PEKERJAAN :
LOKASI :
N. PEKERJAAN PENGECATAN
N.1 Interior Lantai 1
N.1.1 Pek. Pengecatan Dinding (Cat Dulux/ICI) 839.23 m2 43,947.75 36,882,270.23
N.1.2 Pek. Pengecatan Plafond (Cat Dulux/ICI) 500.51 m2 21,686.50 10,854,407.70
N.2 Interior Lantai 2
N.2.1 Pek. Pengecatan Dinding (Cat Dulux/ICI) 482.86 m2 43,947.75 21,220,610.57
N.2.2 Pek. Pengecatan Plafond (Cat Dulux/ICI) 54.57 m2 21,686.50 1,183,432.31
N.3 Eksterior
N.3.1 Pek. Pengecatan Dinding lt1.dan lt.2 (Cat Dulux/ICI Watershield) 592.91 m2 50,217.75 29,774,781.91
Sub Jumlah 99,915,502.72
O. PEKERJAAN LANDSCAPE
O.1 Pekerjaan Carport
O.1.1 Pek. Pasangan Paving Block Carport 517.41 M2 386,567.50 200,013,890.18
- Tebal paving block 6 cm
- Ukuran 10x20 warna abu-abu
- Ukuran 20x20 warna hitam
- Ukuran 10x20 warna merah (untuk border)
- Dasar Paving dengan Sirtu / Split uk 2-3 cm, dengan ketebalan 10 cm
O.1.2 Pek. Pasangan Kanstein 64.62 M' 240,223.50 15,523,242.57
- Uk Kansteen 14x30x60 (merk cisangkan, kanstein wet process)
Sub Jumlah 215,537,132.75
A. PEKERJAAN PERSIAPAN
B. PEKERJAAN BONGKARAN
C. PEKERJAAN TANAH DAN PASIR
D. PEKERJAAN PONDASI DAN BETON
E. PEKERJAAN PAS. BATUBATA, PLESTERAN & PARTISI
F. PEKERJAAN PASANGAN ATAP
G. PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING
H. PEKERJAAN PLAFOND
I. PEKERJAAN GRANITE
J. PEKERJAAN SANITARY
K. PEKERJAAN KUSEN PINTU DAN JENDALA UPVC
L. PEKERJAAN RAILING ACP DAN CANOPY
M. PEKERJAAN ENTRANCE
N. PEKERJAAN PENGECATAN
O. PEKERJAAN LANDSCAPE
P. PEKERJAAN BATU ALAM EXTERIOR
Q. PEKERJAAN WOOD PLANK EXTERIOR
R. PEKERJAAN KOLAM RENANG
S. PEKERJAAN VITALISASI DOME ENTERANCE
T. PEKERJAAN KOLAM IKAN
JUMLAH TOTAL BIAYA PEMBANGUNAN
JASA KONTRAKTOR 8%
JUMLAH
PPN 11%
TOTAL
DI BULATKAN
REKAPITULASI
JUMLAH
(Rp. )
90,244,505.39
115,240,912.50
47,033,356.38
1,375,324,878.23
741,739,512.64
395,510,678.36
221,826,926.63
321,054,583.72
766,839,390.48
147,867,296.00
366,810,053.20
292,838,180.00
11,079,150.00
99,915,502.72
215,537,132.75
22,549,200.00
5,427,000.00
244,402,055.00
81,319,745.25
253,400,000.00
5,815,960,059.23
465,276,804.74
6,281,236,863.97
690,936,055.04
6,972,172,919.01
6,972,172,000.00
DAFTAR HARGA SATUAN BAHAN DAN UPAH
TAHUN 2018 - SEMESTER I
20 x 25 kotak 56,000.00
bh 2,800.00
20 x 20 (KM/WC) kotak 59,000.00
bh 2,360.00
30 x 30 (tekstur) kotak 141,000.00
bh 12,818.18
2. KERAMIK WARNA/TEKSTUR 20 x 25 kotak 56,000.00
bh 2,800.00
30 x 30 kotak 61,200.00
bh 5,563.64
30 x 30 (tekstur ) kotak 141,000.00
bh 12,818.18
40 x 40 kotak 70,700.00
bh 11,783.33
50 x 50 kotak 131,000.00
bh 32,750.00
50 x 50 (tekstur) kotak 131,000.00
bh 32,750.00
Nat keramik bks 16,500.00
No. JENIS BAHAN SATUAN HARGA DASAR (Rp)
No. JENIS BAHAN SATUAN HARGA DASAR (Rp)
6. PEGANGAN TANGGA Pegangan tangga stainless 3/4" & 2") m' 673,000.00
STAINLESS
6. PEGANGAN TANGGA Pegangan tangga stainless m' 317,000.00
STAINLESS kombinasi acrylic (3/4", 1 & 2:")
X. BAHAN KACA
1. KACA POLOS Kaca polos 3mm m2 120,000.00
