C PEKERJAAN BETON
1 Lantai kerja pondasi t = 5 cm
a. Beton mutu K-100 2,07 m3 969.499,86 2.003.471,46
2 Pek.Foot Plat ( 100 x 100 x 30 )
a. Beton mutu K-225 4,80 m3 1.106.480,34 5.311.105,63
b. Pembesian 1.071,82 kg 17.226,79 18.464.099,57
c. Begisting 1x pakai 21,12 m2 192.047,75 4.056.048,48
3 Pek.Foot Plat ( 120 x 120 x 30 )
a. Beton mutu K-225 5,62 m3 1.106.480,34 6.213.993,59
b. Pembesian 1.075,98 kg 17.226,79 18.535.605,74
c. Begisting 1x pakai 20,28 m2 192.047,75 3.894.728,37
4 Pek.Foot Plat Tangga ( 100 x 60 x 30 )
a. Beton mutu K-225 0,54 m3 1.106.480,34 597.499,38
b. Pembesian 146,28 kg 17.226,79 2.519.946,40
c. Begisting 1x pakai 3,60 m2 192.047,75 691.371,90
5 Pek. Kolom pedestal 30 x 30 (t = 1,5 m)
a. Beton mutu K-225 2,16 m3 1.106.480,34 2.389.997,53
b. Pembesian 250,85 kg 17.226,79 4.321.289,85
c. Begisting 1 x pakai 28,80 m2 295.002,40 8.496.069,12
6 Pek. Kolom pedestal 40 x 40 (t = 1,5 m)
a. Beton mutu K-225 3,12 m3 1.106.480,34 3.452.218,66
b. Pembesian 395,83 kg 17.226,79 6.818.865,61
c. Begisting 1 x pakai 31,20 m2 295.002,40 9.204.074,88
7 Pek. Sloof S1 20 x 30
a. Beton mutu K-225 9,00 m3 1.106.480,34 9.958.323,06
b. Pembesian 1.283,70 kg 17.226,79 22.114.102,53
c. Begisting 2 x pakai 90,00 m2 192.047,75 17.284.297,50
8 Pek. Sloof S2 15 x 20
a. Beton mutu K-225 0,28 m3 1.106.480,34 312.027,46
b. Pembesian 38,39 kg 17.226,79 661.373,89
c. Begisting 2 x pakai 3,76 m2 192.047,75 722.099,54
9 Kolom struktur K2 30 x 30
a. Beton mutu K-225 7,38 m3 1.106.480,34 8.165.824,91
b. Pembesian 1.731,88 kg 17.226,79 29.834.792,38
c. Begisting 2 x pakai 98,40 m2 295.002,40 29.028.236,16
10 Kolom struktur K3 40 x 40
a. Beton mutu K-225 10,80 m3 1.106.480,34 11.949.987,67
b. Pembesian 1.691,40 kg 17.226,79 29.137.365,49
c. Begisting 2 x pakai 108,00 m2 295.002,40 31.860.259,20
11 Kolom praktis Kp 15 x 15
a. Beton mutu K-225 0,24 m3 1.106.480,34 268.874,72
b. Pembesian 183,12 kg 17.226,79 3.154.625,06
c. Begisting 2 x pakai 23,19 m2 295.002,40 6.842.167,66
12 Balok Struktur B1 25 x 40
a. Beton mutu K-225 9,18 m3 1.106.480,34 10.157.489,52
b. Pembesian 1.401,90 kg 17.226,79 24.150.170,71
c. Begisting 2 x pakai 96,39 m2 203.778,40 19.642.199,98
NO URAIAN VOLUME SATUAN HARGA SATUAN JUMLAH
1 2 3 4 6 7
13 Balok Anak B2 20 x 30
a. Beton mutu K-225 3,06 m3 1.106.480,34 3.385.829,84
b. Pembesian 509,24 kg 17.226,79 8.772.502,07
c. Begisting 2 x pakai 43,35 m2 203.778,40 8.833.793,64
14 Balok Anak B3 15 x 35
a. Beton mutu K-225 0,81 m3 1.106.480,34 900.398,38
b. Pembesian 136,55 kg 17.226,79 2.352.233,00
