933,00 28.361.623,29
c. Beton K 250 m3 38,03 921.816,76 35.056.691,56
SUB TOTAL 146.302.390,25
C PEKERJAAN STRUKTUR BETON BERTULANG
1 Pekerjaan Sloof
a. Pek. Bekisting m3 125,08 118.060,00 14.766.944,80
b. Pek. Besi Tulangan kg 4.715,04 10.933,00 51.549.532,32
c. Pek. Beton K-250 m3 17,29 921.816,76 15.938.211,86

2 Pas. Kolom
a. Pek. Bekisting m3 144,70 182.780,00 26.448.266,00
b. Pek. Besi Tulangan kg 4.186,24 10.933,00 45.768.161,92
c. Pek. Beton K-250 m3 11,27 921.816,76 10.388.874,94

3 Pas. Balok
a. Pek. Bekisting m3 253,98 186.080,00 47.260.598,40
b. Pek. Besi Tulangan kg 6.509,59 10.933,00 71.169.347,47
c. Pek. Beton K-250 m3 43,90 921.816,76 40.467.755,96

4 Pas. Plat Lantai


a. Pek. Bekisting m3 266,67 118.060,00 31.483.060,20
b. Pek. Besi Tulangan kg 5.741,82 10.933,00 62.775.318,06
c. Pek. Beton K-250 m3 27,49 921.816,76 25.340.742,86

5 Pas. Tangga
a. Pek. Bekisting m3 60,40 118.060,00 7.130.824,00
b. Pek. Besi Tulangan kg 1.083,68 10.933,00 11.847.873,44
c. Pek. Beton K-250 m3 10,45 921.816,76 9.632.985,19
SUB TOTAL 471.968.497,42
D PEKERJAAN DINDING
1 Pasangan Bata Ringan Hebel uk. 10 x 20 x 60 cm m2 214,19 145.579,38 31.181.647,40
2 Pasang Angker Besi kg 132,61 5.000,00 663.050,00
SUB TOTAL 31.844.697,40
E PEKERJAAN PLESTERAN
1 Plesteran dinding 1:4 m2 428,38 53.612,40 22.966.479,91
SUB TOTAL 22.966.479,91
F PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pasang Kusen Pintu & Jendela m3 2,26 5.283.500,00 11.940.710,00
2 Pasang Pintu Panel m2 10,56 536.000,00 5.660.160,00
3 Pasang Jendela Rangka Kayu m2 22,05 446.400,00 9.843.120,00
4 Pasang Kaca Mati m2 15,96 114.030,00 1.819.918,80
5 Pasangan Jalusi m2 24,60 429.340,00 10.561.764,00
6 Pasang Engsel 4" bh 12,00 24.780,00 297.360,00
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN VOLUME JUMLAH HARGA (Rp)
(Rp)
7 Pasang Engsel 3" bh 56,00 17.520,00 981.120,00
8 Pasang Kunci Tanam bh 4,00 109.320,00 437.280,00
9 Pasang Kunci Slot Psg 56,00 23.780,00 1.331.680,00
10 Pasang Kait Angin Psg 56,00 25.780,00 1.443.680,00
SUB TOTAL 44.316.792,80
G PEKERJAAN PLAFOND
1 Pasang Ranga Besi Hollow 40 x 40 m2 257,66 47.187,50 12.158.331,25
2 Pasang Plafond Gypsum (uk. 120 x 240) Tebal 9 mm m2 257,66 51.482,00 13.264.852,12
3 Pasang List Gypsum m' 263,00 12.750,00 3.353.250,00
SUB TOTAL 28.776.433,37
H PEKERJAAN LANTAI
1 Timbunan m3 177,87 60.600,00 10.778.922,00
2 Cor Beton B0 m3 19,91 602.187,46 11.989.552,33
3 Pasangan Lantai Keramik Ukuran 40 x 40 cm m2 157,66 154.800,00 24.405.768,00
SUB TOTAL 47.174.242,33
I PEKERJAAN PENGECATAN
1 Cat Tembok m2 428,38 28.351,00 12.145.001,38
SUB TOTAL 12.145.001,38
J PEKERJAAN LISTRIK
1 Instalasi Listrik Titik 12,00 180.000,00 2.160.000,00
2 Saklar Tunggal bh 5,00 65.000,00 325.000,00
3 Stop Kontak bh 5,00 35.000,00 175.000,00
4 Pasang Lampu TL bh 12,00 90.000,00 1.080.000,00
SUB TOTAL 3.740.000,00
TOTAL 814.545.254,86