1. KACA POLOS Kaca polos 5mm m2 145,000.00
Kaca polos 8mm m2 350,000.00
Kaca polos 10mm m2 450,000.00
Kaca polos 12mm m2 550,000.00
XV. LAIN-LAIN
1 Amplas lbr 8,000.00
2 Diamond wheel bh 130,000.00
3 Tali Ijuk kg 38,000.00
4 Air ltr 66.60
5 Minyak Bekesting ltr 10,700.00
6 Minyak Pelumas/oli ltr 35,000.00
7 Pertalite ltr 10,130.00
8 Dexlite ltr 10,130.00
9 Solar ltr 10,130.00
10 Harosaen/ Minyak tanah ltr 10,700.00
11 Soda api kg 40,000.00
12 Sewa alat las jam 6,700.00
13 Sewa scafolding unit 45,000.00
14 Sewa molen unit/hari 600,000.00
15 Karung goni lbr 9,700.00
16 Plastik m2 3,125.00
17 Geotekstil m2 22,000.00
2. Membuat 1 m3 lantai kerja beton mutu F'c=7,4 Mpa (K100) slump (3-6)cm, w/c=0,87
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.200 150,000.00 180,000.00
Tukang Batu L.02 OH 0.200 200,000.00 40,000.00
Kepala Tukang L.03 OH 0.020 250,000.00 5,000.00
Mandor L.04 OH 0.060 275,000.00 16,500.00
JUMLAH TENAGA KERJA 241,500.00
B BAHAN
Semen Portland kg 230.000 1,340.00 308,200.00
Pasir Beton kg 893.000 89.29 79,732.14
Kerikil (Maks. 30mm) kg 1027.000 351.85 361,351.85
Air Liter 200.000 66.60 13,320.00
JUMLAH TENAGA BAHAN 762,603.99
C. PERALATAN
-
JUMLAH TENAGA ALAT -
3. Membuat 1 m3 beton mutu F'c=14,5 Mpa (K175), slump (12±2) cm, w/c=0,66
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 200,000.00 55,000.00
Kepala Tukang L.03 OH 0.028 250,000.00 7,000.00
Mandor L.04 OH 0.083 275,000.00 22,825.00
JUMLAH TENAGA KERJA 332,325.00
B BAHAN
Semen Portland kg 326.000 1,340.00 436,840.00
Pasir Beton kg 760.000 89.29 67,857.14
Kerikil (Maks. 30mm) kg 1029.000 351.85 362,055.56
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 881,071.70
C. PERALATAN
-
JUMLAH TENAGA ALAT -
4. Membuat 1 m3 beton mutu F'c=19,3 Mpa (K225), slump (12±2) cm, w/c=0,58
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 200,000.00 55,000.00
Kepala Tukang L.03 OH 0.028 250,000.00 7,000.00
Mandor L.04 OH 0.083 275,000.00 22,825.00
JUMLAH TENAGA KERJA 332,325.00
B BAHAN
Semen Portland kg 371.000 1,340.00 497,140.00
Pasir Beton kg 698.000 89.29 62,321.43
Kerikil (Maks. 30mm) kg 1047.000 351.85 368,388.89
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 942,169.32
C. PERALATAN
-
JUMLAH TENAGA ALAT -
6. Membuat 1 m3 beton mutu F'c=26,4 Mpa (K300), slump (12±2) cm, w/c=0,52
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 200,000.00 55,000.00
Kepala Tukang L.03 OH 0.028 250,000.00 7,000.00
Mandor L.04 OH 0.083 275,000.00 22,825.00
JUMLAH TENAGA KERJA 332,325.00
B BAHAN
Semen Portland kg 413.000 1,340.00 553,420.00
Pasir Beton kg 681.000 89.29 60,803.57
Kerikil (Maks. 30mm) kg 1021.000 351.85 359,240.74
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 987,783.31
C. PERALATAN
-
JUMLAH TENAGA ALAT -
4. Pemasangan 1 m2 dinding bata lubang (8x8x16) cm tebal 1/2 batu campuran 1 SP:4PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 150,000.00 45,000.00