c. Begisting 2 x pakai 13,18 m2 203.778,40 2.684.780,42
15 Balok Latei BL-1 15x15
a. Beton mutu K-225 1,39 m3 1.106.480,34 1.542.295,28
b. Pembesian 239,49 kg 17.226,79 4.125.651,28
c. Begisting 2 x pakai 18,59 m2 203.778,40 3.787.221,56
16 Plat lantai
a. Beton mutu K-225 23,14 m3 1.106.480,34 25.599.529,15
b. Pembesian 3.495,04 kg 17.226,79 60.208.277,84
c. Begisting 2 x pakai 192,80 m2 227.234,95 43.810.898,75
17 Plat Tangga 1 (Lebar 90 cm)
a. Beton mutu K-225 6,26 m3 1.106.480,34 6.923.026,19
b. Pembesian 1.465,08 m3 17.226,79 25.238.631,73
c. Begisting 2 x pakai 19,24 m2 309.327,20 5.951.455,33
18 Plat Tangga 2 (Lebar 120 cm)
a. Beton mutu K-225 7,88 m3 1.106.480,34 8.713.931,01
b. Pembesian 1.730,32 m3 17.226,79 29.807.917,03
c. Begisting 2 x pakai 26,69 m2 309.327,20 8.255.324,31
Jumlah C 603.108.300,45
D PEKERJAAN PASANGAN
1 Pek. Pasangan batu belah camp. 1SP : 6PP 67,87 m3 882.082,68 59.866.951,49
2 Pek. Pasangan dinding bata merah 1/6 bata, camp 1PC:6PP 505,83 m2 120.624,00 61.015.479,17
4 Pek. Plester 1PC:8PP, tebal 15 mm 1.011,66 m2 62.040,38 62.764.023,04
5 Pek. Acian 1.011,66 m2 58.959,01 59.646.711,94
6 Pek. Sponengan 500,00 m1 13.981,71 6.990.853,33
7 Pek. Tangga Besi Pijakan Kayu 1,00 bh 11.136.000,00 11.136.000,00
Jumlah D 261.420.018,97
Jumlah E 104.777.425,08
200,00
F. PEKERJAAN LANTAI DAN DINDING
1 Urugan pasir bawah rabat (tebal = 10 cm) 30,00 m3 236.476,80 7.094.304,00
2 Rabat beton (tebal = 5 cm) K 125 6,25 m3 1.001.676,34 6.260.477,13
3 Pek. Pasang penutup lantai Granit Terazzo 60 x 60 cm 191,64 m2 309.557,33 59.323.566,72
5 Pek . Pas Plint granit dinding bag bawah 10 x 60 cm 78,60 m' 49.549,23 3.894.569,48
6 Pek. Pasang Bata Ekspose tempel 17,05 m2 150.000,00 2.557.500,00
7 Pek. Pangan Keramik Dinding Bevel Metro 10x20 cm 3,75 m2 111.000,00 416.583,00
NO URAIAN VOLUME SATUAN HARGA SATUAN JUMLAH
1 2 3 4 6 7
8 Pek. Pasang keramik Lantai KM 40x40 cm 5,84 m2 151.875,00 886.494,38
9 Pek. Pasang keramik 25 x 40 cm dinding KM ex. Platinum t : 1,6 m 19,78 m2 198.573,70 3.926.993,43
10 Pek. Pasang Batu Lempeng Carport 25,00 m2 365.290,41 9.132.260,31
11 Pek. Pasang Penutup lantai Vinyl pada Mezzanine 13,50 m2 185.000,00 2.497.500,00
12 Pek. Pasang Penutup lantai Vinyl pada Tangga Depan 49,12 m2 185.000,00 9.087.200,00
13 Pek. Pasang penutup lantai Granit Terazzo 60 x 60 cm Pada Tangga Belakang 24,57 m2 309.557,33 7.605.823,60
Jumlah F 112.683.272,04
G PEKERJAAN PLAFOND
1 Pek. Pemasangan Rangka Hollow Galvanis 60x80 154,29 m2 80.331,99 12.394.181,74
