HARGA
No URAIAN PEKERJAAN SAT. VOL. JUMLAH
SATUAN
I PEKERJAAN PENDAHULUAN
c. Sewa Direksi Keet / Kantor Sementara, Gudang Alat dan Bahan m2 9.00 1,597,417.58 14,376,758.26
II.1 PONDASI
STRUKTUR BAWAH
A. Pekerjaan galian tanah manual
F. Pembesian
a. Pile Cap
Pile Cap 1 kg 3,953.99 13,348.95 52,781,668.69
b. Sloof
Sloof 1 kg 3,039.27 13,348.95 40,571,073.30
c. kolam
kolam kg 10,912.00 13,348.95 145,663,734.89
d. dinding kolam
dinding kolam kg 1,871.21 13,348.95 24,978,736.17
G. Bekesting halus :
a. Pile Cap
Pile Cap 1 (pondasi 1) m2 53.76 212,071.62 11,400,970.54
b. Sloof
Sloof 1 m2 283.78 219,645.12 62,330,370.70
H. Tanah Urug
Lantai Kolam m3 711.18 317,109.30 225,522,256.83