Tukang Batu L.02 OH 0.100 200,000.00 20,000.00
Kepala Tukang L.03 OH 0.010 250,000.00 2,500.00
Mandor L.04 OH 0.015 275,000.00 4,125.00
JUMLAH TENAGA KERJA 71,625.00
B BAHAN
Bata merah bh 66.000 610.00 40,260.00
Semen Portland kg 6.268 1,340.00 8,398.45
Pasir pasang m3 0.023 125,000.00 2,929.38
JUMLAH TENAGA BAHAN 51,587.83
C. PERALATAN
-
JUMLAH TENAGA ALAT -
9 Pemasangan 1 m2 acian
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.09 OH 0.200 150,000.00 30,000.00
Tukang Batu L.10 OH 0.100 200,000.00 20,000.00
Kepala Tukang L.11 OH 0.010 250,000.00 2,500.00
Mandor L.12 OH 0.010 275,000.00 2,750.00
JUMLAH TENAGA KERJA 55,250.00
B BAHAN
Semen Portland kg 3.250 6,500.00 21,125.00
-
JUMLAH TENAGA BAHAN 21,125.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm (tebal 12 mm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 105,000.00
Tukang Batu L.02 OH 0.050 60,000.00
Kepala Tukang L.03 OH 0.005 3,750.00
Mandor L.04 OH 0.005 15,000.00
JUMLAH TENAGA KERJA
B BAHAN
Gypsum board Lembar 0.364 95,000.00
Paku skrup kg 0.110 60,000.00
Cornis kg 0.300 3,750.00
Lakban gypsum roll 0.070 15,000.00
inc. drop ceiling 15%
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
52,500.00
70,000.00
8,750.00
4,950.00
136,200.00
32,000.00
8,000.00
26,430.00
66,430.00
-
-
202,630.00
20,263.00 10%
222,893.00
10,500.00
3,000.00
18.75
75.00
13,593.75
34,580.00
6,600.00
1,125.00
1,050.00
6,503.25
49,858.25
-
-
63,452.00
6,345.20 10%
69,797.20
ukuran (120 x 240 x 9) mm (tebal 9 mm)
Harga Satuan (Rp) Jumlah Harga (Rp)
150,000.00 15,000.00
200,000.00 10,000.00
250,000.00 1,250.00
275,000.00 1,375.00
JUMLAH TENAGA KERJA 27,625.00
80,000.00 29,120.00
60,000.00 6,600.00
3,750.00 1,125.00
15,000.00 1,050.00
5,684.25
JUMLAH TENAGA BAHAN 43,579.25
-
JUMLAH TENAGA ALAT -
71,204.25
10% X D 7,120.43 10%
78,324.68
Pemasangan 1 m2 lantai granite tile ukuran 80cm x 80cm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 150,000.00
Tukang Batu L.02 OH 0.125 200,000.00
Kepala Tukang L.03 OH 0.013 250,000.00
Mandor L.04 OH 0.013 275,000.00
JUMLAH TENAGA KERJA
B BAHAN
Granite tile bh 1.716 331,680.00
Semen Portland kg 8.190 1,340.00
Pasir pasang kg 0.045 125,000.00
Semen warna kg 1.620 16,500.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
37,500.00
25,000.00
3,250.00
3,575.00
69,325.00
569,162.88
10,974.60
5,625.00
26,730.00
612,492.48
-
-
681,817.48
68,181.75 10%
749,999.23
13,500.00
18,000.00
8,750.00
1,375.00
41,625.00
54,934.50
1,527.60
375.00
825.00
57,662.10
-
-
99,287.10
9,928.71 10%
109,215.81
Jumlah Harga (Rp)
37,500.00
25,000.00
3,250.00
3,575.00
69,325.00
236,070.00
10,974.60
5,625.00
26,730.00
279,399.60
-
-
348,724.60
34,872.46 10%
383,597.06
13,500.00
18,000.00
8,750.00
1,375.00
41,625.00
22,704.00
1,527.60
375.00
825.00
25,431.60
-
-
67,056.60
6,705.66 10%
73,762.26
78,123.50
13,400.00
5,625.00
24,750.00
121,898.50
-
-
191,223.50
19,122.35 10%
210,345.85
28,125.00
75,000.00
11,250.00
5,170.00