2 Memasang Langit-langit Gypsum Board 9 mm (ex. Jaya Board) 148,45 m2 50.251,27 7.459.801,03
3 Memasang Langit-langit Calsiboard 6 mm 5,84 m2 64.370,10 375.728,25
4 Memasang list langit-langit gypsum 10 cm 92,30 m' 29.575,35 2.729.804,81
5 Memasang Panelot Kisi-kisi Plafon Motif Kayu 8,40 m2 640.000,00 5.376.000,00
Jumlah G 28.335.515,83
1 Pek. Pasang lampu RMi 2 x 18 watt ex. Philips 10,00 ttk 487.674,00 4.876.740,00
2 Pek pasang lampu LED 14 Watt dengan fitting setara Phillips 19,00 ttk 100.624,00 1.911.856,00
3 Pek. Pasang Lampu Sorot 8,00 ttk 218.700,00 1.749.600,00
4 Pek. Pasang BOX MCB 2 Group 2,00 Unit 229.827,00 459.654,00
5 Pek. Saklar single ex. Panasonic 5,00 ttk 85.000,00 425.000,00
6 Pek. Saklar double ex. Panasonic 7,00 ttk 90.000,00 630.000,00
7 Pek. Stop kontak ex. Panasonic 6,00 ttk 75.000,00 450.000,00
8 Pek. Pasang Stop Kontak AC ex. Panasonic 5,00 Unit 125.000,00 625.000,00
9 Pek pasang kabel NYM 2x1,5mm SNI SPLN lampu ex. Eterna 105,11 m' 20.849,00 2.191.438,39
10 Pek pasang kabel NYM 2x2,5mm SNI SPLN stop kontak dan line listrik ex. Eterna 51,60 m' 32.000,00 1.651.200,00
11 Pek. Pasang Lampu Led Strip Interior 55,00 m' 15.000,00 825.000,00
12 Pek. Pasang Daya Listrik 5500 5.500,00 VA 2.100,00 11.550.000,00
13 Pek. Pasang (Air Conditioner) AC Daikin Type Standart 2 PK 5,00 Unit 9.375.000,00 46.875.000,00
Jumlah H 74.220.488,39
I PEKERJAAN PENGECATAN
1 Pengecatan Plafond (2 lap. Cat penutup) ex. Catylac 154,29 m2 24.460,35 3.773.914,02
2 Pengecatan Dinding Baru Interior (1 lap Cat Dasar, 2 lap. Cat Penutup) ex. Catylac 1.011,66 m2 25.911,20 26.213.428,24
3 Coating Gloss Batu Lempeng 25,00 m2 33.000,00 825.000,00
Jumlah I 30.812.342,26
Jumlah A 401.082.752,22
B PEKERJAAN PASANGAN
1 Pek. Pasangan dinding bata merah 1/6 bata, camp 1PC:6PP 224,29 m2 120.624,00 27.055.239,46
2 Pek. Plester 1PC:8PP, tebal 15 mm 448,59 m2 62.040,38 27.830.571,78
3 Pek. Acian 448,59 m2 58.959,01 26.448.306,17
4 Pek. Sponengan 224,29 m1 13.981,71 3.136.012,92
Jumlah B 84.470.130,32
Jumlah C 65.543.877,77
E PEKERJAAN PLAFOND
1 Pek. Pemasangan Rangka Hollow Galvanis 60x80 194,49 m2 80.331,99 15.623.768,74
2 Memasang Langit-langit Gypsum Board 9 mm (ex. Jaya Board) 194,49 m2 49.000,56 9.530.118,91
NO URAIAN VOLUME SATUAN HARGA SATUAN JUMLAH
1 2 3 4 6 7
3 Memasang Langit-langit Calsiboard 6 mm 6,25 m2 64.370,10 402.313,10
4 Memasang list langit-langit gypsum 10 cm 129,22 m1 30.508,80 3.942.347,14
Jumlah E 29.498.547,89
F PEKERJAAN PENGECATAN
1 Pengecatan Plafond (2 lap. Cat penutup) ex. Catylac 200,74 m2 24.460,35 4.910.170,66