119,545.00
78,123.50
13,400.00
5,625.00
24,750.00
121,898.50
-
-
241,443.50
24,144.35 10%
265,587.85
Pemasangan 1 m2 Dinding Marmer
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.300 110,000.00
Tukang Batu L.02 OH 0.650 150,000.00
Kepala Tukang L.03 OH 0.065 175,000.00
Mandor L.04 OH 0.035 200,000.00
JUMLAH TENAGA KERJA
B BAHAN
Marmer Alam Import m2 1.060 1,750,000.00
Semen Portland kg 12.440 1,400.00
Pasir pasang kg 0.025 125,000.00
Semen warna kg 0.650 16,500.00
Paku 12 cm kg 3.030 25,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
143,000.00
97,500.00
11,375.00
7,000.00
258,875.00
1,855,000.00
17,416.00
3,125.00
10,725.00
75,750.00
1,962,016.00
-
-
2,220,891.00
222,089.10 10%
2,442,980.10
Pemasangan 1 m2 Paving Block Polos tebal 6 cm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 110,000.00
Tukang Batu L.02 OH 0.500 135,000.00
Kepala Tukang L.03 OH 0.025 160,000.00
Mandor L.04 OH 0.003 175,000.00
JUMLAH TENAGA KERJA
B BAHAN
Paving block t 6 cm m2 1.010 190,000.00
Pasir beton m3 0.100 125,000.00
Split uk. 2-3 cm m3 0.100 475,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
27,500.00
67,500.00
4,000.00
525.00
99,525.00
191,900.00
12,500.00
47,500.00
251,900.00
-
-
351,425.00
35,142.50 10%
386,567.50
16,500.00
27,000.00
3,200.00
1,750.00
48,450.00
165,000.00
3,685.00
1,250.00
169,935.00
-
-
218,385.00
21,838.50 10%
240,223.50
Pemasangan 1 buah closed duduk
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 3.300 150,000.00
Tukang batu L.02 OH 1.100 200,000.00
Kepala Tukang L.03 OH 0.010 250,000.00
Mandor L.04 OH 0.160 275,000.00
JUMLAH TENAGA KERJA
B BAHAN
Closed duduk unit 1.000 5,000,000.00
Jet Shower Tx 403 SMCRB unit 1.000 375,000.00
Perlengkapan Ls 6%xclosed
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
Pemasangan 1 buah closed duduk
Jumlah Harga (Rp) No. Uraian Kode Satuan Koefisien
A. TENAGA
495,000.00 Pekerja L.01 OH 3.300
220,000.00 Tukang batu L.02 OH 1.100
2,500.00 Kepala Tukang L.03 OH 0.010
44,000.00 Mandor L.04 OH 0.160
761,500.00 JUMLAH TENAGA KERJA
B BAHAN
5,000,000.00 Closed duduk Grohe unit 1.000
375,000.00 Jet Shower Tx 403 SMCRB unit 1.000
300,000.00 Perlengkapan Ls 6%xclosed
5,675,000.00 JUMLAH TENAGA BAHAN
C. PERALATAN
-
- JUMLAH TENAGA ALAT
4,500.00
60,000.00
7,500.00
4,125.00
76,125.00
1,361,000.00
88,000.00
1,449,000.00
-
-
1,525,125.00
152,512.50 10%
1,677,637.50
1,500.00
20,000.00
10,000.00
1,375.00
32,875.00
350,000.00
125.00
350,125.00
-
-
383,000.00
38,300.00 10%
421,300.00
5,400.00
12,000.00
1,500.00
550.00
19,450.00
12,000.00
3,500.00
15,500.00
-
-
34,950.00
3,495.00 10%
38,445.00
12,150.00
27,000.00
3,375.00
1,100.00
43,625.00
105,000.00
30,625.00
135,625.00
-
-
179,250.00
17,925.00 10%
197,175.00
495,000.00
220,000.00
2,500.00
44,000.00
761,500.00
7,500,000.00
4,000,000.00
450,000.00
11,950,000.00
-
-
12,711,500.00
1,271,150.00 10%
13,982,650.00
Pemasangan 1 buah closed duduk
Harga Satuan (Rp) Jumlah Harga (Rp) No. Uraian Kode Satuan
A. TENAGA
150,000.00 495,000.00 Pekerja L.01 OH
200,000.00 220,000.00 Tukang batu L.02 OH
250,000.00 2,500.00 Kepala Tukang L.03 OH
275,000.00 44,000.00 Mandor L.04 OH
JUMLAH TENAGA KERJA 761,500.00
B BAHAN
7,500,000.00 7,500,000.00 Closed duduk unit
575,000.00 575,000.00 Jet Shower Tx 403 SMCRB unit
450,000.00 Perlengkapan Ls
JUMLAH TENAGA BAHAN 8,525,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
150,000.00 180,000.00
200,000.00 290,000.00
250,000.00 37,500.00
275,000.00 16,500.00
JUMLAH TENAGA KERJA 524,000.00
1,500,000.00 1,500,000.00
1,340.00 8,040.00
125,000.00 1,250.00
-
JUMLAH TENAGA BAHAN 1,509,290.00
-
JUMLAH TENAGA ALAT -
2,033,290.00
10% X D 203,329.00 10%
2,236,619.00
Harga Satuan (Rp) Jumlah Harga (Rp)
150,000.00 1,500.00
200,000.00 20,000.00
250,000.00 2,500.00
275,000.00 1,375.00
JUMLAH TENAGA KERJA 25,375.00
350,000.00 350,000.00
JUMLAH TENAGA BAHAN 350,000.00
-
JUMLAH TENAGA ALAT -
375,375.00
10% X D 37,537.50 10%
412,912.50
Harga Satuan (Rp) Jumlah Harga (Rp)
150,000.00 1,500.00
200,000.00 20,000.00
250,000.00 10,000.00
275,000.00 1,375.00
JUMLAH TENAGA KERJA 32,875.00
3,850,000.00 3,850,000.00
5,000.00 1,250.00
JUMLAH TENAGA BAHAN 3,851,250.00
-
JUMLAH TENAGA ALAT -
3,884,125.00
10% X D 388,412.50 10%
4,272,537.50
Harga Satuan (Rp) Jumlah Harga (Rp)
150,000.00 12,150.00
200,000.00 27,000.00
250,000.00 3,375.00
275,000.00 1,100.00
JUMLAH TENAGA KERJA 43,625.00
37,500.00 45,000.00
13,125.00
JUMLAH TENAGA BAHAN 58,125.00
-
JUMLAH TENAGA ALAT -
101,750.00
10% X D 10,175.00 10%
111,925.00
Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
-
JUMLAH TENAGA ALAT -
5,376,500.00
10% X D 537,650.00 10%
5,914,150.00
Pembuatan 1 m' Kusen Pintu / Kusen Jendela (Putih)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja Q.01 OH 0.080 110,000.00
Tukang UPVC Q.02 OH 0.050 150,000.00
Kepala Tukang Q.03 OH 0.005 175,000.00
Mandor Q.04 OH 0.001 200,000.00
JUMLAH TENAGA KERJA
B BAHAN
Profil UPVC N.01 m' 1.100 185,000.00
Perlengkapan Kusen - % 0.100 185,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 7% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
8,800.00
7,500.00
875.00
200.00
17,375.00
203,500.00
18,500.00
222,000.00
-
-
222,000.00
15,540.00
237,540.00
8,800.00
7,500.00
875.00
200.00
17,375.00
225,500.00
20,500.00
246,000.00
-
-
246,000.00
17,220.00
263,220.00
275,000.00
25,000.00
300,000.00
-
-
300,000.00
21,000.00
321,000.00
8,800.00
7,500.00
875.00
200.00
17,375.00
203,500.00
27,750.00
231,250.00
-
-
231,250.00
16,187.50
247,437.50
8,800.00
7,500.00
875.00
200.00
17,375.00
225,500.00
30,750.00
256,250.00
-
-
256,250.00
17,937.50
274,187.50
8,800.00
7,500.00
875.00
200.00
17,375.00
275,000.00
37,500.00
312,500.00
-
-
312,500.00
21,875.00
334,375.00
8,800.00
22,500.00
2,625.00
300.00
34,225.00
385,000.00
30,800.00
415,800.00
-
-
415,800.00
29,106.00
444,906.00
8,800.00
22,500.00
2,625.00
300.00
34,225.00
385,000.00