2 Pengecatan Dinding Baru Interior (1 lap Cat Dasar, 2 lap. Cat Penutup) ex. Catylac 201,19 m2 25.911,20 5.213.074,33
3 Pengecatan Dinding Baru Eksterior (1 lap Cat Dasar, 2 lap. Cat Penutup) ex. Jotun 154,92 m2 56.000,00 8.675.312,80
Jumlah F 18.798.557,79
Jumlah G 11.160.216,13
1 Pek. Pasang lampu RMi 2 x 18 watt ex. Philips 4,00 ttk 487.674,00 1.950.696,00
2 Pek pasang lampu LED 14 Watt dengan fitting setara Phillips 13,00 ttk 100.624,00 1.308.112,00
3 Pek. Pasang BOX MCB 2 Group 2,00 Unit 229.827,00 459.654,00
4 Pek. Saklar single ex. Panasonic 8,00 ttk 85.000,00 680.000,00
5 Pek. Saklar double ex. Panasonic 13,00 ttk 90.000,00 1.170.000,00
6 Pek. Stop kontak ex. Panasonic 13,00 ttk 75.000,00 975.000,00
7 Pek. Pasang Stop Kontak AC ex. Panasonic 5,00 Unit 125.000,00 625.000,00
8 Pek pasang kabel NYM 2x1,5mm SNI SPLN lampu ex. Eterna 132,80 m' 20.849,00 2.768.747,20
9 Pek pasang kabel NYM 2x2,5mm SNI SPLN stop kontak dan line listrik ex. Eterna 156,80 m' 32.000,00 5.017.600,00
10 Pek. Pasang AC ( Air Condition ) 2 PK Ex. DaikinType Standart 5,00 Unit 9.375.000,00 46.875.000,00
11 Pek. Pasang Penangkal Petir Non Radioaktif 1,00 Unit 8.250.000,00 8.250.000,00
Jumlah H 70.079.809,20
1 Pek. Pasangan dinding bata merah 1/6 bata, camp 1PC:6PP 31,28 m2 120.624,00 3.773.118,72
2 Pek. Plester 1PC:8PP, tebal 15 mm 62,56 m2 62.040,38 3.881.246,42
3 Pek. Acian 62,56 m2 58.959,01 3.688.475,92
4 Rangka Atap Baja Ringan 26,83 m2 200.000,00 5.365.000,00
5 Penutup Atap Galvalum 26,83 m2 96.000,00 2.575.200,00
Jumlah I 19.283.041,06
A PEKERJAAN ARSITEKTURAL
1 Pek. Finishing Dinding Conwood Lap Siding Warna Abu-abu 73,74 m2 348.550,13 25.700.971,23
2 Pek. Fasad Conwood Lap Siding Motif kayu Coklat 33,00 m2 348.550,13 11.502.154,29
3 Pek. Fasad WPC Click On Hollow 50x75 334,00 m1 165.000,00 55.110.000,00
Pek. Finishing Dinding Pagar Conwood ECP Board/ Panel-Board 60x120x1cm +
4 14,00 m2 215.000,00 3.010.000,00
Rangka Hollow Galvanis
5 Pek. Tulisan Huruf Akrilik AYANA HOUSE 1,00 Unit 300.000,00 300.000,00
6 Pek. Tulisan Huruf Akrilik Coffee Shop 1,00 Unit 265.000,00 265.000,00
7 Pek. Pagar Besi Industrial 1,00 Unit 19.446.000,00 19.446.000,00
A PEKERJAAN INTERIOR
1 Pek. Backdrop depan Motif Marmer, dan Finishing WPC 14,45 m2 710.000,00 10.256.660,00
2 Pek. Finishing Dinding WPVC Motif kayu Pada Cafe 2,75 m2 160.000,00 440.000,00
3 Pek. Pasang MDF Board t:12cm Finishing HPL TACO Warna Abu-abu 14,43 m2 460.000,00 6.637.340,00
4 Pek. Pasang Tulisan Acrylic Nyala 210,00 cm2 8.500,00 1.785.000,00