70,000.00
40,000.00
30,800.00
525,800.00
-
-
525,800.00
36,806.00
562,606.00
8,800.00
22,500.00
2,625.00
300.00
34,225.00
385,000.00
140,000.00
80,000.00
30,800.00
635,800.00
-
-
635,800.00
44,506.00
680,306.00
8,800.00
22,500.00
2,625.00
300.00
34,225.00
385,000.00
350,000.00
200,000.00
30,800.00
965,800.00
-
-
965,800.00
67,606.00
1,033,406.00
8,800.00
22,500.00
2,625.00
300.00
34,225.00
385,000.00
70,000.00
90,000.00
300,000.00
120,000.00
30,800.00
995,800.00
-
-
995,800.00
69,706.00
1,065,506.00
Tipe Bahan tinggi Lebar Jumlah Volume
Lantai 1 Lantai 2
Pintu PK1 1 -
Kusen Kayu Kelas 1 2.40 1.100 5.900
Pintu 2 Daun Kayu Solid 2.35 1.050 2 4.935
Kaca
List
Finishing Oven
Engsel Engsel Pintu Kupu-Kupu 4" 3 6.0
Kunci Mortise Lock Lidah Pelor 1
Double Cylinder 1
Grendel Tanam 1
Handle Push Pull Handle 2
List
Finishing Oven
Engsel Engsel Pintu Kupu-Kupu 4" 3 6.0
Kunci Mortise Lock Lidah Pelor 1
Double Cylinder 1
Grendel Tanam 1
Handle Push Pull Handle 2
Satuan Harga Satuan Total
bh 84,500.00 253,500
Set 270,000.00 270,000
bh 130,000.00 130,000
Set 150,000.00 150,000
Set 800,000.00 1,600,000
8,878,500
bh 84,500.00 253,500
Set 270,000.00 270,000
bh 130,000.00 130,000
Set 150,000.00 150,000
Set 800,000.00 1,600,000
8,916,000
Pengecatan 1 m2 tembok baru untuk interior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 110,000.00
Tukang cat L.02 OH 0.063 150,000.00
Kepala tukang L.03 OH 0.0063 175,000.00
Mandor L.04 OH 0.003 200,000.00
JUMLAH TENAGA KERJA
B BAHAN
Sealer Dulux Kg 0.100 45,000.00
Cat Interior Dulux kg 0.260 85,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Operasional 10% X D
F. Harga Satuan Pekerjaan (D+E)
pis cat penutup) Pengecatan 1 m2 tembok baru untuk interior ( 1 lapis plamir, 1 lapis c
Jumlah Harga (Rp) No. Uraian Kode Satuan
A. TENAGA
2,200.00 Pekerja L.01 OH
9,450.00 Tukang cat L.02 OH
1,102.50 Kepala tukang L.03 OH
600.00 Mandor L.04 OH
13,352.50
B BAHAN
4,500.00 Sealer Dulux Kg
22,100.00 Cat Interior Dulux kg
26,600.00
C. PERALATAN
-
-
3,080.00
6,300.00
735.00
600.00
10,715.00
9,000.00
9,000.00
-
-
19,715.00
1,971.50 10%
21,686.50
( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
-
JUMLAH TENAGA ALAT -
45,652.50
10% X D 4,565.25 10%
50,217.75
HARGA SATUAN PEKERJAAN LAIN-LAIN/ PERKIRAAN
1. Pemasangan 1 m2 rangka atap baja ringan (Kasau C. 75.100 & Reng R.40.45 mm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 150,000.00 30,000.00
Tukang L.02 OH 0.450 200,000.00 90,000.00
Kepala Tukang L.03 OH 0.010 250,000.00 2,500.00
Mandor L.04 OH 0.050 275,000.00 13,750.00
JUMLAH TENAGA KERJA 136,250.00
B BAHAN
Smartruss C 75.100 m 1.488 32,500.00 48,360.00
Smartruss C 75.100 m 0.700 32,500.00 22,750.00
Reng R.40.45 m 5.400 15,000.00 81,000.00
Srew bh 38.000 165.00 6,270.00
Dynabolt bh 1.600 1,500.00 2,400.00
Valery Gutter Talang Jurai m 0.124 39,000.00 4,836.00
JUMLAH TENAGA BAHAN 165,616.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -